PNC Infratech Limited (PNCINFRA) Earnings Call Transcript & Summary

May 25, 2024

National Stock Exchange of India IN Industrials Construction and Engineering earnings 64 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day, and welcome to the PNC Infratech Limited Q4 FY '24 Earnings Conference Call hosted by PhillipCapital India Private Limited. [Operator Instructions]. Please note that this conference is being recorded. This conference call may contain forward-looking statements about the company, which are based on beliefs, opinions and expectations of the company as on the date of this call. These statements are not the guarantees of future performance and involve risks and uncertainties that are difficult to predict. I now hand the conference over to Mr. Vikram Suryavanshi from PhillipCapital India Private Limited. Thank you, and over to you, sir.

Vikram Suryavanshi

analyst
#2

Thank you, Lisa. Good afternoon, and very warm welcome to everyone. On behalf of PhillipCapital, I am pleased to welcome you all on the PNC Infratech Limited Fourth Quarter FY '24 Earnings Conference Call. We have with us Managing Director of the company, Mr. Yogesh Jain, along with senior management team. We'll begin with the opening remarks from the management, followed by interactive question and answer session. Over to you, sir, for opening comments.

Yogesh Jain

executive
#3

Good afternoon, everyone. On behalf of PNC Infratech Limited, I extend a warm welcome to everyone for joining us today on this call. I have with me Mr. T. R. Rao, Director Infra; Mr. D. K. Agarwal, CFO; Mr. D. K. Maheshwari, VP Finance; and Strategic Growth Advisors, our Investor Relations advisers. We have uploaded the financial results and investor presentation on the stock exchanges and company's website for your reference. Initially, I would like to mention key updates of the industry, followed by operational developments of the company and highlights of financial performance during the fourth quarter and for financial year '24, post which we will be happy to answer your questions. During the financial year '23-'24, MoRTH, including NHAI and NHIDCL constructed 12,349 kilometers of national highways, making the second highest aggregate route plan constructed in a year in its history. However, as per the industry reports, road construction activities during financial year '25 would be lesser and will be in a range between 11,100 kilometers and 11,500 kilometers. This anticipated decline compared to financial year '24 is largely attributed to too much slowdown in projects awarding process during financial year '24, persistent land acquisition and other issues in already awarded projects. As far as NHAI is concerned, during financial year '24, 6,644 kilometers length of national highways constructed, exceeding the target of 6,544 kilometers set for, which is higher by nearly 20% as compared to 5,544 kilometers constructed by NHAI during the financial year '23. MoRTH announced plans to integrate an additional 6,000 kilometers of high-speed highways into the country's national highways network. This ambitious initiative will tremendously improve connectivity and increase efficiency of transportation across the geographies of country. As mentioned earlier, on new contract awarding front, the sector witnessed very subdued activity during the entire financial year '24. Slowdown in new projects awarding activity will have significant negative impact on the industry over the next 2 years, particularly in achieving the construction targets and revenue by both authorities as well as by the developers. However, the industry is hopeful that bidding and awarding activity will pick up after the conclusion of the ongoing general elections and a large number of projects would be awarded during financial year 2025. On 16th May '24, company subsidiary, MP Highways Private Limited, received communication from MPRDC authority conveying approval for the extension of concession period for Gwalior-Bhind BOT toll project by 2 years, 9 months, 18 days, that is up to 25th March 2028. On 8th March '24, company received completion certificate from NHAI for Lucknow Ring Road EPC project of value INR 1,069 crores affecting from 29th February 2024. On 7th May '24, company received provisional completion certificate for Meerut-Nazibabad HAM project from NHAI with effect from 4th May '24. Company executed construction agreement with MPRDC for Western Bhopal Bypass HAM project on 7th March 2024. On 26th February, '24, Madhya Pradesh Public Works Department awarded an EPC contract, namely construction of an elevated corridor in Gwalior for a contract value of INR 699 crores. Company's strong balance sheet and financial prudence continue to result in credit rating upgrades, which enables company to secure debt at competitive rates. Moving on to the operational and financial performance of the company. Out of the company's 28 fund-based projects, 3 are BOT toll projects, 2 are BOT annuity projects, and 23 are HAM projects. Aggregate bid project cost of 23 HAM projects is around INR 30,000 crores, which is one of the largest highway HAM project portfolio in the country. Out of the total 23 HAM projects, company achieved PCOD and COD for 10 projects, and 9 projects are under construction, 3 projects achieved financial closure, and appointed dates yet to be declared. For one project, company executed concession agreement in March '24. Regarding equity investment, total requirement for these 23 HAM projects is INR 3,092 crores. As of March '24, company already invested INR 1,975 crores, and the remaining equity of INR 1,117 crores is to be invested over the next 2 to 3 years. The internal accruals that would be generated over the next 2 to 3 years should be adequate to meet the above equity investment requirement. As of 31st March '24, the company's unexecuted order book stands at INR 15,490 crores, which does not include the contract value of 2 EPC contracts recently secured for an aggregate value of INR 4,994 crores. Upon inclusion of these 2 EPC projects, our unexecuted order book would be over INR 20,400 crores, which is 2.7x of financial year '24 revenue. Out of the unexecuted order book of INR 15,490 crores, highway and expressway contracts contribute around 70%, while water and canal projects contribute around 30%. Substantial progress achieved in rural drinking water projects under the Jal Jeevan Mission during the financial year '24 by company. During financial year '24, company had booked a total revenue of INR 1,906 crores in the drinking water segment, while during the fourth quarter, booked a revenue of INR 555 crores. I would like to share that one of the company's subsidiary, namely PNC Kanpur Highways Limited, executed a settlement agreement with NHAI on 9th May 2024 for INR 398.6 crores under the Vivad Se Vishwas scheme, which is expected to be received in quarter 1 of financial year '25. Further, another subsidiary of the company, PNC Raebareli Highways Private Limited received INR 117.15 crores from NHAI in April 2024, pursuant to a settlement agreement executed with NHAI Vivad Se Vishwas II scheme. Now I would present the results for quarter ended March 31, '24 and financial year '24. Before discussing financial performance, I would also like to highlight that during first quarter of financial year '23, the company received INR 37 crores towards bonus for early completion of Purvanchal Expressway Package-VI that is included in the revenue of financial year '23, whereas during financial year '24, the company has received INR 297 crores towards arbitration award for 2 projects, Dholpur-Morena of NHAI and Gurgaon-Nuh-Rajasthan border of HSRDC, Haryana. I would also like to highlight that financial year '23 includes revenue of INR 251 crores from Eastern Peripheral Expressway project, which is not adjusted from financial year '23 financials. Stand-alone revenue for fourth quarter of financial year '24 is INR 2,342 crores, which is higher by 11% as compared to INR 2,115 crores in the fourth quarter of financial year '23. The EBITDA for the fourth quarter is INR 565 crores, which is higher by 101% as compared to INR 281 crores in the fourth quarter of financial year '23. The EBITDA margin for the fourth quarter of financial year '24 is 24.1%. The profit for the fourth quarter of financial year '24 is INR 402 crores as compared to INR 184 crores in the fourth quarter of financial year '23, a growth of 118% on a year-to-year basis. The PAT margin for the fourth quarter of financial year '24 is 17.2%. The stand-alone revenue for financial year '24 is INR 7,699 crores, which is higher by 9% as compared to INR 7,061 crores in financial year '23. The stand-alone EBITDA of financial year '24 is INR 1,277 crores, which is higher by 34% as compared to INR 954 crores in financial year '23. The stand-alone profit for financial year '24 is INR 850 crores as compared to INR 611 crores in financial year '23, with a growth of 39%. The PAT margin for financial year '24 is 11%. Consol revenue of fourth quarter of financial year '24 is INR 2,600 crores as compared to INR 2,305 crores in fourth quarter of financial year '23, a growth of 13%. The consolidated EBITDA for fourth quarter of financial year '24 is INR 736 crores as compared to INR 411 crores in the fourth quarter of financial year '23, a growth of 79%. The EBITDA margin for fourth quarter of financial year '24 is 28.3%. The consol PAT for fourth quarter of financial year '24 is INR 396 crores as compared to INR 146 crores in fourth quarter of financial year '23, a growth of 171%. The PAT margin for fourth quarter of financial year '24 is 15.2%. The consol revenue for financial year '24 is INR 8,650 crores, which is higher by 9% as compared to INR 7,956 crores in financial year '23. The consol EBITDA for financial year '24 is INR 2,005 crores as compared to INR 1,600 crores in financial year '23, a growth of 25%. The EBITDA margin for financial year '24 is 23.2%. The consol profit for financial year '24 is INR 909 crores as compared to INR 658 crores in financial year '23, a growth of 38%. The PAT margin for financial year '24 is 38%. As on 31st March '24, our net working capital cycle is 102 days as compared to 106 days as on 31st March '23. Our net worth on a stand-alone basis is INR 4,781 crores as on 31st March '24, whereas total stand-alone debt is INR 382 crores. The total cash and bank balance as on 31st March '24 is INR 616 crores. We have a net surplus of INR 234 crores. This translates to net debt to equity of 0.8x. On consol basis, our net worth is INR 5,185 crores, whereas total debt is INR 8,016 crores as on 31st March '24. The total cash and bank balance, including current investment is INR 1,793 crores. This translates to net debt to equity of 1.52x. With this, we now open the floor for questions and answers. Thank you.

Operator

operator
#4

[Operator Instructions] The first question is from the line of Shravan Shah from Dolat Capital.

Shravan Shah

analyst
#5

Sir, just first on the guidance front. So on the revenue front, what's the guidance for FY '25 and EBITDA margin. Hopefully, you will be maintaining at 13%, 13.5%, and also on the order info front, given the kind of INR 5,000 crores that we have already received, how much more we are likely to get, and if also possible, in terms of segment HAM, toll, or the water and the other segment, if possible?

Yogesh Jain

executive
#6

Thank you. See, for FY '25, we express our guidance of 10% over FY '24, given the prevalent position. And EBITDA, as the industry knows that the competition has increased, particularly during the last 2 to 3 years, so to secure the projects and all, then we have to be also competitive as far as the industry. So the EBITDA margin for the FY '25, we are expecting around 12% to 12.5%, which is slightly lesser than what it was earlier. And on the business development front, as you had said that we had already secured INR 5,000 crores worth of projects. So we are expecting another INR 8,000 crores to INR 10,000 crores of new projects before end of FY '25, because a robust pipeline of projects are there, which are for bidding. Yes, as far as the mix of bidding is concerned, we'll continue to bid EPC and HAM projects, which will be our priority. And we are also looking at the BOT opportunities. But there, we'll be very cautious and would like to be very comfortable in case of BOT toll projects, where the revenue risk is important.

Shravan Shah

analyst
#7

Sir, when we are saying that we are lowering our EBITDA margin from 13%, 13.5% to 12%, 12.5%, given whatever the orders that we have received, that will be flowing into revenue this year. The new orders maybe will not be contributing that much. So does that mean that the new orders are even coming at much lesser margin? And maybe, going forward, from FY '26, maybe this margin number can further come down to 11%, 11.5%?

Yogesh Jain

executive
#8

No, we don't expect that it will further come down to 11%, 11.5% going forward during the FY '26 and onwards. But this also, 12.5%, we are expressing that we'll be executing the new projects also, a sizable amount during the FY '25. The new projects, as we said that the competition is at a higher level, so we'll be bidding more competitively. So as far as the existing projects are there, that will be around 13%. The mix overall would be around 12.5%. And we don't expect that this will come down further sizably during FY '26 and going forward.

Shravan Shah

analyst
#9

Okay. Got it. Secondly, needed a couple of data points of project-wise order book, and equity for '25, '26 and '27, if possible. And before that, if possible, 10% growth on the revenue we are looking at for FY '25. For FY '26, if we get another INR 10,000 crores, INR 15,000 crores, then also for '26 also similar kind of growth, or it can be a much higher growth that we can look at in FY '26?

Yogesh Jain

executive
#10

It would be speculative as of now to say how these things will unfold. But the growth will not be less than 10% in FY '25 -- FY '26.

Shravan Shah

analyst
#11

Yes. Sir, first in terms of the equity breakup of '25, '26, '27, and then the project-wise order book, I will ask.

Devendra Maheshwari

executive
#12

So total equity requirement on 31st March is INR 1,117 crores, and out of that INR 640 crores will be required to infuse in the year FY '25, INR 330 crores in FY '26, and INR 145 crores in FY '27.

Shravan Shah

analyst
#13

Okay. And in terms of the project-wise order book, so first is, irrigation project is how much?

Devendra Maheshwari

executive
#14

Irrigation is INR 932 crores, sir.

Shravan Shah

analyst
#15

INR 932 crores. Second is this Hardoi project, which was INR 424 crores as on December?

Devendra Maheshwari

executive
#16

It is, Hardoi, INR 268 crores; and Mathura Bypass Hathras is INR 184 crores, Challakere INR 92 crores.

Shravan Shah

analyst
#17

Okay. This Gaju Village-Devinagar is INR 168 crores?

Devendra Maheshwari

executive
#18

Yes.

Shravan Shah

analyst
#19

Okay, INR 168 crores. And Haryana Rail project?

Devendra Maheshwari

executive
#20

Yes, INR 745 crores.

Shravan Shah

analyst
#21

INR 745 crores. Okay. Got it. And retention money, mobilization advance, and HAM debtors, sir?

Devendra Maheshwari

executive
#22

Advance from client is INR 417 crores and retention is INR 130 crores, sir.

Shravan Shah

analyst
#23

INR 130 crores. HAM debtors and water debtors, if possible?

Devendra Maheshwari

executive
#24

HAM debtors is INR 660 crores.

Shravan Shah

analyst
#25

Okay. And water debtors, sir?

Devendra Maheshwari

executive
#26

It is INR 920 crores, sir.

Operator

operator
#27

The next question is from the line of [ Siddharth Shah from Max Overseas ].

Unknown Analyst

analyst
#28

Sir, there was an asset monetization of 12 projects that you had announced a few months back. Can you please tell us when is that money going to be received? And any debt reduction plans of the company?

Devendra Maheshwari

executive
#29

As we have discussed earlier that there are 2 phases in our monetization. Out of 12 projects, in first phase there are 7 projects and in second phase, there are 5 projects. Mostly, we have received the -- there are certain condition precedents which we have to fulfill, and major are NOC from lenders and NOC from NHAI. So majority of the lenders of first tranche assets have already been received and others are expected within the next 4 to 6 weeks. And as regards to the NOC from NHAI, financial consultants of NHAI reviewed the NOC application and observations made by them have already been clarified, compiled with. We are closely following up with finance, concerned technical department, and project implementation unit of NHAI. For accrediting the approval process, NOC from NHAI for the first tranche is expected by middle of July. So we expect that we should receive the payment of first tranche, which is INR 5,015 crores enterprise value, by 30th of September.

Unknown Analyst

analyst
#30

Okay. And sir, any debt reduction plans after this money is received?

Devendra Maheshwari

executive
#31

Certainly. The total debt in 12 projects is INR 6,479 crores. Yes, yes, it will reduce directly.

Operator

operator
#32

We'll move on to the next question that is from the line of Bharani Vijayakumar from Avendus.

Bharanidhar Vijayakumar

analyst
#33

What is the order inflow that we saw in FY '24 for PNC in rupees crore?

Talluri Rao

executive
#34

As our MD has mentioned, the awarding activity during the FY '24 was very subdued. So we got 1 HAM project of INR 1,174 crores. And we got 1 EPC project of INR 699 crores, which comes to INR 1,873 crores. That was the order inflow during the FY '24.

Bharanidhar Vijayakumar

analyst
#35

Okay. And how much was the awarding done by NHAI in kilometers in '24?

Talluri Rao

executive
#36

That we don't have readily -- figures are not readily available with us. We'll share you separately. But however, whatever the awarding target of NHAI was set forth before beginning of FY '24, what award they made is much lesser than that was set forth.

Bharanidhar Vijayakumar

analyst
#37

And according to you, how much is the near-term bidding pipeline of NHAI, say, in EPC, HAM, and the BOT separately, sir, where we would be bidding?

Talluri Rao

executive
#38

See, there is around -- over 90 projects we have identified for evaluation, comprising 20 EPC projects, around 60 HAM projects, and 30 DBFOT toll projects, for a total value of more than INR 100,000 crores. That's what -- otherwise, out of that -- see, maybe next 2, 3 months, these projects is to bid out, but as NHAI as a whole, they floated more than 150 projects with an aggregate value of INR 1.5 lakh crores. So the projects identified by us for bidding would be around INR 1 lakh crores worth of projects.

Bharanidhar Vijayakumar

analyst
#39

Okay. And you're telling it would be without -- this 150 number of projects would be bid out in FY '25?

Talluri Rao

executive
#40

Yes, yes.

Bharanidhar Vijayakumar

analyst
#41

Okay. Do you see any preference for BOT projects first before EPC and HAM projects are awarded?

Talluri Rao

executive
#42

No, no. Our order of preference would be in the sequence of EPC is our first preference, followed by HAM, then our last preference would be BOT toll.

Bharanidhar Vijayakumar

analyst
#43

I'm asking for NHAI, sir. So is NHAI going to prefer BOT?

Talluri Rao

executive
#44

NHAI would definitely prefer BOT, but NHAI is also, and ministry is also having an internal evaluation system. Until and unless BOT projects are viable on a stand-alone basis within limited grant that what they'll be providing, so otherwise, they are going on a HAM mode, because BOT projects would be self-sustaining and sufficient revenue should be coming from them. So they just can't go for a BOT project -- BOT mode for all the projects what they're envisaging.

Bharanidhar Vijayakumar

analyst
#45

Okay. And in the recent MSRDC projects that we won, how much was the competition and how much margins we are expected to make, sir?

Talluri Rao

executive
#46

There was a substantial competition by all big players. And there, we are expecting an EBITDA margin of, as we said, between 12.5% and 13%.

Bharanidhar Vijayakumar

analyst
#47

Okay. Last question on this arbitration that we received on the Vivad Se Vishwas scheme. So this arbitration money we had booked in '24, that is 4Q FY '24. Has it been received by us or yet to be received?

Yogesh Jain

executive
#48

A fair amount we have received already.

Talluri Rao

executive
#49

FY '24, we received before 31st March, that is on 31st.

Yogesh Jain

executive
#50

It is around INR 255 crores.

Talluri Rao

executive
#51

In 1 of the projects in Vivad Se Vishwas, it's INR 255 crores. Apart from, we also received INR 45 crores in another project of EPC of HSRDC.

Bharanidhar Vijayakumar

analyst
#52

And what would be the adjusted PAT and EBITDA for FY '25 apart from this arbitration?

Talluri Rao

executive
#53

As I said, that will be 12.5%. If you don't consider the arbitration awards that we'll be getting during FY '25.

Bharanidhar Vijayakumar

analyst
#54

Sorry, I asked for '24, what would be the adjusted EBITDA and PAT?

Talluri Rao

executive
#55

Yes, '24, I stand correct, it was 13.13%.

Bharanidhar Vijayakumar

analyst
#56

Absolute number can you give sir, EBITDA and PAT, adjusted for the one-off income, sir?

Devendra Maheshwari

executive
#57

It is INR 980 crores, without taking the consideration of arbitration, EBITDA margin. INR 980 crores.

Bharanidhar Vijayakumar

analyst
#58

INR 980 crores. And PAT?

Devendra Maheshwari

executive
#59

PAT is INR 630 crores.

Operator

operator
#60

[Operator Instructions] The next question is from the line of Rohan Kamath from Tiger Asset.

Rohan Kamath

analyst
#61

I have 2 questions. One is, could you provide me details of industry-wise breakup of the current order inflow?

Talluri Rao

executive
#62

The expected order inflow you are telling?

Rohan Kamath

analyst
#63

Yes, I want to know that could you provide a detailed industry-wise breakup of the current order inflow?

Talluri Rao

executive
#64

So see, whatever unexecuted order book is there, as mentioned by my colleague, more than 70% is the highway and expressway projects and around 30% is from our rural drinking water and AP Canal project. So that is the only 2 segments primarily we are operating, only the roads and highways and another is the rural drinking water and a small irrigation project. That is the breakup.

Rohan Kamath

analyst
#65

Okay. And I want to know what is your order inflow guidance for FY '25?

Talluri Rao

executive
#66

FY '25, we have already received projects worth of INR 5,000 crores we secured, we stood L1. And apart from that, we are expecting another INR 8,000 crores to INR 10,000 crores. So the cumulative, it would be around INR 13,000 crores to INR 15,000 crores during FY '25, order inflow.

Operator

operator
#67

The next question is from the line of Vaibhav Shah from JM Financial Limited.

Vaibhav Shah

analyst
#68

Sir, if I remove the exceptional part from the revenue for the quarter 4, so there was a 3% decline in the total revenue. There was a significant growth in the water revenue on a Y-o-Y basis. So what has led to the weak revenue on the highway side? Is there any project specific issues in the quarter 4?

Talluri Rao

executive
#69

See, quarter 4 of FY '24 vis-a-vis the quarter 4 of FY '23, what has happened, during the quarter 4, we got the PCODs for quite a few projects, starting from November and October. So these projects we achieved and completed, so the revenues were a bit lesser when compared to FY '23, when these projects were peak in its execution from particularly in the road sector. So there is a very marginal decline in Q4 of FY '24 in comparison to Q4 of FY '23. Otherwise, there is no other major reason. That time those projects were in peak. Now those projects are in a completion stage.

Vaibhav Shah

analyst
#70

So sir, are there any slow-moving projects in the order backlog right now, which are under execution?

Talluri Rao

executive
#71

No. Almost all projects are going as per the schedule only. There is no major slowdowns in any particular quarter.

Vaibhav Shah

analyst
#72

And sir, for the JJM projects, what revenue do we expect for FY '25?

Talluri Rao

executive
#73

For FY '25, our guidance for the JJM is INR 2,500 crores.

Vaibhav Shah

analyst
#74

Okay. And sir, when do we expect to receive the ADs for the HAM project, for the 4 HAMs?

Talluri Rao

executive
#75

See. One of the 3 HAM projects, that is Varanasi to Kolkata, we are expecting maybe in a couple of months, maybe before July. And the other 2 projects, land acquisition is in progress. So we expect in the current financial year. And similarly, for Western Bhopal Bypass of MPRDC, we executed concession agreement in the month of March. So NHAI has got time to finally declare the appointed date and financials for this. So that also we are expecting in Q3, appointed date.

Vaibhav Shah

analyst
#76

Okay. And sir, lastly, when do we expect to start the work for the MSRDC project?

Talluri Rao

executive
#77

See, now...

Yogesh Jain

executive
#78

Last quarter -- we are expecting in last quarter of current financial year.

Vaibhav Shah

analyst
#79

In the last quarter or the third quarter?

Yogesh Jain

executive
#80

Yes, last quarter.

Operator

operator
#81

The next question is from the line of Parikshit Kandpal from HDFC Securities.

Parikshit Kandpal

analyst
#82

Sir, my first question is on the Phase 1 of EV, which is INR 5,015 crores. So how much is the equity value in this, which you will realize?

Devendra Maheshwari

executive
#83

Equity value, first phase is around INR 1,000 crores.

Parikshit Kandpal

analyst
#84

How much, sir?

Devendra Maheshwari

executive
#85

INR 1,000 crores -- INR 999 crores.

Parikshit Kandpal

analyst
#86

This is our receivable which you will get, right, and rest INR 4,000 crores will go towards that?

Devendra Maheshwari

executive
#87

Yes, INR 1,000 crores equity we have infused, and we are expected to receive around -- INR 5,015 crores is the enterprise value.

Parikshit Kandpal

analyst
#88

Okay. So in that, how much is the debt, sir? That is what I'm asking. Out of INR 5,015 crores, how much is debt?

Devendra Maheshwari

executive
#89

INR 3,560 crores.

Parikshit Kandpal

analyst
#90

Okay. So INR 5,015 crores minus INR 3,560 crore is the equity realization or the inflow to you.

Devendra Maheshwari

executive
#91

Right.

Parikshit Kandpal

analyst
#92

Okay. And second question is on the bid pipeline, sir. So if you can help us understand what is the bid pipeline segment-wise in the state of UP, both on the state side and NHAI side?

Talluri Rao

executive
#93

We have a big pipeline. As we mentioned, around 150 projects, NHAI has floated. Out of that, we identified around 100 projects. But right now, the state-wise breakup is not readily available. We'll share with you separately.

Parikshit Kandpal

analyst
#94

But what about the state projects, any majors? Like after Ganga Expressway, do you think any other projects are lined up for the state of UP in metro, water, or JJM, state highways, any pipeline there which you can initialize or see in the next 6 months?

Talluri Rao

executive
#95

No. As of now, none of the states have declared any major projects announced, particularly in the road sector.

Parikshit Kandpal

analyst
#96

What about the JJM pipeline, sir? Any sense on the JJM pipeline for UP state?

Talluri Rao

executive
#97

In UP, almost all 5 phases they awarded. UP, we don't see. We need to see the other states, but the clarity will emerge only post general elections, because the governments are not coming out with any concrete plan until general elections get over. So only in the next quarter, we'll be in a better position to assess what could be the bidding opportunities across the sectors.

Parikshit Kandpal

analyst
#98

Now you're highlighting, sir, INR 15,000 crores of inflows, when this year is expected to be a truncated year towards ordering. What gives you so much of confidence? Because we don't see any major projects announcement by state government. So you have already won INR 5,000 crores, but another INR 10,000 crores, you need to rely heavily on how NHAI does. And in that, you are also focusing more on EPC and HAM. So in absence of any major state projects, how do you think that you will reach that number of INR 15,000 crores?

Talluri Rao

executive
#99

See, historically, our revenues and our BD has been from the NHAI only, if you see it. And now, as I said, 150 projects, which amounts to INR 1.5 lakh crores. As our Managing Director said, there are 6,000 kilometers of high-speed highways, which would roughly translate into INR 2.5 lakh crore to INR 3 lakh crore. Definitely, government will expedite these projects. So we are a bit confident that the total pipeline during the FY '25 would be more than INR 2 lakh crores. It could be even touching INR 3 lakh crore. In that sense that what we are assuming, INR 8,000 crores to INR 10,000 crores is not an unrealistic figure.

Parikshit Kandpal

analyst
#100

Okay. Sir, just the last question on this Vivad se Vishwas scheme. So how much is the total pending collection claims, which is yet to be recognized or received, though it has been awarded or settled, but yet to be recognized, and when do you expect it?

Talluri Rao

executive
#101

We have actually received INR 398.6 crores, for which we have signed the settlement agreement with NHAI. That we are expecting maybe next 10 to 15 days, we are expecting realization of the said money. It is INR 398.6 crores.

Parikshit Kandpal

analyst
#102

So this is over and above the INR 255 crores you have already received in Q4, right?

Talluri Rao

executive
#103

Yes. This is over and above INR 255 crores we received during FY '24, and also INR 117.15 crores we have received during Q1 of FY '25. Apart from INR 255 crore, we had also received INR 117.15 crores in April 2024, that means Q1 of FY '25, which will reflect in Q1 results.

Devendra Maheshwari

executive
#104

Actually, in FY '25, we are expecting in PNC, INR 378 crores in 2 projects, Kanpur-Kabrai and Raebareli-Jaunpur, in PNC books.

Talluri Rao

executive
#105

And remaining in SPVs.

Parikshit Kandpal

analyst
#106

So remaining in SPVs.

Talluri Rao

executive
#107

Yes. Overall, in a consol, it will reflect.

Parikshit Kandpal

analyst
#108

So just to reconcile, INR 255 crores has been done in Q4, INR 117 crores you've received in April, INR 398 crores is expected in the next 10 to 15 days. And beyond that, is there anything else which is there in our favor yet to be like closed or signed?

Talluri Rao

executive
#109

No, because there are only 3 projects which qualify for settlement under the Vivad se Vishwas scheme II.

Operator

operator
#110

The next question is from the line of Prem Khurana from Anand Rathi.

Prem Khurana

analyst
#111

My first question was with respect to our water orders. If I heard you right, you said you have almost around INR 900-odd crores of debtors from water orders. And if I remember, this is against INR 1,900 crores of revenues that you've done, which works out to be almost 180 days sort of cycle. So is it in line with how you anticipate it to be, or would you say this is higher than what you would have envisaged at the time of bidding for the each project. Because when I see it, this INR 900 crores technically means, I mean some of these payments have been due for more than 4, 5 months, because the last 2 quarters together you've done almost around INR 1,100-odd crores of revenue. So do you see this to correct, or this would remain like this next year as well, the cycle, the debtors cycle with water orders?

Talluri Rao

executive
#112

No, no. That debtor cycle has not been like that. We are having this constraint, we are facing issue only in the Q4. What has happened, whatever billing we have done, we have done around INR 500 plus crores of billing during the Q4 by March 31, and what has happened, after the announcement of elections, and also the present government only passed the vote-on-account budget for 3 months, that is up to June, with a very limited allocation in the Jal Shakti Ministry and the Jal Jeevan Mission. So the whole project, 50% grant is provided by Government of India, and the remaining 50% matching grant is given by the state government. Because of the vote-on-account and the limited budget allocation, so there is a paucity of funds from the central government, which is resulting in the slowdown in the disbursement. This month, Government of India has released INR 1,800 crores and matching grant of another INR 1,800 crores released by state government. We are gradually getting the payments. So once the general elections are over and once the full-fledged budget is presented and approved by the parliament before 30th of June, so going forward, from July onwards, the payments will be streamlined, and we don't foresee that any major issue in getting the repayments on the Jal Jeevan Mission.

Prem Khurana

analyst
#113

Sure. Sir, would it be fair to assume that June, again, the debtors would be on elevated side, because, I mean, till you get to see the central government get settled, till then it will be a little slow in terms of payment cycle, right?

Talluri Rao

executive
#114

Yes, yes. It's only temporary phenomenon. Due to general elections and since the outgoing government was able to pass only vote-on account budget for 3 months.

Prem Khurana

analyst
#115

And when I look at the presentation, so our net working capital cycle has gone up from some 73-odd days to 102 on a sequential basis, I mean, compared to what was reported in the presentation for the 9 months. So this entirely would be on account of this water order, or we've seen some buildup on road side as well?

Devendra Maheshwari

executive
#116

It is mainly on account of the water debtors. If you will compare with the March '23, it has reduced from 106 days to 102 days, sir.

Prem Khurana

analyst
#117

Sure, sure. And sir, so these MSRDC orders that we've emerged L1 with, I mean, what I gather is, I mean, most of the bids are almost 30%, 40% higher than the base cost estimate. I mean, could there be a situation wherein the government comes and starts negotiating with the successful bidder, or you need them to kind of go ahead with the same bid they've placed? Because last time when you had similar sort of situation with somebody, there were some sort of renegotiations, right? So fair to assume, given the fact that it's substantially higher than what they were envisaging or what the base cost estimate was, I mean, will you get to have some sort of renegotiations again? and which could mean, I mean, it could take a little longer than what you generally would build in to kind of start execution at the ground?

Yogesh Jain

executive
#118

We are expecting negotiation. But we have not received any letter from MSRDC until now.

Prem Khurana

analyst
#119

Okay, sure. And the third one was on this arbitration claim under Vivad se Vishwas. So the balance money, which is, I mean, the INR 117-odd crores that you received in April and then another INR 390 crores or INR 400-odd crores are supposed to be with the SPVs, right? And the money would flow through to the parent, right, which is how it will work. So only INR 378 crores out of this INR 500-odd crore plus would reflect in stand-alone. So do we have any receivables due from the SPVs, against which this money, INR 378 crores, would come to us? Or how would the pass-through be? Do we have any costs reflecting in our books of account for this INR 378-odd crores in the stand-alone entity?

Yogesh Jain

executive
#120

No, no. There is no cost on that. Entire will be the EBITDA only.

Prem Khurana

analyst
#121

Okay. And sir, how would the tax structure work then in this case? Because the SPVs would receive the money. They'll book that as a part of the income statement, pay taxes, and then the money would come to us, again would be booked in income statement. Is it? Or how would the tax part work with the arbitration claims?

Talluri Rao

executive
#122

See, these arbitration claims, whatever SPVs write are comprising both the EPC claims as well as the claims belong to SPV. When SPV receives the total amount, the EPC portion will be transferred to the EPC contractor. That will not have any tax impact on the SPV. Whatever the net amount SPV is retaining belongs to SPV will have a tax impact.

Operator

operator
#123

The next question is from the line of Jiten Rushi from Axis Capital.

Jiten Rushi

analyst
#124

First of all, congratulations on the win of MSRDC orders. Sir, my first question is you had said that your FY '24 PAT is INR 631 crores. Am I right, sir? After the adjustment for this arbitration claims?

Devendra Maheshwari

executive
#125

Yes.

Jiten Rushi

analyst
#126

So what is the tax which you paid on the Vivad se Vishwas claims, which you received, INR 296 crores?

Devendra Maheshwari

executive
#127

It's 25.168% sir, normal tax rate.

Jiten Rushi

analyst
#128

Normal tax rate, okay. And sir, on the CapEx, so what was the CapEx guidance for FY '25?

Devendra Maheshwari

executive
#129

Last year, we have taken around INR 46 crores. And this year, we are expecting INR 100 crores to INR 120 crores CapEx.

Jiten Rushi

analyst
#130

This CapEx is largely for the MSRDC project, or this is for the inflows which you are targeting, back-ended CapEx?

Devendra Maheshwari

executive
#131

For new HAM projects and MSRDC, both.

Jiten Rushi

analyst
#132

And sir, on appointed date, so just want to clarify, for the Varanasi package II and III, when do we expect the appointed date, and the package VI?

Talluri Rao

executive
#133

Package VI, as we said that maybe within next 2 months, we'll get the appointed date, we are expected to get the appointed date for Package VI. And package II and III may take further time, but overall, we are expecting appointed dates declaration by end of this financial year for both the remaining packages.

Jiten Rushi

analyst
#134

Okay. So by Q4, we can expect for II and III, and VI by Q2 probably. And you said...

Talluri Rao

executive
#135

February.

Jiten Rushi

analyst
#136

Okay, February. Got it. And sir, the enterprise value for the Phase II, can you highlight what is the enterprise value? And then can you break it down in terms of the equity and debt?

Devendra Maheshwari

executive
#137

Enterprise value of first phase is INR 5,015 crores, and of second phase is INR 3,990 crores.

Jiten Rushi

analyst
#138

Okay. What would be the debt and equity for the second phase?

Devendra Maheshwari

executive
#139

Second phase debt is INR 2,920 crores and first phase is INR 3,559 crores. The total is INR 6,479 crores.

Jiten Rushi

analyst
#140

Sorry, I missed it, sir. You said first phase debt is INR 2,920 crores, right, sir?

Devendra Maheshwari

executive
#141

No, second phase, INR 2,920 crores.

Jiten Rushi

analyst
#142

INR 2,920 crores, second phase. And equity would be how much sir? Second phase?

Devendra Maheshwari

executive
#143

Second phase, INR 740 crores, we have infused.

Jiten Rushi

analyst
#144

INR 740 crores. And what you are expecting the EV, total -- EV is the INR 3,990 crores, which you will receive?

Devendra Maheshwari

executive
#145

Yes.

Jiten Rushi

analyst
#146

So basically, against the EV of INR 3,660 crores, you will receive an EV of INR 3,990 crores. Correct, sir?

Devendra Maheshwari

executive
#147

No, first phase debt is INR 3,559 crores and EV is INR 5,015 crores, first phase.

Jiten Rushi

analyst
#148

Okay.

Devendra Maheshwari

executive
#149

And second phase, debt is INR 2,920 crores and EV is INR 3,990 crores.

Jiten Rushi

analyst
#150

Right. And the equity which you will invest is INR 740 crores, that is what you said, right, sir?

Devendra Maheshwari

executive
#151

In the second phase, yes.

Jiten Rushi

analyst
#152

Got it. And sir, in terms of the guidance, so if you say that 10% growth you expect in FY '26. So bulk of the revenue should come in, in H2 FY '26. So like can we see that in MSRDC we can see the pickup in execution, because, sir, the ordering has happened in the first quarter. And these are the EPC projects, the land acquisition should be faster. Can we not start these projects in H2, like Q3 rather than Q4 and we can push the revenue growth high in FY '25 also?

Talluri Rao

executive
#153

See, these projects are essentially in a greenfield nature, because the land acquisition has to be done and then some further approvals and other things will be there. So what we are hopefully expecting, there will be some sizable amount we'll be doing. Some sizable quantity of work we'll be doing in Q4, which would be realistic. Q3, we don't expect any significant work will be executed. Before that even agreement signing and other things will happen.

Jiten Rushi

analyst
#154

Sir, land is acquired or what is the status of land there, sir?

Talluri Rao

executive
#155

Some of the land is available and the remaining land has to be acquired. This is in progress.

Jiten Rushi

analyst
#156

Okay. Okay. And sir, in terms of the growth for '26, like again, you said 10%, but now with high inflows, which you're targeting, and we have received inflows of MSRDC, which is front-ended. So don't you think the growth and appointed dates also for the 4 projects and 1 EPC projects of Gwalior, we expect this year. So FY '26 should be better in terms of execution and growth over FY '25, if at all, can we have 15%, 20% growth?

Talluri Rao

executive
#157

See, we hope so that with our listing, if growth should be more, and then should do valuation to our stakeholders, shareholders, but as of now, say, before 2 years, saying something, growth of FY '26 would be stark, that it would be premature. The growth of FY '26 of 10% over FY '25 is the growth what we are communicating now. So going forward, maybe in Q2 or Q3 results, we should be able to tell what you see the growth of FY '26, that it should be more than 10% or it would be above 10%.

Jiten Rushi

analyst
#158

Sir, last question from my side is on the irrigation project of Andhra. So now again it is a slow-moving project. So you were saying last time that we might hand it over. So what is the status now? How will we execute or what is the next step we are targeting to do?

Talluri Rao

executive
#159

Actually, when project was awarded, it was a INR 1,000 crores project. We started with the right earnest and so far we've built around INR 196 crores invoices we raised. So we put a pause because we have not received the payments from the state government. After 4th of June, some clarity will emerge, but nonetheless, this project being an important project as a part of Rayalaseema drought relief, whichever government comes, they just can't neglect this project, because a lot of social issues are involved. Entire Rayalaseema is an arid and dry region, so until and unless -- there also there are 2 reservoir on the irrigation -- there is a big ayacut of irrigation is there. So we expect whatever government comes, they will continue with this project. And also will release our amounts.

Jiten Rushi

analyst
#160

And sir, toll numbers, can you give me the toll numbers? Toll collection numbers for the projects, Q4 and FY '24?

Devendra Maheshwari

executive
#161

MP Highways, total FY '24, INR 30.4 crores. Kanpur Highway, INR 95.6 crores; Narela is INR 51.5 crores; Bareilly INR 62.4; and RBJ annuity INR 128.6 crores.

Jiten Rushi

analyst
#162

For Q4?

Devendra Maheshwari

executive
#163

Q4: MP Highways, INR 6.38 crores; Kanpur Highway, INR 24.6 crores; Narela INR 12.5 crores; Bareilly INR 15.8 crores, RBJ INR 32.16 crores.

Operator

operator
#164

The next question is from the line of Shravan Shah from Dolat Capital.

Shravan Shah

analyst
#165

Sir, just a clarification. Sir, when we say, for MSRDC, the negotiation can happen next week. Any broader idea, normally, how the government tries to negotiate? So broadly, is it from the base cost they only try to negotiate 10%, 15% higher? That's how it works? Or any rough ballpark area from your past experience?

Yogesh Jain

executive
#166

We can't say anything now, but it is a procedure in Maharashtra government. They will negotiate first and then award.

Shravan Shah

analyst
#167

But at the current price what we have declared L1, if that is the case, then it is fair to assume that we can have a much, much higher, 17%, 18% kind of EBITDA margin, or L1 price itself is 12%, 12.5%. So just 5% if we further reduce the government negotiation, it comes down 5%, then the margins on that will come down?

Talluri Rao

executive
#168

Yes. See, whatever rate we've quoted, we've quoted competitively. Because substantial competition was there, so we quoted competitively with the EBITDA margins what we assume. But we can't disclose, being a proprietary thing, now we can't say that what margin we quoted and what would be this thing. But whatever negotiation will be there, we assume that it will be very reasonable and justifiable. Accordingly, then we will see how the things will unfold. It will be too premature to say anything now.

Operator

operator
#169

The next question is from the line of Parvez Qazi from Nuvama Group.

Parvez Qazi

analyst
#170

Sir, I just wanted to reconfirm the number that we have given for the asset monetization. So for the first year, the EV is INR 5,500 crores. Is that correct?

Devendra Maheshwari

executive
#171

INR 5,015 crores.

Parvez Qazi

analyst
#172

INR 5,015 crores. And the debt that you have infused is INR 3,564 crores and equity was INR 991 crores?

Devendra Maheshwari

executive
#173

Debt was INR 3,559 crores, yes.

Parvez Qazi

analyst
#174

INR 3,559 crores. Equity is INR 991 crores?

Devendra Maheshwari

executive
#175

INR 999 crores is equity.

Parvez Qazi

analyst
#176

And for Phase II, the EV is INR 3,990 crores, debt is INR 2,920 crores, and equity INR 740 crores?

Devendra Maheshwari

executive
#177

Right.

Operator

operator
#178

The next question is from the line of Shubham Shelar from IDBI Capital.

Shubham Shelar

analyst
#179

Sir, stand-alone number 10% increase that you mentioned. So this factors the Vivad se Vishwas couple of amounts that we'll be booking in quarter 1 FY '25?

Talluri Rao

executive
#180

No. Whatever 10% guidance we have given, this is net of whatever arbitration awards we would be receiving under Vivad se Vishwas for FY '25.

Shubham Shelar

analyst
#181

When you say net of, which means it includes that, or...

Talluri Rao

executive
#182

It doesn't include.

Shubham Shelar

analyst
#183

Doesn't include. Okay. And second is on MSRDC order, I think you did briefly mention to one of the previous participants that there could be some sort of negotiation that could happen. So then 12.5% EBITDA margin that you mentioned, that is on the quoted amount which you have in the BSE notification you have mentioned, on that 12.5%, or from negotiation you're already factoring in something will be there, and then 12.5% margin we'll make?

Talluri Rao

executive
#184

See, this 12.5% is what we had mentioned for FY '25 and FY '26 going forward. And this is the overall company's income. Whatever the percentage of work we would be executing during FY '25 in MSRDC will be insignificant. This is the thing. We can't say that how this particular project will have an impact on the overall this thing. What EBITDA we mentioned, guidance, this is for the whole portfolio of what we are having.

Shubham Shelar

analyst
#185

Right. No, no, I'm not saying for FY '25, but I think in one of the queries you did mention like MSRDC order margins will be like 12.5% sort of number, which I could hear it. So just thought to clarify that it is on the quoted amount of what is there in the stock exchanges or it is already factoring in negotiation?

Talluri Rao

executive
#186

No, no, we have not informed the stock exchange what would be the EBITDA margin on whatever order we secure. So that said, we think, to say, as I said, it's proprietary in nature. And also it's something like a very forward-looking kind of a thing, which we don't want to comment as of now, until and unless the negotiation process is completed.

Operator

operator
#187

The next question is from the line of Gautam Gosar from Monarch AIF.

Gautam Gosar

analyst
#188

Sir, I just needed some clarification on the Vivad se Vishwas scheme. So you mentioned that we've received INR 255 crores in Q4. In April, we've received INR 117 crores, and we are yet to receive INR 398 crores in the next 10 to 15 days. Sir, my question is, how much of this will reflect in the Q1 stand-alone books of ours.

Talluri Rao

executive
#189

Q1 stand-alone books, if you receive INR 398 crores something...

Devendra Maheshwari

executive
#190

INR 378 crores will reflect.

Talluri Rao

executive
#191

Yes. INR 378 crores will reflect on the top line of stand-alone basis.

Gautam Gosar

analyst
#192

Okay. And this INR 378 crores will include the INR 117 crores, which we've also received in April?

Talluri Rao

executive
#193

Yes, it includes.

Gautam Gosar

analyst
#194

Okay. So total in all will have INR 378 crores included in the top line?

Talluri Rao

executive
#195

Yes, yes.

Operator

operator
#196

Ladies and gentlemen, due to time constraints, that was the last question. I now hand the conference over to Mr. Vikram Suryavanshi for his closing comments.

Vikram Suryavanshi

analyst
#197

We thank the management of PNC Infratech Limited for giving us an opportunity to host the call and taking time out for the interaction with the stakeholders. Sir, any closing comments you would like to give?

Yogesh Jain

executive
#198

In case of further queries, you may get in touch with Strategic Growth Advisors, our Investor Relations advisers, or feel free to get in touch with us. Thank you.

Operator

operator
#199

Thank you, members of the management team. Ladies and gentlemen, on behalf of PhillipCapital India Private Limited, that concludes this conference call. We thank you for joining us, and you may now disconnect your lines. Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete PNC Infratech Limited transcript — plus 251,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to PNC Infratech Limited earnings transcripts and 251,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.