OceanaGold Corporation (OGC) Earnings Call Transcript & Summary

July 31, 2024

Toronto Stock Exchange CA Materials Metals and Mining earnings 42 min

Earnings Call Speaker Segments

Operator

operator
#1

Hello everyone, and thank you for joining the OceanaGold Corporation Q2 2024 Earnings Conference Call today. <<operator_script>> Please be aware that this session is being recorded on Wednesday, July 31, 2024. At this point, I'll hand things over to Rebecca Henare. Please go ahead.

Rebecca Henare

executive
#2

Good morning, everyone, and welcome to the webcast and conference call covering OceanaGold's results for the second quarter of 2024. I'm Rebecca Henare, and I serve as Director of Investor Relations. Today we have with us Gerard Bond, our President and Chief Executive Officer; Marius van Niekerk, our Chief Financial Officer; David Londono, Chief Operating Officer Americas; and Peter Sharpe, Chief Operating Officer Asia-Pacific. You can access the presentation we'll be referencing during this call through the webcast and on our website. I'd also like to remind everyone that a Q&A session will follow our presentation. Since forward-looking statements will be made during the call, please refer to the cautionary notes included in the presentation, news release and MD&A, as well as the risk factors set out in our annual information form. Every dollar amount discussed on this conference call is in U.S. dollars. I'll now hand the call over to Gerard for his opening remarks.

Gerard Bond

executive
#3

Thanks, Rebecca. Good morning, everyone, and I appreciate you being with us today. The initial pillar of our corporate strategy involves delivering gold production safely and responsibly. Let me begin by openly stating that we fell short of that in this quarter, since one of our Didipio team members, Christopher Magastino, never returned home to his family. Since 2016 this was the sole fatality for OceanaGold, and for Didipio it was the only one since 2012, prior to the start of production there. Everyone at OceanaGold has been deeply shaken by this loss, especially Christopher's friends and colleagues at the Didipio mine, and above all it is hardest on his family and the local community. According to preliminary investigation findings, he fell from a height while carrying out a work related task in the paste plant area. For roughly 24 hours operations were halted so the area could be secured and crews informed. The paste plant where the incident took place stayed closed for approximately one week. We keep striving for a safe workplace at every one of our sites, especially following this tragedy, and we keep rolling out our key safety programs, namely Our Safe Behaviors and Stop and Think. Protecting our workforce remains a vital priority for all of us, and we are making it plain to our people that safe work is the only work we want.

Gerard Bond

executive
#4

We have several additional measures underway or under consideration as part of this endless effort toward zero fatalities and zero life-altering injuries. On the production side, we turned out slightly more than 98,000 ounces in the quarter, and although both Didipio and Waihi had a softer quarter than anticipated, we still expect to meet our 2024 consolidated guidance, with output heavily weighted toward the second half, just as we laid out at the start of the year. During the first six months, we concentrated on waste stripping at our 2 open pit mines, Haile and Macraes, so that we could get at higher grade ore. I'm happy to report that Haile hit ore in Phase 2 of the Ledbetter pit in May, and at Macraes we anticipate reaching ore in Phase 7 of the Innes Mill pit during this current third quarter. Meanwhile, we have been ramping up output at the Horseshoe underground mine at Haile, and this month we hit target production run rates of roughly 2,000 tonnes per day. We generated positive free cash flow in the quarter, helped along by proceeds from the sale of the noncore Blackwater asset. We also successfully finished the initial public offering of OceanaGold Philippines, the subsidiary that holds the Didipio mine, and we listed OceanaGold Philippines on the Philippines Stock Exchange.

Gerard Bond

executive
#5

The money raised from this offering — which isn't part of our free cash flow figure — together with the free cash flow generated this quarter, leaves us in a net cash position as of the close of the second quarter. We're also continuing to make good on the capital allocation framework we laid out at our recent Investor Day, advancing our attractive growth options, maintaining a strong balance sheet and keeping our focus on returning capital to shareholders. We declared our most recent semi-annual dividend of $0.01 per share and introduced a share buyback not long ago. This slide illustrates how we're tracking against our guidance ranges. As we outlined when guidance was set at the beginning of the year, production was anticipated to be roughly 60% weighted to the back half. At the midpoint of guidance, we produced just under 40% in the first half, which reflected weaker production from Didipio and Waihi. That said, we expect a stronger second half that will deliver our consolidated production guidance. Beyond open pit ore sources coming online at Haile, and shortly at Macraes, we expect Didipio to show improvement in the second half too, driven by progressive sequencing of the high-grade breccia stopes and a rise in underground ore tonnes hauled as new mining equipment is added on site.

Gerard Bond

executive
#6

Higher output at Didipio is going to mean more copper as well during the second half of the year. On the cost side, the result we posted in the first half came in above the all-in sustaining cost guidance we set for the full year. The main reason for that is largely the lower ounces we produced during the first half, and we expect unit costs to decline over the rest of the year as output rises. Capital projects are still on schedule for the year, among them open pit stripping and TSF expenditures at Haile and Macraes, continued capital development at the Horseshoe underground at Haile, and the permitting and study costs that continue at WKP. With that, I'll hand the call to Marius, who will walk through our financial highlights for the quarter.

Marius van Niekerk

executive
#7

Thanks, Gerard, and good morning to all of you. In Q2, we brought in $251 million of revenue, supported by record average realized gold prices. All-in sustaining costs for the quarter came in a bit above $2,100 per ounce. That rise was driven primarily by fewer gold sales at every operation, reduced copper credits at Didipio, and greater maintenance spending aimed at boosting reliability at Haile and Didipio. Partly offsetting this were reduced draws on lower grade stockpiles at both Haile and Macraes. Free cash flow for Q2 totaled $31 million, a figure that includes the divestiture of the Blackwater project. Adjusted earnings per share of $0.04 matched the consensus estimates from analysts, while operating cash flow per share was $0.14. Thanks to $100 million in net proceeds from the Didipio IPO plus $30 million from the Blackwater sale, we finished the second quarter in a net cash position of $30 million, consisting mainly of available cash minus $125 million of drawn bank debt. As we laid out at our recent Investor Day, our framework for capital allocation is straightforward. Given a strong balance sheet, we aim to fund our appealing growth opportunities and boost returns to shareholders.

Marius van Niekerk

executive
#8

Consistent with that framework, the Board declared a semi-annual dividend of $0.01 per share, and in July we announced a share buyback program under which we may repurchase as many as 35 million common shares, which works out to roughly 5% of our shares outstanding. We expect a considerably stronger quarterly production profile across the second half, and when combined with the current gold price environment, we anticipate generating strong free cash flow for the remainder of the year. That free cash flow profile, together with our strong balance sheet, positions us to keep generating shareholder value. I'll now hand the call over to David to discuss the Haile operation.

David Londoño

executive
#9

Thank you, Marius, and good morning, everyone. At Haile, safety stays top of mind for all of us, and through our company-wide programs we are dedicated to finding and removing hazards and unsafe behaviors so that every member of our workforce returns home safely. Core production at Haile during the second quarter came in at roughly 38,000 ounces. When the quarter began, the mill pit consisted of a portion, the ground ore and low grade open pit stockpiles. In May, we started accessing ore from Phase 2 of the Ledbetter open pit, which displaced stockpile ore to the mill, and we will keep mining ore from Ledbetter Phase 2 through the rest of 2024 and into early 2025. Now that Phase 2 pre-stripping is finished, pre-stripping will carry on in Ledbetter Phase 3 as part of the mining sequence for 2025 and beyond. Output for the quarter was affected by an 8 day planned maintenance shutdown at the mill, which resulted in lower throughput, and also by open pit ore that was harder than expected in the upper benches of the Ledbetter Phase 2 open pit. We are dealing with this harder ore by stepping up blast fermentation through tighter blast patterns, assessing additional crushing capacity and optimizing the mid blend.

David Londoño

executive
#10

We anticipate costs will decrease during the latter half of the year as output rises. Now, on the exploration side, our drilling was aimed at establishing a possible new resource at the Horseshoe extension, upgrading resources at Horseshoe at depth, while our surface rigs carried on at Ledbetter Phase 4 along with our additional regional targets. I'm happy to report that, as of today, the underground ramp-up at Horseshoe has been finished and we are now mining at the planned production rates. Faster development during the first six months of the year created additional headings and lets us draw from 2 stopes at all times while a third stope is being worked. That pushed underground output to an average of 2,000 tonnes per day beginning at the end of July, consistent with the plan. I take real pride in bringing the Horseshoe underground to full production and doing so on schedule, and together with Ledbetter open pit ore, this puts us in position for a robust second half that meets our 2024 guidance. I'll now hand the call to Peter to talk about Didipio and our New Zealand assets.

Peter Sharpe

executive
#11

Thank you, David, and good morning to everyone. First, I want to repeat what Gerard said earlier about losing our colleague Christopher Magastino and how that loss has affected his family, his friends, and the wider community. Sadly, since Christopher passed away, we have had another serious injury at Didipio: last week a contractor suffered head injuries while trying to clear a metal blockage from a jaw crusher. He remains in critical condition in the hospital, and an investigation into this incident is underway. With 2 serious incidents at Didipio in recent times, our dedication to making sure everyone returns home safely to their families across all our operations is stronger than ever. At Didipio, we are stepping up infield coaching for the Our Safe Behaviors program, and we are also increasing infield verification of critical controls for high risk tasks. At OceanaGold, our people are our most important asset, and nothing matters more than making sure they get home safely at the end of their workday. Operationally, during the quarter, Didipio achieved second quarter gold production of approximately 23,000 ounces and copper production of 2,800 tonnes. Output was lower than in the prior quarter, because the process plant had a number of unplanned maintenance shutdowns that affected throughput.

Peter Sharpe

executive
#12

Underground grades at the mine were lower as well during Q2, which weighed on total output, because of the resequencing and redesign of the high-grade breccia stopes. What that redesign means is smaller stopes, along with some stopes being pushed into the back half of 2024. Even so, the benefit we capture is better recovery and reduced dilution of those high-grade ore tonnes over the medium to longer-term mine schedule. Mined tonnes nonetheless matched the prior quarter, and we anticipate that number rising across the year as we bring on extra working faces and new underground equipment to lift the mining rate. That supports our objective of raising the underground mining rate to 2.5 million tonnes per annum, and it forms part of the pre-feasibility study now underway that remains on track for delivery in early 2025. At present we still expect to hit 2024 guidance, though at the lower end, and we also forecast that costs will decline through the rest of the year as production and gold sales rise. Macraes met the plan in the quarter, producing roughly 27,000 ounces of gold. Ongoing operating excellence at the mill gave us yet another quarter of record throughput. Feed came mainly from low-grade stockpiles while waste stripping carried on in Phase 7 of the Innes Mills open pit.

Peter Sharpe

executive
#13

We anticipate getting to ore in that location during this quarter, and that material will take the place of the stockpiled feed going into the mill for the rest of the year, lifting the head grade. Having access to ore at Innes Mills should support stronger output in the second half and puts us in position to meet our 2024 guidance, with production roughly 55% weighted to the back half, consistent with plan. As part of work to evaluate chances for further mineralization at Macraes that might be economic at today's higher gold prices, we have arranged an extra 6,500 meters of drilling on site aimed at resources beyond the existing life of mine pit shells. Waihi turned out slightly more than 10,000 ounces of gold during the quarter, about matching our Q1 output. We had expected output to rise in Q2, but we kept running into geotechnical problems in the remnant mining areas, which stopped us from establishing crown pillars in certain stopes and led us to mine stopes out of sequence. We have brought in an outside geotech consultant to help review the design and installation methods for establishing crown pillars in those areas, and we hope the result can offer a longer term fix and let us improve our adherence to the stope sequence in the mine plan.

Peter Sharpe

executive
#14

Work on the Waihi north project — WKP included — is still proceeding as planned, and we expect the pre-feasibility study to be finished by the close of this year. In the quarter, we moved diamond drilling forward at WKP, aiming to keep converting resources and to grow the EG Vein, and we look forward to releasing additional results to the market later in this quarter. At this point I'll hand the call back to Gerard for his closing remarks.

Gerard Bond

executive
#15

Thanks, Peter. Our commitment to a safe and sustainable workplace hasn't changed, and through our 2 key safety programs we'll push further review and training so that everyone gets home to their families. For 2024 guidance, we expect to deliver, with production weighted a little more than 60% to the second half, and all-in sustaining costs should come down in line with that higher production. The balance sheet is strong — the company is now in a net cash position — and we're continuing to advance our growth options and honor our commitment to boost shareholder returns through our existing dividend and, now, the share buyback program. We look forward to giving further updates throughout the year on results from our exciting exploration targets across the business, and on delivering the WKP PFS by the end of the year. I'll now hand the call back to the operator and open up the line for any questions.

Operator

operator
#16

<<operator_script>> The initial question comes from Wayne Lam of RBC.

Wayne Lam

analyst
#17

I just wanted to ask about Didipio — could you clarify the stoping redesign there? Has there been a shift in ground conditions that makes it necessary to reevaluate the mining methods or resequence the mine plan at that site? And would that carry any wider implications for a future underground ramp up, should you proceed in order to support the expanded mill capacity?

Gerard Bond

executive
#18

Peter, over to you.

Peter Sharpe

executive
#19

No, Wayne, ground conditions haven't shifted. The difficulty we've encountered while working the breccia stopes is that conditions there are tough. One genuinely positive aspect of Didipio is that we get large stopes — our stopes measure 20 by 20 by 30 meters. Yet because the breccia material is, I'd say, weak in nature, we're discovering that whenever we try to mine bigger stopes within breccia, the shoulders and the roof fail, and recovery from those stopes simply isn't complete. So our plan is to redesign using smaller stopes. That produces a reduced hydraulic radius — meaning a narrower span — which raises the odds the stope stays open, lets us paste fill it cleanly, and in the end gives us more certainty regarding resource recovery. The consequence of smaller stopes is that you won't move as many tonnes as quickly. In the Monzonite area we enjoy that advantage, but within the breccia it simply means the mining cycle runs slower. So our capacity to mine the breccia zone at the earlier rate probably just stretches out across the coming 2 to 3 years.

Peter Sharpe

executive
#20

Looking at it over the long term, it's a benefit. When it comes to ramping up mining, it will be a benefit as well. So all the PFS work we're doing, likely as a result of that — you know, the redesign, that design change got made. So in summary, that's where things stand. You know, even though there's going to be a short-term hit, over the long term it'll be a benefit overall.

Wayne Lam

analyst
#21

All right, thanks. I'm also wondering about that tougher ore you dealt with at Haile during this quarter — did that come out of the Ledbetter pit? What I'm trying to get at is whether the better grades we expect from Phase 2 are going to be partly cancelled out by reduced throughput when we look at the second half of the year.

Gerard Bond

executive
#22

David, over to you.

David Londoño

executive
#23

Correct, the tougher material is in fact originating from Ledbetter 2, up in the upper bench, exactly as we mentioned. We are likewise seeing better grade, which, just as you noted, will compensate for the reduced throughput we are experiencing at present. Yet at the same time, we are trying out some fresh spacing along with drill bit sizes at Ledbetter to ensure we do not sacrifice too much throughput. We are also enhancing and fine-tuning our blend.

Wayne Lam

analyst
#24

All right, thanks — and maybe just one final question from me. On the full-year guidance front, you’ve stayed pretty consistent in communicating that 60% weighting toward H2. That said, the additional commentary before had been that we should expect steady improvement as the year goes on, with Q2 coming in better than Q1 and then more of a ramp into the back half. With some of the operational challenges that came up this quarter, do you still see the cost guidance as achievable, considering the large cost decline you’d need to deliver in the second half to get there?

Gerard Bond

executive
#25

Yes, certainly. I believe that covered 2 questions. First, yes, we do anticipate a stronger second half, with a step-ladder pattern of improvement — Q3 better than Q2 and Q4 stronger still — and we expect to hit our cost guidance. As is typical for most mining companies, a fairly significant portion of our costs is fixed, and the advantage of that higher grade and higher volumes is that it absorbs a lot of those fixed costs. And we continue to believe that by the end of the year our all-in sustaining costs will land inside the guidance range.

Operator

operator
#26

Cosmos Chiu from CIBC has the next question.

Cosmos Chiu

analyst
#27

And perhaps on your guidance too, Gerard — given what you've delivered in the first half, and I take your point that 60% of production will land in the second half — is it now more realistic that you're aiming toward the low end of the production guidance for the year and the high end on cost?

Gerard Bond

executive
#28

No, hitting the bottom of the range isn’t our goal. What we’re aiming for is delivering on the guidance. And as Wayne mentioned right at the outset, we had indicated it would land somewhere near 60-40, and at the close of the first half we sit at 38 point something out of that 40. So we’re slightly behind, and the shortfall comes from weaker-than-anticipated results at 2 sites. Those happen to be our 2 smaller operations, Waihi and Didipio in terms of output, and together they account for a bit more than a 1/3 of what we produce. So the major assets did well — that’s Macraes and Haile — and we anticipate them doing even better. If that trend holds, and without leaning on Macraes at all, I mean, each quarter it keeps posting these outstanding milling rates. Soon we’ll be feeding it ore of a higher grade. Haile, as David and our materials have noted, has good ore in both the open pit and underground. Grade really is king, and that gives us confidence we can meet the guidance. Reaching the low end isn’t what we’re after. Naturally, with 2 assets sitting at the bottom of their guidance ranges, one could argue that creates pressure, but we do take such considerations into account when we set guidance as a whole.

Gerard Bond

executive
#29

Still, our objective stays the same — reaching guidance.

Cosmos Chiu

analyst
#30

The one thing I'd ask is this: when I take your first-half production and divide it by roughly 0.4, I land very near the bottom of the guidance range. So let me put it a different way. My sense is you'll reach, at best, the low end of guidance. But in your own words, we would still be inside guidance.

Gerard Bond

executive
#31

Absolutely.

Cosmos Chiu

analyst
#32

Perhaps one more item regarding those 2 assets that aren't performing, Gerard. As you noted, both Didipio and Waihi have encountered geotechnical problems. It sounds like a fix is in place for Didipio, and results should improve in the second half. What about Waihi? The reason I bring it up is that geotechnical risk is always difficult. Geology technical issues are always difficult. So what does the best case scenario look like for Waihi? And then maybe could you address how much of your ore is actually coming from fresh ore versus remnant ore? And is there a way that maybe just mining from the fresh mining areas would be a potential alternative?

Gerard Bond

executive
#33

Appreciate those questions. Cos, I'll pass things over to Peter.

Peter Sharpe

executive
#34

Cos, how are you doing? So the question about remnant mining in Waihi — the difficulty we face, I mean, the difficulties involved in creating a competent crown pillar in the remnant areas, you know, we really need to put in place a crown pillar that essentially serves as a stable roof above the stopes we intend to mine, so that we can mine the stopes underneath safely, since we do carry out a top-down mining sequence. Now, in the remnant areas, to create a competent crown pillar, we've had to mine out all of the old remnant fill and failed material from before, because, you know, we simply don't know what condition that material is in. So we have to mine it out, and then we have to refill it with competent material, and we fill it with cemented rock fill, CRF. And what we're finding is that in addition to the CRF, we're actually having to install spiling rods drilled in through the CRF. We have to drill them in from the foot wall to the hanging wall, and then we have to grout or resin inject to ultimately create an engineered crown pillar that we can safely mine beneath.

Peter Sharpe

executive
#35

It has been somewhat of a process—not exactly trial and error, but essentially that is what we have carried out. We have come to understand that reaching that stage is necessary, and getting there has required a substantial number of months, keeping in mind that working in wide mine into these remnant areas is new for us. So we are beginning to see now that the design we have is holding up, and that will let us, clearly, do better on our stope sequencing compliance, meaning we will mine the areas we said we would mine. It has meant we simply had to learn what the process is and, I suppose, the mining cycle, so we can have confidence that those ground problems can be safely established. So I think what we have seen is that we have had to effectively learn how to create those safe geotech conditions in order for us to mine. The remnant area matters a great deal to us. I would say that over the last 6 months plus, during which we have not been able to mine the remnant areas, we have been moving into the fresh ore, or the fresh zone, areas. So, you know, we have effectively used up a lot of the inventory we had in the fresh areas.

Peter Sharpe

executive
#36

Ensuring we mine those remnant zones matters. For the remainder of the year, 40% to 50% of our mining will be remnant, and since that material carries higher grade, it counts. Still, the encouraging part is that we now have a design in place. We're beginning to observe that the design and the execution are delivering results, and we are in fact keeping a safe crown pillar. So we definitely anticipate that the second half will outperform the first half. I hope that addresses your question.

Cosmos Chiu

analyst
#37

Thanks, Peter — that's encouraging to hear. Perhaps a final question about your capital expenditure plan for this year: I saw that you made what looks like a swap, since sustaining CapEx used to be $150 million, yet the new guidance now stands at $110 million, while pre-stripping, or stripping, was $110 million and is now $150 million. Given the $86 million you've already put toward stripping year-to-date, that seems reasonable. What I'd like to know, though, is whether this amounts simply to reclassifying the same work, or whether you're actually carrying out more stripping this year than originally planned. And, conversely, will the sustaining CapEx you aren't spending this year show up, say, next year?

Marius van Niekerk

executive
#38

Cos, this is Marius speaking. From a reclassification standpoint, no, it isn't really a reclassification — we aren't pulling any CapEx forward out of next year. What's going on is simply that certain activity is being classified differently, activity tied to stripping that is longer term and tied to growth. Beyond that, looking at the total picture, we still anticipate being consistent with the guidance, and in fact you'd have observed that on a year-to-date basis, we're moving along that path. Every activity we intend to carry out this year is proceeding according to plan.

Cosmos Chiu

analyst
#39

Okay, so if that's the case, then the sustaining CapEx — the guidance for it coming down from $150 million to $110 million — is that $40 million something you'll show up next year, then?

Gerard Bond

executive
#40

That's not the result of stripping out production. So, returning to what you asked before, those campaigns remain on schedule.

Operator

operator
#41

Moving on, we'll take the next question from Ovais Habib of Scotiabank.

Ovais Habib

analyst
#42

Most of what I wanted to ask has already been covered. I have just two or three questions left. On Didipio, I'm picking up on the first question Wayne raised — perhaps I missed part of the responses. To revisit it, when it comes to reaching those higher-grade breccia stopes at Didipio, is Q3 when you'll get into them, or does that push over into Q4? Any detail you could offer on that would be great.

Gerard Bond

executive
#43

Peter, over to you.

Peter Sharpe

executive
#44

We can still reach the breccia stopes, but what the redesign has involved is making those stopes smaller, and the reason we're doing that again is that, from a geotech standpoint, we know smaller stopes give you greater certainty of recovery. We're still getting to the breccia stopes and we're still mining, but because the stopes are smaller, we're less productive and it takes longer, which means the total tonnes you can mine within a given period is lower. So it's almost like a mine — our original mine plan in the first 2 to 3 years. We came in and we mined every high grade stope in the breccia area, which sits up near the top of the mine. What we're seeing now is something of a flattening of that. So we're still mining the whole breccia area, but it's simply going to take us a year or 2 longer than we planned, because obviously that would bring the average mine grade down somewhat over the next couple of years. What we plan to do, obviously, is mine at a much higher mining rate. So we've discussed the underground optimization, taking the mine to 2.5 million tonnes.

Peter Sharpe

executive
#45

Once we reach that rate, the additional total tonnes mined will more than compensate, even with average grade dipping slightly simply because throughput is slower through the breccia zone. So yes, once again, looking further out, we view this as a net positive in reality, since we'll achieve better recovery from the breccia area.

Ovais Habib

analyst
#46

Also, beyond that, you either have brought in extra equipment or you plan to bring in extra equipment. Is that roughly in line with the plan for raising your underground output — you know, increasing production from underground — or is it more a matter of resequencing the stopes?

Peter Sharpe

executive
#47

Yes, certainly. So I believe we mentioned before that although we are in fact carrying out the pre-feasibility study during this year, we are in fact preparing ourselves to ramp up. So we're doing both at once. We have in fact been bringing on additional equipment. And we do anticipate finishing this year at a mining rate of roughly 2 million tonnes per annum. So we intend to mine and in fact raise our mining rate and reach that 2.5 million tonne mining rate as quickly as we possibly can.

Ovais Habib

analyst
#48

All right, great. Let’s turn to Haile next. This might be one for David. Regarding hitting 2,000 tonnes per day from the Horseshoe underground in July, do you expect that level to be sustainable as we move into Q3 and Q4?

David Londoño

executive
#49

Yeah, at the moment we'll have 2 stopes being mined at any one time, with a third one going through the process drilling stage and so on, so for the rest of the year we're expecting to mine 2,000 tonnes per day on average.

Ovais Habib

analyst
#50

And on that point, regarding the second half, is there any kind of color you can give us on the grade profile we ought to be expecting in the second half?

David Londoño

executive
#51

Yeah, Ledbetter 2 has gone up, and we figure that grade will keep rising there as well. As for the underground, the grade coming through matches precisely what our model forecast, so what we're seeing lines up with what we anticipated.

Operator

operator
#52

<<operator_script>> The following question comes from Farooq Hamed with Raymond James.

Farooq Hamed

analyst
#53

I’d like to return to Didipio once more. Clearly, there’s already been plenty of discussion about it. What I’m trying to get at is this: with those smaller stopes in the brecciated zones, how do you expect that to affect costs — specifically the mining costs at Didipio over the next couple of years, while you’re running those smaller stopes? You’ve kept your guidance for the year, but could you say a bit about what impact on mining costs you anticipate from the smaller stopes?

Gerard Bond

executive
#54

Peter, go ahead.

Peter Sharpe

executive
#55

Sure, Farooq. We don’t expect any meaningful effect from that. It should get absorbed as we ramp up to a higher mining rate. Most of our stopes in the Monzonite area measure more than 20 meters by 20 meters by 30 meters, and the breccia zone is really a higher-grade ore body located in the higher lifts of the ore body itself. So we don’t actually mine many tonnes from the breccia in any case. Most of our stopes are mined down to the Monzonite, and those will be kept at the higher productivity levels. There will be some costs tied to the smaller stopes, mainly involving the cycle and the paste fill. Smaller stopes therefore mean you have to build paste fills, then backflow, and then mine another slot. So there will be some, but it won’t have a material effect on overall mining costs. And again, as we see the overall mining rate rise, all of that will be absorbed. So we actually expect the mining unit rate to come down over time.

Farooq Hamed

analyst
#56

All right, that's fine. And maybe just to follow up on the new equipment you've brought in underground at Didipio — does that equipment raise any concern regarding sizing when it comes to potentially having those smaller stopes? Is it still suitably sized for your redesign, more or less?

Gerard Bond

executive
#57

Yes, that's right. The draw point itself won't be moving. So it's really the stope's shape, rather than the size of the loader that works it. We're going from a 20 by 20 to 30 down to a 20 or a 15 by 5. The aim here is to shrink the span left open at any given moment, since, again, in this weaker monzonite material, we're observing failures in the shoulders and the backs, or the roof. We simply want to ensure we don't have such a large opening at one time. After that we'll backfill with paste, then move on to the next stope alongside. As for the equipment itself, none of it will be affected in any way.

Farooq Hamed

analyst
#58

All right, that's helpful. And perhaps one final point on Didipio. You mentioned the redesign, but you also brought up resequencing. Could you say a bit about what that resequencing involved and the reason it became necessary?

Gerard Bond

executive
#59

Yeah, it really comes down to what I mentioned before: since the stope is smaller, the mining cycle itself makes productivity slower. In any given period, you simply can't extract as many tonnes. So what this does is—instead of likely mining everything in the first 2 to 3 years, with all the breccia high grades depleted in 2 to 3 years—it adds another year or 2 to the overall profile. So you're spreading it out across those 2 to 3 years, but pushing it into year 3 and year 4. All that means is it's not that we're unable to mine certain areas because the stope is smaller; it just means the cycle time runs a bit longer, which means you simply can't mine as many tonnes in a given period.

Farooq Hamed

analyst
#60

Maybe we can go to Haile next. David, on the underground side, you mentioned getting to that 2,000 tonnes per day steady state in July by running 2 stopes simultaneously. And it sounds like a third one is on standby or ready to go as you switch out. Could you talk a bit about your forward development? How far ahead is your development relative to your current mining rate, or where your mining is right now?

David Londoño

executive
#61

Yeah, the mining is taking place at the 950 and 975 levels. Meanwhile, the development decline sits down at the 900. We've already gone past the 900, which puts us 50 meters ahead. So development is in very good shape. That means we're ahead of the mining by almost 12 months.

Farooq Hamed

analyst
#62

All right, that's fine. So perhaps one final question from me: clearly, per your guidance, 60% to 65% of 2024 production at Haile should come in the second half, and obviously that will be crucial to meeting your full-year guidance. We're 1 month into the third quarter, you're accessing from Ledbetter, and now you've ramped up at underground. So the question is just this: what have you seen so far in the third quarter? What you're mining, what you're milling, and what you're recovering — is all of that in line with your plan so far in the third quarter?

Gerard Bond

executive
#63

Yes, Farooq, we will provide updates on the quarter at the close of each quarter. That's largely consistent with the plan, but I don't want to fall into the habit of giving updates partway through a quarter, 1 month in. So, broadly speaking, we're comfortable with it, though I don't want to be pinned down on specifics.

Operator

operator
#64

Thank you. And right now, it looks like there are no more questions. Please go ahead.

Gerard Bond

executive
#65

Alright, thanks to all of you. That brings the call to a close. A replay is going to be posted on our website later today. On behalf of the management team and all of us at OceanaGold, we appreciate your participation and hope the remainder of your day goes very well. Thank you.

Operator

operator
#66

Appreciate that, sir. Everyone, that brings today's conference call to a close. Thanks again for joining us. At this point, we ask that you kindly disconnect your lines.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete OceanaGold Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to OceanaGold Corporation earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in OceanaGold Corporation or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.