operatorLadies and gentlemen, good day, and welcome to the NTPC Limited Q3 FY '21 Results Call hosted by ICICI Securities Limited. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Rahul Modi from ICICI Securities. Thank you, and over to you, sir.
Rahul Modi
analystThank you, Malika. On behalf of ICICI Securities, I welcome you all to the NTPC Q3 FY '21 earnings conference call. We are joined today by the senior management of NTPC, led by Director of Finance, Mr. A.K. Gautam. I would now like to hand over the call to Mr. Gautam and request him to introduce the management team, followed by his opening remarks and Q&A session. Over to you, sir. Thank you.
Anil Gautam
executiveThank you, Rahul. A very good evening to everybody. I, A.K. Gautam, Director of Finance, welcome all of you to the Q3 FY '21 con call of NTPC Limited. I have with me Shri Dillip Kumar Patel, Director, Human Resource; Shri Ramesh Babu, Director Operations; Shri Chandan Kumar Mondol, Director, Commercial; and Shri Ujjwal Kanti Bhattacharya, Director Project. I have also with me the other key members of NTPC team. Today, the company has announced the unaudited financial results for the third quarter of FY '21. The key performance highlights for the quarter and 9 months ended 31st December 2020, have already been disclosed on both the stock exchanges. The company had approved buyback of 2% paid-up capital in the Board meeting held on 2nd November 2020. We are pleased to inform that all associated activities pertaining to the buyback of shares were handled in conformity with the buyback regulations and buyback transaction was successfully settled on 30th December 2020. Now I will touch upon operational highlights for Q3 and 9 months of FY '21. NTPC stand-alone gross generation in Q3 FY '21 is 65.42 billion units and in 9 months FY '21 is 193.28 billion units, as compared to 61.21 billion units and 191.35 billion units in the corresponding previous period. Gross generation of NTPC Group in Q3 FY '21 is 76.53 billion units and 9 months FY '21 is 22.41 billion units, as compared to 68.87 billion units and 214.17 billion units in the corresponding previous periods. NTPC Group recorded generation of over 1 billion units on 18th January 2021, surpassing previous highest day generation of 977.0 million units on 28th July 2020. NTPC hydro and RE stations recorded generation of 0.71 billion units and 4.1 billion units in Q3 and 9 months of FY '21, respectively. In Q3 FY '21, we have added 865-megawatt to our commercial capacity, comprising 800 megawatt at Lara, 15 megawatt solar capacity at Auraiya and 50 megawatt at Kasargod, THDC. With these additions, the commercial capacity of NTPC has become 51,170-megawatt on stand-alone basis and 62,975-megawatt on the group as on 31st December 2020. For 9 months FY '21, 6 coal stations of NTPC were among the top 10 performing stations in the country in terms of PLF. It included Korba with 93.18%, Sipat with 90.36%, Rihand with 89.83%, Vindhyachal with 89.60%, Talcher Thermal with 88.37% and Talcher Super with 85.02% PLF. NTPC's very first unit commissioned 38 years ago at Singrauli, Uttar Pradesh, achieved a higher sale of 100.24% among all the thermal units in the country during 9 months FY '21. During 9 months FY '21, PLF for coal stations was 62.29%, hedged against a national average of 51.50%. During the period, we have suffered losses due to grid restrictions and field supply. The generation loss due to grid restrictions in the coal-based station was 84.12 billion units for 9 months FY '21. For the gas based stations, the loss was 20.24 billion units. The generation loss on account of fuel supply constraint was 0.18 billion units for 9 months FY '21. Now I will briefly set upon the status of fuel supply. During 9 months FY '21, materialization of coal against ACQ was 88.60% as against 92.40% in the 9 months of FY '20. Coal supply during 9 months FY '21 was 124.69 million metric tonne of coal, comprising of 123.91 MMT of domestic coal and 0.78 MMT of imported coal. The coal supply during the corresponding previous period was 125.81 MMT, with 123.66 MMT of domestic coal and 2.15 MMT of imported coal. During 9 months FY '21, 5.75 million metric tonne of coal has been excavated from our captive coal mine as compared to 7.04 MMT during the 9 months of FY '20. Cumulatively, 28.48 MMT coal has been excavated from Pakri-Barwadih, Dulanga and Talaipalli coal mines until 31st December 2020. Dulanga coal mine, having an estimate peak rated annual capacity of 7 million tonne per annum was declared commercial with effect from 1st October 2020. Cumulative expenditure of INR 7,513.71 crore has been incurred on the development of coal mines till 31st December 2020. During Q3 FY '21, NTPC participated in the 1,070-megawatt tariff based placed competitive bidding tender floated by SEBI for grid-connected solar PV projects on build-own-operate basis in Rajasthan, that is [ Tranche-III ] and won 470-megawatt with the second lowest bid of INR 2, 1 paise per kilowatt hour. Further, we had participated in 500-megawatt auction conducted by Gujarat Distribution Company and won 200-megawatt at a record low tariff of 1.99 kilowatt hour -- per kilowatt hour. This is the lowest tariff discovered so far. NTPC has signed MoU with AIIMS Delhi for providing support to set up tele-recording room, SET, Skills, e-Learning, Telemedicine facility at India's Premier Medical Institute as part of its CSR initiative. NTPC has signed up with IIFM Narmada Landscape to restore Narmada riverbed. Now some highlights about the environment management initiatives taken by the NTPC. Flue gas desulphurisation, FGD systems are under various stages of implementation in 64.85-gigawatt of growth capacity. FGD systems have already been commissioned for 1,340-megawatt capacity. FGD system packages for 58.94-gigawatt capacity are under implementation and FGD system, that is for 4.57-gigawatt balance capacity, are under various stages of pending. For compliance with NOx control, combustion modification has already been implemented at 7 units with 3.48-gigawatt of thermal for capacity. Award for contract for supply and installation of low NOx combustion system for 18-gigawatt of capacity have been awarded or -- are yet to be awarded. Award for de NOx system package for 43-gigawatt are under process. As utilization up to December 2020 was 64.62% for NTPC stations, as it was 67.41% for the group as a whole. NTPC continues to explore and implement initiative -- innovative initiatives, ways to use fly ash generated by our plants. Besides fertilizer, brickmaking, amongst other, we used it as a geopolymer road -- as an alternate to cement for road building in Ramagundam. Now I will touch upon the financial highlights of the company. Gross sales for the Q3 FY '21 is INR 24,471.06 crore as against corresponding quarter of previous year gross sales of INR 23,057.67 crore, registering an increase of 4.77%. On 9-month basis, there is an increase of 3.29% in the gross sales, that is from INR 70,193.78 crore in 9-month FY '20, to INR 72,504.83 crore in 9-month FY '21. Total income for Q3 FY '21 is INR 25,268.56 crore as against corresponding quarter of previous year total income of INR 24,022.62 crore, registering an increase of 5.19%. On 9-month basis, there is an increase of 4.31% in the total income, that is from INR 72,199.66 crore in 9-month FY '20 to INR 75,312.89 crore in 9-month FY '21. Profit before tax for Q3 FY '21 is INR 3,561.59 crore as against INR 3,422.04 crore in the corresponding quarter of the previous year, registering an increase of 4.08%. On 9-month basis, EBITA is INR 10,126.31 crore as against INR 10,082.15 crore in the 9 months of FY '20. Tax for Q3 FY '21 is INR 3,315.34 crore as against INR 2,995.14 crore in the corresponding quarter of the previous year, registering an increase of 10.69%. On 9-month basis tax is INR 9,290.30 crore as against INR 8,860.37 crore in 9-month of FY '20. Now I'll give you an update on various other financial activities. The regulated equity as on 31st December, 2020, was INR 64,786.60 crore. Now regarding some input about fund mobilization. During Q3 of FY '21, NTPC signed term loan agreement of INR 5,200 crore and INR 2,000 crore with Bank of India and ICICI Bank, respectively, totaling to INR 7,200 crore. NTPC has conducted a liability management through buyback and repurchase of Masala bond 2021 and '22. Notes amounting to INR 1,085 crores was standard for repurchase by the eligible noteholders and the same were affected for repurchase by the company. CapEx, in 9 months FY '21, we have incurred a CapEx of INR 12,383.49 crore. The CapEx by the other group companies has been INR 8,871.61 crore. Thus, the total group CapEx for the 9-month FY '21 was INR 21,255.10 crore. The capital outlay for FY '21 has been estimated at INR 21,000 crore for NTPC Limited. Now I will briefly touch upon some highlights of the group companies. NVVN, our wholly owned subsidy company, they did -- transacted 12.70 billion units during the 9 months FY '21 as against 10.91 billion units during the 9 months FY '20. NVVN has filed an MoU with Airport Authority of India Limited to set up ground-mounted public rooftop solar PV projects at airports or Airport Authority of India under renewable energy service company model. NVVN will also provide energy solution to Airport Authority of India by supplying electricity through open asset access and to support [Joy's] initiative for adoption of electric vehicles by creation of charting infra and promoting EV at airports of the Airport Authority of India. NVVN had won the tender issued by Bangalore Municipal Transport Corporation for deploying 90 electric buses for Bangalore macro fleet of service. This is the first time NVVN has participated in the tender for e-buses. Andaman and Nicobar Islands public transport system received a fleet of 14 electric buses provided by NVVN under its transit project of supplying 40 e-buses and charging stations, as part of union territory administration's move to reduce pollution. NVVN is working on a pilot project for adoption of hydrogen fuel cell-based electric buses and car projects in Leh and Delhi. NVVN, in partnership with Energy Efficiency Services Limited, had organized technology challenge named as Green Charcoal Hackathon. The purpose of the event was to leverage the innovative Indian mine to bridge the technology gap with the prime objective to clean barrier by eliminating foam fire, producing renewable energy out of Agro residue to promote local entrepreneurship and to increase the income of the farmers. During 9 months FY '21, we have received dividend of INR 520.73 crore from our subsidy and joint venture companies, as against INR 88.75 crore received in the corresponding period of the previous year. NTPC continues to win laurels and awards in various fields. Some of the major awards received in 9-month FY '21 are, NTPC has set the Scotch Award Platinum in the response to COVID category. It is a recognition for the intense effort made by NTPC to help confront the pandemic. NTPC has ranked 14th in 4th June, 2020, ranking for Top 500 corporations in India. NTPC has been confirmed with CSR Times Award 2020 gold category as the best PSU in green and environment stewardship category for its CSR project, Revival of Municipal Solid Waste Plant, [ Karsada ]. NTPC has also won prestigious CIA ITC sustainability award 2020 in the domain excellence of corporate social responsibility. NTPC has also been honored in the corporate excellence category commendation for significant achievement. This is the highest award concurred by CIA ITC in the CSR domain. NTPC is the only PSU to receive the award in the corporate excellence category, second time in a row. NTPC Rihand has received certificate of merit in the thermal power plant coal-based, more than 100 megawatts category from the Bureau of Energy efficiency. These were some of the highlights I wanted to share before the question-and-answer session began. Thank you.
Operator
operator[Operator Instructions] The first question is from the line of Mohit Kumar from DAM Capital.
Mohit Kumar
analystFirst question, sir, what was the under recovery 9-month FY '21 and 6 months FY '20?
Anil Gautam
executiveWhat was that?
Mohit Kumar
analystUnder recovery, fixed cost and the recovery?
Anil Gautam
executiveOkay. This was for the 9-month FY '21, it is INR 569.53 crores, and INR 499 crores for the half year ended.
Mohit Kumar
analystOkay. And secondly, what was the receivables at the end of September '20 and December '20 for greater than 45 days? And what is the outlook on liquidation for the rest of the fiscal year?
Anil Gautam
executiveNow I will request my -- our Director, Commercial, to respond to this question.
Chandan Mondol
executiveGood afternoon. As on 30th September, this receivables beyond 45 days was INR 19,164 crore. And as of 31st December '20, it was INR 16,720 crore.
Mohit Kumar
analystAnd sir, what is the outlook on liquidation of this receivable? It has nearly declined over INR 3,000 crores. Our expectation was slightly higher given the [ GST ].
Chandan Mondol
executiveI'd just tell that from July onwards, we have been able to realize more than 100% of amount. So whatever outstanding is accumulative until 30th of June, that is basically we are yet to liquidate entire amount. And this -- under this Atmanirbhar scheme, the tranche 2 is yet to be released -- yet to be cleared. So once we are getting the tranche 2 of Atmanirbhar -- under Atmanirbhar. So we'll be able to get another INR 8,000-plus crore amount. And now we see this commercial load is increasing and this collection is improving. We hope that by the end of March, we'll be able to bring down substantially [indiscernible].
Mohit Kumar
analystOkay. My last question, sir, what is the kind of cost and PLF you're expecting in the newer solar power plant, which are run in -- especially in the third quarter? Is it possible to give broad numbers?
Anil Gautam
executiveWell, just repeat your question.
Mohit Kumar
analystWhat is the kind of cost and cost -- capital cost expectation is for the power plant, which you're running Gujarat and Rajasthan? And what is the kind of PLF you are expecting in this solar power plant?
Chandan Mondol
executiveRight now, I'll not be able to share that chart because I do not have -- we can't abstractly provide these details to you to [ each other ].
Mohit Kumar
analystSure. Understood, sir.
Operator
operator[Operator Instructions] The next question is from the line of Subhadip Mitra from JM Financial.
Subhadip Mitra
analystJust wanted to get a sense of what would be the adjusted tax number for the current quarter?
Anil Gautam
executiveYes. Just a minute. For the current quarter, the adjusted price would be INR 3,308.34 crore against the corresponding quarter of INR 2,677.52 crore.
Subhadip Mitra
analystOkay. And what would be the broad adjustments here?
Anil Gautam
executiveBroad adjustment would include previous year sales, then [ PVC at will ]. Mainly, these 2 adjustments. And tax impact on the award adjustments.
Subhadip Mitra
analystOkay. Sir, secondly, is it possible to get a little bit more sense on the recent AP renewable wins that -- where we won some 600-odd megawatts? Some bit more color on that? And what is the projected tender pipeline that you look at for renewables for the rest of the year?
Anil Gautam
executiveWell, in case of Andhra, we had submitted 2 bids, 1 for 600-megawatt, another for 1,200-megawatt. As far as 600-megawatt is concerned, that we have owned that as a loan. But 1,200-megawatt, we have some clarification from Andhra, why they have not opened out it. So we have given a letter. Let us see -- we'll not know why they have not opened out.
Subhadip Mitra
analystAnd -- okay, go ahead.
Anil Gautam
executiveYes. And in future, we are participating -- we are participating aggressively. Do not depend on how much this is invited by the discount. We cannot give a certain number, okay, how much it will come.
Subhadip Mitra
analystOkay. Understood. Just 2 more questions. One would be on the Airport Authority of India partnership that you're doing with NVVN. Any projected number in terms of how large in terms of megawatt the rooftop solar can be for these airports?
Anil Gautam
executiveI hope that that figure, I can share afterward. But it will be a small number, definitely, but right now, I do not have.
Unknown Executive
executiveNo, no. Initially, we are vetting very initial stage only. This -- we plan to introduce this rooftop solar and solar plant at most of the airports. Initially, we will start at -- with some small airports. So right now, it is very premature to predict those numbers.
Subhadip Mitra
analystUnderstood. Okay. Lastly, for the rest of FY '21 and FY '22, if you can also chart out, which are the plants which are set for commercial trade?
Anil Gautam
executiveFor commercial -- you are asking about solar power plant or thermal power plant?
Subhadip Mitra
analystThermal power plants, sir. Thermal plant commercialization expected?
Anil Gautam
executiveOkay. Now Mr. Bhattacharya will be…
Ujjwal Bhattacharya
executiveWe had commented in June during this con call that we'll be having a [ COD ] of 4,490 in this financial year, and we are happy to announce that we have already completed 2,799 and well on track for another 2 to 7 sites, totaling 5,074-megawatt.
Subhadip Mitra
analystUnderstood. So this is for FY '21?
Ujjwal Bhattacharya
executiveThis is current financial years. And for the next financial year, we have kept a provision of roughly 4,852 plus one on to solar, roughly 6,000 megawatts.
Subhadip Mitra
analystWill this be all on stand-alone or we're including the subsidiary?
Ujjwal Bhattacharya
executiveI'm talking of the group capacity on a group basis.
Subhadip Mitra
analystOkay. It would be great if you could also give us a split between stand-alone and group, that would be very helpful.
Ujjwal Bhattacharya
executiveOkay. I'll give you that. For the current financial year, just 1 second, 2021, that NTPC group, only 5,074, out of which NTPC stand-alone will be 3080, except THDC and NEEPCO.
Subhadip Mitra
analystUnderstood. So has this -- the stand-alone capacity addition of 3080, most of it is already completed?
Ujjwal Bhattacharya
executiveYes. We are well on track. We have already completed more than 50% of that.
Subhadip Mitra
analystOkay. And for FY '22, what would be the stand-alone [ business ]?
Ujjwal Bhattacharya
executiveThat will be NTPC group will be 6,000, approximately. And we're fine-tuning based on our solar capacity, out of which NTPC will be 4,962.
Subhadip Mitra
analystOkay. So stand-alone capacity would be 4,962 addition for FY '22?
Ujjwal Bhattacharya
executiveRight.
Anil Gautam
executiveYes.
Subhadip Mitra
analystOkay. Perfect. That answers my question.
Operator
operatorThe next question is from the line of Sheena Barbosa from Pro Price (sic) [ T. Rowe Price ].
Sheena Barbosa
analystHello, can you hear me?
Anil Gautam
executiveYes, yes, Sheena, please.
Sheena Barbosa
analystOkay, yes. Sir, just wanted to ask you, in terms of the renewable capacity addition plan, how much have you won in the current financial year and can add in the current year?
Anil Gautam
executiveWe have -- I'll just give the figure total. We have totally commissioned as NTPC Group 1,275-megawatt of RE projects which we have already commissioned. And under incremental 2,759-megawatt. And then under tendering, around 1,448-megawatt. Out of this year, we have owned 200-megawatt from -- in Gujarat, 470-megawatts in Rajasthan, and 90-megawatt in Kerala -- for Kerala, and very recently, the 600-megawatt in Andhra.
Sheena Barbosa
analystOkay. Got it. And can you give us some idea about the kind of competition and the kind of economics and returns for these projects?
Anil Gautam
executiveYes. As you are knowing that we already own this won SECI Rajasthan at INR 2, 1 paise and as far as Gujarat INR 1, 99 paise. This return will be similar to equity that we are earning in coal-based units.
Sheena Barbosa
analystAnd was there a lot of competition for these projects, like how did you win them -- this just purely competitive bidding, right?
Anil Gautam
executiveYes, yes. It is -- there was a lot of competition.
Sheena Barbosa
analystOkay. And your equity -- I mean are returns for you better because of lower cost of funding? How are you funding these projects?
Anil Gautam
executiveYes, that is definitely due to the lower cost of funding and lower cost of, definitely, due to the lower cost of debt. But since this implemented on time, it takes much lower than the thermal power projects. So it will be or IRR will be comparable with the thermal one.
Sheena Barbosa
analystOkay. So it's like 11%, 12%? Or…
Anil Gautam
executiveYes, yes. [indiscernible]
Unknown Executive
executive12-plus percent.
Sheena Barbosa
analyst12-plus percent. Okay. Got it. And in terms of upcoming pipelines, like how do you see the tendering for solar projects happening in India over the next couple of years?
Anil Gautam
executiveWe -- that will definitely depend on this -- how much [indiscernible] is coming from SECI as well as [ Dadri ] each day. But as far as we are concerned, we have a plan that we should achieve at least 30,000-megawatt by 2030. But we are expecting much more than that.
Sheena Barbosa
analystAnd so what sources are they coming in terms of [indiscernible] for you -- can you give us an idea of when that will start to like really pick up?
Anil Gautam
executiveNot just -- repeat your question. When this…
Sheena Barbosa
analystSo in terms of -- you said you're expecting much more than 30,000-megawatt, right? And sir, when will be the inflection point in terms of you think?
Anil Gautam
executiveWe'll tell you that we have already signed with various states for this ultra-mega renewable energy power plant that is like Gujarat, Maharashtra, Rajasthan, Andhra and Uttar Pradesh. These 5 locations, we have already planned to have some 16 -- 17-gigawatt of capacity. So it will not depend. The exact number, we will not be able to tell right now like how much capacity will come. But year wise plan, I think we can share subsequently that is as for our business plan is concerned that we have met. Right now, it is not available with me. We can say it subsequently.
Operator
operatorThe next question is from the line of Atul Tiwari from Citigroup.
Atul Tiwari
analystYes, sir, just 2 questions. One -- the first one is again, on the receivable. So we read in the newspaper before that now that the receivable has been pending for a very long time, NTPC have issued multiple notices to states to liquidate them and institute the LC mechanism. So can you update on that front? What is the pickup of those notices? And has LC payment mechanism has been reinstituted, that is the first question.
Anil Gautam
executiveYes. We have -- we issued earlier these notices to a number of DISCOMs. And subsequently, there are certain improvement in the payment as well as this LC. Of course, we have -- all these states are having LC except J&K. J&K does not have. But we have taken up with the Ministry of Power also for recovery of the balance of turning dues to tripartite agreement.
Atul Tiwari
analystOkay. So sir, is the tripartite agreement being invoked finally? Because it doesn't look like that the receivables are coming down any recently.
Anil Gautam
executiveReceivables have come down definitely by -- from last quarter to this quarter, it has come down by almost INR 3,000 crore. And once the second tranche is approved by PFC, REC, we will be getting another INR 8,000-plus crore. And definitely, last few months, we are able to over this -- overall we did 100% realizations, so we are able to achieve.
Atul Tiwari
analystOkay. Sir, what is holding back the dispersal of the second tranche? Because, I mean since July, we have been hearing that the second tranche has been approved by PFC IFC, but it has not been dispersed. So where is…
Anil Gautam
executiveYes, there are certain conditions of -- where the payment of India, whatever, they are imports [indiscernible], et cetera. Probably some format after we still filled up by the discounts and subject to PFC IFC. But what we understand that shortly, it is going to be approved.
Atul Tiwari
analystBut sir, if those conditions are regarding improvement of P&D losses, then that improvement may not come for a very long time, right? Because we have seen in the sector.
Anil Gautam
executiveThat is -- they are asking the time frame.
Atul Tiwari
analystOkay. So the discount does have to come into a particular time frame by promising and then the money comes?
Anil Gautam
executiveExactly.
Atul Tiwari
analystOkay. Okay. And sir, my last one is on -- if I heard you right during the briefing, it looks like the total coal production in the 9 months is down year-on-year. Is that right? And why would that be, sir?
Anil Gautam
executiveOkay. That coal product, yes, it has come down. That is finance of closure of Pakri mine. There is strike in Pakri for almost, I think, 93 or 96 days. So that is how it has come down, but now it has started. And whatever is lost, we cannot, of course, regain. That is how it is going.
Atul Tiwari
analystOkay. But those issues have been resolved as of now?
Anil Gautam
executiveIt has [indiscernible].
Operator
operatorThe next question is from the line of Aniket Mittal from Motilal Oswal.
Aniket Mittal
analystJust on the renewable front, I understand that 1-gigawatt of projects that you've recently won under competitive bidding. When can we expect the elevating the PPA for the project, sir?
Anil Gautam
executiveWhich 1-gigawatt you are talking about?
Aniket Mittal
analystSir, I'm talking about the 470-megawatt in Rajasthan, 200-megawatt in Gujarat, and 600-megawatt in Andhra Pradesh.
Anil Gautam
executiveYes, 600-megawatt has only happened yesterday. But other than that, this 400 existing has already been signed, I understand. But it is already signed for.
Unknown Executive
executiveNo, no. It is that when the awards will be met.
Anil Gautam
executiveI was thinking, this is already approved, probably is subject to be awarded.
Aniket Mittal
analystSo just to get it clear, the PPAs have been signed for both of them, 470 as well as the 200. And from an execution time line, when do we plan to execute these 2 projects?
Anil Gautam
executiveGenerally, it takes around 15 to 20 months.
Aniket Mittal
analystOkay, sir. So it is decided we would be commissioning around 1.8-gigawatt in FY '22 and then this product should probably come FY '23.
Anil Gautam
executiveRight.
Aniket Mittal
analystSure. And just on a renewal pipeline perspective, I believe you've actually signed certain agreements with Maharashtra and Rajasthan as well to develop solar plant. So if you could just throw some color over here, what is the capacity that we're looking to install and how much of that would be in EPC mode?
Anil Gautam
executiveWell, that will -- it will take time. What the capacity, what we have signed from is Maharashtra is 2.64-gigawatt. And in Gujarat, it is 4.75-gigawatt. But it will take time. It is just at preliminary stage right now.
Aniket Mittal
analystOkay. So maybe I think in Rajasthan, we were actually looking to build some EPC on -- for the north solar park as well, right?
Anil Gautam
executiveYes, yes.
Aniket Mittal
analystOkay. Sir, what would the quantum be? How much of it would be in EPC mode?
Anil Gautam
executiveIt is, I think, 735-megawatt. 735-megawatt will be on EPC mode. For which I think tendering is already under process.
Unknown Executive
executiveNIT issued on 29th of January '21.
Aniket Mittal
analystOkay, sir. So 735.
Anil Gautam
executive735.
Aniket Mittal
analystAnd sir, just to get some clarity over here. Now let's say, again, the 735-megawatt on an EPC mode. How does the tariff for that get determined?
Anil Gautam
executiveThe tariff will depend on at what price I am going to sell it. Only thing I'm doing this in IT, we have kept certain selling price so that it will be within the price at which we'll be able to find a buyer.
Aniket Mittal
analystOkay. Understood, sir. Oh, okay. Okay. So this would be the under implementation, right? I mean this was the 735 -- got that. Got it. And sir, one question, maybe on the thermal side of things. Fixed cost under recoveries have gone up a bit in 9 months as well. And I think because of Kahalgaon. Just wanted to get some understanding on when do we expect the Kahalgaon issue to get resolved? And from an FY '20 perspective, what's the overall fixed cost under the recoveries that we're looking at?
Anil Gautam
executiveMr. Ramesh Babu will address this question, please.
V. Babu
executiveKahalgaon will be -- The dyke will be restored by the end of March and first week of April. And the total under recovery, we are looking at around INR 300 crores to INR 400 crores at the end of the year. And there will be some -- we'll be able to do some of this under recovery in the coming days. And also, we are talking with CRC for the level of high and low demand season. So that talks comes through, we just recoup some of the territory.
Aniket Mittal
analystOkay. What's the impact of the high demand, low demand season on your one recall?
V. Babu
executiveThat would be around INR 80 crores.
Aniket Mittal
analystINR 80 crores. Got that.
Operator
operatorThe next question is from the line of Sumit Kishore from Axis Capital.
Sumit Kishore
analystWhat is the late payment surcharge in December quarter and for the 9-month period, please?
Anil Gautam
executiveYes, this late payment surcharge from customers for the 9 months is INR 1,240 crore and corresponding period previous period it is INR 1,695 crores. Yes, yes, I'm sorry. It is a reverse. April to December '20, INR 1,695 crores, April to December '19 is INR 1,240 crores. Now for the quarter, October to December '20, INR 565 crores. And October to December '19, this is INR 417 crores.
Sumit Kishore
analystOkay. So what is the profit of the hydro subsidiaries, the NEEPCO and THDC for third quarter and 9-month period? If you could also provide the number adjusted for minority? Or we can do that? I mean just the profit for the hydro subsidiaries.
Unknown Executive
executiveYes. If you are talking about NEEPCO and THDC only.
Sumit Kishore
analystYes, yes.
Unknown Executive
executiveNEEPCO, in the 9-month period, this -- just a minute, NEEPCO is a loss of INR 116.60 crores as against previous 9-month profit of INR 132.36 crores. THDC, in the current 9-month, it is a profit of INR 651.13 crores as against 9 months of INR 692.80 crores.
Sumit Kishore
analystOkay. So any specific reason for the loss in the 9-month period for NEEPCO?
Unknown Executive
executiveThey have got one plant where this accident has taken place, one [ GT ] has damaged. So that is under restoration. I think next year, it will be -- we will be again on profits.
Sumit Kishore
analystSo that is a permanent loss that can't be recovered?
Unknown Executive
executiveNo, that can't be.
Sumit Kishore
analystOkay. So when you still -- for -- if you can give me the third quarter NEEPCO and THDC profit numbers also, please?
Unknown Executive
executiveOkay. Quarter, down. So far as NEEPCO is concerned, loss of INR 83.41 crores. And quarter 3 '19, '20, loss of INR 115.17 crores. This is NEEPCO. THDC profit of INR 214.50 crores as against INR 268.72 crores in the corresponding previous quarter.
Sumit Kishore
analystOkay. And sir, just one last question. This RGPPL has become a subsidiary [indiscernible]. What is the dynamics here of the equity shareholding has increased? And what is the update on operations and potential losses from RGPPL going forward?
Unknown Executive
executiveMy -- in RGPPL, we are also going for starting of this equity with Ratnagiri, this GAIL India Limited, whereby my -- I will swap the equity in that KLL and GAIL will swap the equity with RGPPL. After this swapping takes place, my equity holding in Ratnagiri will be around 85%.
Anil Gautam
executive86%.
Unknown Executive
executive86%. And yes, and GAIL will have in Konkan LNG, around 90%. And going forward, we -- this Ratnagiri has signed an agreement with railways. That agreement is well until 31st March '22. And we are also trying that -- because of increase in demand and also, we are hoping that the gas prices will come down. So we think that this plant will get scheduled.
Sumit Kishore
analystSo I mean based on the current status, there would be losses for RGPPL that will now be consolidated to the extent of 86%. And is this part of the commercial capacity that you have given as of December '20, the 62,975, that doesn't include RGPPL, I think.
Unknown Executive
executiveThat includes RGPPL.
Sumit Kishore
analystOh. It's fully consolidated for the -- yes, okay.
Unknown Executive
executiveYes.
Sumit Kishore
analystOkay, sir, I'll get back in the queue.
Operator
operatorThe next question is from the line of Dhruv from HDFC Funds.
Dhruv Muchhal
analystYes. Sir, again, a question on the subsidiaries. Sir, one request before that. Is -- the subsidiaries and JVs are becoming more and more important to you. So probably in the performance result or somewhere in the press releases, if you can mention how these subsidiaries are performing, that would be very helpful in analyzing your numbers.
Unknown Executive
executiveI think this question, we have -- last time also we discussed. Okay, we will do something.
Dhruv Muchhal
analystBasically that you do operational highlights. There also you can mention how the subsidiaries -- at least some of the major subsidiaries and JVs have performed.
Unknown Executive
executiveOkay, okay. Noted.
Dhruv Muchhal
analystSir, on the JV side, I see a decent improvement in quarter-on-quarter basis and also from last year basis. So I believe that was major was an issue earlier. So is that resolved and how are things are? Because a commission, so performance has improved?
Anil Gautam
executiveYes, major issue has been the low growth. This has been declared. Commercial second unit also has been declared commercial with 0 or on 30th -- 31st of December. So it is in operation now. Both the units are in operation.
Dhruv Muchhal
analystOkay. So the path is now about the no materials?
Anil Gautam
executiveYes.
Dhruv Muchhal
analystOkay. And sir, just one bit of confusion on the other income, the NPS charges. Now Q-o-Q, there is a marginal decline in other income. So the more than 645 days receivables have not declined much. So I was just wondering, is there a change in norm of accounting because there were some MOP orders that you cannot book LPS income until -- or you have to book at a lower rate. So is there some confusion there? Or you're looking at 100…
Anil Gautam
executiveThere is no confusion. There is no confusion. We have received a directive or advisory from the Ministry of Power that with respect to the dues, which are being settled through the Atmanirbhar scheme, late payment surcharge will be recognized at a rate of 1% per month instead of 1.5% per month.
Dhruv Muchhal
analystOkay.
Anil Gautam
executiveSo according to that order, we have recognized early time surcharge.
Dhruv Muchhal
analystOkay. So effectively, because most of this amount that you'll recover will be from the Atmanirbhar scheme. So you're effectively recalling this LPs only at 12% now?
Anil Gautam
executive12%.
Dhruv Muchhal
analystOkay. Okay. Got it. And sir, yes, so you also mentioned a bit earlier that you are speaking to CRT or taking CRC for the high demand, low demand period issue. So what is that? I mean are the -- I mean what is the issue there? What is standing there?
Anil Gautam
executiveActually, during this COVID pandemic, some of the units that we have to take for shutdown, the overall duration has extended. And moreover, this high demand, low demand seasons are actually specified for 3 months and 9 months. And due to COVID, we are unable to take some shutdowns. So in…
Operator
operatorThe line from the management has disconnected. Kindly stay on line until I reconnect them. [Technical Difficulty] Ladies and gentlemen, we have the management line reconnected to the call. Thank you, and over to you, sir.
Anil Gautam
executiveNo, you were asking about the high demand, low demand, yes?
Dhruv Muchhal
analystYes. I think I got it because of the COVID. The…
Anil Gautam
executiveYes. Yes.
Dhruv Muchhal
analystSir, just one last bit is -- probably it's still a bit early. So are we reading in press that you have issued a tender for methanol conversion. Is it too early? Or if you can speak something about it, what is the plan here?
Anil Gautam
executiveIt is too early. We have just given an expression of interest there.
Dhruv Muchhal
analystRight. Probably as it develops we'll hear some more from you.
Operator
operatorThe next question is from the line of Swarnim Maheshwari from Edelweiss.
Swarnim Maheshwari
analystSir, if you can just tell us, what is the CWIP ratio currently at the end of 9 months?
Anil Gautam
executiveWhat is that?
Swarnim Maheshwari
analystCWIP ratio.
Anil Gautam
executiveCapital work in progress.
Swarnim Maheshwari
analystYes.
Anil Gautam
executiveCapital working progress at the 9 months is INR 74,000 crores. Out of that total, asset of INR 25,000 crores.
Swarnim Maheshwari
analystSo I believe we see that stand-alone there, right?
Anil Gautam
executiveYes, this is on a stand-alone basis.
Swarnim Maheshwari
analystOkay. Okay. All right. And sir, secondly, also you have already highlighted this, and we are also on the other income. But then there is a sharp 15% increase in the interest cost also. So is it to do with the -- pardon, is this to do with the commercialization of new capacity or why there is such a sharp 15% increase because the other income has not really increased accordingly. And, in fact, on a Q-o-Q basis, there was short [indiscernible] other income. So is there a one-off now with that?
Anil Gautam
executiveNo, no. Other income, you were just discussing when I was answering to Dhruv that other income mainly includes a late payment surcharge. Late payment surcharge, we have received an advisory from the government of India that in respect of dues, which are being settled through Atmanirbhar scheme, the late payment surcharge in those cases will be at -- applied from -- at the rate of 1% instead of 1.5%. So considering that in mind, we have accounted debt payment surcharge at the rate of 12%.
Swarnim Maheshwari
analystYes, sir, I understood that point. My point was, if you look at the breakup of the other income, we have INR 565 crores from the [ LPS ], right? And then there is balance INR 200 crores, so that's for the treasury income?
Anil Gautam
executiveJust a minute, sir. I can give you the breakup of other income for the 9 months. We have [ 1.2 ] dividend around INR 520 crores, INR 525 crores, we have received dividend.
Swarnim Maheshwari
analystSir, if you can give the breakup of Q3 that will be great.
Anil Gautam
executiveOkay. You can obtain this from Aditya Dar subsequently.
Swarnim Maheshwari
analystOkay. Okay.
Operator
operatorThe next question is from the line of Ajinkya Bhat from Macquarie.
Ajinkya Bhat
analystSo just one question. If I look at the budget document, the union budge document, the capital outlook for NTPC has gone up from INR 21,000 crore in FY '21 to INR 22,700 crores for FY '22. If you could just highlight which are the projects on this capital outflow will be spent. So obviously, you have like 1-gigawatt of renewable projects coming up, which I suppose would mature that we might be taking, say, INR 3,500 crores to INR 4,000 crores perhaps. What else would be there which under construction projects? Are any new award planned in FY '22?
Anil Gautam
executiveI'll tell you some of the plants that we are going to commission next year in which this CapEx will be mostly used. One is Darlipalli, unit 2; Barauni, last unit, that is Unit #9; [ Barh ]; Telangana 1 unit out of 2 x 800; North Karanpura 2 units. And in solar, as of date, as already it is 1 on 3, we have considered, but it may go up slightly. Then BRBCL, NPGCL; BRBCL 1 unit, 250-megawatt; NPGCL, 1 unit, 660-megawatt; Rourkela, 250-megawatt; Durgapur, 2 x 20-megawatt total 40, and these are the [indiscernible] we have considered so far for this capital outlay.
Unknown Executive
executiveSo whatever has been taken in the union budget, we are hopeful that we will achieve those numbers.
Ajinkya Bhat
analystOkay. And then no new thermal power plant was planned for FY '22, right? You have any stock pertaining to any land for thermal power projects that we know. Anything else planned in terms of new awards -- new project awards?
Anil Gautam
executiveNo, not right now, no new plants. Only thermal power plants.
Ajinkya Bhat
analystYes. Yes. Understood.
Operator
operatorThe next question is from the line of Rahul Modi from ICICI Securities.
Rahul Modi
analystJust a couple of questions. Sir, I believe the PPS you tender for 5-gigawatt is also underway now. Sir, what is the time line that you are expecting for this bid for the solar?
Anil Gautam
executiveYes. Yes. On the time line for completion of PPS scheme, I believe is end of March, as per information from [indiscernible]. And we'll have to match the time line because they are planning to complete the bid, so since at end of March.
Rahul Modi
analystSure, sir. Just one last question on this. From -- you'd mentioned the number of INR 16,000-odd crores in terms of overdue as in December. So by the end of January, is the overview -- has the overview situation improved from December?
Anil Gautam
executiveYes, just give the January figure. In January, this INR 16,000 crores has come down to INR 15,700 crores. INR 1,000 crores has come down.
Operator
operatorThe next question is from the line of Ankur Deore from Bank of America.
Ankur Deore
analystSir, most of my questions have been answered. Can you just give the figure for TAF APAC based incentives for the quarter?
Anil Gautam
executiveYes. It is, for the 9 months, it is INR 355 crores as against INR 164 crores in the corresponding previous period. And for the quarter it is, current quarter, INR 76 crores versus INR 9 crores -- INR 9 crore.
Operator
operatorThe next question is from the line of Mohit Kumar from DAM Capital.
Mohit Kumar
analystSir, my question -- 2 questions first. Where is the acquisition of Korba West right now? And is there any progress there which you can share?
Anil Gautam
executiveKorba West?
Unknown Executive
executiveAdani.
Anil Gautam
executiveThat is not our…
Mohit Kumar
analystNo, no, no, not Korba West. The other one, which we're acquiring, right, one of them, Avantha Power Plan?
Anil Gautam
executiveYes. Discussions are on with [indiscernible]. And we expect some solution in near term.
Mohit Kumar
analystAnd secondly, on this, sir, what was the impact of Ratnagiri on our profit for the quarter?
Anil Gautam
executiveJust a minute. Yes, for the quarter, it is just -- it is around INR 1 crore profit.
Mohit Kumar
analystINR 1 crore. Okay. Understood.
Operator
operatorThe next question is from the line of Aniket Mittal from Motilal Oswal.
Aniket Mittal
analystSir, just one question to understand if there's been any discussions that you have with DISCOMs. There is a proposal to -- which has come out which said that DISCOMs can relinquish PPAs of over 25 years. So just to understand your view on that and is there some discussion that you had on that?
Chandan Mondol
executiveYes. As far as this PPAs which are beyond 25 years, we have -- primarily Delhi DISCOM, which has raised this issue. And we have already given our reply to them, and we are telling that in our case, all these PPAs are basically on perpetual basis. And this 25 years, what has been being raised, it is basically primarily economic life, not the physical life. And many of our partners, including the DISCOMs, that are much older, I mean that is beyond even 40 years power plants are running. And since we are in a regulated business, as far as our power plant is concerned, so long it is performing and so long it is compliant with the environment, that will. But of course they have taken up, and this matter is now sub-judice in Delhi high court.
Unknown Executive
executiveOnly one case. That is the Delhi.
Chandan Mondol
executiveOnly one, Dadri.
Anil Gautam
executiveIn addition to this I will supplement our Director Commercial, that most of our old plants, their ECR is very, very low. So they are in much demand. Their electricity is in much demand as compared to the new plants where the ECR is very high.
Chandan Mondol
executivePlus we have also argued that they cannot have a -- we can use methodology whereby they will continue to get cheaper cost from Singrauli, Korba and Ramagundam, which are even beyond 30 years old. And they'll relinquish only Dadri. So that is not possible. In case they have to relinquish then they have to relinquish everything. So both -- it has to be only -- what we are arguing is that it has to be only mutually agreed basis, not on-site right will be there.
Aniket Mittal
analystOkay. Okay. Sir, so they think [indiscernible]?
Anil Gautam
executiveYes.
Aniket Mittal
analystOkay. And sir, just -- one question I wanted to ask probably from stretch of 3 to 4 years perspective. If I recollect this correctly, the initial plan actually was in the next 3 or 4 years, I think to retire Singrauli and Talcher, and we would set up a new capacity at Talcher, which will replace the old one. Given the current dynamics, I just wanted some color on that. Are we still going ahead with the retirement of these 2 plants over, let's say, the next few years and a new capacity with Talcher come on board?
Anil Gautam
executiveTalcher, we may award after some time that discussions are on. And so far as Singrauli is concerned, we have not yet decided.
Aniket Mittal
analystOkay. And would the old plant production be retired in Talcher?
Anil Gautam
executiveNo, no, definitely, when the new plant will come, that will be set up at the existing plant location.
Aniket Mittal
analystOkay. Okay. So currently, there are no -- I mean is there a retirement date that we decided for Talcher and Singrauli?
Anil Gautam
executiveNo, no. No such date has been decided.
Operator
operatorThe last question is from the line of Atul Tiwari from Citigroup.
Atul Tiwari
analystAgain, on the RGPPL, sir, how much is the total investment of NTPC both by the way of equity infusion as well as the intercorporate loan that has been advanced to that company so far?
Anil Gautam
executiveIntercorporate loan is around INR 885 crores and equity is around INR 834 -- INR 830 crores.
Atul Tiwari
analystOkay. And now that SPV does not have any external debt. So the only basis is INR 8.85 billion?
Anil Gautam
executiveYes. Yes.
Atul Tiwari
analystOkay. Good.
Operator
operatorLadies and gentlemen, this was the last question for today. I would now like to hand the conference over to Mr. Rahul Modi.
Rahul Modi
analystI would like to thank the entire management of NTPC for the time and having a very thoughtful discussion. Thank you very much, sir.
Anil Gautam
executiveThank you. Thank you, Rahul. Thank you very much.
Operator
operatorThank you. On behalf of ICICI Securities Limited, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.
Anil Gautam
executiveThank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete NTPC Limited transcript — plus 248,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to NTPC Limited earnings transcripts and 248,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.