Pulsar Helium Inc. (PLSR) Earnings Call Transcript & Summary

October 27, 2026

TSXV CA Energy Oil, Gas and Consumable Fuels special 49 min

Earnings Call Speaker Segments

Unknown Analyst

analyst
#1

Good afternoon, ladies and gentlemen. Welcome to the Pulsar Helium "Ask me Anything" investor session. [Operator Instructions] Given the significant attendance on today's call, I suspect we won't be able to get through every question. We've had a number pre-submitted, but we will do our best to cover as many as we can throughout today's session. Before we begin, we'd like to submit the following poll, and I'm sure the company will be most grateful for your participation. Thank you very much indeed. Well, look, that's the intro's over with. Tom, Cliff, thank you very much indeed for joining us this afternoon. Let's not waste any time. I think we've got a lot of questions to get through. So maybe, Tom, the first one is for you.

Unknown Analyst

analyst
#2

The company's share price is up by more than 20% in a week. Are we likely to hit an all-time high in your opinion? And what news and milestones could investors look forward to in the near term?

Thomas Abraham-James

executive
#3

Well, thank you, and good afternoon and good morning to everybody listening. Thanks very much for your attendance. Well, look, thanks for asking because it's -- whilst we don't comment on the share price per se, what I can say is that it's been an incredibly busy week for the company. We've had a lot of news flow actually over the past couple of weeks, I should say. And so what we've had is we've had the signed Chart and Baker Hughes equipment proposal. And so that's for the rare gas hub. So the actual equipment for the production of liquid helium and CO2. We've also had a separate announcement with the City of Two Harbors in Minnesota, which is the proposed rare gas hub site. We've then had the helium-3 evaluation agreement with [ LH3M ]. My colleague, Cliff here, has been on 60 Minutes, which really garnered incredible coverage around the United States and indeed globally. Department of Energy has just put helium onto its critical list in the U.S.A. And prior to that, earlier this year, we managed to raise quite a lot of capital. So we're in a very healthy financial position. So I would think that it's one or all of those combined that's resulted in this resurgence in our share price. And I guess I could say long may it continue, and we're certainly doing everything to continue the news flow and deliver on everything that we stated in all those respective news releases.

Unknown Analyst

analyst
#4

Great. And I think you just touched on the U.S. Department of Energy's putting helium on the critical list. Do you think this will expedite Pulsar's pathway to production? How do you anticipate that this will help the company's growth? And could Pulsar qualify for DOE, EXIM or other federal financing loans, guarantees or trusts? Will this designation accelerate ongoing non-dilutive capital discussions? Perhaps Cliff, one for you.

Cliff Cain

executive
#5

Yes, it absolutely would. I mean this is wonderful news that the DOE moved to put this on the critical minerals list. Again, this is my own opinion. I would suspect that probably the Department of Interior is right behind that. We're obviously in -- there's 2 different major conflicts going on globally. You saw the Pentagon's announcement just a couple of days ago on fortress building resilience throughout the supply chain, specifically for the Department of Defense and U.S. bases. So yes, this definitely opens up a lot of avenues for Pulsar, not just on the helium-4 front, but also the helium-3.

Unknown Analyst

analyst
#6

That's great. Regarding the helium-3 potential at Topaz and your recent collaboration with [ LH3M ], what time line are you working towards regarding development of helium-3 for separation technologies? Maybe, Tom?

Thomas Abraham-James

executive
#7

Yes. So this one, we signed the agreement on the 14th of October, and we're actually at that very moment in time, we were together in California at the NASA research facility, Ames. So it was quite the location to announce this agreement that we've signed. And so it starts off with a deep dive into a desktop review of the Topaz gas and isotope data. And then Phase 2 will then go into laboratory testing plan. And the starting target is at least 95% helium-3 purity. And then a pilot could follow, but that will be under a separate agreement. So we haven't set public dates on when these set milestones will be achieved. I mean, really, we don't want to rush the science. We are looking to do something here, which has never been done at a commercial scale before really because there's never been a requirement for it. There's never been or should I say, an opportunity for it. So it's something that we've already got the federal labs who've looked at it. We've got the Woods Hole Oceanographic Institution. We've also confirmed the helium content in our Topaz gas. And this is really the next iteration to see if we can via a staged approach, which is really coming at minimal to no cost to Pulsar to see if this technology can be utilized at our facility and then add that helium-3 value to it. And so yes, we will announce to the market as and when those stages have been reached and what the decision point is at the end of those.

Unknown Analyst

analyst
#8

Great. And Cliff, I mean, just returning to the U.S. government's interest around the critical minerals importance of helium to the U.S. economy. Do you think it's likely that the U.S. government might consider buying someone like Pulsar?

Cliff Cain

executive
#9

I mean there's always the chance, right? You look at the current administration is making industry moves where if you look at MP Materials out there, this move to bring processing and rare earth mineral processing to the United States. Again, I would say like maybe an outright acquisition, no. But some kind of equity investment, yes, probably. There's always the potential for that. And honestly, that's more for the helium-3 side of things just because it is kind of like the Manhattan Project of our time, terrestrial helium-3 has never been done on commercial scale. I've said it before, Minnesota or the moon. But I don't want to attack the lunar mining folks, right? Listen, we've got to get back to the moon. So what a better place to -- Minnesota is a bridge to the moon is what I've briefed Pentagon officials on, right? Here's our opportunity. So...

Unknown Analyst

analyst
#10

Tom, production question here on production. Given the previous target of Q4 '27 has shifted, what is the Board's confidence level in meeting the new H1 2029 target for first helium production? And maybe could you walk us through some of the primary drivers behind the delay?

Thomas Abraham-James

executive
#11

Yes. Well, look, with that particular production guidance that actually didn't come from the company itself. It came from an analyst out there, so an analyst estimate. What we put out in the public domain was that we put out that we were targeting Q4 2027. And so look, now that since we've made that guidance, we've actually gone and signed the Baker Hughes agreement. So that's in place. And shortly thereafter, then the Two Harbors site was announced as well. So before we could really comment on an absolute time of when production may be possible, we're going through this phase now of site due diligence, EPC selection and then ultimately financing as well, but also in discussions with potential offtakers. So there's many things in there that contribute to it. But as mentioned in the Baker Hughes announcement, we did say that a portion of this equipment had already been fabricated. And so that, therefore, creates an opportunity as well. So whilst I can't answer the question absolutely, the reason for the change, as I say, it came from an analyst. But we do have -- now that helium is on the DOE critical list, we know that the conflict is ongoing and the shortage is ongoing, we have a fair wind behind us in order to realize this potential as soon as we can. That's what we intend to do, and we will keep the market announced when those key milestones. So as I say, the site, EPC and the financing are all ticked, then we will be looking to move forward as quickly as possible.

Unknown Analyst

analyst
#12

Let me stay with you, Tom, for a moment. Of the projected $85.5 million facility cost, is this capital allocated to both helium and CO2 plants or strictly to the helium infrastructure? If they are separate, what's the estimate cost for the CO2 plant? And will both facilities come online concurrently?

Thomas Abraham-James

executive
#13

They're not separate. So that's an all-inclusive cost for the plant itself. So this is for the production of liquid helium and for liquid CO2. So that is the plant itself. The only cost that will be in addition to that is the EPC works. So -- what we like about particularly the Two Harbors site is that it's already effectively in a logistical hub. So that accelerates things. So there's rail there, there's power there. There's water there. There's all the utilities that you would anticipate. And then also the city putting its support behind and also making a level of commitment to contribute and participate in getting this production facility online as well. So look, it's -- the cost is for the plant. It will do both commodities. The additional costs are effectively the connection of it to the site.

Unknown Analyst

analyst
#14

There are a few questions around contracts. And I mean, one of them, are we still on track to secure low-cost drilling contracts for the next phase of the wells? Or has the rising industry-wide profile of helium inflated drilling and supply chain costs? -- that's for you, Cliff, maybe.

Cliff Cain

executive
#15

No, it hasn't inflated. I mean, drilling contracts are -- it's regional, right? If I'm trying to find somebody down in the Permian Basin right now, they're pretty busy. Up here in North Dakota, Montana, fairly available. So I think we're in a good position where it's -- those costs are not really going to impact us at all. So yes, I think we're in a good position.

Unknown Analyst

analyst
#16

Tom, maybe a couple of questions around financing here. Funding for plant construction, 6 new production wells and corporate G&A through to production. What is the target financing structure? Specifically, how will this split percentage-wise between equity debt, government grants and loans and potential offtake agreements?

Thomas Abraham-James

executive
#17

Okay. Well, I'll split this question up into a couple of different components. So the first one is that earlier this year, we raised $25.5 million. So with that, $5 million of that is going to Chart Baker Hughes as the initial payment for the production facility. But we have budgeted within the money that we already have in our account for the up to 6 additional wells to be drilled. We also have the G&A costs in there as well. So look, what -- the question mark then remains the second component, which is the financing of the plant itself and the EPC costs for its installation. So with that one, we put out a news release the other week, clarifying what the company's position is on this. And very much so it is targeting majority debt finance for this. So that is -- we've already started speaking to traditional more conventional banking institutions, of which there's interest. In addition to that, there are a number of government agencies at a federal and state level as well. So the United States Department of Agriculture, they can provide facilities as well for qualifying companies or locations. And so for those, it will be a rural environment with job creation for which we fall into. You then got DEED, which is a Minnesota agency for financing. You then got the Iron Range, which is a local one for the what's called the Taconite Assistance Area, which is what we're within and taconite is iron ore. And so there's a number of iron ore mines around us, some of which are closed. And so the IRRR is there looking at what's the next generation of potential extraction industry that could be receiving support from them. So there's a number of avenues there. Of course, now the DOE will be speaking to them as well after last week's announcement. So we are very much of the opinion that we want to go through and do majority debt for this. We think there are some very good low interest options out there that we're looking to pursue. And what we would be looking at is not so much of a piecemeal approach to it, but having said that for the -- we could say that with each of the milestone payments for this plant that with the financing that we are looking to put into place, we'd be able to effectively cover all of those and with any be able to accelerate the time frame because with the plant itself, we've got a milestone payment, the second milestone to be paid next year. The sooner we get that one paid, the sooner the time frame reduces, and that's our intention.

Unknown Analyst

analyst
#18

That's great. Given the Topaz project requires intensive capital expenditure to reach production, what's your strategic rationale behind concurrently funding both the Falcon project in Michigan and the Tunu project in Greenland? Is there a risk potentially of overextending our financial and operational bandwidth?

Thomas Abraham-James

executive
#19

Look, the minimal capital outlay, we can keep those projects moving along. And they are very good projects. They are just simply at an earlier stage in Topaz. And so we know that Tunu in Greenland that we have identified the helium there that exists. With Michigan, it's at an earlier stage, but certainly from regional work and previous work that has been conducted there by explorers not looking for gas, the gas has been encountered. So it's effectively been derisked to a degree as well. So look, we've got an opportunity here for very low cost. So in Greenland this year, we spent something like less than $100,000 for Michigan. We're doing an airborne survey. And whilst it may seem from a market point of view, not the most exciting programs, technically, they will advance these projects a lot and get them to the stage where the next stage would most logically be drilling. So -- and then a decision will be made at that point in time how that would be financed. But for a low cost, we could get these very exciting projects moving forward. And what really the strategy is, is that we've got Topaz, which we are looking to get online. And then in addition to that, the neighboring Michigan to see if we can increase the resource base there because we are firmly of the belief that we are looking at a regional helium system there. And then Greenland, which is its own project in Europe, where there is absolutely minimum helium available. So each project is exciting.

Unknown Analyst

analyst
#20

Great. There were a couple of questions around Chart processing facility and what caused the final price really to raise from $78 to $85. At what point did you know they needed 2 full years of construction? And are there any discussions with Baker Hughes/Chart about them financing any proportion of those that...

Thomas Abraham-James

executive
#21

Yes, with that one. So when we signed the firm final proposal, that one came through. And prior to that, it was dependent on some unknowns. So that was why we saw a price change. And so those unknowns were purely that, okay, at the time, material costs, what specific requirements are required for our purposes, things like that is what ended up resulting in the final number. As to whether Baker Hughes would participate in financing, I mean it's their call, but it's not something that we're relying upon. I mean this is -- we are seeing it is strictly a vendor purchaser arrangement. So as I said earlier, there's many other options for financing.

Unknown Analyst

analyst
#22

That's great. I think Cliff is busy multitasking addressing as every question I ask you, there's another 2 or 3 that are coming in. So I need to speed up here. But Tom, just another one for you maybe. With 7 wells now demonstrating the presence of the reservoir system across Topaz, when do you expect to publish an updated independent resource estimate? Would it incorporate data from all 7 wells? And should investors expect it to materially expand upon the existing estimate largely based on Jetstream #1?

Thomas Abraham-James

executive
#23

Yes. Well, look, to clarify, the existing resource that we have strictly utilizes data from Jetstream #1. So since then, we've drilled an additional 6 wells. But the recent campaigns for holes 3 through to 7, they are purely exploratory wells. So those are not ones that would be used for production. So they were not set up for that. They were not designed for it. They were designed to be effectively a cheaper form of drilling that would derisk future targets where we'd be looking to get to production-ready wells. And that's the next phase that we're looking to embark upon. And so logically, the resource update would come after that next campaign of drilling. So the one that we've mentioned that we budgeted for, which is up to 6 additional wells.

Unknown Analyst

analyst
#24

Great. Some investors noted that Canaccord recently initiated coverage that assumes more than 1 Bcf of recoverable helium at Topaz. I guess without commenting on their valuation or price targets, does management believe the geological and drilling data collected to date reasonably support evaluating Topaz at that scale, pending obviously an updated independent resource estimate?

Thomas Abraham-James

executive
#25

We're not here to find some tiny pocket of helium. We're here to find something that would make a material difference to U.S. supply. So I have to say that our company's strategy is that to have something that will be meaningful and go some ways is our target to reduce this supply crunch, which is not just related to this current round of conflict. But prior to that, even when things were calmer on the global stage, you still had these significant supply shortages, and it's being treated as a byproduct as well. And no commodity likes to be the byproduct. Just imagine if you're an end user of helium and you're at the whim of another commodity, so you get these quite unfavorable contracts with 0 flexibility built into them. And so really, we are looking to change that. And so you will not change it by finding some small resource. You would change it by having something that's significant. And with the work that we've conducted to date, the drilling success, the high-grade nature of it, a second commodity as well, which is the CO2 and then potentially a third commodity, which is the helium-3, that creates a lot of options for us. So look, for an analyst to say that they've used 1 Bcf, that's their prerogative. But for us, I can safely say that we are looking to get something which is certainly larger. If we look at our existing resource as well, best estimate prospective resource, you're looking at a mean of 1.3 Bcf and a high case of 2.8 Bcf. And once again, this is predicated on that one well. So long way of answering a question, but yes, we're only at the start here.

Unknown Analyst

analyst
#26

That's great. Well, look, Cliff, let me save your fingers for a second. Management have described the pressure results and reservoir continuity is encouraging. What additional information can you provide regarding reservoir pressure, connectivity between the wells? And what the 7 wells have revealed about the potential size and continuity of the Topaz reservoir?

Cliff Cain

executive
#27

Here's what I'll say about that, and Tom can probably add a little bit to this. We've drilled 7 wells, right? All have hit helium. We have 2 production-ready wells ready to go once we get to this permitting here, which we should be done with by the end of the year. Everything is pointing to a very large system, right? It's kind of like that show Landman where you hit 6 out of 6 on the oil wells, he's doing pretty good. And when you look at success rates in any type of drilling, whether it's for natural gas or even helium, a 15% hit rate is considered good. So I think the geology is there. We got a lot of smart folks on this looking at it. We definitely have activity north of the border. I'm pretty excited about what we actually have here in Minnesota and potentially as this thing moves around into Michigan. So I think it looks pretty good.

Thomas Abraham-James

executive
#28

And to add on that, so what we've seen from the wells that we've drilled is certainly where we've been seeing that we're getting increased bottom hole pressure. We know that we hit the gas because of the pressure and then also seeing the gas coming up to surface even through the mud system that we have. So counterbalance of the gas at the weight of the fluid on top of it. And so should you hit something a higher pressure there, then you start to see bubbles coming up through that mud system. And so we don't have to change the weight of the mud on top in order to keep the gas from coming up to surface. So we have that. We also know what intervals that we're hitting the gas as well, what depth, and we're able to correlate those as well between wells. On top of that, we're operating in a brand-new system. So it's worth reiterating that this is not something that's been drilled 1,000 times before, like many U.S. gas plays have. This is every well that we drill is making a meaningful contribution to our understanding of it. So when it comes to the next iteration of the resource, we're going to be in a much better position on reservoir quality. So the reason that we did coring for this instead of -- we didn't use a tricone bit where you get drill fines, we were doing coring where you get sticks of rock. And that's so we could visually see the reservoir itself. We can look at macro and micro fractures and all these things so that we can put real numbers into the resource update and that we're able to then map out across. We've got distances of what roughly -- well, just short of 2.5 miles between wells. And we're now able to see, okay, is it continuous? Is it not? What depth do we anticipate? We've also mentioned that we don't need to drill most likely in excess of 3,500 feet, whilst gas most likely goes beyond that because we're seeing stacked reservoirs that going down to that 3,500 feet. Probably going beyond that is probably not necessary at this moment in time. There seems to be sufficient systems above that depth. So our understanding has increased remarkably. And so when it comes to this next round of drilling, whilst you never say that it comes with 0 risk, we can say that we are able to go in with a much better image of the subsurface, which is saying something when prior to that, we still had 100% success rate of hitting gas. So yes, our feeling of the subsurface is we've got a very high degree of data and a very technically led team.

Unknown Executive

executive
#29

Well, let's move on from there, Tom. You guys previously decided not to conduct additional flow testing and instead you move towards development. What technical evidence gave management sufficient confidence to make that decision? And what should investors infer from it regarding expected commercial deliverability?

Thomas Abraham-James

executive
#30

Okay. So with this -- so as Cliff just mentioned, we hit the gas in each well. So you can see it, you can feel it, it's there. So there's that. So that gave a significant level of confidence in itself. And then when it comes to then the next phase of potential flow testing, I mean, really, the money is better spent. We've derisked it. We know that the gas is there. We could have done flow testing potentially on all those wells. But at the same time, okay, would it be better use of our time to put that money towards drilling the production-ready wells. So the larger bore, the ones which could actually be utilized for production and do all the testing on those and then use those towards the resource. So that was the mindset there. But I just have to reiterate that we drilled, we hit the target depths in each well and each well hit gas.

Unknown Executive

executive
#31

Cliff, over to you, sir. Are discussions currently underway with potential helium or CO2 customers regarding binding offtake agreements? And could an offtake agreement form part of the financing package for the rare gas hub? Cliff, we just lost you for one second. There we go. You're back with us. there, can you hear us?

Cliff Cain

executive
#32

Yes. I turned my camera off. I'm having a little Internet issue here, so my apologies.

Unknown Executive

executive
#33

No problem at all. Do you want me just to repeat that, are discussions currently underway with potential helium or CO2 customers regarding binding offtake agreements? And could an offtake agreement form part of the financing package for the rare gas hub?

Cliff Cain

executive
#34

Yes to all those, right? Obviously, helium is highly sought after. This plant that we will be building will be a QA/QC semiconductor plant. There's only 2 known in the whole world. So having that semiconductor-grade helium is critical for the semiconductor industry. So those offtake discussions are happening, not just with Minnesota end users, which is a big focus, but also some global end users as well. And that goes for the CO2. CO2 also suffers from shortages, and we're in discussions with that as well.

Unknown Executive

executive
#35

That's great. I might just stick with you for the time being, Cliff, if that's all right. Now that Two Harbors has been selected for the rare gas hub, what are the major remaining milestones between today and construction, commissioning and first commercial helium production? And if I may, is there a realistic pathway to production earlier than 2029, if financing and permitting progress favorably?

Cliff Cain

executive
#36

I think we're on a good pace here to get to production by that time. When we look at milestones, one, we've selected the site, which was important. We look at this in a very broad category here where when we talk about Michigan, I see that as feedstock for the future of the rare gas hub there in Two Harbors and the port that's there. I'm looking at the feedstocks from Canada, from the Western United States to come in for that as well. Yes, I mean, 2029, probably doable for sure. And I would say the biggest thing that kind of face us right now from a rule-making perspective, I would say, is our biggest risk. But I think we've done a very good job with a very strong bipartisan effort in the state of Minnesota. We're down to MDH right now, which is the Minnesota Department of Health to do their part in the rule-making process before the session starts. And they've hired a consultant that they were funded to do. And we've been working hand-in-hand with everybody in the GTAC committee to get this thing going forward. So from the Minnesota perspective, they are very excited up here to get this thing done. We haven't had any really roadblocks as far as anybody opposing this project. Now I do feel bad for the hard mineral folks up here for the copper, nickel, they definitely have a much more difficult path than we do, but I think we're in a good spot here.

Unknown Executive

executive
#37

I guess, Cliff, given the national attention on helium supply security and I guess your discussions with policymakers, has Pulsar had substantive discussions with the Department of Defense or any other federal agencies regarding Topaz. Could federal loan guarantees, grants, strategic offtake or other government support accelerate your development?

Cliff Cain

executive
#38

Yes, they could. And yes, I'll answer the first question here. We have been briefing the Department of Energy and the Department of Defense, Department of Interior, USGS throughout this process. One, obviously, there's a big interest in the site. One, as you know, like I talked about earlier in the webinar here, there's conflicts in Iran and Ukraine, right, where helium assets have been targeted. So from the U.S. Department of Defense's perspective, they want to make sure that they have reliability of supply, right? They want to derisk the supply chain. And like to Tom's point earlier, there are other gas fields out here in the United States where they've been picked over many, many, many times over. This is a new system. This is a new opportunity. But kind of the cherry on the top of that is the helium-3 as well. And so with this new race to quantum supremacy and the current conflicts that are ongoing, and it's just been -- it's been a very pleasant journey with the folks on the Hill.

Unknown Executive

executive
#39

Thank you very much indeed. There are probably 2 more questions. I'm going to stick with you, Cliff, if that's okay. Following Minnesota's work on the environmental review and gas resource regulatory framework, what specific state approvals remain on Topaz's critical path? And does management see any remaining regulatory issues or obstacles that could materially delay the current development schedule?

Cliff Cain

executive
#40

No, I don't see any potential delays here in the future. I think we've done a very good job, again, like I said earlier, working with all stakeholders, bipartisan effort there in the cities and up here and also with the tribal communities, right? We are in the 1854 Ceded Territory. We want to honor their right to hunt, fish and gather and then allowing them to participate in this project potentially so.

Unknown Executive

executive
#41

Great. And I think just to wrap up for you just for the time being. On 60 Minutes, Mr. Cain said it would take years to get into production. What specifically would need to happen to get into production as soon as possible?

Cliff Cain

executive
#42

Well, technically, I got it right. If you think about it, this project started back in 2019. And if you look at helium projects around the globe, it's not easy. It's complex. Even the biggest players have difficulties getting these projects done on time. I think my experience in the industry and doing this for a very long time, I think we're well on our way to getting this done under 2 years, this final push for a touchdown, I would say. And yes, so I think that's it.

Unknown Executive

executive
#43

Thank you. Tom, over to you, sir. Are you considering helium extraction and sales of extracted gas prior to any of the Two Harbors facilities being built? And will you allow Pentagon participation in the Topaz project with terms shareholders can vote on?

Thomas Abraham-James

executive
#44

We don't want to rush what we're doing unnecessary. We know there's a shortage. We know that the price is lucrative. But at the same time, we've seen other companies trip over when it comes to getting the actual gas out in a salable form. So we don't want to replicate that. So we want to do it methodically. We want to do it correctly. What could accelerate things is end user support, let's say. So we've talked a lot about U.S. government agencies. But what we haven't talked about is private industry. And so they too are feeling the pinch. And so that's semiconductors, MRIs, fiber optic cables, these other things. So we -- I think that whilst carrying it through and conducting it methodically and getting it done correctly, -- the single thing that could make it all go quicker would be securing the finance. Now we've only literally just a matter of a couple of weeks ago, mentioned that we have the Two Harbors site. And prior to that, we only just mentioned the final contract with Baker Hughes. So it's all very fresh. And we've been -- I've just returned from the United States. I was there for the past 2 weeks, certainly talking to all the relevant people there as my colleagues has been. And so we've got -- according to the contract to make that additional -- the next phase payment, which was $8.5 million to get to Phase 2 is that we've got -- we've got 9 months to be able to do that. Now I think that time frame is very doable, but it simply comes down to, okay, if we secure the finance sooner than that 9 months, if we can get that to a smaller number, that means that the plant can get online sooner. So that's probably the most straightforward way of doing it without unnecessary haste. But otherwise, if there is support from others out there who have a vested interest in getting this product out of the ground, then I guess anything is possible. But for us, yes, I have to emphasize that we would not be doing anything unnecessarily hasty which increases the risk of things going wrong.

Unknown Executive

executive
#45

Got it. Super clear. Since the processing facility will now be in Two Harbors, could you please explain how the raw gas from the 7 drill sites will travel to the Two Harbors processing facility? What would be needed to accomplish this? And what would it cost?

Thomas Abraham-James

executive
#46

Yes, sure. But that's all part of the EPC component. So we've mentioned earlier that the plant itself, they could use $85.5 million. And then in addition to that is the EPC cost, effectively the connectivity of it and the installation. So there are a number of different options there. But what we like about Two Harbors is that the logistical center that's there. So with liquid CO2 to put that on the rail cars, that's important to have the CO2 out on rail to then have access to the Great Lakes and which are effectively also connected to the ocean. And then the power and all the infrastructure that comes with it -- now how do we get it from various different locations to the rare gas hub. There are many different options there, and those ones will be -- they're all in the process of being assessed, and we'll inform the market when a decision is being made. But it's, of course, possible. We wouldn't put the production facility in a location where you couldn't get the gas to it.

Unknown Executive

executive
#47

Great. A couple of questions around maybe some upcoming publications. When will the company, a, produce the independent resource estimate, when will it be published? And when will the economic study be published? Please also identify any outstanding requirements that could prevent publication on this timetable?

Thomas Abraham-James

executive
#48

So the resource update, as mentioned earlier, will be after the next phase of drilling. That will be a logical time to do it. So with that one. And then the economics is -- it really would be then -- we've just finalized the plant itself. We'll soon be getting some of the parameters in the next few months around the consumable costs and so on. So absolute numbers for that and then feeding in the resource as well and potential feed in production. So I think that we would be looking at in terms of order, it will be resource first after the drilling and then an economic study thereafter. I'm sorry, what was the third component of the question?

Unknown Executive

executive
#49

The third component would be please identify any outstanding requirements that could prevent publication on that time frame.

Thomas Abraham-James

executive
#50

Drilling.

Unknown Executive

executive
#51

Got it.

Thomas Abraham-James

executive
#52

So we just have to wait for that to...

Unknown Executive

executive
#53

Excellent. Cliff, I'm coming over to you, sir. I'm just going to unmute you. There we go. What's management's current estimated total capital requirement in U.S. dollars to bring the rare gas hub into commercial operation, including the $85.5 million Chart equipment package, construction, infrastructure commissioning contingency and working capital?

Cliff Cain

executive
#54

I think apologize. total cost probably around $120 million, but we are working closely with DEED here in Minnesota, also the IRRR Taconite Assistance and also the federal government on this. So they have a clear understanding of what this essentially is going to cost at the end of the day. But it's well under the $300 million that some people have pointed a figure at, but I think we're in a good position here.

Unknown Executive

executive
#55

Okay. And let's stick with the rare gas hub. The proposed rare gas hub has a nameplate capacity of approximately 7.5 million liters of liquid helium annually. How many production wells does management estimate will be needed to supply the plant at 80% utilization?

Thomas Abraham-James

executive
#56

That will be disclosed after we drill the next round of wells, and we have the resource update. So until then, yes, we can make inference from the Jetstream #1 well, but nothing conclusive until that next phase is completed.

Unknown Executive

executive
#57

Great. And does management still expect to make the next $8.5 million milestone payment by January 31, '27?

Thomas Abraham-James

executive
#58

Of course.

Unknown Executive

executive
#59

Okay. It says Ask Me Anything on the title, so here I am.

Thomas Abraham-James

executive
#60

But it is worth mentioning, too, look, you've done a great job, Mark. But it is worth mentioning that, that milestone payment at the end of January, it was also mentioned in the news release that there is the option to extend that by an additional 180 days as well. And so we've got plenty of time to make that payment.

Unknown Executive

executive
#61

I'm probably going to stick with you with this one, Tom. Given the success Pulsar has had identifying the presence of helium-3 and the unique geology at Topaz, did the company ever analyze its gas composition for other rare and potentially other valuable noble gases such as neon, krypton and xenon?

Thomas Abraham-James

executive
#62

We have analyzed for everything, yes. And so that's for economic reasons, but then also so we have a broad understanding of our gas. We've even gone down to the isotope level, hence, the helium-3. At this moment in time, the economics appear to be reliant on the helium and the CO2. There trace quantities of the gases that you mentioned, but I don't think that they would make a meaningful contribution, which is why we haven't talked about them. But nevertheless, if the demand is sincerely there, the plant that we're looking to get is geared up for it. So the opportunity exists.

Unknown Executive

executive
#63

That's great. And there's a question here, Tom. We discussed Christmas before we went live about your plans, which may give me a nightmare tonight, but we'll turn on that another day. But the question reads, as we approach Christmas, besides you and your team enjoying some well-deserved R&R, what are Pulsar staff is excited about looking ahead into '27 and beyond?

Thomas Abraham-James

executive
#64

Well, it's very kind to saying that this is an R&R, I must admit it has been quite busy. But look, helium never sleeps. So for us, what I'm looking forward to and my colleagues as well is that we've really been talking about getting to this stage where we can then start to discuss, okay, what does production look like, get to the next phase of Pulsar and realize the strategy. So for me, it's all about with the -- getting the financing sorted, showing to the world that there's that support for what we're doing here, the regional gas hub for the updated resource numbers post drilling at Topaz and being able to talk about economic numbers. I think that's what excites all of us. And then to be able to say that it's not a one-trick pony that our work in Michigan and indeed in Greenland also shows great promise as well. So going another step towards being fulfilling our strategy of becoming a major player for gas that's in demand and is not associated with the production of hydrocarbons. So I just can't emphasize enough that primary helium could really offer something that the world is sorely lacking at the moment.

Unknown Executive

executive
#65

Great. Cliff again, typing to these questions that are coming in. A question here from [ Ashwin ]. Thank you, [ Ashwin ]. When will we hear about the helium reservoir capacities in Michigan and in Greenland?

Cliff Cain

executive
#66

Tom, do you want to take that one?

Thomas Abraham-James

executive
#67

Yes, I'll take that one. So look, we need to drill those ones first. So what we've done is that we've -- in Greenland, if we focus on Tunu -- so there, the helium has been recorded, has been measured. We have mapped the subsurface as best we can using geophysics and then the next stage is drilling. So we would not get any numbers until that drill program is complete and we're looking to see how that can be conducted in the future. For Michigan, with that one, we've got a very large regional play of about 0.5 million acres. The work that's going to be conducted this quarter is a geophysical survey. I think it's called an aeromag, but it's called a Falcon survey and our Falcon project. And that one gives a very good sort of regional overview of the areas of interest to zero in on for further work. So neither of those will get us to the resource phase, but they will certainly get us to the point that will help us with targeting drilling. And we know that with Michigan as well that they've got a well-established framework for drilling and for gas operations. So it could be relatively rapid in Michigan should the geology substantiate that.

Unknown Executive

executive
#68

Great. And just a quick shout out to all those that are submitting questions, [ Josh ], [ Sue ], [ Michael ], [ Steve ], [ Harry ], [ Tim ], [ Troy ], they keep coming. I don't think you're going to have a Christmas holiday if I carry on with these questions there, Tom. But a question here that relates to drilling, I guess, when will the next stage of drilling on Topaz commence? Can you give us maybe some color on that?

Thomas Abraham-James

executive
#69

Yes. We're looking at -- we're targeting Q1 of next year.

Unknown Executive

executive
#70

Okay. Great. And look, as I say, lots of questions. I think we've covered a lot of the themes. I'm mindful that we set out for 45 minutes a tad over, but maybe an interesting question from [ Sukman ] to end with. Have you tweeted Elon Musk regarding helium supply for any of their projects?

Thomas Abraham-James

executive
#71

Cliff, do you want that one?

Cliff Cain

executive
#72

Yes. I mean I don't think we've tweeted him outright. But I will say for SpaceX and even Tesla, they need helium, right, one for launches and the other for producing the vehicles that they got for the leak detection in their batteries. I would say that he is very aware of the importance of helium in his supply chain. But physically tweeting about, I personally haven't. I don't know if anybody on the team has, we haven't. But when you look at any space launch company's launch schedules, right, you can kind of work back the formula on how much they're going to need. So I think this year, they're on pace to do 165. That's up from like 130 last year. My numbers may be -- but -- and then you've got competing agencies, right, European Space Agency, the Indian Space Research Organisation. I mean they're all really trying to get their launch schedules up. So it was a long-winded answer to that.

Unknown Executive

executive
#73

Well, look, there is an open text feedback for investors post this call. So if anyone does have Elon's mobile number, please drop it in there, and we'll be sure to follow up with that question. Well, look, Tom, Cliff, thank you ever so much for giving your time. Ask Me Anything literally. We tried our best to do so. If we haven't asked your question directly, apologies, but we will have a little review post today to see if there's anything that was missed. Tom, before I send everybody up to give you their feedback and hopefully collect Elon's number, perhaps I could just ask you for a couple of closing comments. And then as I say, I'll send investors to give you their feedback.

Thomas Abraham-James

executive
#74

Certainly. Well, look, it's been an incredible year. An awful lot has happened. It's all been quite rapid towards the end of the year. But I'm really pleased and grateful and a big shout out to the entire team and all of our support base because what we're trying to achieve is something that is quite unique and quite different. And we're now getting the support and the interest out there and certainly the demand for what it is that this company exists for. And I on personal note and just extremely excited about this opportunity that we've got and that we started to firmly execute. And with the likes of the bipartisan approach at a state and federal level in the United States, the City of Two Harbors basically extending and asking for us to have the rare gas hub in their city. All these things just give me so much pleasure and sincere belief in what it is that we're trying to achieve here. So we're dedicated to getting this moving forward and realizing the entire portfolio's potential. So it is incredibly exciting and in a time when there is a genuine shortage of this commodity. So thank you, everyone, for listening.

Unknown Executive

executive
#75

Well, that's great. Tom, Cliff and Mark behind the scenes -- thank you very much indeed for your time this afternoon. If I could please ask investors not to close this session as we'll now automatically redirect you in order that you can provide your feedback and Elon's number in order the company can better understand your views and expectations. It will only take a couple of moments, I'm sure, to complete, but the company be very grateful for your participation. On behalf of the management team of Pulsar Helium, thank you for your time. Good afternoon to you all.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Pulsar Helium Inc. transcript — plus 257,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Pulsar Helium Inc. earnings transcripts and 257,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Pulsar Helium Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.