Orezone Gold Corporation (ORE) Earnings Call Transcript & Summary

March 20, 2025

Toronto Stock Exchange CA Materials Metals and Mining earnings 20 min

Earnings Call Speaker Segments

Operator

operator
#1

Hello, everyone, and welcome to Orezone 2024 Year End Results and 2025 Guidance Webcast and Conference Call. Please note that this call is being recorded. [Operator Instructions] Thank you. I'd now like to hand the call over to Patrick Downey, President and CEO. You may now begin.

Patrick Downey

executive
#2

Thank you, and welcome everybody to the Orezone Q4 and year-end 2024 results and 2025 guidance webcast and conference call. While 2024 was another very, very solid year for the company, very strong results. We had record revenue, record EBITDA, record earnings per share and record net income, which I'm very pleased to state today. Gold production in the quarter was 36,502 ounces, which was a 37% increase quarter-over-quarter. We did expect a very strong Q4, and we realized that. Full year 118,746 ounces, which exceeded the midpoint of guidance of 110,000 ounces to 125,000 ounces. Our gold sales in the quarter were 34,833 ounces at an average realized price of $2,632 per ounce, which resulted in $91.8 million in revenue. On our full year sales were 118,697 ounces at an average realized price of $2,384 which resulted in record revenue of $283.5 million. All-in sustaining costs for the quarter, very, very solid in Q4 were $1,273 and for the full year were $1,447 which were within revised guidance, which was affected by obviously the gold price, which increased the royalties and the regional power issues, which were outside of our control. If those had not occurred, we actually would have been inside our actual guidance for the year, which is another very solid year. As I stated, record net income in the quarter was $30.1 million, and for the full year was $55.7 million attributable to Orezone's shareholders. And we ended in -- the year in a very, very strong financial position, cash of $74 million, senior debt of $67.3 million and available liquidity of $103.2 million. And very importantly, for the second year in a row, we have had 0 LTIs which is very much attributable to the team on site. We had 1.33 million hours worked during the quarter and 5.37 million hours worked in 2024, and we've now got over 19 million hours worked LTI-free, which is really and truly world-class. I'll now hand over to Peter Tam, Chief Financial Officer, to go through the financial and operating highlights.

Peter Tam

executive
#3

All right. Thanks, Patrick. For 2024, as stated earlier, Orezone reported record revenue, net income and earnings per share helped by an impressive fourth quarter. Gold production of 36,502 ounces in Q4 was driven by improved head grades and record mill throughput further fueled by record gold prices, resulting in quarterly net income attributable to Orezone shareholders of $30.1 million, adjusted earnings per share of $0.06. For the full year 2024, net income attributable to Orezone shareholders was $55.7 million and adjusted earnings per share was $0.11. Gold sales were 118,697 ounces at an average realized price of $2,384 per ounce, with all-in sustaining costs per ounce of $1,447. This resulted in a healthy all-in sustaining cost margin of $937 per ounce. In terms of growth, we commenced construction of the Phase 2 hard rock expansion in the second half of 2024 after securing over $105 million in new debt and equity. On debt, we upsized our senior secured loan facility with Coris Bank, our trusted partner by another $58 million under a new Phase 2 term loan. A first drawdown of this loan was made in late December. Liquidity at December 31, 2024, stood at $103.2 million, with $74 million in cash and over $29 million in undrawn debt. With this liquidity, Stage 1 construction of the hard rock expansion is comfortably financed to commissioning and first gold expected later this year. Finally, gold has continued its assets with spot prices now above $3,000 per ounce, which will benefit Orezone greatly as our gold production remains fully unhedged to rising gold prices. Next slide. On production and unit cost for mining, mine tonnes were [ 4.7 million ] in Q4 of 2024, a decline of 20% from the same quarter in 2023, as Q4 of 2023 benefited from temporary utilization of a second mining contractor. Mining rates did improve in the last 2 months of 2024 once additional new excavators and dump trucks were placed into service by the mining contractor with mining rates in 2025 now hitting 2 million tonnes per month. Plant throughput hit a new quarterly record in Q4 of 2024 at 1.65 million tonnes processed, a remarkable achievement when compared to plant design of 1.3 million tonnes. Plant throughput was aided by a softer blend of oxide ore in the mill feed as mining progressed into the southern pits at Siga East and Siga South, stable grid availability and no major client maintenance. Processing costs per tonne saw a sharp drop in the current quarter when compared to the same quarter in 2023. This drop was attributable to the record plant throughput and improved power cost as grid utilization was high at 92% and per tonne power consumption was lower due to the softer nature of the mill feed. With that, I'll hand it back to Patrick.

Patrick Downey

executive
#4

Thanks, Peter. So I'll now go through 2025 production and cost guidance. Our gold production guidance will be between 115,000 to 130,000 ounces. It's very similar to 2024, slightly more on the upside on the higher end. All-in sustaining costs, a gain between $1,400 to $1,500. We expect to hold that. Sustaining CapEx of $9 million to $10 million and growth capital of $44 million to $51 million, which I'll go through in a little later here, and our Stage 1 hard rock expansion capital of $75 million to $80 million. Our gold production, like every other year that we've been operating in the oxides will be weighted towards Q1 and Q4, generally due to seasonality and mine sequencing, and we expect another strong Q4 in 2025. We also are investing in the future. We are connected to the grid, but we expect that the availability [ will be ] between 90% to 92% going forward. So we are purchasing a fully installed diesel power plant, which will replace the rental equipment that we currently have and will allow us that 100% availability on the power, which is similar to what the other companies are doing in the region. Our tailings footprint expansion is really a onetime this year. We're doing -- spending $11 million to $13 million. But I want to point out that is for the full construction of the life of mine footprint, which includes Stage 1 and Stage 2 of the hard rock. So we're investing that capital this year that will allow us to go fully forward on the expansion of the hard rock and contain the oxides as well. Our Resettlement Action Plan, which is really villages and infrastructure, and housing will be $11 million to $14 million. We have one more to do after this. So this is our second last one, so we're almost finished on the RAP. They've all gone very smoothly. I've got to say and gone very well. And this will allow us to access into the high-grade P17 area by the end of the year. So production forecast and ramp-up. This is a very important point to make. I've talked about our guidance. We are now well ahead on Stage 1 hard rock that will allow us to exit 2025 at a run rate of 170,000 to 180,000 a year into 2026. We are now looking at bringing the Stage 2 hard rock forward. We were originally planning to do that in 2028 with a start-up in 2029. We are now in an active process of pulling that forward and constructing it in 2026. So we would exit 2027 -- sorry, 2026 at a run rate of 220,000 to 250,000 ounces a year. At current coal prices, that really makes sense for us. We've just done a recent raise, which will allow us to look at that, and we do make a decision to accelerate that forward in the second half of this year. So we're quite excited about that. So where are we at with the Stage 1? Just a reminder, the oxides in the background, which is operating, we're building Stage 1 in the foreground. The jaw crusher will be for the full [ 5 million ], so no changes there. Putting in a SAG mill with 5 tanks and an ore reclaim system and some minor modifications to the gold recovery circuit. Concrete started 3 months ahead of schedule and has remained ahead of schedule. The engineering is ahead of schedule and bulk quantities and all of the equipment are in line with budget and mostly have been ordered. The SAG mill components arrived on site last week, as did all of the tank plate work. And the CIL tank construction [ erection ] will start in end of March -- will likely start beginning of next week. And as I stated, the TSF expansion is underway. At the current schedule, this will allow us to ramp up in Q4, and we'll exit Q4 into 2026 at the run rate of 170,000 to 180,000. Quick photographs to show what it looks like, and we will be putting out videos every month, starting probably in April. In the background, you can see the oxide plant and the tailings Cell 1 that will -- the expansion that we're doing will wrap fully around that, which will be for the full Stage 1, Stage 2 hard rock and the oxide. In the foreground is the oxide plant. You can see plenty of room, plenty of space. We do design our plants so they can run effectively, which has been very much shown in the oxide, which is designed for [ 5.2 ] and it's running at over [ 6 ]. Photograph 2 there is the dump pocket and the jaw crusher. We're just about to shutter those walls and start pouring those walls next week. CIL tanks are finished, all concrete done, and we'll be laying out and erecting the tanks beginning next week. That contractor is fully mobilized on to site. Photograph 4 is the ball mill raft, which is a fairly large foundation poured into the ground -- sorry, the SAG mill raft and then we're pouring -- shuttering the peers right now, and we'll be pouring the peers sometime in April. And you can see in photograph 5, the SAG mill components have all now arrived on site. So all going very well. All managed by us, by the way, it's our team doing all of this work. So how do we get the 5 million tonnes per annum? It again is another brownfield expansion. We expect it will cost between $90 million to $95 million. We're updating that estimate right now. We're updating our detailed engineering with our engineer Lycopodium. And we expect to have that done in the next month or so. It will be 4 extra tanks, an oxygen plant, a ball mill, which we've already identified, a thickener and water infrastructure and a pebble crusher. We expect to go to the board to ask for that decision to go forward in late in Q2 and then we would get into that work and start ordering equipment later on this year. It's about a 12-month construction. We're fairly confident of that. Obviously, we've got real live costing in terms of all components. So we're fairly confident of what we can do here, and the planned accelerated ramp-up would have us completion in Q4 and exiting 2026 at a run rate of around 230,000 to 250,000 ounces a year. So very exciting going forward. I hope to be able to announce that later in Q2 of this year. So in summary, 2025 is really a transformational year for Orezone. We're running the oxide plant very successfully, met guidance 2 years in a row now, sort of last full year this year of oxide only. We are in the stages of completion of the hard rock expansion and that will bring our overall head grade up production to around [ 170 ], [ 180 ] and will also reduce all-in sustaining costs going forward. So as you see this year, the $1,400 to $1,500 will come down in 2026. The -- it will also provide increased operational flexibility. The one thing we're doing here is the oxide plant can run completely independently of the hard rock. So it gives us great operational flexibility. We've also commenced a renewed exploration focus. We started that in Q4 of 2024. We've put out some results already. Just a reminder, we've got 2.4 million ounces of mineral reserve at a $1,500 gold price with an average pit depth of less than 40 meters. So very, very shallow. It supports the full ramp-up of [ 220 ] to [ 250 ]. So anything above that really is additional to that. So the current drilling, we started in the north had very positive results. We went down 200 meters below the reserve pit, and we continue to intercept grades of very thick widths of 1.64 over 46 meters. We're now down in the south, which is a high-grade P16, P17 areas. We've got 2 rigs down there right now. We're looking to planning to bring a third. And we're expecting to release results from P16 and P17 in the near future and that will also start to show the underground potential of Bomboré, which again, we're very excited about. We did announce that we're looking at an Australian secondary listing that is advancing fairly rapidly. We expect that, that will give us increased trading liquidity, and we've seen that already with that announcement, access to new investors, which we've already done. We raised $40 million recently in a very, very strong financing. It was very much oversubscribed. And several largest trading funds participated in that and that will allow us to accelerate Stage 2 here in terms of making that decision on when we do Stage 2 in 2026. So that's it, a very strong year, a record year, very pleased to announce that and a very exciting year in 2025. Thank you. I'll hand it back to the operator.

Operator

operator
#5

[Operator Instructions] Your first question comes from the line of Angelina Guo from Canaccord Genuity.

Angelina Guo

analyst
#6

Congratulations on the quarter. I have 2 questions on the 2025 CapEx guidance provided. First, in terms of the total CapEx for Stage 1. It increased by about 16% to $93 million if we take the midpoint of the 2025 guidance and also factor in what was already spent in 2024. I just want to know what's driving the increase for the Stage 1 CapEx? And could you also provide a bit more color on the other growth CapEx items?

Patrick Downey

executive
#7

Yes. A bit of that is some contingency we've added in there, and we're also doing a little bit more work on preparing for the Stage 2. So we've added a little bit more capital in there. And we've also got more pricing and where we're at. And we've accelerated some of our equipment deliveries. So we want to make sure that we've got things in place for the Q4 start-up. That's really it. On the growth capital, it's really $20 million to $25 million on that power plant. We weren't initially going to do that. We're actually going to continue to rent at one point, which we wouldn't have that capital. But when we looked at that, we decided that it was much better for us to buy that equipment and own it. And we would operate it. We have full control of it then. And it's for the oxide and the hard rock. So it's the decision that we made. We looked at what other companies were doing in the region. I've seen Kiaka are now doing exactly the same thing, and they will be on the grid. So it really was that opportunity to do that. We have the money to do it, so we decided to do it. On the footprint, TSF, we have about $11 million to $13 million, and that's really around the doing the TSF for both the Stage 1 and Stage 2. We could have done a smaller footprint there, but essentially doing a large footprint gives us that optionality that if we do the Stage 2 in 2026, that TSF is there and ready to accept the full 5 million tonnes from the hard lock and the 6 million tonnes from the oxide going forward. That's essentially it.

Angelina Guo

analyst
#8

Okay. That's really helpful. And my second question is when should we expect the 2025 CapEx estimate for Stage 2 as it's on track to start later this year?

Patrick Downey

executive
#9

We're working on it right now. We've actually engaged the engineers on that. They're doing the -- what we call the FEED, the front-end engineering and design. So we know what the -- obviously, a lot of the components are. We will -- we're looking at 3 ball mill options that we would expect to have an answer on here in the coming weeks. Once that's done, we will have our very, very tight estimate of that to go to the Board. I expect that will happen later in Q2 and we'll have an answer and a news to the market probably later in Q2 -- end of Q2.

Operator

operator
#10

[Operator Instructions] Your next question comes from the line of Alan -- my apologies. [Operator Instructions] As of right now, since we don't have any pending questions, I'd now like to hand the call back over to Patrick. Thank you.

Patrick Downey

executive
#11

Okay. Good. Thanks. As I said, very, very good 2024, a record year, 2025 transformational. Really looking forward to getting Stage 1 of the hard rock started up and then making a decision on Stage 2. But more importantly, as well as the exploration that we have coming forward results throughout the year. So looking forward to a very, very busy 2025. Thank you.

Operator

operator
#12

Thank you for attending today's call. You may now disconnect. Goodbye.

For developers and AI pipelines

Programmatic access to Orezone Gold Corporation earnings transcripts and 32,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.