Patel Engineering Limited (531120) Earnings Call Transcript & Summary
November 13, 2025
Earnings Call Speaker Segments
Operator
operatorLadies and gentlemen, good day, and welcome to the Patel Engineering Limited Q2 and H1 FY '26 Earnings Conference Call. [Operator Instructions] Please note this conference is being recorded. I now hand the conference over to Mr. Harsh Patel. Thank you, and over to you, sir.
Harsh Patel
attendeeThank you, and good evening, everyone. On behalf of Share India Securities, I would like to welcome all the participants for Q2 FY '26 Earnings Conference Call of Patel Engineering Limited. We are pleased to have with us the management team represented by Managing Director, Ms. Kavita Shirvaikar; and Chief Financial Officer, Mr. Rahul Agarwal. We will have the opening remarks from the management, followed by Q&A session. Thank you, and over to you, ma'am.
Kavita Shirvaikar
executiveThank you, Harsh. Good evening, everyone, and thank you for joining our Q2 and H1 FY '26 earnings call. We have uploaded the presentation summarizing the company's performance for the quarter and half year ending September 2025, along with the results on the stock exchange. I hope you have had the opportunity to review the same. During this quarter, there was a heavy impact of monsoon in some of our project sites. Despite all challenges, we have been able to achieve around INR 1,200 crores revenue for the quarter. This progress is dedicated to the hard work and commitment of the entire Patel team. I will now walk you through some of the key operational highlights for this quarter. At our Subansiri project, which is located in Arunachal Pradesh, the wet commissioning of the first unit of 250 megawatts out of total 8 units was successfully carried out and the full commissioning of this unit and integration of the power grid is expected shortly for this unit. Further, post the quarter, the second unit wet commissioning is also in progress, and we expect that all the balance units shall also be completed in the coming few months. At Kwar Hydropower project, which is in Jammu & Kashmir, we achieved daylighting breakthrough of the Dam Top Road tunnel and breakthrough in the upper horizontal portion of the pressure shaft 4. We successfully completed pouring of about 1.5 lakh cubic meter of concrete in the project. At the CIDCO water tunnel project located in Mumbai, we achieved a record-breaking 752 meters of tunneling in a single month, one of the highest ever monthly urban tunneling progress recorded in India. At PGRW project, which is an underground water tunnel located in Mumbai, we completed 2,045 meters of tunneling using a 2.8 meter diameter TBM and achieved a breakthrough at the Ghatkopar lower-level reservoir shaft, marking completion of the TBM excavation. There were various challenges pertaining to geology, which the company overcame through rigorous planning and execution. At our T-7 tunnel project site located in Sikkim, we completed the concrete lining works in all aspects, which is significant milestone towards the completion of India's first underground broad-gauge railway station. This quarter, we have been able to achieve a consolidated revenue of INR 1,208 crores, growth of around 3% for the quarter as compared to the corresponding quarter in previous year. And on a half year basis, revenue has increased by around 7% to INR 2,442 crores from INR 2,276 crores in corresponding period last year. Our net profit is at INR 77 crores. And for the half year, it is INR 152 crores. During this quarter, we have settled a litigation in U.S. with insurance companies for USD 5 million against the claim of USD 40 million. This was a claim of indemnity against sureties given by them for one of our subsidiaries where operations were closed earlier. Based on legal advice obtained, there was no adverse outcome expected. But to save on future litigation and other travel administrative costs involved, we agreed to settle this case for a value which would have been anyway incurred to fight this litigation over the next few years with the risk of outcome still open. Now coming to our debt position. Our debt as on September 25 is INR 1,543 crores as compared to INR 1,527 crores in last quarter. During the quarter, we raised an [ NCT ] of INR 90 crores, which carried a coupon of 10.25% per annum having a tenure of 3 years, and we have repaid OCT of around INR 100 crores. Post end of the quarter, we have completed sale of Chengalpattu land parcel in Chennai and realized around INR 135 crores, which shall be utilized to reduce debt. Further, in the quarter, we also received a letter of award for one project, the Teesta-V, by NHPC. The project is located in Sikkim. Now moving on to order book. As of September 30, 2025, our order book stands at INR 15,146 crores. Out of that hydro is 62%, irrigation is 20%, 7% from tunneling and remaining 11% from urban infra and other segments. We have submitted tenders of around INR 34,000 crores, which are currently under evaluation, and we expect it will be open in coming few months. Further, we have projects identified of around INR 18,000 crores, which are in the pipeline and expected to come up for bidding in the near future. We anticipate a healthy order inflow for the remainder of FY '26. This is apart from a list of tenders of more than INR 1 lakh crores worth projects, which will be coming up for bidding in the near future. We are hopeful of achieving our target order inflow of around INR 8,000 crores to INR 10,000 crores in next 6 months. Globally, India is the third largest producer and consumer of electricity. As of September '25, non-fossil fuel accounted for 256 gigawatts, which is 51% of the total installed capacity. India's target of 500 gigawatts of nonfossil fuel capacity by 2030 would double the current capacity. This would mean huge spend by government in this segment. And the government has proposed to increase investment in power sector through its 9 PSUs by 21% to INR 86,000 crores in 2025, '26 project. These investments are allocated to all green energy projects. Further, there has also been progress made on river interlinking projects so far. Detailed project reports have been completed for 11 such projects. The [indiscernible] project was the first to start and has already seen an investment of over INR 3,900 crores. These upcoming projects will help provide water for farming, drinking and also generate clean electricity. Also, there are multiple road, railway, metro tunnels and open excavation projects coming up, which will add diversity in our order book. It's a huge set of upcoming projects. And to ensure that we are ready to undertake large value projects, Board of Directors has decided to raise fresh capital of up to INR 500 crores via rights issue, which will ensure that all existing shareholders are given an opportunity to invest. These funds shall be utilized for debt servicing so that the cash flow from operations shall be available for deployment in new projects as we expect huge inflow of new orders. Before I conclude, I would like to share a few moments of pride that reflect the dedication of our team. We were honored to be recognized as the fastest-growing construction company in medium category at the 23rd Construction Times Global Awards 2025. We also achieved an important safety milestone, 11 million safe man hours at the Parnai project. This achievement is a testament to our unwavering commitment to safety and quality, which are values that remain at the core of everything that we do. The government's strong focus on hydropower, pump storage and tunneling is well aligned with our core strengths. Further, there is a huge opportunity coming up in metro and other works. This is creating a large pipeline of new opportunities. We remain committed to timely execution and steady sustainable growth. Thank you. Now I will ask Rahul to take you through the company's financial numbers.
Rahul Agarwal
executiveThank you, Kavita, and good evening, everyone. I will now take you through the company's financials for the quarter and H1 FY '26. On a consolidated basis, the revenue for the quarter is INR 1,208 crores, up by 3% year-on-year, driven by a strong project execution. Operating EBITDA for the quarter is INR 159 crores, which is a margin of 13.13% and profit after tax stands at INR 77.35 crores with a margin of 6.4%. On a stand-alone basis, the revenue is INR 1,198 crores, an increase of 3.74%. Operating EBITDA is INR 151 crores with a margin of 12.6% and profit after tax is INR 64 crores with a margin of 5.37%. Sector-wise revenue breakup for the quarter, hydro is 55%, irrigation is 28%, tunneling is 10%, roads and others are another 7%. And our book-to-bill ratio currently stands at around 3.1. Now moving to the numbers for the half year. On a half yearly basis, our consolidated revenue is INR 2,442 crores, up by 7.29%. Operating EBITDA is INR 324 crores, a margin of 13.27%. Profit after tax has increased by around 18% and stands to INR 152 crores with a margin of 6.24%. On a stand-alone basis, revenue is INR [ 2,422 ] crores, an increase of 8%. Operating EBITDA is INR 310 crores with a margin of 12.79%. Profit after tax is INR 134 crores with a margin of 5.5%. Moving to debt. The total debt as of September is INR 1,543 crores, out of which working capital debt is INR 1,014 crores and remaining is term debt of around INR 529 crores. This debt has reduced from INR 1,603 crores as of March '25, so a reduction of INR 60 crores. Total debt and contracted advances as of 30th September is INR 2,100 crores compared to INR 2,267 crores as of March '25. Hence, overall serviceable debt has also reduced by INR 164 crores during the first 6 months. Finance cost for the quarter is INR 79 crores as compared to INR 76 crores in the corresponding quarter in the previous year. Overall debt to equity stands at around 0.39 and net working capital base is 125 days. That was all on our Q2 FY '26 results brief from our side. Now we are happy to take any questions that you may have. Thank you very much.
Operator
operator[Operator Instructions] The first question is from the line of Dhananjay Mishra from Sunidhi Securities.
Dhananjay Mishra
analystAm I audible? I hope I am audible.
Rahul Agarwal
executiveMr. Dhananjay?
Dhananjay Mishra
analyst[Foreign Language] So numbers are on...
Rahul Agarwal
executiveVijay, you can get onto the next question. And we can take him later.
Dhananjay Mishra
analystAm I audible, sir?
Rahul Agarwal
executiveYes. Yes.
Dhananjay Mishra
analystSo Dhananjay here from Sunidhi Securities. So just wanted to know this extra INR 31 crores...
Operator
operatorSir, requesting you to please rejoin the queue because the management cannot hear you. The next question is from the line of Viraj Mahadevia from MoneyGrow.
Viraj Mahadevia
analystCongratulations to the management team for setting a strong foundation. A couple of questions. Your cash collections have been very robust in the first half. What exactly happened there? Because your receivable days are down to 52 days...
Rahul Agarwal
executiveWe are not able to hear anything.
Viraj Mahadevia
analystCan you hear me?
Operator
operatorMr. Viraj, can you have a few lines from your end?
Viraj Mahadevia
analystYes. Can you hear me? Can you hear me? Other participants can hear me. I think I could hear the other participant as well. I think there's a problem with the management line. Can you hear me? Can you ask the management please to dial back in? I think the problem is their end.
Operator
operatorLadies and gentlemen, I request you to please stay connected. I will just disconnect the management and connect them again. The next question is from the line of from [indiscernible] Unique PMS.
Unknown Analyst
analystIf I look at the consolidated segment reporting, there has been a substantial increase in profit in the civil construction segment. So what are the reasons for that's?
Rahul Agarwal
executiveSorry, can you once again please repeat the question?
Unknown Analyst
analystYes. If I look at the consolidated segment reporting, there's been a substantial increase in the profitability for the civil construction segment. So what led to that increase in profitability? And also, again, looking at the real estate segment, there's a loss. So what are the reasons for that loss?
Rahul Agarwal
executiveSo there is no actually revenue as such during the current quarter from the real estate segment. It's only operational expenses. And one settlement of a contractor, if you have -- for the real estate segment, that should be showing in the loss.
Unknown Analyst
analystOkay. And so all the profitability that is improved is in the civil construction segment?
Rahul Agarwal
executiveCorrect. Correct.
Unknown Analyst
analystOkay. And second question on this rights issue. So we were expecting a lot of money from these noncore asset sets in there. So while that is there, we are also raising money via rights issue. So can you explain the rationale behind this.
Rahul Agarwal
executiveSo the timing of the cash flow requirement is the question. So we are -- as told on the call, we have sold one land bank, but that money is going to repay the debt. Now if we raise some funds right now, we can use funds for new projects. And because there are so much projects in pipeline, we have bidded for around INR 34,000 crores. Another INR 18,000 crores, we'll bid before March. And next year, another INR 1 lakh crores is coming up for bidding. So we are wanting to have money so that we are easily able to plan these projects.
Unknown Analyst
analystOkay. And 1 or 2 clarifications. So one, do we have any business -- operational business in the real estate segment or...
Rahul Agarwal
executiveNo, we don't have any operational business right now in the real estate segment. We have shut that business down. There's one project which we had done in Hyderabad, which OC is still pending, but the project is completed. So apart from that, nothing in the real estate business.
Unknown Analyst
analystOkay. And secondly, we reported some settlements on the exchange. So have all those settlements been accounted in Q2 results or anything is pending?
Rahul Agarwal
executiveNo, no, everything is accounted.
Unknown Analyst
analystOkay. And thirdly, in the cash flow statement, there was a INR 65 crores ex credit written back. So that was also netted off in the exceptional items, right?
Rahul Agarwal
executiveNo, no. See, mostly, it will be part of other income.
Unknown Analyst
analystOkay. Part of the other income.
Operator
operatorThe next question is from the line of Viraj Mahadevia from MoneyGrow.
Viraj Mahadevia
analystCan you hear me now?
Operator
operatorYes. You are audible.
Viraj Mahadevia
analystSorry for earlier. Congratulations on the steady shift and I think exciting years ahead. Sir, a quick question. Cash collections were very robust in the first half. What happened there? Your receivable days are down to 52 days. Is that sustainable?
Rahul Agarwal
executiveSo see, the first half for the year has been pretty good. And generally, the last quarter is also good. So we see that our receivable days between 45 to 60 days. So that should be there.
Viraj Mahadevia
analystThat's a meaningful change from earlier, right, Rahul, because we were -- 2 years ago, we were at 114, then down to 80, down to high 60s. Now you're saying 45 to 60. Going forward, is it sustainable? Is it part of the contract?
Rahul Agarwal
executiveYes, yes. So once the bills are getting certified, they're getting paid in 45 to 60 days.
Viraj Mahadevia
analystFantastic. That's going to make a huge difference in your cash flow profile. Okay. Great. Second question is your inventories have been restated from INR 4,386 crores in March '25 accounts to INR 1,092 crores as of current statement for March '25. Can you explain what happened there?
Rahul Agarwal
executiveSo there's a reclassification. The inventory has been moved to other current assets and other noncurrent assets.
Viraj Mahadevia
analystWhy is that?
Rahul Agarwal
executiveSo based on accounting policies, we reviewed for other entities also, and they are moved -- basically the WIP has been moved to as contract assets in other current and noncurrent assets.
Viraj Mahadevia
analystIs that market and accounting practice? And why was it not being followed till now?
Rahul Agarwal
executiveNo, no. So it is a policy practice which some companies follow and some do not. This time, we've discussed a lot in length with auditors, and we were convinced that we should also do it.
Viraj Mahadevia
analystOkay. Okay. My next question...
Rahul Agarwal
executiveEssentially, what also marks is the portion of which completed projects has been moved to noncurrent assets.
Viraj Mahadevia
analystSo this has nothing to do with your settlements in regards to Vishwas scheme or anything like that?
Rahul Agarwal
executiveNo, no, nothing like that.
Viraj Mahadevia
analystOkay. Next is your improvement in ratings. Are you expecting further ratings review given the [indiscernible] asset sales in the months ahead? And are you also seeing and negotiating lower borrowing costs?
Rahul Agarwal
executiveSo negotiation of lower borrowing cost is a continuous process. As and when the banks take it for renewal, we -- based on the recent improvement in the ratings, we request for the reduction in interest cost. And we are looking that some banks have started reducing also. As regards rating upgrade, we see that post March, we will go again, request for an upgrade.
Viraj Mahadevia
analystUnderstood. How much of your loans are fixed versus floating interest rate loans? Where do you get the benefit if the entire rate curve comes down?
Rahul Agarwal
executiveSo it is all the working capital loans are floating.
Viraj Mahadevia
analystRight. And fixed -- the term loans?
Rahul Agarwal
executiveThe term loans are mostly fixed.
Viraj Mahadevia
analystTerm loans are fixed. So that's what we are repaying faster and we take advantage on the working capital.
Rahul Agarwal
executiveYes.
Operator
operator[Operator Instructions] The next question is from the line of Dhananjay Mishra from Sunidhi Securities.
Dhananjay Mishra
analystSo just wanted to know based on whatever bid pipeline we have and another INR 18,000 crores bid that we are going to do. So you said INR 7,000 crores to INR 8,000 crores order inflow for next year, right? And what is the number -- guidance for this year, FY '26?
Rahul Agarwal
executiveSo FY '26 only, we had said INR 8,000 crores, INR 2,500 crores we have already done. Balance, we are expecting next 5, 6 months, it should come.
Dhananjay Mishra
analystSo next 4, 5 months, I mean, how many bids are going to be finalized and out of the 34,000 bids we have completed? Any idea on that?
Rahul Agarwal
executiveSee, we expect that most of this should come out in the next 6 months.
Dhananjay Mishra
analystOkay. So we are pretty confident of achieving these numbers INR 7,000 crores to INR 8,000 crores?
Rahul Agarwal
executiveYes, yes.
Dhananjay Mishra
analystAnd secondly, again, coming back to this extraordinary INR 31 crores. So in Note 5, we have mentioned that apart from this settlement claim, there was also a provision write-back for associate company. So what is the breakup of INR 31 crores? What was the settlement we had to pay? And what was the write-back we got from associate company?
Rahul Agarwal
executiveSo the settlement, what we have to pay for the U.S. settlement, which is $5 million, around INR 44 crores, INR 45 crores and rest INR 13 crores, INR 14 crores is the write-back of provision.
Dhananjay Mishra
analystOkay. So INR 14 crores, INR 15 crores we have provision in write-back?
Rahul Agarwal
executiveYes, yes.
Dhananjay Mishra
analystOkay. And what is the margin outlook going ahead in H2?
Rahul Agarwal
executiveMargin outlook will be similar, 13%, 14%.
Dhananjay Mishra
analyst13%, 14%. And you also mentioned that we are entering into the new sector, I mean, to diversify. So which all sector and whether -- the upcoming bids of INR 18,000 crores, whether we are entering into new sector where we are going to be?
Rahul Agarwal
executiveSo we are looking at some sectors like maybe Kavita can answer more, but metro or other excavation and all that.
Kavita Shirvaikar
executiveSo related segment only, like there is a lot of work coming in underground metro and surface metro. So we are exploring the opportunity available in the sector, selectively road sector and metro, that we are planning to enter into. And some related work excavation work, earth work. That also we will explore.
Dhananjay Mishra
analystAnd we will be bidding standalone or we are going to do some joint venture with some other players who already have proven track record in these segments?
Kavita Shirvaikar
executiveSo it will be decided based on the project which will be coming up for bidding. So based on the PQ criteria, we'll decide.
Operator
operatorThe next question is from the line of Varun Mishra from SK Investment.
Unknown Analyst
analystSo I just wanted to know about the recent NCD, which we have raised, like what will be like utilizing the funds for? Also as of now, how much of the funds has been utilized and how much still remains to be like utilized? Could you give a bifurcation for that?
Rahul Agarwal
executiveSee, as of now, we've utilized everything.
Unknown Analyst
analystAll right. We've utilized everything.
Rahul Agarwal
executiveYes. Yes.
Unknown Analyst
analystAll right. And like what has been like the purpose of that, if you could clarify a bit on that?
Rahul Agarwal
executiveThe purpose was completely replacement of debt only. So we had other debt to be repaid. So it is a replacement of debt.
Unknown Analyst
analystAll right, sir. And any further plans for fundraising for CapEx or anything like that, sir?
Rahul Agarwal
executiveSo we have proposed the right issue and this Board has approved up to INR 500 crores. So that we will be taking up at the right time. It is that we have taken a Board approval and kept for that.
Unknown Analyst
analystAll right. And like what is the long-term potential for orders, like which we see for like us with respect to CEA and the recent announcement related to the hydropower capacity transmission from the Brahmaputra Basin? If you could throw some light on that.
Rahul Agarwal
executiveSo you're talking about that 76 gigawatt transmission?
Unknown Analyst
analystYes. Yes, sir.
Rahul Agarwal
executiveSo there are a lot of opportunities. See, that is the reason we are now looking at raising capital so that we are ready when these projects come up because not only hydro, other segments are also coming up, and there are many, many opportunities there.
Operator
operatorThe next question is from the line of Jeet Gala from Centra Insights LLP.
Jeet Gala
analystCan you hear me?
Rahul Agarwal
executiveYes.
Jeet Gala
analystSir, the new order rate has been slow, right, in the first half. So we've added some INR 2,500 crores and probably expecting another INR 6,000 crores, INR 7,000 crores for the second half. So what is the trend of new order coming in that happened in last year first half? If you can just -- can explain why the order flow is very slow this time?
Rahul Agarwal
executiveSee, last year was an exceptional year because of elections, the order inflow was very low. And before that year, it was -- last 2 years before that, around INR 4,000 crores, INR 5,000 crores per year was there. And it is not fixed. Actually, it depends upon when the bid happened and when they will complete everything and open. So what we have seen right now is a lot of bidding has already been done, around INR 34,000 crores. And so we expect them to open -- start opening any time. That's why we said a few months, it will...
Jeet Gala
analystUnderstood. And sir, we have a long-term debt of around INR 525 crores. So what is the repayments for the -- repayments coming up in the next 6 months and in FY '27?
Rahul Agarwal
executiveSo between next 6 months -- next 6 months will be around INR 30 crores, INR 40 crores, and FY '27 is around INR 150-odd crores.
Jeet Gala
analystAll right. And sir, the entire money of rights will go towards debt servicing, largely long-term debt?
Rahul Agarwal
executiveSo what we will do is we will use the money to service the debt so that the operational cash flows can be redeployed in the business.
Jeet Gala
analystSo working capital closure also is what you're looking at?
Rahul Agarwal
executiveYes.
Jeet Gala
analystOkay. And sir, I'm actually new to the company. So if you can just highlight what are the noncore assets of the company that probably you are looking to monetize in the next 1 year?
Rahul Agarwal
executiveSo we are looking at raising money around INR 150 crores, INR 200 crores from noncore assets in the next 1 year.
Jeet Gala
analystThis is in addition to INR 135 crores that we already did, right?
Rahul Agarwal
executiveYes, INR 135 crores we have done. Additional next 1 year by FY '27, this much more can happen.
Jeet Gala
analystUnderstood. And sir, any guidance for FY '26, what will top line and margins look like for the balance 6 months?
Rahul Agarwal
executiveSo this year, we had given because of last year, order inflow was less, so only marginal growth around similar INR 5,000 crores as last year and margins around 13%, 14%.
Jeet Gala
analystOkay. And sir, can you help me understand the margin profile with respect to the order book breakup? I mean, is hydro a better margin profile work or is irrigation better or is tunneling better? I mean just within the work profile, I mean, which kind of has a better margin?
Rahul Agarwal
executiveSo traditionally, hydro has been a better margin, maybe 100, 200 basis points better than the others. And irrigation and roads have been lower. So on an average, it is around 13%, 14%.
Jeet Gala
analystUnderstood. And sir, one last question, sir, when you said book-to-bill ratio of 3.1, it is which what you are doing, right INR 15,000 crores of order divided by INR 5,000 crores every year kind of a number that you're working at, right?
Rahul Agarwal
executiveThat's correct right now.
Operator
operator[Operator Instructions] The next question is from the line of Vivek Gupta from Star Investments.
Unknown Analyst
analystSo sir, can you provide a brief on the order pipeline and which states are you planning to focus on, if I may, for the project bidding?
Rahul Agarwal
executiveSee the order pipeline, around 50%, 60% is from the hydro PSP segment only. And so the states generally for hydro is in the north, like J&K, Himachal, Northeast. PSP is coming up in other states also. Then there are other segments, for example, irrigation projects, urban infra projects and tunneling projects. So this has all spread across various states, Maharashtra, Chhattisgarh, everywhere.
Unknown Analyst
analystOkay. Okay. So could you please elaborate on the amount by which you intend to lower your debt during the current fiscal year?
Rahul Agarwal
executiveSo current fiscal year, see, we will -- we are expecting debt to go down by another INR 100-odd crores from now.
Operator
operatorThe next question is from the line of Bhavya Shah from Wallfort PMS.
Bhavya Shah
analystMy question is what is the interest cost that we are estimating for the financial year '26 on the consolidated level?
Rahul Agarwal
executiveSo right now, we are somewhere around INR 75 crores, INR 76 crores a quarter. So this around should be there.
Bhavya Shah
analystSo by that calculation, it should be around INR 280 crores to INR 300 crores?
Rahul Agarwal
executiveYes, yes, correct.
Bhavya Shah
analystSo wouldn't we get the benefit of interest rate reduction that has happened in last couple of months at the same time, the reduction of the debt?
Rahul Agarwal
executiveYes. So see, last year, we were at around INR 330 crores. So this year, almost 10% reduction is there.
Bhavya Shah
analystOkay. And any update on the promoter share that has been pledged? Any update on the release of that?
Rahul Agarwal
executiveSo not yet, but we are working on them. Let's see maybe by March or post March, something should work.
Operator
operatorThe next question is from the line of Viraj Mahadevia from MoneyGrow.
Viraj Mahadevia
analystSo these recent litigations were settled, you said it's totally settled. Are there any other such litigations or disputes that are still pending?
Rahul Agarwal
executiveSo Viraj, there are no such material litigations which we have against us right now. I mean, obviously, there are arbitration awards and claims that we have...
Viraj Mahadevia
analystThat's separate. I mean, yes.
Rahul Agarwal
executiveYes. So there is nothing material against us.
Viraj Mahadevia
analystOkay. Great. My next question is there were some very large hydropower projects coming up for bidding towards the end of this year. Is the INR 30,000 crore bid, does it include that? Or is that still to be put in as a bid going ahead?
Rahul Agarwal
executiveSo one is already bidded. One...
Viraj Mahadevia
analystHow large is that project, if I may?
Rahul Agarwal
executiveAround INR 15,000 crores plus.
Viraj Mahadevia
analystOkay. So that bid is already in. And when is the results expected for that?
Rahul Agarwal
executiveMaybe 3, 4 months.
Viraj Mahadevia
analystOkay. Understood. And given -- so congratulations, obviously, on the land monetization, Chengalpattu, 200 acres. We've been asking for this for some time. So this year, between arbitration and this land monetization, should we have upwards of INR 200 crores coming?
Rahul Agarwal
executiveWe do expect that, yes.
Viraj Mahadevia
analystOkay. And your land in Telangana, 430 acres, is that prime land or is it rural land? Because I believe land prices in that region are really skyrocketing.
Rahul Agarwal
executiveSo it is actually a little outkirts.
Viraj Mahadevia
analystOkay. And Panvel land is obviously very prime and getting more prime with completion of the airport.
Rahul Agarwal
executiveYes, hopefully.
Viraj Mahadevia
analystAny plans to monetize that anytime soon?
Rahul Agarwal
executiveNo, we are -- actually for Panvel, we are waiting and we are evaluating various options what would be the best way to monetize that land also.
Viraj Mahadevia
analystUnderstood. Great. And I saw your debt with 25% of the projects 50% to 70% completed and 20% of them 30% to 50% completed, presumably FY '27 and FY '28 should be big years for the company. Is that correct, in terms of growth, revenue growth?
Rahul Agarwal
executiveYes, we are also expecting that.
Viraj Mahadevia
analystFantastic. And the rights proceeds are entirely for working capital to improve your ability to bid for further projects? Or is it also for debt paydown?
Rahul Agarwal
executiveSo the way we are taking it is we will use it for debt repayment so that next year, all debt repayments we are doing from this. And so that we can use the operational cash flows from -- for the working capital or mobilization of new projects.
Viraj Mahadevia
analystUnderstood. So immediately, the rights money will go towards debt paydown and then you will draw on your working capital [indiscernible].
Rahul Agarwal
executiveRight. Right. So that way, we can save on interest cost.
Viraj Mahadevia
analystAbsolutely. Any time line for this rights plan?
Rahul Agarwal
executiveNot fixed yet. I mean we will see now. We've just taken some...
Operator
operator[Operator Instructions] The next question is from the line of [indiscernible] Capital.
Unknown Analyst
analystSo we have targeted an order book of INR 25,000 crores by the end of FY '26. So are we still on track to achieve that?
Rahul Agarwal
executiveWe are looking at around INR 8,000 crores total by this year. So with that, it should happen.
Unknown Analyst
analystSo INR 8,000 crores in H2?
Rahul Agarwal
executiveINR 8,000 crores total for the year, so another INR 6,000 crores.
Unknown Analyst
analystAll right. All right, sir. And also can we reach like INR 6,000 crores or maybe INR 5,500 crores revenue by FY '27 and maybe like a 15%, 16% EBITDA margin?
Rahul Agarwal
executiveThat is our target.
Unknown Analyst
analystAnd is this your target or maybe even higher than this?
Rahul Agarwal
executiveNo, the first target is that only, that 10% to 15% growth we get the next year.
Unknown Analyst
analystAll right. And for margin?
Rahul Agarwal
executiveMargin-wise, it's a similar profile, 13%, 14%.
Operator
operatorThe next question is from the line of Bhavya Shah from Wallfort PMS.
Bhavya Shah
analystSo again my question is, is there any change in employees spend from quarter-on-quarter? Like what is the employee spend as of now we have?
Rahul Agarwal
executiveAround INR 4,600 crores.
Bhavya Shah
analystAnd is that an increase or a decrease as compared to the last quarter?
Rahul Agarwal
executiveMinor increase only.
Bhavya Shah
analystOkay. And I think one of the participants asked about rights issue. So is the promoter category going to participate in this rights issue? Or is there any clarity on that?
Rahul Agarwal
executiveSo we expect them to participate.
Operator
operatorThe next question is from the line of Viraj Mahadevia from MoneyGrow.
Viraj Mahadevia
analystRahul, there were some cost optimization initiatives that you all were piloting. Have you made any meaningful progress on that? And can you guide towards any kind of savings starting FY '27?
Rahul Agarwal
executiveIt is difficult to put a number to it, but we are working on various options for that. And...
Viraj Mahadevia
analystWould you like to maybe detail that in the subsequent call?
Rahul Agarwal
executiveYes, yes. We can detail that in the subsequent call.
Operator
operatorThe next question is from the line of Rajeev Rupani, an individual investor.
Rajeev Rupani
attendeeSir, I had a follow-up question on the promoter pledge. So you just informed us that post March, you will request the bankers for release of some pledge. So let's say, 1 year from now, what will be the promoter pledge? What percentage can the promoter pledge come down to?
Rahul Agarwal
executiveSo if discussions with lenders go well, we are targeting around -- pledge going down to around 50%, 60%.
Rajeev Rupani
attendeeOkay. And my next question was on the arbitration awards. So what amount can we expect going forward in this year and next year? Any amount expected?
Rahul Agarwal
executiveSo see, between arbitration awards and real estate monetization, we had kept a target around INR 150 crores, INR 200 crores each year.
Rajeev Rupani
attendeeSo what we have realized is full from the real estate. So any amount expected from the arbitration awards?
Rahul Agarwal
executiveYes, maybe INR 50 crores, INR 60 crores.
Rajeev Rupani
attendeeIs that in the current year or next year?
Rahul Agarwal
executiveCurrent year, current year.
Rajeev Rupani
attendeeAnd any estimate for next year?
Rahul Agarwal
executiveNext year, again, see, it is difficult to say anything between arbitration award and real estate. We are saying between INR 150 crores, INR 200 crores should come next year also.
Rajeev Rupani
attendeeOkay. And now we have submitted tenders for about INR 35,000 crores. So out of this, how much for pump hydro storage projects?
Rahul Agarwal
executiveOut of INR 34,000 crores, pump hydro storage is around 10%.
Rajeev Rupani
attendeeOkay. And going forward, will this bid submitted increase next year?
Rahul Agarwal
executiveYes. Pump storage projects, we are expecting an increase in the bidding.
Rajeev Rupani
attendeeOkay. And my last question was on the tunneling part. So any orders expected going forward for tunnels?
Rahul Agarwal
executiveTunnels also we have bidded and more projects are coming up for tunnel. So we should be getting -- so generally, if we have our order book mix what we have today, in between it may go higher, but it may be remaining in the same range in the longer period.
Rajeev Rupani
attendeeAnd this land which we have sold, is the full 200 acres in Chengalpattu have been sold?
Rahul Agarwal
executiveYes, yes, it is all together.
Operator
operatorLadies and gentlemen, that was the last question. I now hand the conference over to the management for the closing comments.
Kavita Shirvaikar
executiveThank you, everyone.
Rahul Agarwal
executiveThank you all, and we can take your call separately on e-mail or whatever if you have more. Thank you.
Operator
operatorOn behalf of Share India Securities, that concludes this conference. Thank you for joining us. You may now disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Patel Engineering Limited transcript — plus 251,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Patel Engineering Limited earnings transcripts and 251,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.