Paladin Energy Ltd (PDN) Earnings Call Transcript & Summary
July 22, 2026
Earnings Call Speaker Segments
Operator
operatorThank you for standing by, and welcome to the Paladin Energy Limited June 2026 Quarterly Results Call. [Operator Instructions] I would now like to hand the conference over to Paul Hemburrow, CEO. Please go ahead.
Paul Hemburrow
executiveGood morning, everybody, and thank you for joining us today. I have Anna Sudlow, our CFO, with me this morning. And on the line we also have Scott Barber, our COO; and Alex Rybak, our Chief Commercial Officer. There are two areas I want to cover today on the call. First, I'll take you through the June quarterly results and the key achievements from FY '26 and then we'll move into the FY '27 guidance for Langer Heinrich, which builds directly from the operating platform we established throughout this last year. At a high level, FY 2026 was about transforming Langer Heinrich from a restart project into a stable operating uranium mine, while laying the foundation through our next phase of growth through Patterson Lake South. I'm pleased to report that we successfully completed the ramp-up of Langer Heinrich Mine during the quarter. This is a commitment we made to shareholders. We've now delivered on that commitment. For the June quarter, production was 1.23 million pounds of U3O8 bringing full year production to 4.82 million pounds, right at the upper end of our revised 2026 production guidance range. Sales were strong. We sold 1.35 million pounds during the quarter and 4.35 million pounds for the full year, exceeding the top end of our guidance range. Operationally, the business continued to improve throughout the year. Total mine material increased steadily and reached 7.45 million tonnes in the quarter, the highest quarterly mining rate since the restart. The full mining fleet is now operational and positioned to support our 2027 objectives. Processing performance remains consistent with plant recovery averaging 90% during the quarter, demonstrating a stable operation and plant performance at the top end of our recovery target. During the quarter, we achieved an average realized price of $70.60 per pound with FY '26 averaging $70 per pound. From a cost perspective, FY 2026 cost of production was $43.30 per pound, outperforming our guidance range of $44 to $48 per pound. While quarterly costs increased to $51.60 per pound as a result of the mine development work and transition to full mining activities and mining lower grade areas in line with our mine plan. The successful completion of ramp-up provides a strong platform as we move into FY 2027. While Langer Heinrich remains our producing asset today, Patterson Lake South represents a significant component of Paladin's future growth strategy. During the quarter, we reached one of the most important permitting milestones since acquiring the project. The Canadian Nuclear Safety Commission confirmed that our construction license applications had achieved sufficiency status. This means the application has met the required completeness and technical standards and can now progress through the formal regulatory assessment process. Subsequent to the quarter end, we signed an administrative protocol with the CNSC, which establishes a targeted pathway aimed at completing construction license hearing by the end of calendar year 2027. This provides greater clarity around the permitting process and represents another important derisking milestone. At the same time, our Canadian team continued progressing the FEED study and advancing engineering activities while maintaining strong engagement with indigenous partners and local communities. We also executed a binding term sheet with Birch Narrows Dene Nation as part of the mutual benefits agreement process, further strengthening our relationship and social license in the region. A highlight during the quarter was the Atlas discovery. Atlas is a new high-grade uranium ore body located approximately 3.5 kilometers south of the Triple R deposit at Patterson Lake South. 7 of 8 exploration holes intersected significant uranium mineralization confirming the existence of an entirely new mineralized system within the broader Saloon trend. Importantly, Atlas remains open along strike and at depth. We believe this discovery reinforces the significant exploration potential across the broader PLS land package and supports our view that there are opportunities to enhance the long-term value and development potential of the project beyond what is currently contemplated. We ended the quarter with cash and investments of USD 265 million and an undrawn $70 million revolving credit facility. This strong financial position provides flexibility to continue advancing Patterson Lake South, support our exploration programs and optimize Langer Heinrich as we enter the next stage of growth. So in summary, the June quarter closed out a year of delivery to Paladin. We successfully completed the ramp-up of Langer Heinrich, met the upper end of guidance range on production and exceeded guidance on sales, costs and cost performance. We advanced Patterson Lake South through major regulatory milestones established a clear pathway towards licensing, strengthened indigenous partnerships and delivered significant exploration discovery at Atlas. That delivery gives us the right platform for 2027. With Langer now through ramp up the focus shifts from restart execution to disciplined operating performance, safe production, cost control, mine and plant optimization and, of course, reliable delivery to customers. I'll now turn to FY '27 guidance for Langer Heinrich. FY '27, we expect Langer Heinrich to produce between 5.1 million and 5.6 million pounds of U3O8 on a 100% basis. Sales volumes are expected to be between 4.8 million to 5.3 million pounds of U3O8. Production will not be evenly weighted across the year. We expect lower production in the first half due to planned maintenance shutdowns as well as lower grades from the mine in September and December quarter. Production is expected to improve in the second half as high ore grade feed to the plant increases. Cost of production is expected to be between USD 44 and USD 48 per pound. We expect cost to trend upwards -- sorry, we expect cost to trend toward the upper end of the range in the first half reflecting lower production volumes and additional cost impact of planned maintenance. It's also important to note that all ore processed in FY 2027 will be sourced from the mine following depletion of the previously mined MG3 stockpile. This means longer haul distances compared with FY '26, whilst ongoing removal of overburden and waste will continue to open up future mining areas. Operationally, our focus remains on mining and plant optimization through FY 2027. Medium and high-grade ore will be delivered to the processing while lower grade material will be stockpiled for future processing. This supports improved grade outcomes and provide operational flexibility over the life of mine. We'll continue to report actual costs associated with capitalized stripping and the building of low-grade ore stockpiles on a quarterly basis. These items are not included in the cost of production guidance. On capital, capital expenditure at Langer Heinrich is expected to be between USD 29 million and USD 35 million for FY 2027. The key areas of expenditure include tailings storage facilities design and construction, process improvement studies in infill drilling as well as the completion of selected capital exploration activities deferred from FY '26. On sales and pricing, Paladin's contract book continues to provide leverage with strengthening uranium market. During FY '27, sales are expected to reflect both customer delivery schedules and our intention to repay part of the current uranium product loan balance. As at 30 June 2026, Paladin had 400,000 pounds of U3O8 in outstanding uranium product lines. Consistent with industry practice, we maintain access to short-term uranium product loan and swap facilities to support operational and delivery flexibility. Realized pricing will vary from quarter-to-quarter depending on customer delivery nominations, contract pricing mix, individual contract terms, shipping schedules and prevailing spot prices. Based on the contract book, as at 1 July 2026, we have updated the realized price sensitivity table. In summary, FY '27 is about disciplined delivery from Langer Heinrich following the successful completion of ramp-up. We have provided clear guidance on production costs, capital and sales while retaining the flexibility to manage quarter-on-quarter movements in production and deliveries. We remain focused on safe operations, reliable production, disciplined cost management and leveraging our contract book as the uranium market continues to strengthen. And with that, I'm happy to take any questions.
Operator
operator[Operator Instructions] Your first question comes from Alistair Rankin with RBC.
Alistair Rankin
analystJust firstly, on Langer, you mentioned the maintenance work in the first half of FY '27. Can you just confirm what you're actually doing there? Is this something that is just a periodic piece of maintenance you have to do? Or is it something a little bit more structural?
Paul Hemburrow
executiveYes. Thanks, Al. It's really just a periodic planned preventative maintenance work. Typically, in these plants, you have wear and tear on things like the scrubbers, crushing circuit. And we're also updating our furnace in the final packaging and recovery plant. So it's all planned preventative work.
Alistair Rankin
analystOkay. Understood. That's clear. And then just also on Langer, the pit performance of the J-pit so far. You said you're looking to lift to high-grade ore for the second half of FY '27. So I guess what do you need to do between now and then to sort of achieve that?
Paul Hemburrow
executiveYes. I want to hand over to Scott to answer this Alistair.
Scott Barber
executiveSure. Thanks, Paul. Basically, we've got all of our mining equipment in pit right now and are developing a few different mining fronts. So some of the material is coming out as high grade right now, and the other material is still developing. We've got multiple levels of grade coming out of the pit. The next 6 months will essentially see us stabilize the feed that's going to be going into the mill as more high grade, medium and high grade, whereas for the -- right now in the last quarter, we're still in that upper level of weather and lower grade material. So basically, it's just continuing to mine and develop the J-pit.
Alistair Rankin
analystOkay. And then I might just sneak in one quick one on PLS. Interesting, you got that agreement with the CNSC, I understand it's not binding, but is this something they've done before? Or is this then the CNSC acknowledging that they want to try to speed up these processes to get these construction licenses through a little bit faster?
Paul Hemburrow
executiveYes, that's a really good question, Alistair. I was in Ottawa recently spoke to a number of government departments and everyone is really keen on advancing uranium projects and CNSC are trying their best to support them as well. So I met with the President of CNSC, and they're very keen to make sure that the right work is done to help us deliver the project according to the schedule that we published. That's really -- it's really a concerted effort by the Canadian government to get these projects up and running as efficiently as possible.
Operator
operatorYour next question comes from Hugo Nicolaci with Goldman Sachs.
Hugo Nicolaci
analystThanks for the update today. Look, first one on the missing pieces around CapEx for FY '27 from the guidance. Just firstly, at Langer you spent $56 million on stripping and low-grade stockpiling in FY '26, but you don't guide that on a forward basis, given that your strip ratio is probably flat to slightly higher next year, your plant maintenance, maybe you build a little bit of stockpiles. Is it fair to assume that $56 million is higher in FY '27.
Anna Sudlow
executiveLook, We're obviously not guiding on those numbers. They will be variable quarter to quarter. We will give you actuals on a quarterly basis. I think if you look at our Q4 FY '26 outcomes, that's not an unreasonable representation going forward.
Hugo Nicolaci
analystGot it. That's helpful. And then also on CapEx, but on Patterson Lake. How much of the $115 million pre-feed spend that you were planning on spending before the end of calendar '27, do you expect to spend in FY '27.
Anna Sudlow
executiveYes, again, Hugo, we haven't guided on that number. We've said in our quarterly that we've spent $20 million to date. Of that amount that we disclosed in the use of funds I can say that you can expect those costs to increase over the 18-month period. So it will definitely be weighted into half 1 FY 2028.
Hugo Nicolaci
analystGot it. That's helpful. And then just if I can squeeze in a third, just on then pricing sensitivity. I appreciate the updated table there. I just wanted to dig into the comment in the footnotes that the sensitivity table takes into account the flexibility under your contract terms. Does that mean that in that table, you've assumed that you'll sell more volume if prices are higher? And is there a math broadly right that if you're selling roughly 2 million pound under legacy contracts at sort of mid-60s a pound to sort of back solve into that pricing sensitivity?
Paul Hemburrow
executiveThat's a question to you, Alex.
Alexander Rybak
executiveThanks, Paul. On the first part, we've assumed -- we've run that sensitivity table on the basis of a midpoint of the sales range, which is 5.05 million pounds. And we're essentially assuming nominal contract volumes, but obviously, some contract volumes do have flexibility and where those contracts are in the money we've assumed that they -- that those flex options will be exercised by the utility. And sorry, could you just clarify the second part of the question?
Hugo Nicolaci
analystIt was more just sense checking the math that if you're delivering a bit over 2 million pounds under that fixed legacy agreements that, that pricing on those agreements must be sort of in the mid-60s today. Is that what that table assumes?
Alexander Rybak
executiveYes. Look, I mean, we're obviously not providing the pricing on a price mix basis. But on average, I think if you look at that sensitivity table, you can pretty much -- I think you're on the right track, you can pretty much work out what the base escalated and fixed price contract pricing is implied within that book.
Hugo Nicolaci
analystGot it. And then just lastly, if I can, just -- apologies if I've missed it, you put out the cash flow piece separately today, but the $265 million cash and investments, how much of that is actually cash?
Anna Sudlow
executiveOf the $265 million?
Hugo Nicolaci
analystYes.
Anna Sudlow
executiveYes. It's all cash other than funds held in term deposits.
Operator
operatorYour next question comes from Daniel Roden with Jefferies.
Daniel Roden
analystI just wanted to start first of all, just following up on the half 1, half 2 production. I know you talked about it, but just wanted to get a better sense on, I guess, the half 2 exit rates. And I guess kind of looking forward into FY '28 and beyond what that implies on what, I guess, the midpoint annual production rate would be over the life of mine? Are you able to kind of articulate and clarify what that would look like, please?
Paul Hemburrow
executiveThat's a good question, Daniel. What we've done is provided an annual guidance that we did last year. And what will happen in the years to come is that with the 2 plan maintenance shut and development of that J-pit. According to the mine sequence, we have slightly lower grades in that first half and about a week less production on each quarter, plus or minus. It is going to be a game of 2 halves. What we're not going to do is guide on a quarter-by-quarter basis. And -- but what we will do is be absolutely transparent as we have been in the last 12, 18 months on our actual performance at the end of each quarter. But we do expect a fairly significant uplift in the second half of the year. The mine plan does show absolutely solid grade coming through for that second half. So our plan is to stick to the plan, do the shuts properly mine the ore as it comes in sequence, exercise a high level of operating discipline, manage our costs as best we can and deliver on the annual target. So I know I haven't answered your question directly, but we're committed to the guidance range that we have set for production.
Daniel Roden
analystNo, that makes sense. I appreciate the color there. Just wanted to touch on as well. I know it's not in FY '27 guidance, I guess, thresholds. But in FY '28. If I look back at your restart plan and life of mine plan, you are expecting to do a little pre work on and H-pit and TSF1 relocation kind of at the end of FY '27 and come start of FY '28. Just wanted to get a bit of color and commentary on are you seeing anything in, I guess, the life of mine process that would either accelerate or defer works going into the H-pit and TSF1 relocation and just kind of noting that H-pit is a pretty meaningful step up in strip ratio on the disclosed tables, it goes to 4.1 from J-pit which is 1.8 at the moment. So just I guess you're saying that inflection point still in the same process? Or is there anything that you're seeing that changes that kind of sequencing.
Paul Hemburrow
executiveThat's one for you Scott.
Scott Barber
executiveYes. Thanks for that. I think the best way I can answer that is that the TSF strategy with our TSF6 lift that we're currently doing right now. And then we will be moving into the H-pit early in next year to start stripping that. That would be the next source once J is depleted. That becomes a long-term tailings facility as well. And so the H-pit will be fully mined out over a few years, and then that becomes our -- one of our tailings ponds. The TSF strategy is constantly being looked at based on volumetrics and what we actually need. We've moved the TSF1 relocation out a little bit. And that's to allow the mining in J and H-pit to progress the best possible and most economic. Does that answer your question?
Daniel Roden
analystJust a really quick follow-up and I'm sorry, I probably ask it. But I guess is part of the TSF 1 relocation and I guess, H-pit pre-strip, are they included in the back end of FY '27 guidance? Or is that exclusively an FY '28 item?
Scott Barber
executiveIt's not in FY '27, it would be in FY '28 and beyond.
Operator
operatorYour next question comes from Branko Skocic with JPMorgan.
Branko Skocic
analystPlant recoveries were strong again in that 90s range. Is there any reason we shouldn't be assuming recoveries stay in the low to mid-90s moving forward, particularly as grades start to lift.
Paul Hemburrow
executiveYes. Thanks for the question. Our typical target range for recovery is to 90%. And when we have stable conditions I'm actually really happy with anything within that range. Above that range is more difficult to maintain continuous sort of operations. So we -- it's always a balance, too. So we'll continue to operate it as stably as we can. And if we stay at the upper end of our target range, I'll be really happy.
Branko Skocic
analystAnd just a final question from my end, just on the production versus sales weighting. I understand the prepayment coming in into this, But should we expect it to, I guess, closely match moving forward, I'm thinking to '28 onwards? Or are we still expecting a bit of a mismatch medium term here?
Anna Sudlow
executiveI missed the first part of your question, Branko. But I think if it's around the working capital cycle and the kind of movement quarter-to-quarter. We are going to see ongoing ups and downs quarter-to-quarter. That's really just a function of the working capital cycle and the shipping schedule and the particular deliveries in the quarter. So I think you'll continue to see that movement quarter-to-quarter.
Branko Skocic
analystI think it was more just on the annual numbers. The last couple of years, you've been guiding sales less than production, and I guess during ramp-up, that also makes sense. But when we think about FY '28 onwards, should we expect it to on an annual basis to closely match or should we still be expecting a bit of a mismatch.
Anna Sudlow
executiveI think, Branko, there's always going to be a slight mismatch because it is, as I said, a function of those shipping schedules. I mean, I think theoretically, you would expect over the years as we kind of get into the cycle, but they should be more closely aligned. I think what we're also seeing this year is in the guidance, the repayment of the loan, which is reducing -- increase that gap between the 2 as well.
Operator
operatorYour next question comes from James Bullen with CGF.
James Bullen
analystJust on PLS, BHP has been picking up tenements, that's pretty proximal to your project. I know you've got a lot of prospectivity within your current permits and that's clear from the Atlas. But are you looking at picking up additional acreage in that area?
Paul Hemburrow
executiveThanks for the question, James. I have good neighbors. And what I think it does show is I think there is prospectivity of the region. And what's good for us is we've got absolutely fantastic ground. We've got a lot of ground that's still unexplored. There's lot of potential in the ground that we do have. And when the team in Saskatchewan put holes in the ground, we're having a high level of success. So never say never to pegging more ground, but we already have a lot of highly prospective ground that is demonstrating the capacity to produce more and more value for PLS.
James Bullen
analystYes, understood. And congrats on putting the Birch Narrows Dene Nation MBA in place. How are you going also with Metis, are they the final one that you have to put in place?
Paul Hemburrow
executiveYes. First of all, it's a binding term sheet. We haven't quite got the MBA yet, but that's the obvious next step. So as you rightly point out, James, there are 4 First Nations groups in the area where we operate. And we've now completed 2 of those MBAs. And now we have the binding term sheet with Birch Narrows. We have a good relationship with Mati. We're working with them very closely. And in due course, where we'll have an agreement with the remaining 2 groups. What we do think is important is making sure that the relationships that we have with them are by their definition, mutually beneficial and sustainable, and we're committed to supporting the First Nations groups as well as other stakeholders in the regions where we operate.
Operator
operatorYour next question comes from Glyn Lawcock with Barrenjoey.
Glyn Lawcock
analystJust going back to Langer Heinrich for '27, just on the production. Can you help me just think about how that's made up, just throughput grade recovery. I mean if I think about it, you've been running, I think it's 4.8 million tonnes of throughput, recovery is now up around 90%, but you now move into a pit that's got high-grade and medium-grade component, which is about 570 ppm in grade. And I'm assuming you'll put the rest of the low grade to the waste or to your stockpile, sorry, how do I think about that? And then you've also said you're looking at optimization. Where is the best lever you can pull to flex that volume and maybe do better than you have done through '26 as well?
Paul Hemburrow
executiveThey are really good questions, Glyn, which I'm probably going to try and dodge most of them T.he key levers, of course, are grade recovery and throughput. And I think what we've done is we've demonstrated the ability to operate the plan very, very consistently. But of course, the grade is highly dependent on what presents itself in the pit. So we'll operate the pit as efficiently as we can from a trucking perspective, whatever grade comes out and whatever the grade that comes out, besides the fact that we can divert the low and have change the cutoff. And that will provide us with the opportunity to operate the plant in a fairly stable way and get those recoveries in the high 80s and maybe even sort of the low in 90s. So like every other place, I know that Scott Barber and I work -- we're always working on optimizations and ways to improve. The biggest lever that we've got is the grade. And the second is, of course, throughput. Throughput is complicated by the fact that we have varying or feed types, fine course. And we've talked about this on a number of occasions before, but finding the best blend that gives us the best throughput. And we'll continue to optimize that blend for both throughput and grade as we progress. But what we've done is we've demonstrated the ability to be able to do that so far. What we've got now though is we've got 100% of the mining fleet. And what we delivered this year was 7.48 million tonnes of total movement. And so that gives us a bit of flexibility above what we had last year to deliver more tonnes to the crusher. So I think I've managed to dodge most of your questions, and I'm unlikely to give you any more detail than that.
Glyn Lawcock
analystMaybe just if I can push you a little bit, though, your resource of statement for that J-pit had a high zone and a mid-grade zone of about 14 million tonnes, about 570 PPM. Obviously, you've drilled it, you probably haven't -- you've not mined it yet. But is there anything to suggest so far what you've seen that the resources you provided for the pit are not coming through as expected?
Paul Hemburrow
executiveThe reconciliation is actually very good. So the challenge, of course, is when does it present itself. Yes. So the sequence actually is going to determine the -- how the year flows, which is why it's going to be a game of absolutely 2 halves with slightly lower grades presenting in the first half with the reduction in number of operating days, higher grades in the second half with absolute maximum number of operating days. So the pit is what it is, and the reconciliations are about right.
Glyn Lawcock
analystNo worries, Paul, I think I pushed you as far as I can. But one other question, but now moving to Canada just on PLS. And assuming it all goes to the new plan, which is you get the hearings done by the end of calendar '27. What's the time line look like beyond that then? What's left? And like if we think through it, when could you FID and start construction if you get this time line of end of '27 hearings completed?
Paul Hemburrow
executiveYes. So there's a few things to do over the next 18 months, of course, thinking about our financing options starting to populate the contract book. We get the FID construction window heavily depending on weather. So assuming it all goes to plan, I still believe that the 2031 production is realistic and achievable.
Glyn Lawcock
analystAnd sorry, what would that mean you start construction when to achieve first production in 2031?
Paul Hemburrow
executive2028.
Operator
operatorYour next question comes from Dim Ariyasinghe with UBS.
Dim Ariyasinghe
analystJust I guess on PLS, you do have the strategy day coming up. Can you give us any granularity as to what to expect there and maybe what to watch out for.
Paul Hemburrow
executiveSorry, Dim, do you mean the Investor Day?
Dim Ariyasinghe
analystYes. Yes.
Paul Hemburrow
executiveSo there's nothing really -- but by then, we should actually be past the next quarter. I guess we'll continue working -- we'll continue working through Langer performance, continue to work through the CNSC process, continue working with First Nations groups.
Anna Sudlow
executiveYes. And I think, Dim, we'll have the full year results just prior to that Investor Day or so.
Dim Ariyasinghe
analystAnd just -- we spoke about that I guess, earlier in the year, it's less of a focus now. But on the cost base, impacts from what's going on in the Middle East, which have flared up again. I think you guys mentioned at the start of the year, you had 3 to 9 months of supply of like all your inputs. Has that eased at all? Maybe just an update there, both in terms of availability and impact on your cost base?
Anna Sudlow
executiveYes, Dim, I think what we're seeing is that we have reflected the current cost base in the FY '27 guidance that I would say. I don't think it's having a material impact on our cost base. I think when we look at this quarter, it's definitely probably more of an outcome of grade and the cost per pound, I mean, than necessarily the Middle East conflict. So we continue to monitor and probably Scott can give you a view as to line of sight of those inputs. But from a cost perspective, it's reflecting -- we're reflecting the current pricing, we're not seeing massive shifts at this point in time, but we obviously continue to monitor.
Operator
operatorYour next question comes from Andrew Hines from Shaw and Partners.
Andrew Hines
analystPerhaps a question for Alex. Just give us a bit of an update on what you're seeing out there in the broader uranium market in terms of contracting activities. It seems like it's still very quiet out there. The level of contracts that have been reported by UxC is still extremely low for the first half of this year. And Paul mentioned that you're probably starting to engage already now with PLS offtakes for the next decade. What are you seeing? What's the current terms in these contracts that are being discussed now and when do you expect to see levels of activity pick up?
Paul Hemburrow
executiveThanks, Andrew. Yes, look, I mean, the backdrop is really strong with -- in the U.S., the loans that the U.S. government has announced $17 billion for the U.S. utilities is a good wind in the sails when we speak with our customers, that's exactly the support they're looking for as well as some backstop on cost blowout. But it's certainly a move in the right direction. In terms of other markets, China is really powering ahead with the construction of reactors and their procurement of supply. India is now in the mix, as you've noted as well in your notes, with sort of implications for Australia as well. In terms of our discussions with utilities, very strong interest, very cognizant of the tightness in supply and some of the challenges that some other producers are having with ramp-up and start-up issues. So that's positive for the short-term window to 2030. But really, that supply-demand deficit in the 2030s is coming home to roost and the utilities are really chasing supply out in the 2030s, and it's not really clear where they're going to meet those requirements. So the volumes are still, as you've noted, Andrew, below replacement levels. And it's interesting because even at those lower volumes, we're seeing stronger term pricing. So the term pricing $97 reported by Ux. But in reality, from our discussions with utility, we're seeing prices more in the $100-plus range, which is very encouraging. And I think it just shows that the utilities are willing to pay more pretty much every quarter for the uranium they procure I think for me also an interesting delta between term and spot that's emerged. We've obviously term leading the pricing environment and the spot is largely expected to catch up to terms. So I really like that dynamic where the fundamental market is really leading the spot market. So very positive developments, and we're always looking to monetize those -- that sentiment in our contracting discussions for more Langer Heinrich contracts and PLS as well.
Andrew Hines
analystWhat's your preference these days, Alex, for the nature of the contract? Is it for the market-based contracts with the floors and ceilings or is it the fixed-price contracting?
Alexander Rybak
executiveSo very much a balanced book approach which we're continuing. The utilities preference is definitely swung into the base escalated favor given that they are concerned with ever-increasing prices. So there's that element. But of course, they recognize they need to pay a premium to secure more fixed volumes, which again is positive for the pricing and for any additional contracts that we'll layer into our book.
Andrew Hines
analystGreat. Look, a follow-up question for Paul on PLS. I mean that was a pretty exciting discovery Atlas in the quarter and still the early days and no sign yet on how big that will end up being. But what's the plan of action going forward, Paul, on Atlas? How many rigs are you going to get going? How quickly are you going to drill that out. When are you sort of thinking about maybe the first resource being declared there.
Paul Hemburrow
executiveYes. Good question, Andrew. We've got 3 priorities for drilling around PLS. Number 1 is the resource upgrade of the Triple R deposit. Number 2 is the extension drilling of Triple R because that still remains open along strike and depth as well. And the third priority is close proximity exploration like Saloon East, like Atlas and others. So we'll just adopt a very sort of sensible pragmatic approach to these 3 priorities and drill them out, I guess, at an appropriate time and pace.
Andrew Hines
analystGreat. I'm looking forward to the Investor Day coming up where we get all the insights on PLS, it looks like a really exciting project going forward. I'll leave it there. Thank you, Paul.
Operator
operatorThere are no further questions at this time. I'll now hand back to Paul for closing remarks.
Paul Hemburrow
executiveThank you very much. Look, I'm really pleased with the performance from Langer Heinrich in FY '26 and the delivery against the revised guidance. Importantly, it sets a solid foundation for ongoing improvement and delivery. But more importantly, I'm excited about derisking and driving further value at Patterson Lake South through the CNSC process through close proximity exploration, through continuing to develop relationships with First Nations and closing out the FEED study. So thank you once again for joining us and for your ongoing support.
Operator
operatorThank you. That does conclude our conference for today. Thank you for participating. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Paladin Energy Ltd transcript — plus 252,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Paladin Energy Ltd earnings transcripts and 252,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.