Pilbara Minerals Limited (PLS) Earnings Call Transcript & Summary
July 29, 2025
Earnings Call Speaker Segments
Operator
operatorHello, and thanks for being with us today. Welcome to the PLS June 2025 Quarterly Activities Report. <<operator_script>> Kindly note that this conference is being recorded at present. I'll now pass the call to our first presenter of the day, PLS Managing Director and CEO, Dale Henderson. Please proceed.
Dale Henderson
executiveThank you, Maggie. Good morning and good evening, everyone. We appreciate you being with us today. First, I want to acknowledge the traditional owners of the lands where PLS operates. Here in Perth, that's the Whadjuk people of the Noongar Nation. We also recognize the Nyamal and Kariyarra people, whose land hosts our Australian operation in the Pilbara region. Our respects go to their elders, past and present. With me today are Flavio Garofalo, our Interim CFO, and Brett McFadgen, our Chief Operating Officer. Other members of the senior team are also on the line. This call should last roughly an hour. We'll start with a presentation covering our June quarter performance, then go through our FY '26 guidance and market commentary, and wrap up with Q&A. Questions submitted through the webcast will be addressed at the end of the session. The June quarter was a pivotal milestone for PLS, as we finished our major capital investment cycle and moved into a new phase of operational excellence and performance, supported by our industry-leading technology. We achieved several critical objectives, and the key one was the successful optimization of the Pilgan Plant after completing the P1000 expansion, which delivered significantly higher production volumes and enabled lower cost performance.
Dale Henderson
executiveAnd it's important to note that we delivered these results while keeping our fortress balance sheet intact — we ended the quarter with roughly $1 billion in cash, which gives us the strength and flexibility to lead through the cycle as the market rebalances. The June quarter wraps up what has been a landmark year for PLS. FY '25 was genuinely transformational, and we're looking forward to sharing more detail when we release our full year results this August. Since the quarter closed, we've seen renewed market volatility, this time moving in our favor. I'll speak more to that later in the presentation. Please turn to Slide 2. PLS is the world's largest independent hard rock lithium producer. Our independence gives us agility and responsiveness in a fast-changing global market. The foundation of our business is the high-quality, long-life Pilgangoora operation in Western Australia. The P680 and P1000 expansions have created a leading process platform with increased capacity and lower operating costs, strengthening our position on the global cost curve. We're also building a globally diversified platform with downstream exposure through our POSCO JV in Korea and early-stage optionality in Brazil through the Colina Project. Importantly, our balance sheet, with $1 billion in cash and $655 million in undrawn credit facilities, gives us the flexibility to invest and lead through this period of the cycle.
Dale Henderson
executiveMoving to Slide 3 to discuss the quarter's results. Among the quarter's main highlights was record output of 221,000 tonnes, a 77% increase, which shows the operational leverage delivered by the optimized Pilgan Plant. Our unit costs fell 10% to $619 per tonne, giving us tangible cost leadership in a low-priced environment. This cost gain clearly reflects optimization of the larger operation, which is now finished, and Brett will make some remarks about that shortly. Revenue rose 28%, and we saw strong cash generation despite soft prevailing pricing, with $98 million in operational margin. Part of this improvement stems from timing, but significantly higher sales volumes also contributed. Importantly, we met or beat every FY '25 guidance metric. That speaks to execution discipline and team capability. As I mentioned, we also released our FY '26 guidance today. This result confirms our operational excellence and reinforces our position as a sector benchmark for execution, scale and efficiency. With that, to provide a bit more detail on the operation, I'll now hand over to Brett.
Brett McFadgen
executiveThanks, Dale. Now turning to Slide 4, beginning with safety. I'm happy to say the June quarter delivered another solid result, with our 12-month rolling TRIFR coming in at 2.79 — an excellent outcome. That figure means more than just a statistic; it shows the work we keep doing to build and reinforce our safety culture. We're continuing to reinforce our systems, processes, and leadership engagement so that every team member returns home safely each day. I want to thank the whole operational and projects workforce for their dedication to safety excellence. Now on to Slide 5. The June quarter represented a major operational milestone as we advance the P1000 optimization, which sets us up for steady-state operations in FY '26. Output for the quarter hit 221,300 tonnes, a strong result made possible by better plant throughput, helped along by the expanded Pilgan Plant. Unit operating costs fell quarter-on-quarter, showing early gains from scale and cost leverage thanks to the growing operating platform. The Ore Sorting facility remains a key enabler, permitting more use of contact ore, boosting lithia units recovered from the pit, and raising overall resource utilization. Lithia recovery averaged 71.6% for the quarter, consistent with expectations given the larger share of contact ore in the feed blend.
Brett McFadgen
executiveWe moved 216,000 tonnes of product at a 5.1% grade. Grade dipped temporarily in the quarter as commissioning and ramp-up continued, but we anticipate product grade coming back to target specifications in FY '26. Now that both the P680 and the P1000 projects are complete, the Pilgan operation has been fundamentally transformed. We've brought on 420,000 tonnes of production capacity, enhanced operational flexibility, and delivered a scalable platform with lower costs. Above all, this transformation puts us in position to capture margin through the cycle, supported by better efficiency, stronger resource utilization, and greater adaptability to market conditions. Thank you. I'll now hand back to Dale.
Dale Henderson
executiveThanks, Brett. I also want to give a shout-out to the operating team, the Projects team, and everyone at PLS — this has been a truly outstanding quarter, capping off a massive year. It was a ramp-up year, and ramping up here is unbelievably hard, yet everything fell into place: more scale, the new tech cyclones, construction out in the Pilbara region — you name it, we dealt with all of it. And we navigated every bit of it. So we're absolutely thrilled to have helped bring about a step change in the operating platform, but credit clearly goes to our fantastic people, who worked through the challenges to deliver what I'd call cracking results — well done to the PLS team. Turning to Slide 6. FY '26 guidance was hit. So FY '25 — apologies, FY '25 guidance was achieved. FY '25 is, naturally, a really strong year. And we're delighted that we met or beat guidance on every one of the key metrics. Thanks to this very robust quarter, production volumes of 755,000 tonnes came in above the top end of market guidance. Unit operating costs for the year came down to $627 per tonne, with additional gains in the final quarter, so scale and efficiency at P1000 took hold.
Dale Henderson
executiveWhen it comes to capital, our capital expenditure was handled well, landing at $569 million, which shows disciplined execution even in a year of high activity. As I said, I'm proud of what the team has accomplished against a very difficult market backdrop in a ramp-up year. And across the year, we of course had several very important strategic firsts, including the Latin Resources acquisition and, of course, graduating to lithium hydroxide produced at the Gwangyang JV in South Korea. These results mark a standout finish to what has been a transformational year for the company. And from that, well, PLS is incredibly well positioned. We're not only a well-run lithium producer, but a Cost Smart and technology-enabled operator. We are uniquely positioned to thrive as the cycle ultimately turns. Now moving to Slide 7. PLS has built a platform of strategic growth options designed to drive long-term value through flexibility, diversification and market responsiveness. In Australia, construction of the midstream demonstration fund progressed during the June quarter, with completion targeted for the December quarter of 2025. This project remains central to our downstream value strategy. The Ngungaju processing facility remains in care and maintenance for FY '26 and provides immediate, low capital restart potential, when market conditions improve, a unique optionality advantage.
Dale Henderson
executiveThe POSCO joint venture, P-PLS, keeps moving forward. Train 1 has brought on board one more certified customer, whereas output at Train 2 has been temporarily scaled back, running at reduced throughput, so that cash is conserved before customer certification wraps up. In the quarter, PLS took part in a rights issue by P-PLS, putting in roughly $40 million — the first equity injection into the JV since it was formed in 2022. Over in Brazil, drilling work and technical studies are advancing in support of the Colina project, which is, naturally, a central pillar of our strategy for diversifying future supply. Taken together, these efforts show a portfolio-based approach to growth, bringing together Tier 1 assets, global reach and optionality throughout the lithium value chain. With that said, I'll pass things to Flavio, who will walk us through the financial performance.
Flavio Garofalo
executiveThanks, Dale. If you go to Slide 9 in the deck, you'll find a rundown of the main financial metrics for the June quarter. In the June quarter, we saw the operational leverage of our optimized Pilgan Plant now that the P1000 expansion has been successfully completed. Group revenue came in at $193 million, which was 28% above the previous quarter, and that was driven by a 72% rise in sales volume, partly offset by a 20% drop in the average realized price, which was USD 599 a tonne for SC5.1 product grade. Production volume reached 221,000 tonnes, 77% above the prior quarter, driven by higher output from the optimized Pilgan plant now that the P1000 expansion is complete. Unit operating cost, FOB, came down to $619 a tonne, a 10% improvement quarter-on-quarter. That reduction reflects the benefits of higher production volume as well as efficiencies delivered through the P850 model and our continued focus on cost discipline. Unit operating cost, CIF, also fell to $721 a tonne, a 9% reduction in line with our lower FOB costs. Our cash balance stayed strong at approximately $1 billion as at 30th of June 2025. That underscores our ability to maintain financial strength despite lower pricing and the capital investments in the P1000 expansion, which is now complete.
Flavio Garofalo
executiveMoving on to Slide 10, which presents a cash flow bridge for the June quarter of FY '25. Over that June quarter, our cash balance fell by $88 million, going from $1.1 billion down to $1 billion. The main drivers of that decrease were the completion of the P1000 expansion along with infrastructure capital expenditure. Cash margin from operations came in at $98 million, helped by higher sales volume, lower costs under the P850 operating model, and favorable cash timing. When we subtract mine development and sustaining CapEx from cash margin from operations, the result was positive at $63 million, which reflects strong operational performance and reduced capital expenditure in the second half. Total capital expenditure on a cash basis was $116 million, mostly attributable to infrastructure and project investments, including finalization of the P1000 project. We also contributed $40 million in equity to the P-PLS joint venture, reflecting our pro rata 18% interest. That marked the first equity investment since the joint venture was formed in 2022, and it is aimed at providing additional working capital during the ramp-up phase and navigating the current environment of low lithium pricing. Now turning to Slide 11, which summarizes the group's key financial metrics for the FY '25 period. Production volume reached 755,000 tonnes, up 4% year-on-year, driven by volume expansions enabled by the P680 and P1000 projects.
Flavio Garofalo
executiveFor fiscal year 2025, group revenue came in at $769 million, which is a 39% decrease from the previous year. The main driver was a 43% fall in the average realized price, partly offset by a 7% rise in sales volume. Unit cost FOB was $627 a tonne, 4% below the prior year. That reflects greater sales volume and reduced operating costs, helped along by ongoing operating efficiencies made possible through the transition of the P850 operating model. These results show that our strategic investments in production and process optimization are paying off in concrete ways, keeping us lean, competitive and future-ready. Moving to Slide 12. Our closing cash balance is still solid at $1 billion, even with a tough price environment. Cash margin from operations of $192 million reflected strong cash generation at a low average realized price of USD 672 a tonne. Cash margin from operations, after mine development costs and sustaining CapEx, stayed positive at $28 million. Capital expenditure of $653 million marks the completion of our major investment cycle, setting us up for better returns in FY '26 and beyond. Moving to Slide 13. During the past 2 years, we've proactively carried out a set of cost and cash flow reduction initiatives that have produced measurable benefits and strengthened our balance sheet.
Flavio Garofalo
executiveThe steps we've taken include halting dividend payments, locking in a $1 billion credit facility, trimming capital expenditure, optimizing our workforce, rolling out the P850 operating model, and starting our Cost Smart program — a continuing effort aimed at fostering an efficiency-driven culture. With P1000 now complete and plant optimization still underway, FY '26 offers a clear chance to unlock additional value for the business and to instill cost-consciousness throughout the organization. We stay firmly dedicated to protecting the balance sheet. Our financial standing is solid: $1 billion in cash, a $1 billion loan facility with $375 million drawn down at present, and total liquidity of $1.6 billion. That gives the group a strong position to steer through today's conditions and take advantage of the market recovery that lies ahead. I'll now turn things back to Dale.
Dale Henderson
executiveThanks, Flavio. Moving to Slide 15. With FY '26 now underway, our attention is tightening on operational excellence, disciplined cost control and capital efficiency, after several years of investment across the Pilgan Plant and the wider Pilgangoora asset base. The strength of this new operating platform is now something we can flex. Now, to speak to each pillar of our strategy as it connects to the operation, we aim to capture the full value of our recent capital investment by generating performance uplift at Pilgangoora. We also intend to grow and more deeply embed our Cost Smart program for FY '25, which Flavio just mentioned. Continuous improvement in cost reduction opportunities will be our target across the operations, procurement, maintenance and other support functions. On growth, we aim to preserve optionality through targeted investment and studies that position us for the next phase of the cycle. On chemicals, we aim to progress certification of Train 2 of our P-PLS JV, a chemical plant located in South Korea, which enables commercial sales while managing ramp-up prudently to pace and to preserve cash. On diversification, we aim to carry on with measured investment in the Colina project in Brazil, through targeted exploration and study activities, positioning PLS to speed development as market conditions improve further.
Dale Henderson
executiveTaken together, these priorities show a disciplined, resilient approach that is ready to seize opportunity, and they make sure PLS stays well placed to lead through the cycle. Now to Slide 16. I wanted to give just a little deeper insight into our ore sorting technology. Because in FY '26, we'll build on the P850 operating model by expanding how much we apply this ore sorting technology. Put simply, we're aiming to get the most out of this lever so we can achieve lower unit costs. Our core focus will be the progressive utilization of contact ore fee. This is a blended material from the ore host rock boundary, which you can see in the hatched area on the photo. This shift unlocks multiple operational benefits. First, it lowers mining costs by cutting total material movement and raising the proportion of mined material that is processed. Second, it improves mine flexibility and resource utilization by reducing dependency on clean ore, which enables more efficient extraction sequencing and longer-term optionality. Now, while these changes deliver meaningful unit cost reductions, they're expected to cause a modest decrease in lithium recovery because of the characteristics of the blended ore feed. For FY '26, we're targeting average recovery of approximately 72%. This optimization reflects our focus on applying smart technology to unlock greater value, drive down costs and strengthen resilience through the cycle.
Dale Henderson
executiveMoving on to Slide 17. Regarding our FY '26 guidance, I'm glad to report this marks a step change delivered via multiple years of investment at the Pilgan Plant along with our ongoing emphasis on disciplined cost management. On production, the forecast range is 820,000 to 870,000, with volumes steady each quarter as we keep plant utilization high. On unit costs, FOB guidance sits at AUD 560 to AUD 600 per tonne, supported by greater throughput, ore sorting optimization and better operational efficiency. On capital, capital expenditures are forecast at AUD 300 million to AUD 330 million, after a thorough review to prioritize critical spend, optimize timing and preserve balance sheet flexibility. Finally, on Brazil, cleaner project costs are estimated at AUD 40 million to AUD 45 million, mostly tied to targeted exploration to extend resources, progression of project studies and other operational activities, which will be largely expensed and therefore not included in the capital guidance. Now moving to Slide 18 for some comments on the market, and stepping forward to Slide 19. So there are signs the lithium winter may be lifting, but it's early in this change.
Dale Henderson
executiveVolatility is still elevated for us, and as always, it's hard to get a clear read on market fundamentals. The lithium market has been characterized by volatility for a long time, with prices that are prone to sharp swings that can sometimes seem counterintuitive. In recent years, we've cycled through stretches of pricing that couldn't be sustained, followed by corrections down to levels far under the cost curve and out of step with long-run fundamentals, as we saw over the past year. That volatility isn't incidental. It's a reflection of a market that is still nascent, with limited liquidity, few futures mechanisms and trading infrastructure that remains undeveloped — pricing is still inefficient. In this kind of environment, short-term moves are frequently driven by sentiment, policy signals or speculative flows instead of durable shifts in supply and demand. The pricing pattern seen over the last 12 months is a clear example. Spot spodumene prices dropped to levels that left much of global LCE production loss-making, a point the forthcoming slide clearly illustrates. That outcome wasn't solely the product of a fundamental oversupply, but of an immature market that is still in development. The recent rally in prices, which started late in the June quarter and gained pace into July, follows this pattern — a sentiment-led rebound set off by perceived supply risks. In this instance, Chinese regulatory reviews of brine and lepidolite operations, together with the suspension of a major project, refilled renewed price momentum.
Dale Henderson
executiveWe’re still cautiously optimistic, though we keep watching to see whether the adjustments on the flag supply side actually materialize. Turning now to Slide 20. The graphic on this slide highlights an important reality. Even after the recent rally, spodumene pricing is still far under the levels needed to encourage new investment, and it falls considerably short of long-run price expectations. From PLS’ perspective, a few key market dynamics deserve attention here. First, pricing is still structurally inefficient and susceptible to sentiment-driven swings. Second, the recent uplift is only a partial correction, not a full recovery. And finally, long-run sustainability will need materially higher prices to support our future supply, as the graph shows. For PLS, our strategy has not changed. The business was built to handle this volatility, and we are positioned to capitalize as market conditions improve; a low-cost operating platform, a strong balance sheet and a diversified growth pipeline give us the resilience required to navigate power conditions and capitalize as the market cycle changes. Moving now to Slide 21. Near-term pricing is volatile, but the long-term demand picture remains robust and keeps strengthening. Global EV sales reached 5 million units in the June quarter, up 27% year-on-year. In China, EV penetration hit 50% in June, while global EV market share reached 25%.
Dale Henderson
executiveLooking at calendar year '25, we're forecasting EV sales growth of 23% year-on-year, and through to 2030 we expect a CAGR of 14%. Turning to energy storage, that market is likewise speeding up global ESS installations, which hit 65 gigawatts in Q2 of calendar year '25 — a 36% rise year-on-year — and year-to-date installations reached 116 gigawatt hours, marking a 46% increase. Forecasts point to 40% year-on-year growth for ESS during this calendar year alone. By 2030, EVs and ESS together should make up roughly 90% of lithium demand, which underscores a demand trend that is powerful, durable and structural. As I mentioned earlier, today's pricing won't support the investment needed to bring on the next wave of supply. That gap, as the prior slide shows, poses a long-term risk to supply security and is probably a source of volatility down the road, yet it also opens up an opportunity. PLS is strategically placed to lead through this cycle, being a scale-independent operator with a strong balance sheet and a low-cost platform. We bring a rare mix of flexibility, resilience and growth optionality, including the Ngungaju restart, the Colina Project and P2000. This portfolio approach lets PLS adapt as conditions change and capture value as demand keeps accelerating across global battery markets.
Dale Henderson
executiveNow, before we turn to questions, I want to offer a few closing thoughts. The June quarter was a defining period for PLS, as we finished our expansion successfully and moved into the next stage of our journey—one defined by scale, efficiency, and discipline. We met every FY '25 guidance metric, which clearly shows how well our team executes, and our FY '26 targets reflect the strength of the platform we have built: cost optimized, capital-efficient, and margin resilient, with a scalable, technology-enabled operating base and a fortress balance sheet, and with a globally diversified growth portfolio, PLS is uniquely positioned to lead through the cycle and to capture value as market conditions improve. Although near-term pricing remains volatile, the long-term demand story has not changed. Structural drivers, from electric vehicles to ESS, continue to grow, yet current pricing does not support the investment needed for future supply, which signals potential future tightness ahead. Our confidence is anchored in what we can control: disciplined execution, operational excellence, and strategic agility. These are the hallmarks that set PLS apart, making us a partner of choice in global supply chains and a company well positioned to capitalize on the lithium recovery theme. With that, I will now hand back to Maggie to open the floor for questions.
Dale Henderson
executiveThanks, Maggie.
Operator
operator<<operator_script>> Austin Yun of Macquarie has our first question.
Austin Yun
analystSolid results and a robust close to the year. One question about the production plan. I’ve already seen the guidance, and as you noted, the market is quite volatile, though you remain constructive over the medium to longer term. I just wanted your view on the Ngungaju plan — is that maintenance cost something you intend to think through, or do you see that fund being off-line for some period before it restarts?
Dale Henderson
executiveAustin, thanks for asking. So our assumption has been that Ngungaju would remain offline for the year. That said, if economic conditions improve well, bringing it back online is quite easy, and we've said before that a 4-month window is needed from the decision point to get it online and ramped up. So it's sitting there waiting in the wings. But yes, there's no cost involved there. As I say, it just sits in the wings, ready to be deployed whenever market conditions improve.
Operator
operatorMoving on, Jon Sharp of CLSA is our next questioner.
Jonathon Sharp
analystI have just one brief question. When it comes to hitting the bottom end of next year's cost guidance, what would you identify as the main risks? Would it be the labor strip ratio, variability in feed? I'm just curious to hear your thinking on that.
Dale Henderson
executiveI'll give a brief remark first, and then this is a good one for Brett to add to as well. I think when you look at it in the context of the year, we've just come through our construction ramp-up optimization. Comparatively, stepping into this year, our confidence is at a much higher level, since we're looking at a steady-state platform. That said, these large operations obviously come with a whole bunch of variables. But with an open pit — with multiple open pits, we're relatively derisked there. Our operating team is very stable and consistent and has kept on perfecting its know-how as it relates to the plant. So on a relative basis, a lot of the trouble areas you see at many operations — we're in pretty good shape there. But Brett, why don't you touch on that.
Brett McFadgen
executiveYes. Thanks, Dale. And yes, look, the past two years have been a period when we brought in new capital projects — the P680 and the P1000. So managing those costs downward is always hard when you're adding new variables. But this year really centers on steady-state operation following the optimization phase of P1000, and our Cost Smart program, which we've now been rolling out into its second year, is truly beginning to deliver strong results through our people's initiatives, as we start seeing excellent cost-saving efforts and innovation. So I believe there's a lot of innovation still remaining in the mine. And at this point it's really about that steady-state operation and embedding some of that new technology in the plant. So from a cost perspective, I think we're well positioned to handle any impacts coming from other variables such as suppliers or supply chains. So yes, I think FY '26 will be a very good year for PLS.
Operator
operatorRahul Anand with Morgan Stanley has the next question for us.
Rahul Anand
analystI've got two questions, and they're — well, one's about mining and the other's probably about pricing. On the mining side, I noticed your product grade came in at 5.1% this period, and recoveries were 71.6% still, while you've guided to 72% for next year. Dale, could we go over that once more — why were recoveries low, and what's changing in the strategy? I also saw in your physicals that mine volumes are much higher, at 1.5 million tonnes, and that you stockpiled a bit of everything. Is selective processing going on? Or what exactly is happening there? That's the mining question. I'll come back with one on pricing.
Dale Henderson
executiveOkay, there are a few pieces to that. First, just regarding the backward look and the quarter — the 5.1 grade came about because of the optimization effects during that quarter. Naturally, the March quarter centered on ramp-up. The June quarter centered on optimization. So produced product grade came in slightly lower. Even so, those return levels are back to roughly the usual 5.2. So definitely nothing to worry about on that front. When it comes to the operating shift we have outlined here and the commencement recovery, actually, let me give a bit more detail on that. The whole point there is capturing a mixed ore feed out of the mine. So it is not just the clean ore — historically we followed a strategy of clean ore only. We lacked ore sorting capability, which obviously we now have. But what ore sorting capability lets us do is capture the entire ore body and go right up to the boundary, the host rock boundary. The host rock boundary is, of course, a co-mingled mix of the host rock together with the actual ore. So the opportunity here is to capture all of it and effectively raise the volume that comes from the mine.
Dale Henderson
executiveThat's basically the main advantage. But the consequence that comes along with it is that you're clearly leaning on the ore sorting capability to clean that ore up. And for the most part -- it does clean it up considerably. Yet that does involve a very small amount of impurities, which get carried through into the operation. Therefore, a small effect on lithium recovery. Therefore, we've guided to a target recovery of 72%, which you might remember, in the past, we consistently referred to an average of 75%. So that's really the foundation for that. When it comes to mine volumes, well, there's nothing unusual happening there. It's simply a function of where we sit in the mine plan right now. Just so there's no doubt, we are definitely not high-grading.
Rahul Anand
analystYes, I get that, and I have a brief follow-up. Regarding the ore sorting approach, my sense is that it hasn’t really changed. What’s different, then, and what I’m finding confusing, is the reason recoveries are anticipated to be lower.
Dale Henderson
executiveAbsolutely, Rahul — the main effect we're after is pushing the share of contact, or the boundary, up to a significantly higher level so that unit costs come down. That means running volumes above what we had initially planned for the ore sorting facility.
Rahul Anand
analystUnderstood. All right. That is perfectly clear.
Brett McFadgen
executiveYeah, I'd say that's the crucial point. What we're doing here represents a step change in how much contact ore we're bringing in. So with the ore sorters, we spent the prior quarter optimizing them. At this point, we're letting them run a bit harder, and we're bringing in considerably more of that material from the mine. Along with that come elevated iron levels and, now, the contaminants. So recovery takes a hit because of that. Still, we're truly tuning the whole thing for the lowest cost across that entire value chain.
Rahul Anand
analystUnderstood. All right. Look, I've posed one detailed question, and I'll keep the second one very brief. Pricing is what I want to ask about, and clearly pricing came in somewhat softer than what some peers in the market posted. From what I understood, at the close of last year you reworked an agreement and wrapped up deliveries under one of your offtake arrangements. So what aren't we seeing? Is it just a matter of timing, or is there another factor affecting the price you realized? Anything worth flagging on that front?
Dale Henderson
executiveYes, thanks for that, Rahul. First, regarding the March quarter, we outperformed our Australian peers when it comes to realized pricing. Turning to the June quarter, it seems we may land in the middle, with some below and some above spot, fundamentally. What's behind us is that pricing for the June quarter has turned quite volatile once again. We saw a range between the low 600s and mid-800s over the June quarter. So naturally, that will have an effect across producers, depending on whether they've made spot sales or on what their pricing formulas are based. So I think that's likely the underlying reason for any variances you're seeing across the group right now. As for our offtake agreements, it's very much business as usual. And there's nothing — there are no interesting activities there. It's just very much BAU.
Operator
operatorHugo Nicolaci with Goldman Sachs has the next question.
Hugo Nicolaci
analystDale and team, congratulations on wrapping up FY '25 and beating guidance. This is my first one, so I just have a few clarifications regarding CapEx. Could you confirm how the split between sustaining and mine development broke down in the quarter that just ended? And then on full year CapEx, is the gap between your $569 million and the $653 million in guidance in your cash flow purely a cash versus accrual matter, or are there other spends on Colina and studies and other items within that number that we should take into account?
Dale Henderson
executiveYes. Thanks for asking, Hugo. On Colina, starting with the back end, are we able to expense our costs there? That means no capital expenditure at all in that area. Acquisition costs are the only thing we capitalize; anything spent on Colina gets expensed. As for how capital expenditure breaks down, it divided among mine development, P1000, and sustaining CapEx, with roughly $20 million to $26 million going to each of those parts, and that adds up to the total across them.
Hugo Nicolaci
analystUnderstood, that helps. Then I want to dig a little further into the POSCO joint venture and the equity raise connected to it. Looking back at FY '24, that JV had pulled down additional debt that was meant to carry both trains through construction and ramp-up. The raise you've announced suggests the JVs have had to contribute roughly another $220 million at this point. Could you give us some added detail on where unit costs stand there and what the CapEx requirements look like, so we can get a clearer picture of the JV's cash flow outlook and, as a knock-on effect, what your option to purchase a larger stake in it is worth?
Dale Henderson
executiveOkay, thanks Hugo. There are a few things to cover here, and I'll begin with the build. In hindsight, the build went the way we expected. Naturally, though, it happened at the same time the market price was falling. So bringing a new hydroxide facility online right now is difficult. That's really why we made the equity injection we provided to the team there. As for unit cost, we haven't given any guidance on it, since obviously that facility remains very much in ramp-up mode, as the release indicated. So we're looking for it to prove itself over time, and we're definitely very pleased with how it's progressing. Does that answer your question?
Hugo Nicolaci
analystYeah. I suppose what the question is really getting at is whether we should anticipate having to put more equity into that JV, and when — if prices remain at their current levels?
Dale Henderson
executiveYes, Hugo, it's premature to comment on that. Clearly, the main factor in all of this is how pricing develops. Of course, the recent appreciation has everyone feeling upbeat, and we're all waiting to see whether it holds, as I mentioned in my earlier remarks about the market. So that really is the critical variable. In the meantime, we're monitoring and observing the team getting on with the work of ramping up that operation, which we're doing very successfully. And of course, the recent certifications, and the additional certifications the team is securing with Tier 1 customers, are tied to that solid progress. So yes, whether any requirements will be needed in the future is still to be determined, but as I said, pricing is really the key determinant.
Hugo Nicolaci
analystUnderstood. And if I may, one additional item while I have the floor. Only on P2000 — there was no reference to it in today's release, more about the timing of it.
Operator
operatorHugo, the operator here. Kindly get back in line for your next question.
Executive
executiveRight, Hugo — nothing to report regarding P2000 at this point.
Operator
operatorMoving along, our next question comes from Mitch Ryan at Jefferies.
Mitch Ryan
analystI have a quick question about the ore sorting technology and how it will be used going forward. In your cost guidance for FY '26, how much of that is essentially amortization of, I suppose, the contract on stockpiles, and what percentage of these do you think will be contract sign, whether that comes from the stockpiles or directly from the pit?
Dale Henderson
executiveRegarding how much of the material is contact ore, we haven't made that level of detail public. So I can't give you much insight on that. But as I said earlier, we're aiming to reach volumes beyond the design criteria we originally set for ourselves, which clearly underpins the better cost performance. On the amortization, would you like to take that?
Flavio Garofalo
executiveCorrect, thank you. That will be amortized across the mine plan throughout the upcoming FY '26 period and afterward.
Mitch Ryan
analystBut is part of that going to show up within the unit operating costs? So, I suppose, would that give your cash flows a slight boost?
Flavio Garofalo
executiveYou'll see a few modest gains from mixing in a portion of that contact ore, yes.
Mitch Ryan
analystAll right, can you put a number on that as well?
Flavio Garofalo
executiveThat's not something we're considering right now. No.
Operator
operatorMoving on, our next question comes from Kate McCutcheon at Citi.
Kate McCutcheon
analystThis morning I've got an accounting question that's exciting. So you mentioned you expect the stat accounts to show another net loss from the POSCO JV, similar to last half. Could you remind me what that figure was? And second, since you've just finished that P1000 spend, can you share anything with us about depreciation or D&A expenses for the next FY?
Flavio Garofalo
executiveKate, thank you for asking. Regarding POSCO, we hold an 18% stake in that joint venture and account for it under the equity method, which has been our approach from the start, and we will keep doing so throughout FY '25.
Kate McCutcheon
analystBut you mentioned a net loss hitting the P&L for this half. And what — you also said you anticipate it being comparable to the prior half. Could you remind me what that figure was?
Flavio Garofalo
executiveThe figure for our most recent half came in at roughly $20 million, so for this stretch of the second half we're anticipating comparable results.
Kate McCutcheon
analystAlright. Do you have anything to say about depreciation? My assumption is that there’s a step-up at this point, now that P1000 has wrapped up?
Flavio Garofalo
executiveCorrect. With the P1000 project now capitalized, we will see a modest rise in depreciation, and that amount is going to be amortized using a unit-of-production method across the life of mine.
Operator
operatorMoving on, our next question comes from Al Harvey at JPMorgan.
Alistair Harvey
analystRegarding stripping in FY '26 — through FY '25, I believe we're sitting at roughly 4 to 5. Could you remind us of your loan figure and, I suppose, the levers available to pull in 2026 and how that affects cost — affects your cost guidance for this year?
Dale Henderson
executiveLet me just make a brief point on that, Al, and then Brett can chime in. On the levers we can pull, we've obviously discussed the ore-sorting pieces, and the main one we're trying to maximize beyond those is simply going back into the mine. We're partway along what is really a multiyear maturity path there, with an ongoing shift toward owner-operate. So we're mid-way through that over the course of this year. We've just recently taken on drill and blast. There's additional work coming in that area, and further fairly straightforward productivity gains lie ahead there as well. When it comes to processing, the goal will always be more recovery improvements. So obviously the team is working on successive waves of new programs around that, all aimed at chasing incremental gains. So we'll pursue that. Beyond that, of course, you have what I'd describe as the bread-and-butter items — bulk procurement and running trials on spares, longer-life and more durable materials, and so on. The team has a number of programs underway that sit under the Cost Smart umbrella, which is a continuous improvement effort within the business. Brett, over to you.
Brett McFadgen
executiveYeah, so the key thing there is that in FY '26 we can lower how much stripping we do — not by high grading, but really by making the most of the ore sorters to take all of that contact ore material, which sort of lets us cut down the time we spend in the waste stripping areas so we only have to uncover the clean ore mixture. As we get into later years, we do move into some of the bigger cutbacks. Basically, our strip ratio for FY '26 comes down to using all of that contact ore. And then it rises slightly in FY '27 and beyond, once we get into some of the cutbacks we've planned as part of the mine plan.
Alistair Harvey
analystOne more item. Regarding the CapEx deferral tied to Stage 2 of the power priority, could you give more detail on how large those savings are, and does it carry any effect on OpEx going forward? And perhaps also how you're thinking about which market conditions you'd want to see before bringing it back into the plan?
Flavio Garofalo
executiveYeah, I can address that. So the deferral comes to roughly $5 million.
Alistair Harvey
analystThose market circumstances.
Dale Henderson
executiveOn that particular item, the operational gain was going to be fairly small. So the approach we adopted for FY '26 was to focus only on essential CapEx, on a one-off basis. And because of that, certain of those additional investments that carry a longer payback period — we've pushed those out to a later date. So — but I don't have any kind of broad market price in mind, though we will bring that back online, and in the end, we will.
Operator
operatorThat brings us to the final question, which comes from Glyn Lawcock of Barrenjoey.
Glyn Lawcock
analystI just wanted to say a few words about the '26 guidance. You've provided us with costs, and you've provided us with Brazil. I was just wondering whether you might be able to give us a bit of color on SG&A, plus any other exploration and study costs on P2000, and then leasing spend too, for the year ahead?
Dale Henderson
executiveGlyn, I’ll talk about studies, and Flavio can address leasing costs. On the studies side, the amount being spent in that category is quite small, but naturally we are moving forward with those required studies for both P2000 and the cleaner project; relative to the overall picture, though, those are not large sums. Flavio.
Flavio Garofalo
executiveYes, Glyn, thank you for asking. Regarding the leasing expenditure shown on Slide 12, looking at how that $95 million in cash flow breaks down: roughly $68 million of it relates to leasing, and we anticipate a comparable figure in the coming financial year, FY '26, as well.
Glyn Lawcock
analystAnd then the SG&A figure specifically for head office, since my understanding is that it sits outside the $560 million to $600 million cost guidance. So does that mean roughly another $70 million beyond the cost guidance?
Flavio Garofalo
executiveYes, we anticipate that figure will come in a bit lower, Glyn. Also, through the Cost Smart initiatives, we've implemented certain cuts in that area too. As a result, for FY '26 we're expecting it to be somewhat reduced.
Glyn Lawcock
analystSo if we roughly put 70 toward leasing, 60 toward SG&A, and then another, say, 10 to 20 for exploration and studies outside of the Brazil guidance, would that probably cover everything in your view?
Flavio Garofalo
executiveYeah, I'd say that sums it up pretty well.
Operator
operatorThank you. At this point we'll turn to the questions coming in from the web. James Fuller, over to you.
James Fuller
executiveThanks, Maggie. So we've got a few questions coming in on the webcast. The first one is: which project will go into production first — P2000 or Colina?
Dale Henderson
executiveYes. I appreciate you asking about that. Yeah, regarding P2000 or Colina, a number of factors kind of converge and shape that choice. It comes down to approvals, studies, and the investment case itself. And those projects each sit at different stages of maturity. So my guess is that when the moment arrives, it will be fairly clear which one makes the most sense to move forward first, depending on one of those factors.
James Fuller
executiveOkay, and thanks, Dale. Is there anything new regarding the study with Ganfeng on a joint downstream partner, which is still expected to come out in CY '25?
Dale Henderson
executiveYes. Regarding the Ganfeng study, we're collaborating on it and it keeps moving ahead. Both sides are really enjoying the partnership and making progress on it. It's in motion and on schedule. Of course, whether we'll pursue that in this market — probably not yet; there are conversations to be had with Ganfeng about it. But ultimately, over time, we like the idea of carrying on exploring this down the road.
James Fuller
executiveAll right, let's take the next question. If prices recover, how quickly might you get Ngungaju running again? What sort of timeframe would the ramp-up need?
Dale Henderson
executiveWe've given a guidance of 4 months from the decision points to ramp-up. My suspicion is that, in practice, some optimization will follow that 4-month period to bring things back to full nameplate, but the majority of the ramp-up would happen within that 4-month window.
James Fuller
executiveAll right, thanks. Moving on to the following question. Is that dividend going to be distributed during fiscal '25?
Dale Henderson
executiveIn the end, whether to do that is a call the Board has to make. My guess is that, should pricing stay where it has been lately, the Board most likely — it won't declare a dividend. Still, in the end, that is something for the Board to weigh under its capital management framework.
James Fuller
executiveAll right, going forward, do you feel you've completed any additional acquisitions either in Australia or overseas, given that we're currently at a cyclical low point in the lithium cycle?
Dale Henderson
executiveThe main priority for the business is the base operation. And as we laid out during today's call, we aim to show how strong the new platform is that we've built, along with the knowledge — we've been through a heavy investment cycle. That said, naturally, our strategy does contemplate organic growth, and that hasn't changed, but that isn't a focus — that isn't a key focus for us right now.
James Fuller
executiveAlright, let's take the next question. There has been some low pricing for SC6 lately, though news from the past few weeks points to prices moving higher. What's behind that?
Dale Henderson
executiveYeah, thanks for asking about pricing. I'd like to think my comments on the market already addressed some of that. The main factor driving this price improvement has been the news out of China regarding possible supply curtailments there — approvals and other reviews by China appear to be the principal catalyst. That said, as I noted earlier on the call, pricing had been sitting well below what the industry really needs to be sustainable. This has prompted some action, but I think there's definitely a lot more ground to cover before we get to a more sustainable market.
James Fuller
executiveAlright. This final question comes from the webcast. With prices having risen recently, is the BMX platform being used at this point?
Dale Henderson
executiveNot at this point. Given that we've scaled the operation back to Pilgan only, which covers our core offtake, spot sales have been quite scarce. So the volume of spot sales we're doing isn't large. The BMX platform is the asset we have on hand there. It's parked beneath the dust covers, ready to be brought into use should we judge that it makes sense for the market. Okay. That, I believe, wraps up the questions from our webcast. So, finally, from me. Once more, thank you all for joining today. It's been an enormous quarter, closing out an incredible year for the business, and we look forward to providing another update at the full year results in a few weeks' time. Thank you very much.
Operator
operatorThat brings us to the end of today's conference call. Thanks for joining us. You're free to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Pilbara Minerals Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Pilbara Minerals Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Pilbara Minerals Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.