Orient Green Power Company Limited (GREENPOWER) Earnings Call Transcript & Summary
July 27, 2026
Earnings Call Speaker Segments
Operator
operatorGood morning ladies, and gentlemen, and welcome to the earnings conference call for Q1 and FY '27 for Orient Green Power Company Limited. [Operator Instructions] Let us now begin with the introduction of the management team. We have with us today Mr. T. Shivaraman, Managing Director and CEO of the company. Also joining us today is Ms. J. Kotteswari, Chief Financial Officer. I would now like to request Mr. T. Shivaraman, Managing Director and CEO, to give his opening remarks and share the company's performance in Q1 FY '27 with the audience. Thank you, and over to you, sir.
Thyagarajan Shivaraman
executiveThank you. Good morning, everyone. I'm pleased to welcome you all to OPL's earnings call for Q1 FY '27. Thank you for joining us today and your continued faith and support in our journey. We started the quarter by commissioning a 3.3-megawatt wind turbine at the beginning of the quarter. With the 6.6 megawatts commissioned towards the end of the last quarter, we have 9.9 megawatts of incremental wind capacity for operation -- available for operation in this quarter. Also, we had a 7-megawatt solar power plant, which is commissioned in December 2025, which is also available. So this is additional to the capacity that was available in the previous quarter in the last financial year. With regard to the further other expansions, we have the 17.6 megawatt of solar capacity, which is being implemented is progressing satisfactorily. Also, we have a 7.8 megawatts of repowering of all old wind assets under the new wind repowering scheme of Tamil Nadu, both are proceeding as per plan. There have been some delays due to the change of government and certain approval requirements, but that seems to be behind us, and we hope to commission both of them by end of September 2026. Now with regard to the performance of the quarter. The current quarter has been a little moderate in terms of wind availability. The wind season as well the monsoon was delayed this year, as all of you know, and therefore, the wind season is also delayed. And the first part of the wind season has also been a little muted compared to the previous year. However, the shortfall of wind generation was somewhat mitigated by the generation from the new capacity. Therefore, we've been able to kind of come close to the corresponding quarter last year's numbers. And the wind availability for the second quarter till date has been reasonably good, and we hope to recover a significant portion of the shortfall during the second quarter. Running through the numbers. In Q1 FY '27, the revenue from operations and EBITDA were INR 81.43 crores and INR 3.01 crores, respectively. This is lower by 7% and 9% as against Q1 FY '26 due to lower wind availability. PAT for the quarter came in at INR 23.94 crores, 16% lower than the corresponding period last year. In addition to wind, there's a reduction in interest income as the rights issue proceeds were in fixed deposits in the previous -- the same quarter last year have been deployed for implementing the projects. Also, there was an increase in depreciation due to the additional capacity additions, which also contributed to a slightly lower PAT. As we look forward, the second quarter of this financial year looks to be better as compared to Q1, given the improvement in the wind availability. The completion of the greenfield solar and the recovering CapEx, which will happen before September of this year, will -- along with full year operation of the newly commissioned 9.9 megawatts and 7 megawatts of wind solar will support profits for the forthcoming quarters and the current fiscal. The currently operating turbines are performing nominally. We have no significant issues with turbine availability and the performance is quite satisfactory. As far as on the balance sheet front, financial and liquidity position continues to remain healthy. our interest costs are under control, and we are making continuing efforts to reduce the cost of borrowing. The above positives along with the strong performance of the turbines should generate improved returns while reinforcing our balance sheet strength during the course of this year. Thank you again for taking time out of your busy schedule to join us. We look forward to sharing more updates over the course of the year as they arise. Happy to answer questions as they come up. Thank you.
Operator
operator[Operator Instructions] The first question comes from the line of [ Vishal Hawa ] with H.G. Hawa & Company.
Unknown Analyst
analystSir, my name is Faisal Hawa. What is the plan going forward now? Because our stock price is at INR 10. So to get any kind of money further from preferential issue or any other capital raising is almost impossible. And to do another rights at the same price will also not be a very good option. And we have not been able to give any kind of return to our shareholders for the last 1 decade or so. So are we still on with the plan to make our company 1 GW operation?
Thyagarajan Shivaraman
executiveYes. See, we are working on it. Unfortunately, we don't have control over the share price and the markets. However, we are currently not fully leveraged on the assets that we have added. For example, the solar project that we added 25 megawatts which we added, we leverage on that. The original plan was to leverage that to expand capacity organically in certain areas. We are evaluating some further repowering, which will give us a substantially improved return. We are also looking at various options of fund raise. Let's see how things develop. I'm not in a position -- I mean we did have some serious conversations, which unfortunately did not proceed the way we wanted, but there are a lot of stuff. There's a lot of stuff happening at our end. And we are hopeful that something will start moving during the course of this year. So we are still moving to expand, but we are -- it's been slower than what we anticipated.
Unknown Analyst
analystSo 2 years ago, we had set up a target of [indiscernible] year. So now what is the new [indiscernible]
Thyagarajan Shivaraman
executiveYes. We are still working on it. There will have to be -- I mean, we are looking at certain, should we say, brownfield or certain acquisition possibilities that those will -- as they develop, we will keep you
Unknown Analyst
analystAnd what are the kind of valuations that we are looking at for the acquisition?
Thyagarajan Shivaraman
executiveI don't -- I can't talk about it right now because we don't come in until it comes to a stage where we have a firm project or a firm thing that we need to take to the Board and the shareholders, I don't think it'll take
Unknown Analyst
analystSo is the Board looking at any other options to create any kind of shareholder value given what [indiscernible]
Thyagarajan Shivaraman
executiveThey're looking at the we are looking at multiple things, but I don't think we are in a portion to discuss this in a public manner right now.
Operator
operator[Operator Instructions] Next question comes from the line of [indiscernible]
Unknown Analyst
analystSir, I just want to ask 2 things. One is, how do you see the current year season versus the last year? Because last year was very good, right? I mean -- how do you perceive current year caring to be? I mean do you see this year to be at least as good as last year or it could be different?
Thyagarajan Shivaraman
executiveIt does not look at the moment to be as good as last year. It is probably as good as the year before last, but then we have to see. It's still early in the season. As I said, Q1 was significantly worse than last year. But Q2, as of now is more or less matching pace with last year. So we will have to wait for the next couple of months to see how things work out.
Unknown Analyst
analystAnd sorry, I missed about first 4, 5 minutes of the call, so I'm not sure what was mentioned on the call. But how do you see the repowering? What's the potential for repowering? I mean one of the issues with repowering is many places, it might be possible. But because of the size of the holding, it's difficult. There are a lot of tactical difficulties to take larger turbine into the small places access to the location. So there are multiple challenges actually in repowering. So actually, practically, how much repowering is possible according to you over the next 2 years?
Thyagarajan Shivaraman
executiveSee, we are -- as I said, we are now doing a 7.8 megawatt repowering. We have another project which is kind of which we are working on. But you are right, some of our sites are difficult to repower because of turbines surrounding it. There are other sites where repowering is possible, but the older turbines are still performing well enough that it doesn't make economic sense to knock them down and put in a new turbine. It is better to use that money to do a greenfield project, and we would be able to get a better overall return because when you repower a turbine, which is say giving you 15%, 16%, 17% PLF, you are losing that PLF, you may get 35%, 37% PLF from a new turbine, but then putting the new turbine somewhere even at 33%, it is still better because you lost this 15%. So that's the dynamic thing that we are doing on a farm-by-farm basis to figure out what makes sense to repower and what mix sense to defer. Frankly, there are 1 or 2 locations where the urbanization has happened so much around the turbines that the land is probably more valuable than -- as real estate than building wind turbine. So those are things that we look at on a basis.
Unknown Analyst
analystSo precisely, that's my question. I mean there might be some location where the land might be more valuable, and it may be worthwhile taking out the wind from what we have and then put that money at some other location [indiscernible]
Thyagarajan Shivaraman
executiveYes, we are doing that. We are constantly evaluating that, and we are definitely looking at doing that on an ongoing basis.
Unknown Analyst
analystSo is there a significant potential in terms of the land monetization? I mean if you look at [indiscernible]
Thyagarajan Shivaraman
executiveNot huge, not huge because those are not those are not -- I mean it's not like we have hundreds and hundreds of acres, which can be monetized. And these, again, are in the remote rural areas. It is not like I have a city land, which can be monetized for very large numbers. So -- but at the end of the day, we do the math and then we see what makes sense. So there are advantages in that. The old turbines are running, we continue to run them because it makes economic sense.
Unknown Analyst
analystSo what is the for losses that we carry in the balance sheet where we have a tax cover?
Unknown Executive
executiveAbout in [indiscernible] around INR 800 crores of loss, I mean, in the material subsidiary, about -- in total, we have about INR 800 crores to INR 850 crores of loss.
Unknown Analyst
analystOkay. So when I look at the whole total picture, sir, I mean, we have the tax losses, we have potential. We have significant experience in the business the biggest hurdle for us to grow is capital -- so is there innovative ways by which you can get a partner who will invest money and we will jointly share some of the returns?
Thyagarajan Shivaraman
executiveSee, we have been in conversations with multiple people on that. There is a challenge that many of the traditional private equity-type investors are now more comfortable investing in unlisted entities rather than listed entities, so that they don't have to take a mark-to-market loss every quarter. So we are in conversations with multiple people, we'll have to see how things develop.
Unknown Analyst
analystSo that is one of the way to go around. The capital [indiscernible] another way we have industrial customers, right? I mean, is there a potential that if there is a large customer and we get significant money from them for the project and then share the [indiscernible]
Thyagarajan Shivaraman
executiveThat doesn't really see most of our industrial customers are focused -- I mean, on their core business. So for them, buying power is a side business, I mean if they're buying power because they need the power. They are not really invested in power as a business, if you see what I mean. So...
Unknown Analyst
analystBut if you look at your listed peers, one of the ones who came with IPO in recent past, I mean, they get 25% from the large customer and balance they [indiscernible]
Thyagarajan Shivaraman
executiveIn our new projects, we are doing that. In our new projects, we do -- because these are group capital. So they have to invest 26% equity in the projects, and that happens. That, in any case, happens. So that [indiscernible]
Unknown Analyst
analyst[indiscernible] that happens -- beyond that, they will not do it.
Thyagarajan Shivaraman
executiveBeyond that they'll not do it. 26%, they have to invest because otherwise, they don't -- they qualify as further -- as a group capital customer. So that investment, obviously, we get.
Unknown Analyst
analystThen one of the other alternative is to merge with a large profitable renewable player, where we have a -- where we can get value from the carry for losses. We have the experience, right? if they are profitable then these might be worthwhile instead of acquiring small companies...
Thyagarajan Shivaraman
executiveManoj, we can't talk about what we are discussing now until something comes to a stage. Let me assure you that all these 3, 4 possibilities we have looked at, we have had conversations, we have had discussions, but we have not come to a stage where we can come to the shareholders and say [Foreign Language]
Unknown Analyst
analystNo, I agree with you, sir. I agree with you that you can't talk about it. But there should be a time limit we should put, right? The first best alternative you say that we do it in 1 year. Second best alternative may be 1.5 years, 2 years. Third alternative if nothing happens in 2 years and third alternative is -- so we have to keep evaluating this alternative to ensure that...
Thyagarajan Shivaraman
executiveWe are continuously evaluating all possible [indiscernible] conversations are ongoing. Don't worry.
Unknown Analyst
analystAnd I hope to see something developing. I mean, because genuinely, I mean, I see a lot of value in the business and [indiscernible]
Thyagarajan Shivaraman
executiveThere's a lot of potential. [indiscernible] we have to make it happen.
Unknown Analyst
analystRight. Right. And all the best, sir. I hope to see something very positive happening soon, hopefully this year.
Thyagarajan Shivaraman
executiveThank you.
Operator
operator[Operator Instructions] Our next question comes from the line of [ Rakesh D. ], an individual investor.
Unknown Attendee
attendeeSir, what is your debt guidance for the next quarter? What is the -- will be the quarter interest cost on current
Jagathpathi Kotteswari
executiveQuarterly interest cost will be around [indiscernible]
Thyagarajan Shivaraman
executiveSo you are talking about the interest rate or the total amount?
Unknown Attendee
attendeeInterest rate on quarterly basis.
Thyagarajan Shivaraman
executiveInterest rate is 9.1%. 9.1% is average interest rate about 9.1%.
Unknown Attendee
attendeeAnd the future debt guidance?
Jagathpathi Kotteswari
executiveNo, that will be -- interest will be around INR 13 crores per quarter and the debt we may go if the second repowering project if we are going, then we will be leveraging the delta, which is the new 17 megawatts solar and take the debt to reap our next phase. But that will take probably next year only that will be trial will happen. So the current year, we will be repaying around INR 90 crores of debt and [indiscernible] INR 535 crores will be the debt, which is same as -- no, slightly lower than last year. Because we have got new debt for delta as well as in the gamma new assets of 10 megawatts and for the current recovering, which is happening we have taken around INR 70 crores. So the increase in debt is around INR 170 crores, decrease in debt will be around INR 100 crores. So net-net, there will be INR 70 crores increase from the last year's debt.
Unknown Attendee
attendeeOkay. And when we exit the promoter share coverage completely released?
Thyagarajan Shivaraman
executiveThat should happen shortly. I think the conditions are over. I have to check. [indiscernible]
Unknown Attendee
attendeeOkay. And the renewal scheme, how many products completed, sir, and how many is still pending?
Jagathpathi Kotteswari
executiveREC certificates.
Thyagarajan Shivaraman
executiveYou're talking about repowering?
Unknown Attendee
attendeeYes, repowering.
Thyagarajan Shivaraman
executiveRepowering, we are currently doing 7.8 megawatts, which should get commissioned by September of this year. The next batch of repowering, we will start only after this is completed.
Operator
operatorOur next question comes from the line of [ Narander ], an individual investor.
Unknown Attendee
attendeeYes. In the recent business update I've seen that you are liquidating the Europe business which is having 10 megawatts?
Thyagarajan Shivaraman
executiveNo, no, no. We are liquidating a 100% subsidiary in Netherlands, which has no assets. That was a holding company for the Croatia asset. So there was an intermediate company which we are liquoring because it doesn't make sense to have multiple layers there. [indiscernible]
Unknown Attendee
attendeeSo currently -- what's the revenue getting from that?
Unknown Executive
executiveNo, no, it is about EUR 1 million every year.
Thyagarajan Shivaraman
executivetop line.
Unknown Attendee
attendeeIndian currency?
Unknown Executive
executiveNo, no, I'm talking in euro terms.
Thyagarajan Shivaraman
executive[indiscernible] about INR 10 crores, INR 9 crores or something [indiscernible]
Unknown Attendee
attendeeOkay. If you are liquidating how much you are expecting from the asset?
Unknown Executive
executiveNo, we are not liquidating. See, the thing is on subsidiary. The asset remains reserved. [indiscernible] in the structure we are eliminating.
Unknown Attendee
attendeeOkay. You're eliminating the structure. Okay.
Unknown Executive
executiveYes. Exactly, the 10.5 megawatts will still remain with us.
Unknown Attendee
attendeeOkay. Okay. And the next question is come to -- actually, you're doing the repowering scheme. So actually, what is the total margin for the repowering scheme? How much your planned for it? That means I'm asking -- I'm not asking about the recent updates of 7.5 megawatts or what is the need to be done in the scope? How much repowering are you planning for the old sites?
Jagathpathi Kotteswari
executiveSee, currently, we are doing 7.8 megawatts of referring in 1 of the subsidiaries in that another 2.8 megawatts we may look at the next year. In there will be around 17.5 megawatts of recurring happening in the next year. This feasibility study, which we have studied done based on the lowest wind generation, whichever machines are generating lowest wind and it will be -- EBITDA wise, it will be better to reap over those winds only we are taking care. The rest of the machines are still giving very good return at that area because the capital employed is less and being an old machine, we are not repowering. First stage, it will be only 10 plus 17 around 28 megawatts of repowering.
Unknown Attendee
attendeeOkay. But that is the targetted financial year, right?
Jagathpathi Kotteswari
executiveEnd of next financial year, that will be 28. This year, first phase. Second, gamma will be next year.
Unknown Attendee
attendeeOkay. Okay. I can see that recently you have given 2 targets for completion plant, it was on time. But for this time, we have given as June 19 but it was pushed September 30 [indiscernible]
Thyagarajan Shivaraman
executiveYes, there have been some delays because of the change in government in Tamil Nadu a lot of the approvals got completely held up. So that is now -- but that holdup has kind of gone and things are moving again.
Unknown Attendee
attendeeOkay. In the recent quarter, I have seen that the interest per quarter is INR 14 crores so how much in for the next quarter can we expect?
Thyagarajan Shivaraman
executiveNext quarter will be more or less the same.
Unknown Attendee
attendeeOkay. It will be around INR 14 crores, I can assume for the next quarter [indiscernible] next financial year?
Jagathpathi Kotteswari
executiveNo. In the current year, it will be around INR 14 crores per quarter.
Unknown Attendee
attendeeOkay. Roughly, it can go in gradually increase up to?
Thyagarajan Shivaraman
executive[indiscernible] actually we're borrowing anything new. We are repaying almost INR 100 crores this year. So the interest next year will reduce unless we borrow more for the next project.
Unknown Attendee
attendeeSo from the last quarter, like in the March can able to see that the debt INR 525 crores. So that means, can I expect how much we are going to repay from it?
Jagathpathi Kotteswari
executiveNo, we are repaying around INR 100 crores. And this year, because we have taken new loans for repowering other INR 535 crores by year-end.
Unknown Attendee
attendeeBy the end end. That will mean more or less it will be constant for a quarter, right?
Thyagarajan Shivaraman
executiveCorrect.
Jagathpathi Kotteswari
executiveCorrect.
Unknown Attendee
attendeeOkay. Yes. Sir, from the last quarter con Call, I can see that you have made some provisions for Andhra Pradesh government up to INR 30 crores around. So what is the state of it?
Thyagarajan Shivaraman
executiveNo, that is basically the -- there was a couple of years back [indiscernible] Andhra Pradesh government, which after the association went to the court, we won the cases and we got the principal back. As per the PPA, they have to pay us interest on the delayed amount, so that interest amount we are spending, we are kind of in, should we say, there is a dispute with the AP government on that. Unfortunately, the Andhra Pradesh Electricity Regulatory Commission, which has to rule on this and we have to give the instructions for this payment is currently nonfunctional because they don't have the necessary members to run commission. So once the EPRC starts functioning again, we hope to push it. Since this interest has been delayed for some time by a measure of prudent this thing, we are making provisions for the receipt. But legally, we are entitled to that interest, and we are certain that we will collect this money over a period of time.
Unknown Attendee
attendee[indiscernible] the provision percentage still now?
Unknown Executive
executiveAs of now, we are making the interest of about 5% on the -- on an annual basis.
Thyagarajan Shivaraman
executive[indiscernible] You expect expense. Total provision is -- we have made a provision.
Unknown Attendee
attendeeCan I know the percentage of it like 100%, 30%, 40% for the exposure?
Jagathpathi Kotteswari
executiveNo, no. Until now, we have provided around INR 6.5 crores on the INR 20 crores. But on an annual basis, 5% to 6% depending on the cost of borrowing and the cost of capital, which auditors will work out and -- it's part of India AS we have to provide for the expected credit loss. So that's what it's provided. So it will be around 6% of the total outstanding amount.
Thyagarajan Shivaraman
executiveAs of now, it is about INR 6.5 crores on a total outstanding of around INR 20 crores. So about 30% of it has been provided for, okay?
Unknown Attendee
attendeeOkay. Do you have any further plans for the solar development? Are you focusing clearly on repowering?
Thyagarajan Shivaraman
executiveNo, no. We will do repowering. We are looking at solar possibilities. We are also looking at battery storage for the existing solar projects. So both these, we will look at during the coming quarter. We will look at it. There are still certain regulatory kind of things that we need to resolve before we look at battery for the existing solar projects. So that's something that we are working with the government of Tamil Nadu for getting the regulatory situation straight for implementing battery storage. Only even the battery storage, should we say, regulation is clear, we can do more solar because for -- as a supplier, solar without battery is not making sense anymore.
Unknown Attendee
attendeeYes, than we can expect in the next year in upcoming year?
Thyagarajan Shivaraman
executiveWe can expect in the next year. Yes. Yes. Yes.
Operator
operatorNext question comes from the line of [indiscernible] Capital.
Unknown Analyst
analystSir, how much revenues are we targeting for this year and can we sustain like 50% margin?
Thyagarajan Shivaraman
executiveYes. See, the margins will be sustained because for us, the major cost is the O&M cost is more or less fixed. Interest and deposition are also kind of predictable. So margins are reasonably predictable. In terms of top line, we are dependent on the wind. So we can't really I mean precisely predict how much is going to be a top line. But definitely, we will be able to maintain what we have done last year. We are hoping that we will exceed, but that depends on
Operator
operatorOur next question comes from the line of Faisal Hawa with H.G. Hawa & Company.
Unknown Analyst
analystSir, what are our blended interest rates for all the projects? And what is the best interest rate that we can achieve and are we making efforts to go towards that?
Jagathpathi Kotteswari
executiveSee, currently, the blended interest rate is at 9.1% and the best rate, which we got for the old assets loan, which we took from HDFC that was at around 8.2%. But current interest rates are actually slightly strengthening. Going forward, the interest rates will be -- we can make it around 8.75% lowest, but that is on the not on beta. Beta, which is a major project is with and there again, we had come down from 9.75% in the last 3 years to 9.15% right now. So we are approaching them for internal rating also to reduce another 15 basis points. Let's see how it works out because they take time being a government NBFC. But overall, the interest rates, if you see from last 4 years, we've been constantly dumbing down. The external credit rating agencies generally don't see that change and accept faster. So we are going -- moving step by step from like BBB, BB, so we have to achieve BBB+ and then a for increase in external perception. But in terms of bankers and our new lenders who want to come. They are looking at it positively. I think we will be able to achieve 9% as the interest rate going forward
Unknown Analyst
analystCan you give me the division in our sales between corporate and government? And what is we are realizing from the corporate and how much is from the government per megawatt?
Jagathpathi Kotteswari
executiveSee, per megawatt more or less, it will be except for solar because even with Andhra also the net rate of PPA, which we have contracted, will be the same transmission lines here with the corporates, whatever rates which we have contracted less transmission cost will be around same. All of them will be around INR 4.75 net rate to us.
Unknown Analyst
analystAnd do we have any outstanding above 90 days?
Thyagarajan Shivaraman
executiveNo, we don't have at the moment anything above 90 days -- anything material above 90 days other than the Andhra outstanding, the interest standing which we already discussed. We are quite comfortable...
Unknown Analyst
analystSo suppose you want to expand our overall how much can we expand through debt alone?
Thyagarajan Shivaraman
executiveNo, we can't expand only through debt. We have probably another about 20, 25 megawatts, we can do by just leveraging the existing assets. Beyond that, it can't be done only through this. There has to be some equity coming in. That's something that as I said we are working on.
Unknown Analyst
analystSo the promoters are not even thinking of increasing their stake by some kind of a rights issue or...
Thyagarajan Shivaraman
executiveThose are conversations that are going.
Unknown Analyst
analystOkay. So that is a chance that even the promoters increase their stake and actually do something and...
Thyagarajan Shivaraman
executive[indiscernible] of course we have all this creeping acquisition requirements and things like that. So [indiscernible]
Operator
operatorOur next question comes from the line of [ Manoj Bagaria ] with [indiscernible].
Unknown Analyst
analystIf you talk about the solar, the 25 megawatts, is this a pure solar or as a part of the setting up to be able to have a BESS or battery storage also along with that?
Thyagarajan Shivaraman
executiveAt this point, it is a pure solar because when we started this project, the requirement of a BESS were not that currently at is still not there in Tamil Nadu. But we are looking at the possibility of retrofitting the BESS which we'll probably do in the next year.
Unknown Analyst
analystOkay. So anything that you do in future, apart from this 25 megawatt in solar battery storage will be included in that, right, which reduces your returns on the investments.
Thyagarajan Shivaraman
executiveAny further solar that we do will almost certainly have a better storage element. Wind does not require because battery storage is not really help in wind, but definitely solar.
Unknown Analyst
analystSo this 25 megawatts, even if you don't put a battery storage, you have enough transmission capacity available that you can have?
Thyagarajan Shivaraman
executiveYes, these are already contracted to customers for supply of the entire product. That is not a execution is not a problem. [indiscernible] Consumption is also not a problem. But we are looking at battery storage because we feel that we can serve the customer better and probably improve our realization if we are able to provide with batter.
Unknown Analyst
analystBut then if you talk about the return, like when I see the project, right, you have a repowering. You can put a fresh wind capacity. You can put a fresh solar versus battery storage, how does the return capital employed or payback defer on all these actually?
Thyagarajan Shivaraman
executiveSee on this, the repowering is probably the best then between batteries the solar with battery storage and new wind, they are not -- they are more or less equivalent. Choice between the 2 is on 2 sides. One is what my customer wants because here, we are doing We are not doing selling power to the grid. So we don't have long-term So basically, we look at our customers' demand portfolio, I mean, demand spread. And then based on that, we have to balance.
Unknown Analyst
analystOkay. And on your existing sites, where the wind is there, if you have to put the solar, that will be driven by the new policy only with BESS only or you would have some leeway because...
Thyagarajan Shivaraman
executiveNo, no, not necessarily. There is a repowering hybrid policy in Tamil Nadu, which allow you to put solar within wind farms, that also there is some fine tuning and notification of the policy that is pending. But we can do a solar, wind existing wind farm without adding the BESS. Whether it makes economic sense in the calculation that we have to do it, nothing preventing us from doing battery without any solar without battery. But whether it is economically better to put battery or not put battery is something that we calculate within.
Unknown Analyst
analystSo how much hybrid potential is there in the policies, right? Because what I understand from the industry is hybrid is the best in terms of the economics as of today?
Thyagarajan Shivaraman
executiveYes. See, on our existing wind farm sites, we can probably do at least another 100 megawatts of solar, probably more as hybrid, but it also defines some places we have to buy land, we have to see what is the cost of the land. So we have acreage. We have a point And in hybrid, you always have the problem that during the peak wind season, there is amount of element of backdown of solar because you cannot generate more power than is permitted to be connected to the grid in that substation. So during -- especially in the afternoon during wind season, you will have excessive generation. So that's the balancing that has to be done. Definitely, hybrid as technical solution is better than fuel wind pure solar, but each project, you have to look at the economics.
Unknown Analyst
analystSo practically, hybrid will come with BESS, right, battery storage and then the economics would again change because of the battery storage.
Thyagarajan Shivaraman
executiveBut again, we'll have to see because BESS, the problem is that you target once during the afternoon and then you restage it at night. So we are able to use the battery for only 1 cycle per day. that costs quite a bit of money in terms of if you convert it into cost per kilowatt hour, it is quite significant. So unless we are able to make more than that money from my customer it's unfortunately, battery costs have gone up a little in the last year. They have dropped quite a bit, but they are now back on the uptick. So -- but still, on a single cycle charging, discharging, it's just about okay. We are trying to find a structure which we are allowed to be able to use it twice a day, that's still kind of still requires certain government modifications, which we are working with them on.
Unknown Analyst
analystSo hopefully, all these things will be maybe by end of this year, right? I mean, hopefully...
Thyagarajan Shivaraman
executive[indiscernible] As far as Tamil Nadu is concerned, they're expecting that all the open issues will get close in the next 2, 3 months. now that the new government has taken charge and are beginning to understand the subject because as you are aware, all the ministers are new. They have not been ministers before, so they are taking time to kind of get a grip of the subject, which is happening. I mean we are working very hard on it. So we are expecting that in the next couple of months, we will get clarity in Tamil Nadu.
Unknown Analyst
analystAnd when I see your target of 1 gigawatt, right? I mean what kind of solar is improved impact. I mean in case everything goes according to what you are planning and you get money...
Thyagarajan Shivaraman
executiveNo, [indiscernible] you see but the 1 gigawatt will be a combination of acquisition that is inorganic and organic. So the organic would probably be more of winter than solar because that's more available. the solar projects are relatively new and expensive for acquisition. Our C&I, at least for the next 1 year, I am seeing to be more wind continue to be more wind-focused and solar focused. Until we have a good group of battery, we are hoping for at least some small reduction in battery prices, then
Unknown Analyst
analystOkay. acquisition you think there are enough opportunities in the wind sector [indiscernible]
Thyagarajan Shivaraman
executiveThere are enough opportunities.
Unknown Analyst
analystOkay. So if we have the equity or the cash, then you can do the acquisition?
Thyagarajan Shivaraman
executiveThere are enough and more opportunities. See, we are still at a very low penetration of renewables compared to the target that is required. And as far as our industry customers are concerned, they all want to go to 100% renewables. So definitely, there are opportunities. even the government sector there are opportunities because governments start wanting to -- want to buy more noble power, particularly more wind power.
Unknown Analyst
analystSo sir, 1 thing I clearly understand that the demand is there. Demand is not an issue. It's a question of your ability to get -- put it together the project in a viable fashion. And for that the money, I think money is the biggest issue if you can resolve that, then there is no
Thyagarajan Shivaraman
executiveThere's [indiscernible]
Operator
operator[Operator Instructions] Next question comes from the line of [indiscernible] Associates. As there is no response from [ Manav ], we'll move forward to the next participant. Next question comes from the line of [indiscernible], an individual investor.
Unknown Attendee
attendeeMy question is could you share your capacity addition road map for FY '27 and FY '28 across both wind and solar.
Thyagarajan Shivaraman
executiveSee, I think as far as FY '27 is concerned, we are adding 17.5 megawatts of solar and about 7.8 megawatts of wind. I don't see a -- plus, we've already added 3.3 megawatts of capacity in wind. So there will be a total of about 12 megawatts of -- with 11 megawatts of wind and about 15 megawatts of solar happening this fiscal. Next fiscal, we have a lot of plans, but I don't think we -- there are so many moving parts. I don't think I'll be able to give you a clear number on how much of capacity will be added. We will probably add 15 to 20 megawatts of repowered assets in the next fiscal. But beyond that, what we will do, we will work on -- I think we will have better clarity towards the end of -- towards the middle of Q3.
Unknown Attendee
attendeeOkay, sir. My second question is, how should we think about the revenue, EBITDA and profitability for the rest of FY '27, any broad guidance would be helpful? And finally, could you share the management's long-term vision for the business and the key growth drivers over the next 3 to 5 years?
Thyagarajan Shivaraman
executiveSee, as far as this year's revenue and EBITDA is concerned, we are -- should be better than last year. We are working on it. As I said in the earlier -- answer to an earlier question, it a lot depends on the monsoon and the winds. So as of now, would we look to be equal to or better than last year, but we have to see how things move. Going forward, as I think we have asked answered in many of the previous questions, we are looking to expand the capacity in both wind and solar, but we have -- we need some strategic We are working on those to this. And as and when something kind of use we will be in touch with the shareholder community.
Operator
operator[Operator Instructions] Our next question comes from the line of [indiscernible] Management.
Unknown Analyst
analystJust 1 question. When we say that we are trying to be or we will be equal or slightly more than what our past previous year has been, are we being conservative here because like we are adding capacities and why are we...
Thyagarajan Shivaraman
executiveYes, I'm being conservative because I'm not able to predict the wind. If the wind is as good as last year, definitely, I would say we would be significantly better than last year. given the fact that this year's monsoon has been patchy, and it's quite delayed. Now we have lost potential revenue in Q1 because of the monsoon as I said, until that has been okay, but we are still kind of -- it's still not as good as the wings last year. So I think this will probably be from a wind availability perspective, similar to year before last. But since we have better capacity this year and more machines operating this year in terms of machine availability is better this year than it was 2 years back. So definitely, we will exceed last year. But by how much we are -- it's difficult to well exceed last year, but thanks to the additional capacity. But by how much we will exceed will depend on how the rest of the monsoon progresses. -- because, unfortunately, in this business, we don't have too many levers other than ensuring that the machines are fully operational.
Operator
operatorOur next question comes from the line of [indiscernible], an individual investor.
Unknown Attendee
attendeeSir, I remember when we completed December '25 results, we are a discussion in the Feb '26 meeting thing that you would promise with our promoters will unpledging the entire 100% share. But even after 2 quarters, it's still not done, why the promoters are not interested in unpledging the shares? Basically, giving the negative impact to your company share value and the shareholders as well.
Jagathpathi Kotteswari
executiveNo, no, no. Please, we have never said that it is going to be 100% released in the same quarter. We had said it will be released in the phased manner depending on the promoter companies loan. The promoter company had taken a INR 300 crore -- INR 400 crore of loan out of which INR 150 already they have paid. So to that extent, the leverage is coming down. And in the current year, the rest of the loan also will be paid by end of financial year, hopefully, we will be releasing the entire pledge. Even though the loan amount is coming down, there is no partial release of shares. That's why the showing has pledged the corresponding loan which has been taken on the pledged shares is coming down because we have been paying the installments regularly. In fact, ahead of the time. So hopefully, by year-end -- actually September '27 is the promoter loans final due. So as per the terms, it will be September '27 that will get released.
Unknown Attendee
attendeeSorry, come again, please?
Jagathpathi Kotteswari
executiveThe promoter loan, which has been taken by pledging of the share is the installments are running as per the loan terms after September '27, so after repayment of debt loan only that will get released. As of now, we have repaid loans close to 40%, which is much more than whatever is the installment. So we are hopeful of retiring the pledged by end of this year if we go ahead in the same manner, the repayment.
Unknown Attendee
attendee[Technical Difficulty]
Operator
operatorSorry to interrupt you [ Shivam ], but your voice is breaking. We can't hear you properly.
Unknown Attendee
attendee[Technical Difficulty] as of 30 June [Technical Difficulty]
Operator
operatorWe're still not able to hear you properly.
Unknown Attendee
attendee[Technical Difficulty]
Operator
operator[Operator Instructions] All right, as there is no further question from the participants, I would like to hand the conference over to Mr. T. Shivaraman, Managing Director and CEO. Thank you, and over to you, sir.
Thyagarajan Shivaraman
executiveThank you all for joining us and for the insightful questions. We will work on upholding the confidence that the shareholders have in us and hopefully start generating significant shareholder returns during the course of this and the next following years. Thank you for joining us, and wishing you a very profitable week going forward. Thank you.
Operator
operatorThank you so much, sir. Ladies and gentlemen, on behalf of Orient Green Power Company Limited, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Orient Green Power Company Limited transcript — plus 252,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Orient Green Power Company Limited earnings transcripts and 252,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.