PowerCompute, Inc. (LMFA) Earnings Call Transcript & Summary

November 13, 2026

NASDAQ US Information Technology Software earnings 20 min

Earnings Call Speaker Segments

Phil Carlson

executive
#1

Thanks, operator, and thanks to everyone for being with us on PowerCompute's third quarter 2026 earnings conference call. With us today are Bruce Rodgers, our Chairman and Chief Executive Officer, and Richard Russell, our Chief Financial Officer. A supplemental investor presentation that goes along with today's call is now posted in the Events section of our investor relations website. Before we get started, I want to point out that what we say today includes forward-looking statements as defined under the Private Securities Litigation Reform Act of 1995. Such statements should not be taken as guarantees of future results, and they carry risks and uncertainties that might make actual results differ materially. Among the important factors are our capacity to keep our securities listed on the Nasdaq Capital Market, our liquidity, our ability to continue as a going concern, and our ability to secure additional financing on acceptable terms, our ability to repay or refinance the remaining secured note when it matures, the timing and cost of installing new miners, and our ability to reach expected hash rate, the early stage of our AI infrastructure business and the fact that we lack operating history in it, the volatility of Bitcoin prices, and our ability to secure customers and capital for any conversion of our power capacity. We'll also refer to certain non-GAAP financial measures. For a full reconciliation to the most comparable GAAP measures, please see the earnings release issued this morning and our Form 10-Q, and for a more comprehensive discussion of these and other risks, please refer to our SEC filings and the Investors section of our website at power-compute.com/investors. I'll now hand the call over to Chairman and Chief Executive Officer Bruce Rodgers. Bruce, please go ahead.

Bruce Rodgers

executive
#2

Thanks, and good morning to all of you. Our third quarter can be captured through three figures. We produced 36% more Bitcoin than we did a year earlier. In November 2026, we spent cash on 600 new S21++ miners, which we anticipate will boost our hash rate by roughly 10% by the middle of December. Since June, our secured debt has fallen 94%, and none of our Bitcoin is pledged. Our mission is to generate the strongest possible return on each megawatt we hold, and here is how the quarter progressed for us. To begin, we are extracting more Bitcoin from power we already possess. PowerCompute owns or controls 26 MW of interconnected power, consisting of a 15 MW site in Calumet, Oklahoma, and an 11 MW site in Columbus, Mississippi. For the third quarter, after curtailment and energy sales, we ran at a blended net cost of roughly $0.024 per kilowatt hour. Our power carries variable market rates and will move around. During the quarter we mined 23.9 Bitcoin, a 36% increase from a year ago, and our mining margin after curtailment and energy sales came to 50.7%, compared with 29% in the second quarter. After curtailment and energy sales, our energy cost to mine one Bitcoin was roughly $35,000, versus about $58,000 a year ago, while average revenue was roughly $71,000 for each Bitcoin mined. This bears repeating. Our average cost to mine a Bitcoin has dropped to $35,000 per Bitcoin mined at an average price of $71,000; we are in the business of Bitcoin going up, and we mine coins at about $35,000 apiece. We are also swapping out older miners for newer machines that deliver more hash rate on the same power. Degradation across our older fleet dragged hash rate from roughly 771 petahash per second on June 30 down to about 718 on September 30. Thanks to the newer machines, it hit roughly 800 on October 31, an increase of about 11% with no additional megawatt. In October, we mined nine Bitcoin, 20% above October of 2025. This month, we spent about $1 million in cash on 600 Antminer S21++ miners. They will occupy existing slots in Columbus, replacing roughly 500 older S19s and 100 S19j Pros, and we expect them to contribute 80 to 85 petahash per second of net hash rate, adding roughly 10% once deployed in mid-December. That should take us to approximately 880 petahash per second. Hash rate determines how much Bitcoin we mine. Assuming steady network difficulty and Bitcoin price, roughly 10% more hash rate translates into 10% more Bitcoin. This estimate supersedes the 964 petahash projection in our September 30 release. We assumed a 3.5 MW expansion in Mississippi that is not reflected here. Next, we tidied up the balance sheet. In late September, we repaid and terminated our Bitcoin-backed credit facility with Arch Lending. Secured debt dropped from about $19.4 million on June 30 to $1.25 million on September 30, a decrease of roughly 94%. Interest on the remaining balance runs us about $138,000 annually. Nothing in our Bitcoin holdings has been pledged, and following the close of the quarter we pushed out the remaining note of one million per quarter, moving its maturity from December 31, 2026 to December 31, 2027. Next, we locked in our power situation in Mississippi. In August, the Tennessee Valley Authority, or TVA, approved a fresh data center tariff that carries capacity commitment charges of roughly $1.5 million per megawatt for anything beyond the initial 5 MW. For anyone constructing a data center in this area, that shifts the economics, even with its cheap power; we switched onto the new rate ahead of its October 1, 2026 effective date. Even more significant, we increased our contracted power demand from 8.5 MW to 11 MW while avoiding the capacity commitment charge on all of it. Under that tariff, a new data center project pursuing the same 11 MW would confront roughly $9 million in TVA capacity commitment charges before spending anything on build-out; that explains how we convert our power into Bitcoin at present. At our Oklahoma location, we are likewise gaining know-how in converting that same power into high-performance computing. We have listed our GPU capacity on Vast.ai and are accumulating operational experience with it. HPC has the potential to bring in more revenue per kilowatt than Bitcoin mining, yet it demands sustained uptime, extra infrastructure, and committed customers. Our program remains at an early stage. We aim to be prepared to build out our own HPC capacity powered by our own electricity once we judge that the technology, the customers, and the economics justify it. I will now hand the call over to Rick to review the financial results.

Richard Russell

executive
#3

Appreciate that, Bruce. Turning to Q3 2026: we generated total revenue of approximately $1.9 million. To put that in context, Q2 2026 came in at $2.1 million, while Q3 2025 was $2.2 million — a 13.3% drop year over year. Digital mining brought in around $1.7 million this quarter, compared with $2 million in the prior-year period. Nearly the entire year-over-year swing was driven by Bitcoin's price, not by our output. We produced 23.9 Bitcoin in Q3, which is 35.8% more than the 17.6 Bitcoin we mined in Q3 2025. Over that same window, the average price of the Bitcoin we mined dropped 37.5%, going from roughly $114,000 down to $71,000. To frame it differently, we ended up with significantly more Bitcoin, and the cost per coin was significantly lower. By September 30, 2026, the 63.8 Bitcoin we held was worth roughly $5.3 million, assuming a Bitcoin price of $83,800. For the third quarter of 2026, our mining margin came to 50.7% once curtailment and energy sales are factored in, compared with 29% in the second quarter of 2026 and 49% in the third quarter of 2025. That quarter-over-quarter improvement comes from cheaper energy, greater energy sales, and deliberately switching off machines during peak hours, all of which were influenced in part by the lower average Bitcoin price. During the quarter, curtailment plus energy sales recorded as a cost-of-revenues reduction came to $304,000, versus $152,000 in Q3 2025 — about twice the prior-year figure. We compute mining margin by taking digital mining revenue and subtracting digital mining cost of revenues, net of curtailment and energy sales. Operating costs and expenses overall ran roughly $2.8 million this quarter, a drop of $2.9 million from $5.7 million in the third quarter of 2025. The main factors behind that shift were staff costs and payroll falling by $1.5 million, largely driven by lower incentive compensation. Depreciation and amortization also fell by $1.2 million, landing at $800,000 versus $2 million in the same quarter last year — a drop tied to the impairment of mining machines recorded in Q4 2025. In addition, we booked a gain of roughly $1 million from the fair market value adjustment on mined digital assets, matching the $1 million gain seen in Q3 2025. Our operating loss shrank to about $900,000, down from $3.5 million twelve months earlier. For Q3 2026, net income came in at approximately $400,000, equal to $0.20 per basic and diluted share, versus a net loss of roughly $3.7 million in Q3 2025. Core EBITDA income came in at about $2.3 million. That compares with a core EBITDA loss of $1.4 million in the third quarter of 2025, and a core EBITDA loss of $2.8 million in the second quarter of 2026. Within the third quarter EBITDA figure there is roughly $2.8 million of net gains tied to the Arch loan facility, and I'll go through that next. Down below the operating line, we booked a gain of around $6.7 million on the fair value of the digital assets receivable — that's the Bitcoin held in custody under the Arch facility — which was partly offset by a $4.4 million loss on the related loan derivative. We also incurred $1 million of interest expense, and $700,000 of that was non-cash and linked to the loan derivative. Those fair value loans tie back to a facility that no longer exists, and going forward they won't show up again in this form. With that facility now repaid, the interest on the secured debt we continue to hold comes to roughly $138,000 per year. Since June 30th, we've eliminated the Galaxy, Liebel, and Arch borrowings along with the interest and collar-related costs tied to them. As of the September 30th, 2026 balance sheet, total assets were approximately $22.5 million, which includes 63.8 Bitcoins. Total liquidity — cash, Bitcoin, and marketable securities combined — stood at about $6 million as of September 30th, 2026. The Bitcoin was valued at roughly $5.3 million overall, while cash was approximately $650,000. None of that Bitcoin is collateral. Liabilities overall came to about $3.7 million, compared with $21.6 million as of June 30th, 2026, and $22.4 million as of December 31st, 2025. As of September 30th, 2026, debt outstanding totaled roughly $1.5 million, consisting of a $1.2 million secured promissory note with Brown Family Enterprises — its maturity was extended after quarter end to December 31st, 2027 — plus $212,000 in unsecured insurance premium financing. No borrowing we still carry is secured by Bitcoin. Per the settlement terms of the Arch facility, Arch sold about 267.4 of the 307 Bitcoin to settle the facility and gave back the other 39.6 Bitcoins, worth roughly $3.3 million, to the company. That facility had no recourse, no margin call, and no provisions for liquidation triggered by price, and it was settled on a scheduled reset date. In the quarter, we sold roughly 1.5 million shares via the at-the-market program, bringing in $2.8 million of net proceeds, which we directed toward new miner investments and working capital. A going concern disclosure is included in our Form 10-Q, tied partly to the drop in Bitcoin prices, cash used in operations, and the $1.25 million secured note we still have outstanding. The filing contains the complete discussion. As a later update, as of October 31, 2026, we held 65.7 Bitcoin, worth about $5.1 million, using a Bitcoin price of roughly $77,000 on that date. Bruce, the floor is yours again.

Bruce Rodgers

executive
#4

Thanks, Rick. So in summary, we mined 36% more Bitcoin compared with a year earlier. Our mining margin sits above 50%. We used cash to buy 600 new miners, which ought to boost our hash rate by roughly 10% by mid-December. Secured debt has fallen 94% since June, and none of our Bitcoin is pledged. In Mississippi we brought on 2.5 MW of contracted demand with no capacity commitment charge; now that interest expense is down to around $138,000 annually, a larger share of our capital can flow into our miners and sites rather than debt service. What we're focused on is completing the miner refresh, holding our power costs down, and steering every megawatt toward the use with the best return; we're eager to bring you up to date on how we're doing. Thanks for your ongoing support. Operator, would you please open the line for questions.

Matthew Galinko

analyst
#5

Hi. Thanks for taking my question. Maybe first, I might have missed this in the script, but could you give a rough estimate of what your mining margin will look like, all else equal, with the new machines and hash rate deployed?

Bruce Rodgers

executive
#6

No, I don't believe we made any forward-looking disclosure in the script regarding the new machines deployed. We took the mining. What's in the script is that our mining margin rose above 50% from 29% in the second quarter.

Richard Russell

executive
#7

Looking ahead, Rick, figuring out the margin is going to be tough given what the Bitcoin price turns out to be, correct?

Matthew Galinko

analyst
#8

Yeah, absolutely.

Richard Russell

executive
#9

It pulls roughly the same amount of power.

Matthew Galinko

analyst
#10

Right, okay. So I mean, if you sort of take out the curtailment and then factor in the higher efficiency and utilization, you land at incrementally better, though perhaps not quite as high as this quarter with the curtailment benefit?

Richard Russell

executive
#11

Right. Curtailment is elevated this quarter; it will come down somewhat in the fourth quarter; so the rate per hour per kilowatt will likely rise a little on average compared with what we had in the third quarter. But the newer miners will produce better, right, at that same price.

Matthew Galinko

analyst
#12

Yeah. All right. So I believe it's been at least a quarter, possibly a quarter and a half, since you started running the GPUs. Is there anything you've learned that you can share, or any extra detail you could give on how that's going?

Bruce Rodgers

executive
#13

Nothing quantitative, just from anecdote: the demand for our machines amazes us, and the utilization rate is coming in above what we expected. There's also an interesting piece to it, which is that when people use the machines for an instance, they leave their data behind, and then they pay rent for, we charge them rent for leaving their data, and we never really factored that into the revenue of it; so that's the kind of thing we learn in that.

Matthew Galinko

analyst
#14

I mean, when we look ahead to 2027, obviously I think there's some planning you need to do and capital does matter, but do you see — I think you said that the higher value per megawatt probably lies in that direction. Is there any early thinking about putting more toward that direction?

Bruce Rodgers

executive
#15

I guess what you're asking is whether to put more toward buying GPUs or more power toward GPUs?

Matthew Galinko

analyst
#16

And on that point, considering what the election cycle has shown us, I'm wondering whether you've formed any fresh opinions about sites, or about getting access to additional sites, to bring more power into your portfolio.

Bruce Rodgers

executive
#17

So, in Mississippi we have 3.5 MW that isn't currently powering Bitcoin machines or GPUs. After the refresh finishes, that's where the easy revenue opportunity sits for us. When that's done, using that 3.5 MW in Mississippi really calls for the next chunk of capital, and which kind of use we go with remains up in the air.

Matthew Galinko

analyst
#18

Okay. That's great. Thanks. I'll rejoin the queue.

Bruce Rodgers

executive
#19

Thank you, Matt.

Operator

operator
#20

With no more questions coming in, that wraps up PowerCompute's earnings conference call for the third quarter of 2026. We appreciate everyone joining us. You can go ahead and disconnect now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete PowerCompute, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to PowerCompute, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in PowerCompute, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.