operatorWe appreciate everyone holding. I’m the conference operator, and I’d like to welcome you to Pan American Silver’s conference call on first quarter 2022 results. <<operator_script>> This call is also being recorded. <<operator_script>> At this point I’ll hand the conference to Siren Fisekci, Vice President, Investor Relations and Corporate Communications. Ms. Fisekci, the floor is yours.
Siren Fisekci
executiveWe appreciate you being with us on today's call covering Pan American Silver's first-quarter 2022 results. Remarks on this call contain forward-looking statements and information, and we will refer to non-GAAP measures. For details, please review the cautionary statements included in our MD&A, our news release, and the presentation slides for the unaudited Q1 2022 results, each of which can be found on our website. At this point I'll hand things over to Pan American's President and CEO, Michael Steinmann.
Michael Steinmann
executiveThank you, Siren. The Omicron variant, which was spreading rapidly across the globe, had a major effect on how the first quarter began. Across all our operations, we saw considerable decreases in workforce deployments during January and early February. Luckily, this mostly resulted from our COVID screening process and the isolation periods required by governments, rather than from serious illness. Because we lacked visibility into how Omicron would unfold, we pushed back the release of our 2022 guidance to late February. At that point, the Omicron surge was easing and our workforce deployment levels were climbing. I'm happy to report that we remain on track to meet our production guidance for 2022, weighted toward the back end and the second half of the year. This outlook accounts for the substantial effect Omicron had in Q1. It also reflects our expectation that COVID generally will have less of an impact on workforce deployment levels going forward, along with demand sequencing at La Arena and Dolores and ongoing operational improvements at La Colorada. We are likewise keeping our cost guidance for 2022 unchanged. That said, we are right now facing inflationary pressure across the board that is higher than expected, especially for diesel and certain consumables, plus cost pressures and shortages driven by the supply chain. We are closely watching this largely global inflationary pressure and will revise our cost estimates should that become necessary.
Michael Steinmann
executiveDuring Q1, our silver output reached 4.6 million ounces. All-in sustaining costs for the silver segment came in at $13.41 per ounce. Cash costs in that segment stood at $10.23 per ounce. Even with Omicron's effects and inflationary pressure on costs, stronger prices for by-product metals helped bring costs down at Huaron and Morococha. Similarly, at La Colorada, improved by-product metal prices along with better silver grades resulted in reduced costs, even though throughput fell 13% from Q4 owing to Omicron. Manantial Espejo delivered a robust Q1, helped by high grade ore coming from COSE and Joaquin. As we anticipated in our 2022 guidance, mining activities at COSE are now winding down. Q1 silver production and costs took a negative hit from lower grades at San Vicente, caused by greater dilution as the vein structures there narrowed as expected. Before Morococha was placed on care and maintenance in late February, we booked some production and related costs from it during Q1. As we said in February when our 2022 guidance was released, the Amistad processing plant will be decommissioned so a neighboring mine can expand. We finished closure of that plant in Q1, and right now we are looking into alternative opportunities for Morococha — among them monetization, joint venture operations, or speeding up exploration of prospective areas that might make allocating capital toward building a new processing facility more attractive.
Michael Steinmann
executiveNow turning to the results from our gold operations. During Q1, we generated 131,000 ounces of gold. All-in sustaining costs for the gold segment came in at $1,502 per ounce, while cash costs stood at $1,069 per ounce. Lower mined grades stemming from mine sequencing at La Arena, as anticipated, and at Dolores affected gold segment production and costs. Costs in the gold segment during Q1 were also affected by Omicron and inflationary pressures. At Dolores, a sizable net realizable value, or NRV, inventory adjustment pushed all-in sustaining costs at that operation up by $321 per ounce and raised consolidated gold segment all-in sustaining costs by $94 per ounce. As a reminder, NRV inventory adjustments represent accounting adjustments made to recognize the production cost of inventory against the market value of that inventory at the time of assessment. Cash costs are not affected by NRV inventory adjustments. At Dolores, production was affected by lower mined gold grades stemming from mine sequencing and the reconciliation shortfall in Phase 9B of the open pit. This looks like a localized issue, since our model has performed well over the past 3 years, and we are now mining into Phase 10 of the pit. Shahuindo contributed strongly to gold production in Q1, thanks to improved oil blending and weather that was drier than expected, which let us increase the tonnes stacked on the heap.
Michael Steinmann
executiveQ1 revenue came in at $439.9 million, and that figure included inventory drawdowns totaling 531,600 ounces of silver along with 17,600 ounces of gold. Net earnings for Q1 reached $76.8 million, or $0.36 per share. That number includes a onetime $44.6 million fair value adjustment related to our interest in Maverix. We've changed how we account for our interest in Maverix, based on the determination that we no longer have significant influence over Maverix. Our 17% interest in Maverix is now recorded as long-term financial assets on the balance sheet and will not affect quarterly earnings. Adjusted earnings in Q1 were $32 million, or $0.15 per share. Cash flow from operations came to $68.8 million, which includes $58.3 million in cash taxes and a $15.1 million buildup in working capital, largely from timing of accounts payable and receivable. Typically, our annual tax payments are highest in Q1 and in Q2. We're in a strong financial position, with net cash of $224.8 million. Based on the dividend policy we introduced in February, we announced a dividend of $0.12 per common share with respect to Q1. Our dividend policy provides for a base dividend of $0.10 per common share and the supplemental amount tied to the net cash on our balance sheet.
Michael Steinmann
executiveThis lets shareholders share in the upside as financial performance improves, while also supplying liquidity to support our growth projects. Now turning to those growth projects. Earlier this week, we put out additional drill results for the Skarn at La Colorada. During the quarter, we finished close to 26,000 meters of infill and exploration drilling on the Skarn — more than in any other single quarter. Infill drilling verified continuous mineralization across a 400-meter wide zone in the Central Eastern portion of the deposit, and step-up drilling extended the mineralization toward the East, South and West. Since the last resource estimate, dated August 4, 2020, we have now completed more than 100,000 meters of infill and exploration drilling. We also moved our Skarn project forward, advancing precincting for the concrete line ventilation shaft and beginning commissioning of the refrigeration plant. We have been looking into bulk mining methods, which seem to present an appealing alternative for mining the deposit. We will evaluate those methods against an updated resource estimate for the Skarn that we plan to deliver early in Q3, along with the annual company reserve and resource update. At Escobal, the inclusive ILO 169 consultation process is ongoing, with the pre-consultation meeting held on May 9 and the next meeting scheduled for June 5.
Michael Steinmann
executiveAhead of taking your questions, last week we published the sustainability report for 2021. That report covers how we performed against environmental, social and governance metrics, along with the goals we have set in those areas. One thing worth highlighting: we issued a climate change policy statement laying out an attractive to cut our GHG emissions by no less than 30% by 2030, measured against baseline emissions from 2019, plus an aspirational objective of net 0 carbon-dioxide equivalent emissions by 2050. With that said, I'd like to begin the Q&A portion of the call.
Operator
operator<<operator_script>> Our initial question is from Trevor Turnbull at Scotiabank.
Trevor Turnbull
analystMichael, I went to the site for the Escobal consultation process a moment ago, and it appeared that the most recent update was from February. So I appreciate the extra details you just provided regarding the May meeting, and I believe you mentioned the following one would be either June or July. On the website, it did seem as though roughly 12 meetings were required to happen. And so, counting the May and summer ones, that would bring us to 7, it seems. Is that the correct way to think about the duration of the process — that there will be approximately 12 meetings?
Michael Steinmann
executiveTrevor, honestly, I wouldn’t say there’s any fixed number of meetings. I think we’re in a comparable spot to where we were last quarter, when I noted that we were seeing more meetings — and now you can see the schedule is quite a bit fuller. There are far more meetings than we had last year, clearly because of COVID, as I explained on earlier calls: the 2 years of COVID brought a long delay, and for obvious reasons that really kept the Ministry of Mines from calling meetings with many people in person. So at present, and ever since January, we’re seeing these meetings go on every month at minimum, and sometimes in between as well. My assumption is that this will keep going. But Trevor, I don’t believe you can simply tally up some specific number of meetings and declare that it’s finished at 12 — still, I’m definitely encouraged by the schedule we have now. And hopefully COVID will remain under control around the world for all of us. I think all of us hope that, and so far, as I also said on the call, we’re seeing a really big difference compared with the last wave that struck the world — the one we want to call the first Omicron wave.
Michael Steinmann
executiveMy take is that the later waves we’re seeing from Omicron likely won’t matter all that much. Plenty of people have gotten the vaccine. Within the company, our vaccination rate is very high. And for the first time, I believe I can say that worker levels everywhere are pretty much back to normal. So don’t read too much into that. I think things are progressing as hoped for at the start of the year, and we’ll see where it stands.
Trevor Turnbull
analystYeah. No, it's good to hear that it clearly appears to be progressing and perhaps accelerating somewhat. And without seeking any guesswork regarding timing or results. Still, I'm curious whether you could give some indication of how long — assuming you're permitted to restart operations, what sort of lead time would be required to get recommissioned?
Michael Steinmann
executiveSo, the mine is currently under care and maintenance. Under the environmental management plan for that care and maintenance program, there's work we can do and are required to do. Naturally, we keep the underground portion and the mill maintained in good condition. So everything is ready to go. Naturally, we aren't carrying out any stope development or anything of that nature. So that would need to restart, and we'll have to replace some underground equipment and, naturally, bring on a workforce. So as you can imagine, it will take a few months, but as I mentioned -- to get back into production. Yet as I mentioned, the plan for mining everything falls under ongoing care and maintenance programs, and everything is maintained well. So that's where -- and you saw we spent roughly $1.8 million to $2 million each month on that program. So you can imagine a fair amount of work is going into it.
Trevor Turnbull
analystYes. My final question concerns La Colorada Skarn. You have been drilling, and the pending resources are due later this year. It seems you have completed a huge amount of drilling since the previous estimate. By the time you provide the update, it looks like almost 50% more potentially. I know some of the work focused on infill drilling, and some was step-out into the new areas. I just wondered how we should expect the resource update to be focused. Will this be more about upgrading inferred resources? Or will it be more about just adding to the inferred with the step-out holes?
Michael Steinmann
executiveWell, it’s going to accomplish both things, correct? I mean, infill drilling has given us a lot more information. But with the step-out holes, we were obviously still searching for the fringes or the ends of this ore body, and we haven’t found them so far. So as you can see, it remains open in many, many directions — pretty amazing when you look at those holes. And Trevor, if you’re familiar — and surely you are — with this type of Skarn deposit, this is actually a remarkable continuation of the mineralization, right? Usually, lots of skarns I’ve seen during my career have been far, far more variable and irregular than this one. So, so far, so good. It’s growing, still growing, and I’m really looking forward to that resource update. As we said, we’ve drilled over 100,000 meters since the last one, and they’re very active. We have 13, 14 rigs drilling on it constantly. So that drilling is quite a production. And — so just expect both, as I said: a lot of infill drilling, but the step-outs will certainly increase the inferred resource as well.
Operator
operator<<operator_script>> Our following question is from Don DeMarco at National Bank Financial.
Don DeMarco
analystPerhaps, Michael, if we stick with the Skarn and take a few more questions. Yes, we're definitely anticipating that resource update in Q3. But what comes after that resource update? Naturally, there was a PEA that had at one stage been planned, perhaps for some point last year, and it got deferred. What information do you need at this stage to get that back on the calendar, to get a technical report back on the calendar?
Michael Steinmann
executiveRight now, a great deal of effort is being devoted on the engineering side, and the real purpose is to pin down the mining method. You'll recall around November, or late last year, when we discussed this, that we began suddenly encountering these very large, wide, high-grade zones — what we refer to as extremely high-grade zones — and some of the intercepts we released in November showed a value optimization similar to that of our veins. And then, clearly, there's the larger size we're seeing, which keeps expanding in every area. So the fact that we can now consider potentially larger bulk minable, or bulk mining, approaches — that's exactly what the engineering work is focused on, to determine what the mining method will be. As you'd expect, that is the primary cost driver for that mining. And once we've got that settled, well, it will clearly establish the mineable portion of that resource. So those really are the upcoming steps. I believe once that's in hand, we'll understand far better what the daily tonnage will actually be. And that, clearly, will determine the plant size we need to drill and the tailings management we must examine, equipment size, access, et cetera, et cetera.
Michael Steinmann
executiveThat is essentially what comes next. So we should hold off until that resource is available. That truly is step one. A great deal is happening — I'm aware the engineering team is putting in substantial effort on the mining method front, naturally, alongside that. And we're eager to see those results.
Don DeMarco
analystOkay. Yes, same here. So — alright, as my second question, if I can, let's turn to Dolores. Dolores came in well above guidance, and there was some discussion about Dolores on the call. Could you just restate here the factors behind the cost at Dolores and say whether they are temporary and whether you expect that cost to come back down over the remainder of the year?
Steven Busby
executiveDon, this is Steve Busby. In Q1, the main thing pushing that cost higher was that we wound up running ore at a lower grade than we had expected. We mined into a section of Phase 9 of the pit — the open pit — where a high-grade hole from the original exploration drilling on the project suggested we might have stretched a bit too far in that spot. As a result, the ore we hit there came in at a considerably lower grade, and that is really what pushed those costs upward. We look at it as a very localized problem. It sat at the bottom of that pit phase. We have since moved into Phase 10. I want to repeat that the model we work with has not really been changed in 3 years, and it has performed extremely well. So this was just the one area that happened to fall within Q1. But those lower grades pushed the cost per ounce up considerably. That said, COVID was the other major factor — simply not having enough people and not being able to deploy our workforce brought productivity down and drove our unit costs up during that stretch.
Steven Busby
executiveI wouldn't say we really dealt with the sort of inflation figures that we might be seeing now, on average, during Q1. It arrived rather forcefully, as you've observed across the globe—inflation rates for fuel prices, explosives, supplies, and consumables have genuinely intensified over the past couple of months. So I wouldn't really single out inflation factors as having been that significant a driver in Q1. It's something we're very focused on and monitoring very closely right now. But the actual drivers at Dolores were lower grade and the inefficiencies tied to COVID.
Michael Steinmann
executiveJust to add to that, Don — obviously, the NRV adjustment we've seen there on the cost that Dolores sees is quite sizable, and if you take the NRV, it makes a pretty big difference. And there are different drivers behind that. As you know, NRV adjustments are adjustments to the heap, but of course they don't impact our cash costs — they're mostly driven by either metal prices or costs. And definitely, we see the inflationary cost pressure that had an impact on that. And the sooner that comes up, obviously, the sooner we'll probably see a change there, depending on where metal prices go. But definitely, higher energy costs across the world and the inflationary pressure we see everywhere in the world and in our daily lives have an impact on this kind of noncash adjustment as well.
Don DeMarco
analystAlright, alright. Then for a third question, I'd like to turn to one of your assets that receives relatively little attention, La Arena II. Could you simply outline what your strategic plan is for that asset? Is it a candidate for divestment? Do you intend to drill it, possibly expand it, or publish an updated technical report — or perhaps develop it at some stage?
Michael Steinmann
executiveYes. I believe there are two primary factors why it doesn't receive much attention. The first is that Chris and his team have been remarkably effective in exploration, extending the lifespan of what I'll refer to as La Arena I, or the oxides — the gold output at La Arena. I remember three years back, when we examined the assets and our resources, we assumed that the La Arena oxide, the existing mine, would be exhausted by 2021, yet we are still drilling there successfully. We'll find out what results come from our new resource and reserve update at midyear, but the outcome there is very positive. So we've now added a considerable number of years of extra gold production from the oxides at La Arena I. And that, I think, is among the reasons nobody focused on it when we completed the transaction — I received quite a few inquiries regarding La Arena II, but I don't necessarily — everyone assumed La Arena I had a very brief life, which clearly has changed quite dramatically. That's one factor. There's certainly more time available now, and many people are examining it because when Power conducted their technical study, I believe they employed roughly $3 to $3.30, somewhere in that vicinity, to carry out the study.
Michael Steinmann
executiveAnd as you might expect, three years back that didn't seem particularly appealing. Now it appears quite appealing as a substantial copper-gold project. And just to remind anyone who isn't acquainted with La Arena II, it's essentially the copper-gold porphyry located beneath the La Arena I open pit, and it would essentially extract the existing pit and create a larger pit underneath. And it's a copper-gold porphyry, roughly about 75% copper, 25% gold revenue. So definitely a type of asset that many precious metal companies are seeking. So a significant shift has occurred over the past few years. And I think it hasn't been on the radar for some time, as I mentioned, because of metal prices and because we simply continue producing gold at La Arena likely for quite a while longer, obviously, but it has definitely begun to attract more interest, and they are steadily drawing more interest on my side too, as you might imagine, at today's copper prices, at the copper price outlook, and in fact, as I said, many process metals companies are looking for porphyries, copper-gold porphyries, and we already hold one in the portfolio.
Michael Steinmann
executiveSuch a really fascinating initiative.
Don DeMarco
analystAlright, we’ll be watching for that resource update in Q3, and best of luck over the next few quarters.
Michael Steinmann
executiveThanks, Don.
Operator
operatorThat brings the Q&A portion to a close. At this point, I'd like to hand the conference back to Michael Steinmann, who may offer some closing comments.
Michael Steinmann
executiveAppreciate it, operator, and thanks to all of you for joining the call. I'm looking forward to bringing you an update on our Q2 results — which will be, well, August before we know it. So make the most of spring and the start of summer, and we'll talk in August. Thanks, everyone.
Operator
operatorThat brings us to the end of today's conference call. Your lines can be disconnected now. We appreciate you joining us, and we hope the rest of your day is pleasant.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Pan American Silver Corp. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Pan American Silver Corp. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Pan American Silver Corp. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.