Primoris Services Corporation (PRIM) Earnings Call Transcript & Summary

February 25, 2020

New York Stock Exchange US Industrials Construction and Engineering earnings 42 min

Earnings Call Speaker Segments

Kate Tholking

executive
#1

Thanks, Doug. Hello, everybody, and good morning. We appreciate you being with us today. Tom McCormick, our President and Chief Executive Officer, will be speaking on this call, along with Ken Dodgen, who serves as Executive Vice President and Chief Financial Officer. Along with the press release issued this morning, we have also made slides available on our website covering the main points we intend to address during this call. To find them, visit our corporate site, www.prim.com, and click on Investors. After you reach the Investors page, the slides can be located under Events & Presentations, right beside the webcast link for today's call. Prior to starting, I want to remind all of you that certain forward-looking statements may be included in what is said on today's call, among them statements about the company's future performance. Terms like estimates, believes, expects, projects, may and future, or comparable expressions, are meant to signal forward-looking statements. Risks and uncertainties are inherently part of forward-looking statements, including, without limitation, those covered in this morning's press release, those described in the Risk Factors section and other portions of our annual report on Form 10-K for the period ending December 31, 2019, which was filed this morning, and other filings with the Securities and Exchange Commission. Primoris has no obligation to publicly update or revise any forward-looking statements, whether from new information, future events or otherwise, except as applicable securities laws may require. At this point, I'd like to hand the call over to our CEO, Tom McCormick.

Tom McCormick

executive
#2

Thanks, Kate. Good morning, everyone, and I appreciate you being here as we go over the results for both the fourth quarter and the entire year. For the first time ever, Primoris exceeded $3 billion in annual revenue, and that milestone came about through the dedication of every one of our field personnel, along with our project managers, the support teams in our back office, and the members of our leadership group. It is a team I feel very fortunate to guide. During Q4, severe weather and a handful of delayed projects held us back, though we also gained from excellent performance in our solar pipeline field services and in the Canadian markets. As we had anticipated, operating cash flow in the fourth quarter came in very strong, which let us finish off the whole $50 million stock buyback plan, delivering value to Primoris and to our shareholders, and we closed out the year with a healthy balance sheet. Our year-end backlog is still robust, with long-term MSAs making up 44% of it, and the bidding work we currently have underway gives us confidence looking toward 2020; we keep scrutinizing how we bid, seeking improvements to the process so that we pursue the correct projects with the correct clients. The opportunities in our pipeline appear highly encouraging for a strong beginning to 2020. We remain focused on SG&A, and we stay disciplined regarding where our money goes and the manner in which it is spent, emphasizing efforts that can boost efficiency across the business unit, segment and corporate levels, while simultaneously ensuring that the people working in the field possess the tools and equipment required to succeed. Fourth quarter earnings of $0.53 per share enabled us to hit our guidance for the fiscal year, even with the obstacles created by pipeline delays and the poor results in our Transmission segment, which we restructured and renegotiated with an eye toward what comes next. It makes me very happy that we reached the guidance range we were aiming for, and I think it deserves mention that this happened even though certain big projects we had initially expected to begin during 2019 never materialized. Let me provide a bit more detail on each of our segments, beginning with gas utilities and distribution. Although revenue across our California markets dipped somewhat, we enjoyed a favorable blend of work that produced stronger margins than we saw in the fourth quarter of 2018. Conditions in our Midwest markets proved more difficult, since late November brought heavy rain and snow to every Midwest market where we do business. That type of harsh weather severely hurt productivity and labor costs, and in the end it dragged down both revenue and earnings for that region during the fourth quarter. Even so, weather has no bearing on how appealing the gas utility market is over the long haul, because we keep witnessing broader national acknowledgment of the necessity to swap out our outdated gas pipeline and distribution infrastructure. Only a year ago, the State of Texas enacted legislation mandating that replacement of the highest-risk pipelines throughout the state rise by 60%, along with eliminating every known cast iron pipeline by 2022. Work of this integrity and replacement nature is frequently carried out under MSAs, and these recurring, long-term programs are precisely what Primoris does best, leaving us favorably positioned to take advantage of such opportunities. The Transmission & Distribution segment, which targets the electric T&D market, is our other utility segment; results there in 2019 left us disappointed. Of this segment's 4 divisions, 2 performed well, while the remaining 2 came in below expectations. As I mentioned earlier, we do have certain rate issues in 2 of those divisions, and we're collaborating with the clients to have them adjusted. During Q4, we saw a slowdown in spending from a number of our major utility clients, after their purchases had been running strong through the first three quarters of the year. The reason is that many utilities reduced what they were spending in the fourth quarter, driven by several internal factors. We were able to recover a portion of the revenue we lost, and we're looking at this situation as an opportunity to bring down our direct cost by right-sizing crews, using and managing equipment more efficiently, making better use of subcontractors, and keeping ancillary costs under tighter control. The clients who scaled back in Q4 have subsequently informed us that those cutbacks were only short-term and that projects would resume during the first quarter of 2020. We continue to engage in ongoing conversations with them regarding the way their shifting budgets impact our expenses, as well as collaborating on the development of a model that can be sustained over time. Another point to mention is that working through a revised long-term MSA agreement with a key customer in our T&D business required more time than anticipated, which delayed when we could start capturing the advantages of the updated contract conditions. The gains from each of these efforts should become visible in 2020, and our confidence remains high that significant long-term possibilities exist within the electrical utility sector. Results were mixed for the Power, Industrial & Engineering segment during Q4. Work tied to our MSA agreements at industrial sites is going quite strongly. That said, revenue in California fell, which we had anticipated, since demand for newly built natural gas-fired power plants remains under pressure. Growth in renewable power, though, is absorbing a large share of the softness in the natural gas power market. Phase 1 of our West Texas solar project wrapped up in the fourth quarter, while phase 2 is running ahead of schedule, with completion now projected before the second quarter of this year ends. During the past two years, we've built a reputation as a top-tier contractor in the utility-scale solar space. In the next few years, that market will remain attractive to us, driven by state-level renewable portfolio standards and increasingly competitive solar electricity pricing. Outside of solar, we continue pursuing additional renewable work — battery storage, biodiesel, and biogas facilities — and in 2019 we announced one of those projects. Another growth avenue for us is renewable natural gas, because developers are looking for partners who can provide a full solution. Since Primoris provides a wide array of services, we're able to deliver a tailored solution to each customer that fits what they need. Our industrial team along the Gulf Coast had a tough fourth quarter, as 2 industrial projects encountered additional difficulties. One of them finished during Q4. The other — harmed by numerous design revisions and delays on the client side — is close to wrapping up, and we're working closely with the clients connected to that project, since changes led by the owner created a negative effect: impacts on productivity plus greater costs. Even though I don't like having projects that underperform, I think it's important to recognize them and take lessons from them. Over the past few months, we've added more experienced professionals and field supervision to our Gulf Coast team, giving us the right skills and expertise to carry out and oversee the projects we're going after. Now shifting from the Gulf Coast to Canada. In Western Canada, the results we're seeing continue to exceed our expectations, and the bulk of our activity there falls under MSAs.

Tom McCormick

executive
#3

The performance we're seeing from them has us pleased, and we expect 2020 will be another strong year. The transformation in our Civil segment makes me very proud. If you set aside the effects of the Belton claims, that segment had an excellent quarter and proved it can be both profitable and safe. Tighter execution and better contract management are paying off, as is being more selective when bidding on our heavy civil projects. Our I&M team collaborates closely with our renewables and industrial teams, and the follow-on work they're seeing — things like site work and road construction for solar facilities, LNG plants, and industrial chemical facilities — looks robust for 2020 with a bit of a back-end weighting; and lastly, our Pipeline & Underground segment. Demand keeps rising in the pipeline field services sector — 2019 brought us revenue growth beyond 50%, and the 2020 bid pipeline appears extremely robust. We are growing that side of the business, working alongside clients to prolong the useful life of pipelines already in service as well as related facilities; within our pipeline market, the top line fell short of 2018 levels, though this came as no surprise given that permitting hurdles and legal disputes hit the industry hard during 2019. Because big projects got pushed back, a lot of contractors went after smaller scopes just to keep their essential staff and skilled tradespeople occupied, and that ripple ran through the whole marketplace. Still, we made the deliberate choice to hold our margins rather than slash them, so we walked away from work instead of accepting jobs that would lose money. Looking ahead to 2020, the picture is much brighter than what we saw in 2019. A number of projects—some with unions, some without—are either underway already or set to kick off during the first quarter of this year. We also have multiple bids where we've been told we made the shortlist or received a verbal award. As for our biggest pipeline job, oral arguments were heard by the Supreme Court just yesterday, and a ruling should come down in late June or early July. The soonest we'd anticipate getting back to work on that project is late in the third quarter. Let me be clear that this single project isn't what's driving our positive outlook for the 2020 pipeline market, and it isn't factored into our 2020 guidance either. When I look at each of our segments, what makes me incredibly proud isn't just the financial numbers they delivered — it's also how they performed on safety. In 2019 we logged 24.5 million work hours, which is 25% more than 2018, and we never let our attention to safety slip. Our 2019 TRIR sits well below the industry average, but when it comes to safety, there's always room to do better; that's why I've asked our team to beat our 2020 safety goals. Over the course of the year, a number of safety honors came our way. Four of our business units earned the Liberty Mutual Safety Excellence Award. Canadian Occupational Safety magazine named us among the safest contractors in the oil & gas category. We also took home the 2019 ENR California Safety Award of Merit. On top of the solid organic growth we expect in 2020 from our utility pipeline and renewable markets, we're evaluating potential acquisitions as well — everything from smaller bolt-ons to bigger transactions. An able group is already evaluating possibilities, and my expectation is that we will close no fewer than one deal before this year ends. With a healthy combination of master service agreements and project work in our backlog, positive conditions across the utility, pipeline and renewable sectors, and a Civil division that has returned to the operating margin range we anticipate, I feel certain that 2020 will bring further success for the Primoris group of businesses. Ahead of handing the floor to Ken for the financial specifics, I'd like to note that our executive compensation program has been revised. When it comes to bonuses, we've long considered things such as backlog, operating profit, cash flow and safety. Those measures are now officially linked to senior management's bonus determinations. In our view, this benefits our leadership group, since the objectives they're working toward are now spelled out very plainly. It additionally gives up-and-coming leaders a way to acquire a stake in Primoris stock, which keeps their incentives in line with what our shareholders want. Ken, over to you.

Ken Dodgen

executive
#4

Thanks, Tom, and good morning to all of you. I'll cover how we did in the fourth quarter, along with the balance sheet, cash flows, and backlog, and then I'll finish with what we're expecting for 2020 before we take your questions. Revenue for the fourth quarter of 2019 came in at $789.8 million, versus $877.7 million during the same quarter of 2018. That drop came mainly from the anticipated falloff in the Pipeline segment, since some projects got pushed into early 2020, though growth in the Power and Civil segments offset it a bit. When it came to our biggest customers this quarter, 3 large utility customers together made up 21.4% of revenue, and a renewable energy company made up 5.6%. Our top 10 customers now represent under half of revenue — just 44.8% in the fourth quarter and 47.2% for the entire year. Gross profit for the fourth quarter of 2019 totaled $89.5 million, compared with $103.3 million in the fourth quarter of 2018. That lower gross profit stemmed mostly from reduced margins in the Power and Transmission segments, plus weaker revenue in the Pipeline segment. As you may remember, in Q4 2018 the Power segment gained from a sizable settlement on a disputed receivable and from a successful closeout of a major power project. During 2019, that segment had no settlements or closeouts, and instead faced 2 difficult industrial projects on the Gulf Coast that Tom mentioned earlier. Together, those factors caused this big drop in profit between 2018 and 2019. Tom already covered the problems we're working through in the Transmission segment. I'll repeat what he said: we keep making organizational and operational improvements to bring this segment back to the profit levels we expect. Partially offsetting the overall gross profit decline was a gross profit increase in the Civil segment, driven by stronger performance on our civil projects and headway toward settling claims on the 2 remaining Belton area projects. We're still working through the claims process with TxDOT, and in Q4 we revised our recovery estimates on the 2 remaining claims. By year-end, all 5 projects were substantially complete. SG&A expense for the fourth quarter of 2019 was $48.6 million, a slight decrease from $50 million in the fourth quarter of 2018. Even with that decrease, SG&A edged up as a percentage of revenue to 6.2% because revenue was lower in 2019. For the full year, SG&A came to 6.1% of revenue, and we expect to stay in the low 6% range as we head into 2020. Interest expense for the fourth quarter of 2019 was $2.6 million, versus $7.1 million in 2018. In 2019, we had a $1.3 million unrealized gain from the change in fair value of our interest rate swap, whereas in 2018 that figure was a $2.8 million loss. If we set aside the noncash unrealized movements in the value of our swap, my expectation is that interest expense for 2020 will come in at about $4 million each quarter. On income attributable to Primoris, the effective tax rate came to 29.3% in the fourth quarter and 29.1% for the year. For all of 2020, we anticipate that rate staying at around 29%, though it could shift a bit based on the states where we operate and how much we pay in per diems, since those aren't deductible for tax purposes. Net income attributable to Primoris in the fourth quarter was $26.9 million, or 53% — $0.53 for each fully diluted share, versus $32.4 million, or 63% per fully diluted share, in 2018. Across the full year, we posted a record $1.61 per share, beating the record $1.50 per share set in 2018. Now to our cash flows. The fourth quarter came in very strong, as we anticipated, at $158.1 million in cash flows from operations; that figure includes roughly $100 million in cash from selling customer receivables and from settling the 3 Belton area claims we talked about in the third quarter. During the fourth quarter, we put about $16.2 million into property and equipment. Over the full year, our investment was $94.5 million, and $57.5 million of that went toward construction equipment. We're nearly finished with upgrades to a number of our offices and facilities, and we anticipate 2020 capital spending landing between $50 million and $60 million, with nearly all of it directed at construction equipment. On top of that, we're selling off equipment we don't need anymore and resizing our fleet as required. Proceeds from selling property and equipment reached $28.6 million in 2019, which is almost $17 million more than the $11.7 million sold in 2018; we intend to keep assessing our equipment fleet in 2020, and equipment sales could be at similar levels. Our year-end balance sheet was in strong shape. We finished our $50 million share repurchase in December and still closed the year with $120.3 million in cash; combined with $164.2 million of borrowing capacity under our revolver, total available liquidity at year-end came to almost $285 million. Total debt fell to $351.3 million. Net debt stood at $231 million, and the debt-to-equity ratio finished the year at 55.9%. At year-end, our weighted average interest rate was just under 4%. We think this mix of low debt and available liquidity will let us pursue every opportunity for organic growth and strategic acquisitions in 2020. Fixed backlog at year-end was $1.07 — sorry, $1.76 billion, and our 12-month MSA backlog was $1.42 billion, giving total backlog of $3.18 billion, basically flat versus where we finished Q3 of 2019. Looking ahead to 2020, we anticipate recognizing roughly 76% of the backlog we hold at year-end as revenue. And then, our outlook for 2020: we anticipate fully diluted earnings per share to land somewhere between $1.70 and $1.90 per share. That range leaves out any possible benefit from the Atlantic Coast Pipeline project, though we stay dedicated to backing our customer once that project is prepared to proceed. With all that said, let's open things up for your questions. Doug?

Lee Jagoda

analyst
#5

On the Pipeline segment, considering that $260 million in work you secured during late January, what extra capacity remains available for taking on more projects before ACP potentially kicks off in Q4?

Tom McCormick

executive
#6

It truly hinges on how large the project is and when it's scheduled. As you're aware, pipeline projects burn quickly. Mobilization follows award pretty fast. Our teams are out there working on those jobs already. Should we manage to work them into our schedule, we could handle roughly up to 5 spreads simultaneously, based on what kind of work is involved; so the mix matters, along with each project's size and its schedule.

Lee Jagoda

analyst
#7

So next, I realize you essentially removed ACP from what you’re projecting for Q4, but when it comes to filling in that work during Q4 so you can hit that projected range, what assumptions are you making?

Tom McCormick

executive
#8

Lee, let me make sure I’ve got your question right. What is it exactly that you’re asking?

Lee Jagoda

analyst
#9

Okay, so removing ACP from the fourth quarter, and with your guidance sitting at $1.70 to $1.90, I'd assume you'll be doing additional work tied to Rockford during that period.

Tom McCormick

executive
#10

That's right.

Lee Jagoda

analyst
#11

What do we have baked in for Q4 in the way of backfilling?

Tom McCormick

executive
#12

Under $30 million in revenue; our expectation had not been — regardless of whether ACP is granted approval during this year, our expectation had not been that a significant amount of work would get done during this year. I'm referring to trees coming down, possibly clearing, additional right of way. In West Virginia, no work happens during winter. By that point you'll be in winter, particularly if notice to proceed arrives late in the third quarter. A bit of work could get done in the Carolinas. So it might be a larger figure than that, but my belief is our original plan for ACP contained under $30 million. And let me address this as well. Let me go back to your previous question briefly. My remarks were mainly about Rockford, including with regard to the capacity they have. There's a nonunion business of ours that likewise possesses the CAT capacity needed to handle multiple spreads, and honestly they are performing very well.

Lee Jagoda

analyst
#13

Understood. Then one additional item regarding Transmission. I realize you brought up a few problems that led to the margin coming up short in this quarter. Could you discuss the MSA renewal a bit, and on a like-for-like comparison, if conditions stay the same—though my expectation is they'll improve, but if they stay the same—how much does the renewal of that MSA add to margins, ideally starting in Q1?

Tom McCormick

executive
#14

Let me consider how to respond to that without revealing many specifics about that MSA. On a percentage basis, I'd expect—honestly, I'm not certain how to respond to that. That's 200—approximately—it accounts for roughly $208 million of work that we ought to be able to complete over the span of this year. Our margins will be, I'll simply say, within the 8% to 10%—well, actually, gross margins will fall in the 14% to 16% range for that work; so does that address your question without truly providing many specifics about that MSA?

Lee Jagoda

analyst
#15

That's really useful. Is there any way to frame that in terms of — how would it stack up against what that work would have delivered this year?

Tom McCormick

executive
#16

Had we simply been performing work for that same client this year at those same levels, those margins would be low single digits.

Sean Eastman

analyst
#17

The first thing I want to ask about is those industrial projects along the Gulf Coast. My recollection is that during the prior quarter, you told us the drag from them would stay contained within Q3. From what I'm hearing, one of those projects has now wrapped up in Q4. So when does the other one wrap up? And I'm wondering whether this remains a drag as we move into early '20, or whether your outlook assumes margins there get back to normal right from the start.

Tom McCormick

executive
#18

Let me jump in — I'll take your question directly. I'll speak to the one — that project gets completed during the fourth quarter. Sadly, when projects turn bad, they tend to be — in our view, they're like a gift that never stops giving. It simply took somewhat more time to bring that project to completion. As for the second one, it has slipped into 2020, mainly due to the — you heard me mention design changes as well as client-led changes. Those changes have kept coming — on this particular project we've encountered numerous changes that stretched out both the work scope and the schedule; we'll wrap it up within the next couple of weeks. So that project gets completed within the next couple of weeks. Right now we're in talks with the client about selling our claims, and all of those discussions are moving in a positive direction; so that — we expect to have it behind us within the next 2 to 3 weeks. With new projects kicking off the year, that particular group is performing quite well; they've managed to win some work, and their performance so far this year is solid. We brought in — as I mentioned in my statement earlier, we brought in some new key people, mostly field-level type people, to help ensure we get the right skill sets in place. It's not that we lacked good people, but these — they need to focus on managing their contracts a bit better and let some people focus on some work in the field, and we're seeing the benefit of that now; so I believe you're going to see a return to traditional performance in the coming weeks. In fact, we're seeing it now.

Sean Eastman

analyst
#19

All right, that's useful. Then regarding the civil claims, could you quantify how beneficial that was versus what you had expected internally during Q4? Also, are all the claim resolutions finished now, or will additional ones arrive in 2020? And has some portion of that been factored into the 2020 outlook?

Ken Dodgen

executive
#20

Yeah. Sean, we typically don't discuss specific customers or claim recovery, particularly at this stage. As for resolution, though, it sits within the CCC process, and Tom, feel free to chime in at any point. However, it's a legal matter beyond our control, unless TxDOT decides to remove it and reach a settlement with us.

Tom McCormick

executive
#21

Right, so what we had anticipated — what we were hoping for — was that we'd be able to resolve these 2 claims within this year. Should things not proceed favorably, I suppose they might stretch out over roughly another year; however, what we expect is that we've established a precedent through how the first 3 claims were resolved; and at present we're in conversations with TxDOT, and over the next few months we'll be getting into more detailed talks regarding the potential — the possibility of taking those out of the CCC process and selling them based on the precedent established by our 3 prior claim settlements.

Sean Eastman

analyst
#22

Understood. Now, when we consider the limited visibility surrounding that first 2020 guidance, which key developments still need to occur for us to reach roughly the midpoint? For instance, I believe the sizable solar installations currently moving through will wrap up around the middle of the year. Is it necessary for us to land an additional major solar contract during the first six months to achieve that guidance? Or could you offer any insight regarding the larger project category and how those efforts are progressing?

Tom McCormick

executive
#23

Sure, I'll address three points. Regarding our pipeline — the groups handling both union and nonunion work keep securing bids successfully. Even though nothing has been publicly announced and no agreements have been executed, we've been told we were either among the shortlisted candidates, the lowest bidder, or verbally selected for the job, and at this point we're negotiating contractual details on multiple endeavors worth more than $200 million. In addition, our field services division, which falls under that same Pipeline segment, is achieving wins for which contracts haven't been completed yet in 2020, though we anticipate those being finalized and made public within the next few weeks. Furthermore, we've obtained a limited notice to proceed on a major solar undertaking that we are now advancing, and after the agreement is executed, we will finalize and disclose it — it's a rather substantial endeavor too. So we are observing — 2020 has gotten off to a strong beginning when it comes to newly acquired business.

Sean Eastman

analyst
#24

And just to finish up on that, suppose those pipe projects and final talks get moving, and suppose this big solar project gets going — does that point to potential upside for the outlook? Or is all of that already accounted for?

Tom McCormick

executive
#25

Honestly, it's far too soon to say anything, given that we're speaking with you in February. But it would be — in any year since I joined this company, we'd likely be in a stronger spot than we ever were before. So having that much work in backlog going forward would be a terrific way to begin the year. What that would essentially accomplish is hold space for the ACP project so it can advance in the third or fourth quarter, but it would essentially provide both of our pipeline groups that capacity, something we haven't seen in earlier years.

Brent Thielman

analyst
#26

I wanted to ask something, or actually follow up, regarding the Transmission segment. How soon do you anticipate those margins returning to the levels you mentioned? Or do you figure it arrives in stages over this year?

Tom McCormick

executive
#27

Their operation moves in cycles, much like certain other units of ours that depend heavily on MSA work; consequently, Q1 will be somewhat sluggish. Once customers begin ramping up — obtaining budget approval, then deploying those budgets and deploying that work — my sense is that, once again, Q2, Q3, and Q4 are the periods when we anticipate seeing it.

Brent Thielman

analyst
#28

All right. All right. Turning to the U&D segment — for the first time in quite a while, I believe we've seen no expansion there. I realize there have been certain unusual circumstances behind that during this year. How are you thinking about that business turning that pattern around in 2020? What level of growth do you believe it could achieve, meaning in a case where weather isn't complicated and all of those other elements are sort of removed?

Tom McCormick

executive
#29

Well, you're not — my sense is you won't witness much growth in California. If we're able to simply keep up the work that we've got in that market, my view is that's excellent. The place we'll find growth is in the chances for Q3C and PDS, which are 2 of the remaining business units within that segment, to enter various regions and secure MSA — keep securing MSA work and renew a portion of their MSA work. My view is that's where the chances lie. And that's what's expected for both of those business units this year too.

Brent Thielman

analyst
#30

All right. And what we're hearing from customers in California is mostly just things getting back to usual for the year after...

Tom McCormick

executive
#31

Well, on replacement projects, eventually you get through a portion of that work. That's happened with certain clients of ours, and we're handling some fresh projects out there for them. It's simply a matter of keeping that workload in balance. Beyond that, getting the work pushed out via their engineers and having it released plays a role too. But really, we've been active in the California market for many years. And eventually, that work is going to level off somewhat.

Brent Thielman

analyst
#32

All right. And turning to the Power, Industrial business — your bookings there in 2019 were genuinely impressive. It seems as though a few of the bigger opportunities, perhaps some of those along the Gulf Coast, may have slid to the right somewhat. Could you perhaps share what you're seeing in that region that fits your capabilities; and, I suppose, is matching that kind of bookings level in 2020 achievable?

Tom McCormick

executive
#33

Sure — let me start with California, for the union portion of that segment. Last year they actually managed to — even though they came in somewhat below their revenue, they did really well when it came to securing work, and here's the thing: no single big project was won by them. Everything came through the core of MSA work plus smaller capital projects. My expectation is you'll see the same from them in 2020, though at this moment they have a few opportunities — a project where they're on the shortlist. Should they land it, it's quite large; it exceeds $100 million. We're expecting to hear something within the next few weeks. Moving over to the Gulf Coast, there's still room for that business to expand. We're seeing plenty of opportunities — prospects, and plenty of chances to bid on work. Our focus is simply on being careful to confirm we've got the proper teams lined up and the proper execution strategy so those projects end up successful. And I don't believe — at present we aren't seeing any ceiling in the Texas, Louisiana area when it comes to work. What matters is chasing the correct projects with the correct customers; and my sense is there will be additional LNG projects down the road. There are also some chemical and petrochemical projects that we've — we've been in discussions with clients about for quite a while, projects we thought would be awarded in 2019 but which got pushed. And I'd say we have a — we sit in fairly good favor, a fairly good position on those projects should they move ahead in 2020.

Adam Thalhimer

analyst
#34

In both union and nonunion categories, what's sold out? And under that scenario, how would revenue shape up for the P&U segment?

Tom McCormick

executive
#35

Ken can take that one. He's got the...

Ken Dodgen

executive
#36

Are you referring to what we'd expect in 2020?

Adam Thalhimer

analyst
#37

Not 2020, actually. Say you ran at complete utilization across a whole year — what sort of revenue would that segment generate?

Ken Dodgen

executive
#38

Let me think. We closed out the year at just above $500 million for that segment. Running flat out, somewhere in the range of $800 million to $900 million. That assumes every spread is operating, as Tom mentioned, and lined up in a good sequence, so crews move from completed jobs onto the next ones.

Tom McCormick

executive
#39

And that's not even counting the field service group, which could add another $250 million, right?

Adam Thalhimer

analyst
#40

So compared with 2019, you could genuinely see that segment twice as large?

Ken Dodgen

executive
#41

Correct. Plus...

Tom McCormick

executive
#42

Yeah. I wouldn't put it quite that way, though it would take everything lining up perfectly.

Ken Dodgen

executive
#43

Precisely.

Tom McCormick

executive
#44

Even so, my view is that growth opportunities definitely exist in that area.

Adam Thalhimer

analyst
#45

Yes. And how much of...

Ken Dodgen

executive
#46

And regarding what Tom brought up about the field services business, correct, that isn't a business defined by segments, the way it is with mainline pipeline construction; what matters is work crews stationed at different facilities, plus small- to medium-sized projects that typically run from $3 million to $4 million at the lower end, all the way to $12 million to $15 million at the upper end.

Adam Thalhimer

analyst
#47

Considering the positions you've already made public along with those verbal commitments, do you figure that by year-end you'll be tracking toward peak levels?

Ken Dodgen

executive
#48

Peak might be a stretch, though we're certainly heading for the upper portion of that band.

Adam Thalhimer

analyst
#49

Yeah. Alright. So what happens if ACP really does go away?

Tom McCormick

executive
#50

Then that's just extra gravy.

Adam Thalhimer

analyst
#51

All right, I understand. And regarding that California T&D contract you secured, has it scaled up by now? It was a master service agreement with a major California utility, on the power side.

Tom McCormick

executive
#52

So, it's functioning. It hasn't scaled up. Once more, during the first quarter, it's slow, approvals may only just be beginning; however I recall that at the close of last year, we likely had 35, 40 crews. They'd asked us to increase to roughly double that number, yet we hold the right to cap it until they could demonstrate the work backlog, and we're probably in that same posture this year. Thus I believe it'll be somewhat sluggish in the first quarter and then build in the second, third and fourth quarter; so we're eager to watch that expand.

Adam Thalhimer

analyst
#53

All right. And regarding the underground segment, specifically the pipe side and the distribution activity in California — you mentioned they indicated a Q1 ramp-up, but have you actually observed that happening at this point?

Tom McCormick

executive
#54

Not yet. Honestly, we don't anticipate seeing much of that before Q2, based on where things stand right now. We do have a pipeline project in that region. A smaller one is going to be taken care of by that underground team and it will get underway, though it's quite common for a significant portion of that work to not really begin accelerating until Q2.

Adam Thalhimer

analyst
#55

All right. So across California as a whole — both the gas utility and the electric utility — the demand outlook is solid, but does it genuinely pick up in Q2 and then strengthen during the back half?

Tom McCormick

executive
#56

That's right. The real acceleration kicks in as Q2 nears its finish, continuing through Q3 and Q4.

Adam Thalhimer

analyst
#57

All right, that's useful. Then my final question concerns the solar contracts. I take it you haven't completely worked out what that opportunity looks like yet, though you certainly come across as quite optimistic. So what exactly are you observing when it comes to bidding? And what size do these jobs typically run for Primoris?

Tom McCormick

executive
#58

The range goes from $50 million up to more than $280 million; we believe we've found a genuinely strong niche within that $100 million to $250 million — $280 million band. The number of opportunities sitting there is disproportionate. You simply need to align yourself with, or find a match with, the correct client or the correct partner. So many of these involve developers pursuing PPAs, and we ensure our pricing aligns with whatever their expectations happen to be; we've completed work for several of them that also have additional opportunities. Our performance has left them extremely satisfied. So I believe you can go out and secure — there's plenty available for us — any contractor possessing this kind of experience could go out and land themselves in trouble, should they choose to accept an excessive amount of work. You must be cautious and confirm you've got the proper staffing levels to assign to those projects, since they differ considerably from our industrial construction projects, and they resemble much more of a production facility style of project rather than an industrial one. So succeeding at that kind of work demands a different sort of mindset.

Adam Thalhimer

analyst
#59

what kind of pace are they burning at?

Tom McCormick

executive
#60

after engineering work wraps up — generally speaking, a bigger-scale project takes roughly 1.5 years to complete. As for RoadRunner, it should have spent close to 1.5 years out in the field, and phase 2 wraps up during this summer.

Julio Romero

analyst
#61

So, building on what was just asked regarding solar and perhaps renewables more broadly. One factor that appears to distinguish you could be the capacity to deliver a more all-encompassing offering compared to certain competitors in this area. Could you speak to that, and whether it serves as a differentiator as those renewable projects become increasingly competitive down the line?

Tom McCormick

executive
#62

Our belief is that it does, since we're able to engage early with the customer and examine a — visit a site, assign a price to it, assist them in shaping their scope, assist them in figuring out what the cost per megawatt might be so it aligns with their model, and then proceed into detailed design. Within our I&M group and our Heavy Civil group, we have firms that on projects have handled site clearing, grading, and soil stabilization, and constructed the roads leading to the top of a mesa for a project. We're capable of — we can construct the substations on their behalf. We can install the transmission lines and handle the interconnects for them, and after that we can design and build the solar plant; so honestly, we are essentially — not every client utilizes all of our services, but when it comes to that, we operate as a one-stop shop.

Julio Romero

analyst
#63

Understood, that's useful. Now, a quick administrative item. I believe you said we ought to expect roughly $28 million from equipment sales during 2020, the same as in 2019?

Ken Dodgen

executive
#64

Well, sure, though I'm not sure we can count on $28 million, since it's unclear how that rightsizing will play out; even so, I wouldn't be shocked if our equipment sale proceeds in 2020 came in above what we've seen in past years. In the past, we've generally landed somewhere between $9 million and $12 million. So I can't say whether it will reach $28 million, but it ought to exceed the $9 million to $12 million we typically saw before 2019.

Tom McCormick

executive
#65

Well, to start off, thanks to each of you for being here. It was — 2019 turned out to be a good year. There were certain opportunities plus areas we have to address and get better at. I believe we're in good shape — those efforts are already moving along nicely. And we're anticipating a strong 2020 across the entire Primoris group of companies. Appreciate you being with us.

Operator

operator
#66

Everyone, that brings today's teleconference to a close. We appreciate your participation. At this point you're welcome to disconnect your lines, and enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Primoris Services Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Primoris Services Corporation earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Primoris Services Corporation or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.