OM Holdings Limited (OMH) Earnings Call Transcript & Summary

February 3, 2025

Australian Securities Exchange AU Materials Metals and Mining earnings 23 min

Earnings Call Speaker Segments

Jenny Voon

executive
#1

Good morning, everyone, and thanks for joining OM Holdings' webinar this morning. I'm Jenny from the IR Department at OM Holdings. Ritchie is here with me, and the two of us will be hosting today's webinar. OM Holdings is a magnesium silicon smelting company with vertical exposure in mining and trading, and it just released its December 2024 quarterly production and market update last Tuesday. I'm delighted today to have OMH's Managing Director, Adrian Low, with us; he will run through the key points, followed by a Q&A session. If we can't answer your question, we'll try to address the query after the webinar. So without any further ado, I'm pleased to hand over to Adrian. Adrian, over to you.

Ngee Tong Low

executive
#2

Thanks, Jenny. And thank you to all of you for joining our webinar this morning. I think we're wrapping up 2024, and here we are already in February. So we'll be publishing our full year 2024 results very soon. So any questions about the full year will, unfortunately, obviously have to wait until those results come out. So I'd appreciate it if today all the questions stayed within the area of operational details, so to speak. So in 2024, I think we finished the fourth quarter more or less as planned. So if you look at what we published in our announcement, and indeed, at the numbers, you'll see that we ended 2024 above the top end of the guidance by 3%. So I think that matters for 2 reasons. First, I think we're on track with how we forecast production. And second, something that's perhaps not very visible to analysts and shareholders is the effect that an additional ton of production has on fixed costs. Because the furnace -- because the smelter complex is built for 16 furnaces, this affects the unit cost of production.

Ngee Tong Low

executive
#3

Regarding silicon metal output, we did get that furnace commissioned. Some of you who hold shares may remember that our initial conversion of the furnaces to silicon metal ran into a commissioning problem. In 2024, though, we succeeded in commissioning the silicon metal furnaces. Having said that, given market prices and the wider pricing patterns for silicon metal compared with ferrosilicon, we decided to return those furnaces to ferrosilicon production, since the per furnace day utility comes out higher when making ferrosilicon. I believe some shareholders have already brought this up in one way or another. That is the answer. Producing ferrosilicon today is more sensible and more commercially sound, and at the same time, the company remains ready to change production according to what the broader trends turn out to be. Okay. On sustainability, OM Sarawak received the Champion award for the prestigious Diamond Award in the Large Enterprise category. It was a competition run locally in Sarawak, and our submission described the circularity of how byproducts and waste are handled within OM Sarawak. So obviously, that covers selling ferrosilicon fumes and micro silica, plus how we repurpose and reuse slag, correct?

Ngee Tong Low

executive
#4

That covers ferrosilicon slag and high-purity manganese slag, both of which we use in production, plus the silicomanganese slag we sell to local enterprises. For that work, we received the champion award. On financing, I've likely mentioned this across several quarters now, but during Q4 we paid back $2.4 million to project finance lenders. This has been underway for some time. Last year we noted that we'd be pursuing alternatives and examining what the optimal capital structure for the company looks like. That effort is ongoing. Shareholders should expect something within this calendar year. Okay. On production volumes, our guidance for 2025 is visible. These figures come from the plants involved in better production for FY 2025. The numbers are as shown below: 170,000 to 190,000 tonnes for ferrosilicon and 270,000 to 300,000 tonnes for manganese alloys. To caveat again, this depends on product mix, and we do change that through the year, but we have marginally lowered guidance based on looking at the maintenance plan of ourselves and also this year of Sarawak Energy, our main energy supplier.

Ngee Tong Low

executive
#5

I think the details speak largely for themselves. On the mining side, the mine really is still under care and maintenance. Restarting mining is not the intention. As for UFP, all the installation work is complete. The optimization work has been finished. A trial production run has been completed, and it went relatively well. We're running a second trial in quarter 1 this year. The purpose there is, in a sense, to establish the parameters for how we select yield and to try to optimize what manganese content we should be targeting. So once that's finished, I think you'll be in a position to restart commercial operations at the mine. On smelting, nothing significant has changed. 14 out of 16 furnaces have finished major maintenance, and that has been the situation for a long time. We have deferred the 2 ferrosilicon furnaces mainly because they're running well, so there isn't really a reason to accelerate the major maintenance, and there's no reason to spend the CapEx before it needs to be spent. That said, I think in 2025, we expect to put those furnaces through major maintenance. Okay. So that's it for production guidance.

Ngee Tong Low

executive
#6

When it comes to the markets—the next 2 slides are where I usually cover developments in ferrosilicon and manganese alloys. As for ferrosilicon, if you review what took place during 2024, I have to say it wasn't particularly thrilling. Prices have been trending downward steadily for a couple of years at this point. You'll see a bit of a blip in the second half of last year, and I think that reflects a gradual response to reduced ferrosilicon supply coming from places such as Russia. That gain then gets somewhat eroded toward the end of last year as markets fell, driven I believe mainly by pressure in China and also across the rest of the world. Over the long run, I'd say ferrosilicon demand and supply are roughly in balance. We've essentially found our place in global markets, and that means there won't be needless price wars or buying your way into markets, that kind of thing. So I think we're convinced that OM Sarawak, today versus pre-COVID, sits in a structurally much stronger position, simply by looking at the power tariff differential between what we enjoy in Sarawak and in China.

Ngee Tong Low

executive
#7

Russia is still facing significant cuts, so I won’t go into speculation about that, though that differential does exist as well. Moving to silicomanganese on the following slide, 2024 was considerably more eventful for manganese alloys. From Q1 of last year, the force majeure at South32 caused ore prices to surge—I believe by 4x—which pushed silicomanganese prices, shown by the blue line, up by 20% to 30%. After that, both fell very sharply, ending the year at a substantially lower level. So 2024, in my view, was a year of whipsaw and overreaction on both the upside and the downside. Looking ahead from Q1, I think we’ll see these prices normalize. That means manganese ore prices are near $4 today; the December closing price was $4.08. For Q1, we anticipate an increase to between $4 and $5 per dmtu. As for silicomanganese, which closed at $885 at the end of December, that should normalize into a range of $900 to $1,000. These, I’d say, are fairly normal price ranges for manganese, and they move together—except during ’21 and 2022 with COVID—typically, the monthly correlation between these two prices should be around 80% to 90%.

Ngee Tong Low

executive
#8

That's what we're anticipating. And given these typical patterns, OM Sarawak's profitability has remained extremely steady inside those ranges. That's everything we have to share today. I believe there are a few questions, so let's leave more time for the Q&A.

Jenny Voon

executive
#9

Okay, thanks a lot, Adrian, for that presentation. Now we’ll go on to the Q&A session with the questions we’ve received. The first one concerns the Ultra Fines Plant at our Bootu Creek mine. Could you give us some insight into why the upgrade of the UFP has taken so long? And why it has taken close to 5 years, mainly?

Ngee Tong Low

executive
#10

Okay, so first off, I don't think it's actually been 5 years. Whoever posed that question is probably looking at where things stand today versus when the UFP was launched. Obviously, the reason we needed this rectification comes down to the fact that screening efficiency at the time the UFP plant was commissioned wasn't optimal. The screens weren't performing well — they were scrubbing out mud and all the other material that had gone into the tailings dam. When it was commissioned in 2020, that was obviously during peak COVID. And the rectification exercise — working out what should be done and what could be done — took a long time, right? The actual full commercial reassessment was really done kind of post — or around the same time as mine closure. So 2021, 2022. And from that point, I think the Board only gave its blessings to proceed at the end of 2023. So from then on, the time it takes to — and then the screens have been sort of redesigned and install them and go into sort of trial production took about 9 months, I think, so most of 2024, and we were in place to restart towards the end of last year.

Ngee Tong Low

executive
#11

And really, I think at this moment, during Q1 2025, a second trial is underway. So when you view that against the broader picture, there are explanations for the different holdups in this process, and that said, I believe the UFP is genuinely complementary when it comes to the group's economics and profitability, as well as its cash generation. It may not be the primary project we ought to be pushing and speeding up without cause. So that is partly why it has required the length of time that it has. So we want to bring the plant back online at the proper moment, in the proper location, with the proper economics.

Jenny Voon

executive
#12

Appreciate that, Adrian. Let's go to the second question. This one has 3 parts. The first part asks if you can give us some general commentary on how our past projects have been executed. I imagine that mostly centers on furnace conversions as well as the major maintenance work. The second part of the question is really about what the industry standard is for maintenance, and why it appears to take close to 0.5 year for each furnace. The third part was actually covered in your earlier first question, and it has to do with the UFP. So perhaps we start by tackling the first part, giving some general comments on the past projects.

Ngee Tong Low

executive
#13

Yeah, absolutely. So when it comes to Sarawak, that's essentially the conversion project. And I'd also like to remind shareholders that we began the Sarawak project with 16 ferrosilicon furnaces back in 2014. That was the package agreed upon with project finance lenders, in consultation with them at the time. Obviously, by 2016 that wasn't ideal. At the end of 2016, we had converted 6 of those furnaces to manganese alloys — what we now call Plant A. Those were commissioned in sequence during 2017. So that represented the first big chunk of the conversion work. After that, I think we carried out another tranche of conversions. Of the 10 ferrosilicon furnaces remaining, we decided the optimal balance was 6 ferrosilicon furnaces. So 2 of them were switched to metallic silicon and 2 were switched to manganese alloys. That happened over the last couple of years. Part of it was delayed by COVID. But as of last year, the manganese alloys furnaces were commissioned very, very smoothly. Really bread and butter. It's also not a very complex product, and not a complex conversion process.

Ngee Tong Low

executive
#14

As most shareholders are aware, though, switching over to metallic silicon required some time. The actual conversion wasn’t especially prolonged, yet the commissioning work, the shift of output to ferrosilicon, and then last year’s decommissioning consumed a fair amount of time. So I believe that really comes down to the technical distinctions between metallic silicon and ferrosilicon. In a sense, ferrosilicon is the simpler product to make. It contains just 75% SI, with 25% iron. Iron melts at a very, very low temperature. Running the furnace is quite easy, while metallic silicon is far more difficult to operate since it is 99% SI. Tolerances for error are much tighter, and you lack the advantage of circulating iron to enhance furnace conditions. Having said that, perhaps I could just walk through the economics of metallic silicon. As I see it, China clearly has established a surplus in silicon capacity at present. That extends all the way upstream from metallic silicon output through to the furthest downstream, down to solar, correct? So I think, in that sense, metallic silicon’s economics will hinge heavily on geopolitics. And it goes without saying, I think, that everyone at the company, along with most shareholders, I would imagine, will be watching the tariffs and the sort of tit-for-tat duties that are going to arise in the days and months ahead.

Ngee Tong Low

executive
#15

So there may be room, right, for metallic silicon sourced outside China, though at present that remains a quite narrow niche—very small indeed. And my view is that making ferrosilicon today is considerably more profitable and considerably more economical. That, I believe, addresses the first portion of your question, Jenny. Apologies—what was the second part again, if you wouldn't mind reminding me.

Jenny Voon

executive
#16

The next part concerns the major maintenance piece. So the question asks: what is the industry standard for maintenance? And why does it appear to require nearly half a year for each furnace?

Ngee Tong Low

executive
#17

All right. I'd say the industry norm is quite near what we're delivering, roughly 2 months for each furnace. So it has never been 0.5 year, in my view. Most of those furnaces, I believe, we completed across a 12 to 18 months span. So if you go back through the announcements, it ought to come out at somewhere between 2 to 3 months per furnace.

Jenny Voon

executive
#18

Right, thanks. And the third question actually concerned UFP, but I believe you already covered that in your first question, on the screen fee distribution side and where some optimization work is underway. All right, we'll move to the final question. This one has to do with how the company is valued. I think we've gotten very few questions of that kind, and it concerns the company's valuation. How does OM Holdings actually intend to turn this valuation around?

Ngee Tong Low

executive
#19

Yes, correct. So, yes, clearly, we've had comparable inquiries at different points in time. And I think the overall trajectory genuinely hasn't shifted, correct? Management's focus is on building up our assets and producing cash from them. Since COVID, we've brought in more than $400 million of operating cash flow. That has been put to use in various ways. I mean, the biggest single item was buying the minority stake in OM Sarawak. That was, I think, around 2021 and 2022. We've put substantial work into sustainability, into getting the product basket right, and into how sales markets are distributed. So that's where management's attention has been. And I should also bring up what we're doing on the debt side, which I touched on earlier. So I think we've followed through on that, and we've shown we can hold up even when market conditions are depressed. So we're fairly nimble while also running things in a very, very firm and steady way. So while all of that holds, I think I wouldn't dispute that there's a problem with valuation, obviously. And this really — I think we've devoted the last 2 years to talking with plenty of investors, plenty of buy-side funds, plenty of brokers, and I think what we've concluded is that this mostly really comes down to the fact that liquidity is low.

Ngee Tong Low

executive
#20

Like many shareholders who could be on this call, I believe the great majority of investors checking the registrar have been through a fair number of cycles alongside us. And they, just like all of you, clearly recognize that the company is undervalued. How far that goes is genuinely not something we should be disclosing. But I think the upshot is that, similar to plenty of our shareholders who may be dialing in, they don't feel much like selling. So as time passes, ironically, that shrinks the free float. And I think we have witnessed that ever since we listed on Bursa, since in fact the free float has gone down from that point, because other sorts of convinced shareholders have arrived. And so, very ironically and oddly, the situation genuinely mirrors conviction in the company, yet you don't see it showing up in the valuation, because the free float keeps shrinking. So I think what truly has to happen goes past items such as the dividend policy and enhancing the news flow, or I think what has to happen is a sort of structural rethink of how the corporate structure ought to look. And I think this is going to be a priority for management as well as the Board, engaging with the Board in 2025 and 2026.

Ngee Tong Low

executive
#21

You can be sure this is a real priority for us. Our hope is that we can put forward something resembling a plan across 2025 and 2026 — those 2 years. So regrettably, that's likely everything I'm able to share right now, and I look forward to sharing more once we get to some kind of concept.

Jenny Voon

executive
#22

Okay. Appreciate you passing that along, Adrian. That seems to address most of what our audience asked today. Should anything else come up, please send it to investor.relations@ommaterials.com. A recording of this webinar will be posted on our LinkedIn profile over the next few days. That brings today's webinar to a close. Thanks to all of you for joining. And Adrian, thank you for the thorough update.

Ngee Tong Low

executive
#23

Thanks to all of you for joining the call. Have a good day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete OM Holdings Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to OM Holdings Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in OM Holdings Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.