PureCycle Technologies, Inc. (PCT) Earnings Call Transcript & Summary

November 11, 2022

NASDAQ US Materials Chemicals earnings

Earnings Call Speaker Segments

Charlie Place

executive
#1

Thanks, Kevin, and hello everyone — you're joining PureCycle Technologies' Q3 2022 corporate update call, and I'm speaking to you from Orlando, Florida. As some of you might know, a hurricane came through the area earlier today, and although the worst part is behind us, should the power go out during this call, we'll dial back in, and we appreciate you bearing with us. My name is Charlie Place, and I serve as Director of Investor Relations at PureCycle; with me today are Dustin Olson, who is our Chief Executive Officer, and Larry Somma, our Chief Financial Officer. On this call, we'll be walking through what's new with the company for the third quarter. The presentation that we'll be using during this call is available on the Investor Relations section of our site, purecycle.com. A great deal of what gets said today is forward-looking in nature, resting on management's beliefs and assumptions along with information management has on hand right now. Known and unknown risks and uncertainties apply to these statements, and many of them could be outside our control, such as those laid out in our Safe Harbor provisions covering forward-looking statements, which you can locate at the conclusion of our third quarter 2022 corporate update press release, plus in the quarterly report on Form 10-Q we filed yesterday, and in our other reports on file with the SEC, which give more specifics on risks tied to our business. Also, keep in mind that what the company actually achieves could differ materially from what's expected, and unless the law demands it, we take on no duty to revise any forward-looking statement. Preliminary non-GAAP estimates may also come up in our comments, and those carry risks and uncertainties, including, among other things, changes tied to quarter-end and year-end adjustments. There could be material differences between PCT's actual results and the preliminary financial data presented here. You're welcome to follow along with our slide deck, or if you're on the phone, you can pull it up whenever you like at purecycle.com; we're eager to share what happened over the last quarter with all of you. Now I'll hand things over to Dustin Olson, PureCycle's Chief Executive Officer. Dustin?

Dustin Olson

executive
#2

Thanks, Charlie. Morning, everyone, and thanks for being on the call with us today. I'm happy to walk you through how far PureCycle has come since we last gave a corporate update in August; but first, I'd like to spend a moment reminding everyone where we came from and what we're trying to do. Back in 2012, Procter & Gamble made a bet on a different future. They surveyed the sustainability landscape and realized that the technologies already out there simply wouldn't get them to their ambitions around the world. So they came up with something entirely new; PureCycle came into being in late 2015, and we set out to bring this inventive concept to scale. We produced our initial pellets at the feedstock evaluation unit during 2019, and at this point we are on the verge of pellet production at commercial scale; so what drives us to do this? We can't lose sight of it. Globally, roughly 850 billion pounds of plastic and 170 billion pounds of polypropylene get made from fossil fuels annually. Within the U.S., about 16 billion of polypropylene gets produced each year, and annually, under 5% of polypropylene gets recycled. Each year, people put in tremendous effort toward their brand goals, and each year the world comes up short, and yet another 150 billion pound polypropylene opportunity disappears. It's simple to lose track of PureCycle's core mission, or the reason we're pursuing this new future, but we must keep in mind who PureCycle is and what makes our company so extraordinary. Circularity is what the world wants. What the world wants is a new and real plastic solution, and PureCycle is positioned to change the paradigm, and deliver a technical solution that the world so desperately needs. Following a decade of R&D and seven years of scaling efforts, we're almost there. Ironton will be the site of PureCycle's first commercial plant. In Augusta we will scale domestically, and in South Korea we will begin scaling globally. The right team, the right infrastructure and the right systems are in place to scale our solution. Kindly turn to Slide 4. Mechanical completion of pellet production at our flagship facility in Ironton, Ohio is now expected in the first quarter of 2023, keeping that project essentially on schedule. This modest construction delay isn't something only we're facing, and we don't expect it to affect the nine-month ramp up timeline for Augusta operations that we discussed previously. Work continues on Phase 1 of our Augusta project, though lead times for delivery of certain critical equipment have grown longer. And although closing our debt financing is taking more time, in light of current market conditions, we've generated substantial options designed to minimize our overall cost of capital. Consequently, we now expect purification lines one and two in Augusta to reach mechanical completion and start ramping up operations in the second half of 2024. In October, we signed a joint venture agreement with SK Geocentric for the construction of the purification facility in Ulsan, South Korea, representing our first non-U.S. facility and a key milestone in our global expansion strategy. What we've signed goes well beyond securing capacity. It shows confidence in the technology at our core, opens a door into Asia, and brings a strong technical team along with it. At this point, Ironton Feed PreP is wrapping up commissioning and has started taking in feedstock. Our people were genuinely thrilled to see that first feedstock bail make its way through the system and land in the silos at Ironton. For all of us, that marks a significant step up in scale. There's plenty left to accomplish, but it gave the team real motivation. As we've said before, one of the original pre-SPAC counterparties — under contract for supplying feedstock as well as taking offtake — pursued termination obligations, and we don't accept the rationale they gave. Right now we're working hard to respond to what they've done. Replacement contracts are in the last stage of negotiation, and we'll shift pricing structures so they capture market dynamics more accurately and bring more predictability to PureCycle's economics. Over in Augusta, engineering of our final PreP operations keeps moving forward, and for the three East Coast PreP facilities we're revising operational timelines so they line up with the updated schedule for purification startup. The way this operational design is shaping up has us quite enthusiastic; once complete, it establishes a foundational network along the Eastern seaboard for collecting and sorting plastic waste. We're also still trying to settle the matters tied to the Central Florida site. Though certain moves by local government have been a disappointment, we see the net effect on our PreP strategy as limited. That volume won't be required until 2023, and we're exploring many solutions that don't carry material weight for the company overall or for project economics. Our feedstock acquisition strategy keeps being executed successfully. Feedstock LOIs on hand for Ironton plus Augusta lines 1 and 2 are enough to operate at nameplate capacity — together amounting to over 408 million pounds each year. Members of our team remain in active talks with feedstock sources, building a supply pipeline that will serve the extra purification lines at Augusta. It makes me very proud to share that, since our previous corporate update, our commercial sales group has signed contracts covering 106 million pounds of offtake, and offtake for Ironton and Augusta lines 1 through 2 is now entirely sold out. On top of that, we unveiled a new 100% recycled polypropylene concentrate created alongside Milliken & Company. Work continues on feedstock in Europe, along with offtake and site selection, and we're hopeful more details can be shared on our next call. Even with market conditions that have been extremely difficult since the last time we updated you, our finance team still aims to close financing for the Augusta project before the year is out. We've set aside $168 million for Augusta to carry the project through execution, with operations expected to start up in mid-2024. The quarter closed with $416 million across total cash and investments. Let's turn to Slide 5. Most of what we're doing centers on finishing Ironton and Augusta, yet we keep chasing chances to expand our technology around the world. Like we said earlier, today's market situation has delayed the schedule at Ironton by two weeks or so, and for projects we take on down the road, somewhere between three and six months; our commitment stands to arrange financing for the Phase 2 build in Augusta — that's lines three and four — plus our plant in South Korea and the one in Europe, and all of these are presently slated to begin operations and reach full ramp in mid-2025. That said, we'll take whatever time is needed to make sure the design delivers process and cost efficiencies. Slide six is one we enjoy. Each trip to Ironton shows us something different, it has transformed; day by day it resembles an actual facility more and more. And if you've ever brought a major capital project to completion, you know the feeling that comes as startup draws near; and you can tell how much ground we've covered since 2021. With the last components of our modular build now going into position, it's obvious our construction crews are fully focused on getting this project done. As you can see, we're nearing the closing stages of construction at Ironton. Mechanical completion, along with first pellet production, is anticipated during the first quarter of 2023.

Dustin Olson

executive
#3

On slide 7, you can see the specifics of where we stand with the last construction work. Even though a few equipment pieces arrived late, we've received all 26 modules and set them into position. Feedstock PreP is now in commissioning and has started processing feedstock. The central utilities have reached functional mechanical completion and are close to final commissioning, while the control room, offtake, and rail operations should hit mechanical completion by the end of November, and purification plus co products should reach that milestone in Q1 of 2023. When mechanical completion actually happens will hinge on the final extruder delivery schedule. Everyone on our team takes real pride in what we've accomplished, considering the construction market challenges we faced in 2022 — the war in Ukraine, COVID-19 in Germany, supply chain problems, and more recently low water levels in the Mississippi River, which affected some module deliveries. Judging by all external markets, though, it looks like our project schedule is beating other industry projects. PureCycle and its contracting partners are pushing relentlessly toward mechanical completion as fast as possible; we're still on track to hit full operating capacity within the nine month ramp up timeline we've talked about before. Slide 8 is explanatory. Each month, we publish a construction monitoring report put together by an independent engineer retained by Ironton bondholders to monitor construction progress at Ironton; they report independently on every critical aspect of the project, covering cost and schedule, and ultimately publish a date for the final project performance test. The September report indicated a delay to March 3, 2023. That delay stemmed from the headwinds I just listed — Ukraine, COVID, supply chain, and Mississippi water levels. Still, we want to be completely clear about when our project will start generating first pellets. Over the past several quarters, I've spoken about pellets by the end of 2022. Although that statement has moved two to four weeks, into early January, the underlying premise hasn't changed. What separates first pellets in January from the final performance test in March is the operational commissioning phase for the plant. Following mechanical completion, but prior to the March 3 performance test, we'll be testing multiple feed sources under various conditions to validate unit operations. After that's done, we'll run our five-day 100% capacity test. During that period, we'll be producing pellets and selling them to our offtake partners. Our initial commissioning plan runs ahead of our nine-month ramp, so we remain confident that PureCycle will be operating at full capacity by the fourth quarter of 2023. Turning to Slide 9. In the third quarter, we kept up Phase 1 engineering and construction activities at our first multiline facility in Augusta; however, because capital markets are tightening and delivery equipment lead times are growing, we now expect mechanical completion start-up and full commissioning in the second half of 2024, assuming complete financing by year-end. We've likewise revised the schedule for bringing our three East Coast plants online so that it matches the updated construction plan for Augusta Phase 1. Even though Augusta Phase 1 has been pushed back for now, we're still coordinating with the AEDA regarding when we build, and we're still working alongside our partners to chase every chance to shorten equipment lead times, keep building expenses under control, and boost building efficiency, all so this project wraps up in mid-24. Turning to Slide 7, on the subject of the project's core fundamentals, I'm happy to report that Augusta purification lines one and two now have feedstock volumes fully committed at offtake capacity. We hold signed feedstock LOIs totaling 301 million pounds, which is roughly 7.5% more supply than needed, while offtake contracts cover 289 million pounds per year — a rise of 106 pounds since we last updated you, amounting to excess demand of about 11%. Once again, this shows how strong our technology is, both when it comes to converting feedstock and in delivering pellets of superior final quality; moving to Slide 11, as noted previously in the presentation, we signed a definitive joint venture agreement with SK Geocentric covering development of the Purification Facility in Ulsan, South Korea. We anticipate breaking ground during the third quarter of 2023, with startup operations slated to start in the second quarter of 2025; for our global expansion strategy, this JV marks a significant first step. As I said earlier, this project is about far more than capacity alone. It serves as a gateway into Asia, a robust technical partnership, and mutual trust. Our pride in this relationship with SK Geocentric could not be greater. Beyond that, we're still shaping the framework of an agreement with Mitsui and assessing possible locations for our purification facility in Japan. Our European expansion plans keep moving forward. We've whittled down the candidate sites, are putting together an engineering procurement plan, and have grown our operations team; we're aiming to announce which European site we've chosen during our next corporate update call. For our company, Ironton is a significant starting point, yet it's only the beginning. Everyone at PureCycle is motivated and committed to carrying out its global expansion strategy and leveraging market leading technology to tackle the worldwide problem of plastic pollution. With that, I'll hand things over to Larry Somma, our CFO, for the financial update.

Larry Somma

executive
#4

Thank you, Dustin. Before I get into where our liquidity stands and what the third quarter balance sheet looks like, I'd like to give everyone a quick update on the financing process. This should come as a surprise to no one: raising debt capital has been extremely difficult ever since our update three months back. Even with that backdrop, the meaningful interest and encouraging feedback we've gotten through our conversations with investors have left us optimistic. Right now, we're assessing quite a few options, and they give us confidence that we can secure the capital required to fund Phase 1 of our multi-line development in Augusta along with three East Coast PreP facilities, which should carry us through to the point where Ironton revenue and operating profitability are delivered. That said, we're working hard not just to get the funds raised by year-end, but to do so in a manner that preserves financial flexibility and optionality for our post revenue future. So, turning now to Slide 12; we closed the quarter with a bit more than $416 million in total available liquidity. Throughout the quarter, we kept making significant investments in our Ironton, Augusta, and PreP facilities, with most of the money coming from unrestricted assets. Cash and debt securities available for sale fell by 134.8 million compared with June. We moved 95.8 million into an Augusta Construction Escrow account and drew down 27.4 million for pre-engineering and long lead equipment purchases. Augusta Purification and PreP investments made up 14 million of what we invested in the third quarter. Corporate and pre-operational employee expenses came to $7.6 million in the third quarter; we also used 5.4 million of cash in the quarter for routine corporate operations, including insurance, professional fees, and various other expenses. Now let me talk about the cash invested in the Ironton plant, since we're getting close to mechanical completion. We had previously disclosed that we expected the project to run $55 million to $65 million over the initial budget. As of now, we anticipate it will take an additional $8 million to $10 million to finish the project, which results in an expected final budget of $315 million to $317 million; these extra project expenses are being funded from our unrestricted cash, and we spent roughly 5.2 million this quarter. In addition, the bond agreement requires us to keep a certain level of reserves, so we moved 6.8 million out of unrestricted cash into other required reserves. We also made payments of 41.2 million, taken directly from our project fund, for construction progress payments. Now let's turn to Slide 13. As we get closer to commercial scale operations, we wanted to share how we've strengthened our business strategy not just to grow, but to stabilize the profitability of our operations; with feedstock plus offtake contracts now in place, PureCycle operating profitability is stronger and more stable than the Pre-SPAC forecasts, no matter what the economic environment or business cycle looks like. Combined with our PreP strategy, this delivers greater economic and feedstock certainty. Also, at a moment when the feed ecosystem is still being built out, having operations that are vertically integrated is meant to give us security in feedstock volume; another key point is that when feed costs are low, competitors get eliminated and investment in sortation drops away, yet PureCycle stays shielded from that because our purification is expected to earn better profits under those conditions. That ought to mean a steadier operating business plan for PureCycle. Now let's move to our last slide, Slide 14. During this quarter, we kept gaining operational momentum across several important areas. At Ironton, we remain on schedule for mechanical completion and pellet production in Q1 2023; offtake contracts grew strongly, and Augusta offtake is now oversubscribed. Feedstock is starting to be processed at the Ironton PreP facility. For lines 1 and 2 at Augusta, feedstock supply reached 107% of what nameplate capacity requires; we also signed a JVA with SK geo centric. We have financing options, along with a plan to fund the Augusta project by year-end. We introduced the first fully sustainable PP concentrate, created together with Milliken & Company. We closed the third quarter with $416 million in total cash and investments. We're eager to update the market on upcoming milestones as we complete our flagship Ironton facility and move through the Augusta financing process, as soon as we can. As Dustin mentioned, we also think we'll be able to talk about the European site as soon as we're able. Thanks for being with us on today's call, and we'll now take questions.

Noah Kaye

analyst
#5

Morning, and thanks for taking my question. Perhaps we could begin with what you said about the supplier feedstock and the offtaker development — I'm wondering how much more you can share with us. First, can you say what volume of offtake is required to backfill this? Second, should we reasonably expect that the contracting terms are now more attractive, given that you're moving to feedstock plus? And third, a comparable question regarding feedstock: what quantity of feedstock must be supplemented in order to offset this development?

Dustin Olson

executive
#6

Yes. Many thanks, Noah. Great to speak with you once more. Yes, on the question of the quantity — how much feedstock and how much offtake that contract covers — my understanding is 40 million pounds per year of feedstock, with offtake at roughly 15 million pounds per year. As for the terms, if you look back to when these projects were originally assembled, they were truly constructed before a market around recycled feedstock streams had begun to emerge. I mean, number five wasn't even traded particularly well at the time those contracts were drawn up. So since then, in certain respects, the contracts have grown somewhat stale; therefore, on the feedstock side, we'll be referencing a number five bale price, which differs from what the original contract specified. Then on the offtake side, we'll tie it to a feedstock plus mechanism that we've talked about before; so from where we sit, this helps generate a good deal of stability in the overall economics for Ironton and truly brings the Ironton economics up to date with more current market conditions. Over the past year and a half to two years, we've done a really solid job building momentum for both Augusta lines 1 and 2. And so the conversations we've held across a market, both on feedstock and offtake, have helped us deepen our grasp of the overall ecosystem and get opportunities ready to pull in; so for us, it meant pivoting to a different feedstock supplier and a different offtaker, yet we didn't need to look far, since we could examine our existing, let's say, relationship base and draw on that to get those contracts closed.

Noah Kaye

analyst
#7

Okay, that's clear, and I appreciate it. Also, could you tell us — if you're able — what caused the split there? Was it related to commercial uses or technical requirements? In the Q, I noticed you got another piece of good news regarding the FDA LNO. So I'd guess that isn't the cause. What can you tell us to help us make sense of that situation?

Dustin Olson

executive
#8

Yeah. Honestly, it's tough for us to put ourselves in our counterparty's position and figure out where their head was at. We had a lot of discussions about changing the deal so it better reflected what's happening in the market right now, and for some reason, they decided to take a different path. From our standpoint, that's okay. We do have alternatives, and by going this route, we're able to add more stability to the whole project. So, I'd rather not guess at why they went the way they did.

Noah Kaye

analyst
#9

All right, that's useful. Then, regarding the actual process of getting Ironton operational, it sounds like you're essentially waiting on certain extruders, which are the main bottleneck, and those deliveries have slipped somewhat. Is that entirely because of shipping logistics and similar issues? In other words, has the equipment been completed and is merely being moved, or does it still need to be manufactured?

Dustin Olson

executive
#10

Noah, are you present?

Noah Kaye

analyst
#11

Yep, I'm on the line. Is my audio coming through?

Dustin Olson

executive
#12

All right. So, yeah, we can pick you up at this point. Seems like the Hurricane call just came through for us, since our wireless signal cut out, though we did have a secondary handset sitting here. So, allow me to wrap up what I was saying and then likely hand things over to you for a follow-up question. Listen, I'd rather not get into the reasoning behind their decision to take a different path, but we're at peace with it, and we have every confidence that we can fill that gap with no effect on the business.

Noah Kaye

analyst
#13

All right, that's great. Thank you. I'm hoping everybody on your end is doing well. So then, for my second question, it was essentially about bringing Ironton online. From what I gathered, the bottleneck seems to involve certain extruder machinery. So would I be right that any holdups are simply tied to shipping and delivery — meaning the units are already fabricated and are about to be transported, or something along those lines?

Dustin Olson

executive
#14

Yeah, well, yeah, to put it precisely, Noah, we've got equipment currently under construction over in Germany. And when you look at the COVID outbreak figures for Germany, what took place in early October was a spike. And that early-October spike genuinely disrupted the wider supply chain needed to complete that single unit. So that pushed things back. Quite significantly, in fact, though we've collaborated with our partner to compress that timeline, yet it remains the bottleneck; that's essentially the point we're making with the slide showing boxes around the various sections of the facility. The facility resembles a facility, the facility is taking shape. The bulk of the facility is in commissioning, however there's essentially a single unit that's going to be the bottleneck; and once it arrives and we've got it piped up and commissioned, we'll then start up the remainder of the plant. So there's nothing beyond that to observe. That's the whole story.

Noah Kaye

analyst
#15

That's really useful. I'll share it with the rest of the team.

Dustin Olson

executive
#16

All right. Appreciate it, Noah.

Hassan Ahmed

analyst
#17

Morning, everyone. I just had a question — you've given us quite a bit of detail on the ramp-up timeline. To me, 9 months feels like a long stretch, honestly. If you look at how commissioning tends to go at other facilities, and then the ramp that follows. Why — and I fully understand this is the first facility of its kind and things can be somewhat unpredictable. But still, why is your forecast calling for a 9 month ramp?

Dustin Olson

executive
#18

Thanks very much for that, Hassan. Let me walk through how the commissioning process begins. Once we're mechanically complete and, say, we begin starting up the plants, there are multiple feedstocks we plan to test early on. First, we'll actually use a virgin type material to check flow through the plant. After that, we'll begin with — we'll shift to a feedstock number one, followed by a feedstock number two; and our last commissioning tests will use a blended feedstock 1 and 2. That brings us to the March third timeline. As we move through feedstock 1 and feedstock 2, we'll be commissioning at roughly 50% rates, then 100% rates, and then feedstock to 50% rates and 100% rates. That's essentially what those dark blue bars on the graph represent, since there are many different parts of the operation we need to road test to confirm everything works as it should; and like you said, we're certain there will be some hiccups, some trips, and we'll need to work through them to get running again. Honestly, the nine month ramp is an original assumption from the Pre-SPAC Ironton project days that we've kept, okay. The truth is, we know ramping supply up to our customers so they can integrate it into their application base will take time; we also know ramping the feedstock supply up to the plant will take time. That doesn't mean it isn't available. It just means getting the trucks moving, getting them into a routine, and getting the operation reliable will take time. So when we discuss the nine month ramp, we've really pointed to three items. We pointed to the technical startup to work through all those details and confirm it works properly. And then we also pointed to the feedstock supply chain and the offtake supply chain. So your question is insightful, because what we're effectively saying is that in March, keeping the schedule we indicated today, we will run the plant at 100% rate for five days; we have the chance to outperform the nine-month ramp. Alright, regarding that delay of two to four weeks and the mechanical completion at Ironton that stems from the situation in Germany, honestly, we still can do better when it comes to how much material we move, which means better revenue and better EBITDA as well. There's a chance for us to beat the nine-month ramp, yet we are keeping to the nine-month ramp since that is what we stated at the outset, and unless we demonstrate something different, we will remain with that.

Hassan Ahmed

analyst
#19

Got it, that's really useful. And when it comes to feedstock, there's clearly a lot of chatter about the inflation we're dealing with and so on, and it's hitting everything. So while you're out there securing and signing for feedstock for the projects you'll build down the road, what kind of pricing or agreements are you landing these days?

Dustin Olson

executive
#20

Well, what's changed since Ironton, that was 3 or 4 years back, is that a market now exists for the number 5 bale price, right? It trades actively. People can point to it as a reference. That means a large share of the contracts we point to are linked to it. Because of that, and we pair it against the offtake agreements at our feedstock plus, we're basically hedging the feedstock risk in both directions, right; but keep in mind, our technology handles feed in ways that nobody else's can, right. So often, feed that can't be sold into the number 5 bale market goes at a discount to number 5; it goes at a discount to number 5, right. That creates a differential chance for us to purchase under market for a few of the LOIs we hold in the Augusta project.

Hassan Ahmed

analyst
#21

Understood. Thank you so much.

Dustin Olson

executive
#22

Thanks, Hassan.

Eric Stine

analyst
#23

Hi, Dustin. Hi, Larry.

Dustin Olson

executive
#24

Hi Eric.

Eric Stine

analyst
#25

Morning. So perhaps regarding Augusta only, could you discuss — clearly you have faith in the funding picture, the capacity to complete something before the year ends, yet maybe just address the talks you've had with AEDA. Are those constructive at this point? And what — does any flexibility exist around that year-end deadline? I'm asking because if you couldn't reach it, considering the difficulties in bond markets at present, I'm just wondering how that would — how the situation might unfold under those circumstances?

Dustin Olson

executive
#26

Right. Look, I believe our conversations with AEDA have been extremely productive. They've proven to be a genuinely solid ally for us throughout the entire process. Look, their situation mirrors ours — we're both putting in effort to advance the Augusta project, and they're quite eager for us to join the park and proceed. That said, they expect progress on the project. And although we've already invested a considerable sum into this endeavor, the truth is that at the Augusta site, since the majority is modular and most depends on equipment shipments, nothing visible has appeared there as of yet, all right. So we're collaborating with them to clarify the schedule and the alternatives at our disposal for funding the facility. Regarding the consequences, the actual consequence is this: should we fail to secure funding before the year concludes, then AEDA might withdraw the land and give it to another party. But the truth is, they understand how tough the financing environment is for every project in today's market, and there likely isn't a lengthy queue of parties eager to claim that facility. Therefore, although there's a certain danger that land negotiations might become more difficult early next year, I believe practically speaking that will be offset in line with the capital markets we're observing. So that addresses it.

Larry Somma

executive
#27

Right. Hello, Eric. Let me mention something else as well. Dustin and I have had in-person meetings with the AEDA. That's a fairly big organization. On that committee, 2 individuals are either former or presently serving bankers. So they understand the situation. I believe, as Dustin hinted, they're just as worried that we might leave them, since every dollar we've invested — which exceeds 100 million — has gone into modular design, and nothing has been done at the site so far. And so, honestly, we can't say how this will turn out. We brought up the fact that we hold optionality to raise capital. So, that's a really positive thing. But the key point is that we'll keep talking with them, meet them in person, and keep working through the discussions to ensure both sides feel comfortable with where each of us stands.

Eric Stine

analyst
#28

Eric, that makes sense, and it's useful.

Dustin Olson

executive
#29

One more thing worth pointing out: for that land, we really haven't laid out meaningful capital. What's happening here is essentially a leaseback arrangement for us. So we're not in a situation where we paid millions of dollars to acquire that land just to keep it available. Instead, it's a partnership structure in which we'll lease the land back from them for some period, and then further down the road, after several years, we'll purchase it back from them. As a result, there isn't much of a CapEx exposure when it comes to the Augusta land.

Eric Stine

analyst
#30

Understood. All right. Great. So perhaps we can shift focus to Ironton. From what you're saying, there's strong conviction that you can substitute the offtake arrangement there, and you can even argue it would work in your favor, but I just want verification — is this somewhat isolated? I want to verify, does this set off any right for bondholders to demand redemption of the bonds? Anything along those lines? Or is it genuinely, it's sort of a singular event, it's isolated, and you believe you can substitute it?

Dustin Olson

executive
#31

Sure, so, there's a formal response and then there's a practical response. The formal response is it might set off a number of things involving the trustee and the bondholders, but the truth is it doesn't serve their interests for that to occur and we're talking with them. The second formal aspect is that we've talked with the bondholders and repairing this or substituting this agreement is truly a deal-related matter right now, all right. We have 2 agreements, 1 for feedstock and 1 for offtake that will substitute the counterparty that is departing. and that is underway currently with the trustees and with the bondholders for substitution. And we're simply waiting for a few of the administrative and technical specifics to move through the system. Most of this probably would be finished by now, but in fact the bondholders have brought on a new legal firm and they're getting familiar with the entire system. And so, we're stuck somewhat now and in a bit of a timing, sort of pocket where we must wait for them to catch up before we can fix it. But from an isolation standpoint, we're quite pleased with the substitutes that we have lined up for this agreement. We believe it's going to bring a lot of stability to the business.

Larry Somma

executive
#32

Eric, there are a few more points I'd like to make. Like Dustin said, once this happened we held a call with the bondholders, since we wanted to tackle it head-on. What we heard back from them, taken together, was essentially: when will we be able to come see the site? It's been quite a while since you folks extended an invitation. So here's the thing — no event of default exists, and if a cure period applies, we're addressing it, as Dustin noted; we hold contracts, and the bondholders have been invited. A site tour is set for late November, open to any bondholder who wishes to attend, including the one who showed a strong level of interest. So it truly is an event, yet one we feel quite at ease about, and one we are sure — or at least highly confident — will be resolved within the coming weeks, since, as Dustin said, we hold replacement contracts. And keep in mind, during construction of the Ironton project and likewise while we build the Augusta project, we are oversubscribed on feed and offtake for each of them. So this is not a zero sum game. We have some float across the overall feedstock and offtake agreements for the two facilities. Therefore, the risk of losing a single counterparty, frankly, doesn't worry us. Right; and there's one further point I failed to mention earlier. If you imagine yourself in the bondholders' position, as I said, they wish to see the site. The position they hold is very, very highly collateralized. Even under the worst case scenario, there's no way these people would genuinely want to seize the asset, because nobody operates it better than we do, and we possess the cure for the problem to replace the situation we're in.

Eric Stine

analyst
#33

Understood; and the cure, which could come fairly soon.

Dustin Olson

executive
#34

Yes, it is extremely close. We're wrapping up talks on those 2 agreements; it's simply a question of getting the deal mechanics finalized.

Eric Stine

analyst
#35

All right, that's helpful context. Thanks.

Gerry Sweeney

analyst
#36

Morning, everyone. Dustin and Larry, I appreciate you taking my question.

Dustin Olson

executive
#37

Appreciate it, Gerry. My question concerns the financing for the project — clearly, that's moving lower. What I'm hearing is that your aim is to hit that target before the year wraps up, but are you still pursuing the same figure as originally planned, or might there be alternatives, like arranging a smaller facility, getting Ironton operational, which would clearly cut the project's risk substantially, and then perhaps seeking a tranche? I'm just wondering whether anything on that front has shifted.

Larry Somma

executive
#38

Yeah, that's a really good question, and this has been a work in progress for a while now. We brought it up 1 quarter back, so it's not a situation where, oh great, we have to begin from scratch. It's more that we have to wrap it up. I mentioned that we've got optionality. If we end up not raising the amount we initially anticipated, could we shift direction? Of course we could. That's precisely why plenty of choices exist for us. Between Dustin and me, we've likely got at minimum 5 to 7 scenarios, and each one of those has its own sub-scenarios too. So yeah, we're mapping out the whole terrain — surveying everything to figure out what all those choices look like. And you're raising an excellent point, correct? Since a portion of this depends on the AEDA and the conversation we're going to have with them, we know as a matter of fact that once we're past Ironton and pellet production is happening, we'll be able to tap into not just a broader pool of capital, but also a less expensive pool of capital. So, we also want to make the smartest calls possible. So, our talks with the AEDA have been productive, and we're going to do whatever works best for total cost of capital so we can preserve financial flexibility and optionality.

Gerry Sweeney

analyst
#39

Might it be possible simply to secure an option on that property through the AEDA, paying a modest sum, so to speak, under a land option arrangement? That would serve just to prolong things. Does that route exist as well?

Dustin Olson

executive
#40

Yeah, I'd say all of that falls within the granular talks we're having with the AEDA. What it comes down to is that we have a handful of meetings scheduled with them across the coming six weeks, and the purpose is to demonstrate what our activities look like, the way we're handling it, so they feel assured that the scenarios and choices we've laid out are in place. So, I suppose, from my view, conversations of this kind are certainly something we're open to considering.

Gerry Sweeney

analyst
#41

Understood. So what you're suggesting is that there are possibilities, and you have a level of confidence that at some point soon you might land somewhere in the middle.

Dustin Olson

executive
#42

That's right. And I want to make one thing clear as well — the AEDA land <<inaudible>> isn't oversubscribed. A large expanse of property exists there. Flying over it, you see essentially a single facility located somewhat north of our position, plus one more that's in the works, awaiting financing, to our south. That said, it's track one among many tracks in Augusta. So our confidence is fairly strong on two fronts: first, that sufficient land is on hand for our needs, and second, that we can reach an arrangement with them to prolong this and continue progressing. Nobody has questioned that the AEDA is thrilled to have us located in their park. So this comes down to a scheduling matter that we need to resolve alongside them in order to reach the other side.

Gerry Sweeney

analyst
#43

Got it, got it. Larry might be the better person for this, but you took us through where the cash stands, the restricted cash — I think it was 215 million moving to unrestricted. A few questions have come my way about what portion of that 215 million is earmarked for, you know, Ironton — I realize we'll say $75 million <<inaudible>> for the build-out, well, not the build-out, but the higher cost. Part of that, I believe, comes in later during the project, maybe even in the next couple of months? And what amount is being held back for different events across, let's say, the coming 12 months, and what extra cash beyond that do you have on hand to run the business, and so forth?

Larry Somma

executive
#44

Yeah, I mean, that's an excellent question. And you're exactly right. When we discuss the overruns at Ironton, those must be covered by unrestricted cash, which comes from that 215. So naturally, that's the first item we've designated against it. We've done a really, really solid job examining our forward commitments to make sure we can operate in the worst case scenario, for as long as possible. So, we have several strategic initiatives underway. They depend on our capacity to raise the capital regarding Augusta; and as a result, we're not committing to things that leave us in a situation where we lack capital. The key priority for us is making sure we have the longest possible runway to run the company, which gives us the most flexibility to make the right decisions—that means keeping our capital structure flexible and as close to optimal as we can manage. It's tough being pre-revenue, and it's tough carrying technology risk without commercial scale, but as I said in my remarks, what Dustin and I find overwhelming is this: yes, we don't currently have as many commitments as we'd like for the financing we were trying to raise, but just look at the market—we're not unique, not even close. No one in our situation is able to raise capital. The thing that really stands out to us is just how many people genuinely love what we're trying to do, okay. And that's not a secret. During this process, we talked with over 100 different investors. And there was one thing all those investors had in common — almost every one of them took it to their investment committee, because they'd done the underwriting, they'd done the business evaluation, and they wanted in on this. Once it reaches investment committee, it's out of their hands, and unfortunately in this environment, those committees are pretty tough, and it only takes one person on that committee to say no. The evidence for that is clear: what came back to us was that each member of the investment committee gave approval for a single individual. So our stance isn't that any misstep is occurring on our side. We see it as a matter of the surrounding circumstances, and our effort is to preserve as many paths as possible, which allows us to build the capital structure best suited to this organization across the long haul.

Gerry Sweeney

analyst
#45

Understood. Thanks for that. I'll get back in the queue. Appreciate it.

Brian Butler

analyst
#46

All right. Am I coming through okay?

Dustin Olson

executive
#47

Yep, we hear you perfectly. Thank you.

Brian Butler

analyst
#48

Great, thanks. I suppose my first question concerns cost—you mentioned where things stand with Ironton. Could you provide some detail on that, as we get closer to finishing up, regarding what you expect the first line, or perhaps the first two lines, at Augusta to run? And then, following on from that, I'd ask what makes you confident that a six-month pushback is the correct call right now, rather than something longer, with the real date being the close of 2024?

Dustin Olson

executive
#49

Yes, good question. If we turn our attention to Augusta, what makes it so compelling is the opportunity it provides to expand into a cluster complex where several lines can be installed. As I believe we've mentioned previously, eight separate lines could fit on the initial 150 acres of that project, which hands us a tremendous degree of operational flexibility when it comes to sorting feedstock and pursuing various activities. That project generates excitement because of the scale it will deliver. With plant number one comes a utility plant whose cost for line one exceeds what it will be for line two. For the first line, roads, sewers, and infrastructure run higher in cost compared to the second line. Therefore, even with line two included, we anticipate a significant drop in this project's cost curve, all right? Beyond that, the Augusta project involves more than just purification. On the PreP side, it also includes an infrastructure build, okay. The truth is that the market holds plenty of feed, and while sorting of that feed keeps increasing among operators, it may still fall short of what our growth requires. So the eastern seaboard PreP facility we've discussed constructing is essentially a site for collecting and sorting material to supply Augusta, and we have room to expand into it as time goes on. Alright, so when you factor in both the infrastructure work and the first PreP facility, the per-pound cost for the project on line one goes up. If we're talking CapEx dollars for each pound of polypropylene, my sense is that once we're past that initial round of operations and move into a runway situation — just constructing an additional line with fresh feed arriving — those lines should still land somewhere around $1.50 to $2 per pound on the CapEx side. After that, adding the infrastructure build alongside PreP and the other line already online will push it somewhat higher, all right. At this point, I can't really speak to what Augusta's infrastructure will cost. A lot depends on how we ultimately arrange the financing and which options we choose there. That said, we're actively looking for opportunities to reduce line one's infrastructure costs, and we're also exploring ways to bring down CapEx for pound going forward.

Brian Butler

analyst
#50

All right, that's excellent. Then regarding only the postponement — those 6 months — what exactly is driving that, and what makes you sure that this length of postponement is appropriate? I assume it's mainly connected to the financing, though is there anything additional causing that shift, or that might cause it to move even later?

Dustin Olson

executive
#51

Well, we're encountering what you might call lead time problems with certain equipment, but keep in mind, most of the long lead — actually, I'd say every one of the initial long lead equipment items, all right. So, the equipment for this facility with the longest lead time has been bought. That's mentioned in the initial upfront capital we discussed regarding the Augusta project. It's been bought, it's already in the pipeline. Therefore, the scheduling danger from that batch of equipment is fairly reduced. The following batch of lead items is what we're dealing with right now and honestly, we're simply holding off on submitting those orders until the financing is completely secured.

Larry Somma

executive
#52

Well, I believe Dustin brought this up during his comments, or at least touched on part of it — but when it comes to a key pillar in putting this plan together, that's tied to the central utilities. There's a company we've engaged to handle construction of those central utilities on our behalf. That means our plant can't go up any quicker than the central utilities come online, and as far as when the central utilities will be ready, that ranges somewhere between 15 and roughly 18, 19 months.

Brian Butler

analyst
#53

All right, good. Then regarding the financing, could you perhaps provide a brief update on, I suppose, how things in the debt market are sitting relative to what you'd initially anticipated for your cost of debt?

Larry Somma

executive
#54

Well, we're able to, yet we're not able to. It's clear it will end up pricier than what we first planned. Take the 10-year treasury — it's been trading at various points, and I believe as of today it's fallen roughly 20 basis points thanks to the inflation report, which is a positive, putting it under 4. When this whole thing kicked off for us, that same 10-year treasury sat near about 2-ish. So what I can say is you're looking at a 200 basis point rise in cost compared with when our conversations began. But something I've brought up is having choices and room to maneuver; thus, even though we recognize the price tag will be higher, given the market conditions themselves and given the investors we've been engaging with. What matters most to us is keeping options open, and ensuring we don't land in a spot where that cost becomes unworkable for an extended stretch. On top of that, we're fortunate since, as you know from how our business operates, we generate strong profits at the operating EBITDA margin line, and that lets you take on additional debt while still generating surplus cash flow past it. That hands us considerable leeway in how we think about this too — something other players in this market simply cannot manage. So our operating approach lets us make calls right now that competitors are unable to.

Brian Butler

analyst
#55

Okay. If I may, just one final item. Regarding the supply matter involving the SG&A, do you fellows have any avenue of recourse—could PureCycle return to them, and, as they end this contract, I suppose, in violation of those agreements?

Dustin Olson

executive
#56

Yeah. Well, I value that question. It's something we're very conscious of, but I'll sidestep it and simply save that for a later time. Legal conversations are better kept within the legal domain. Still, as we've said, well, we take issue with how this is being handled. In our view, nothing improper was done on our side throughout this process, yet we'll leave it to others to work out.

Brian Butler

analyst
#57

All right, excellent. Thanks a lot for accepting the questions.

Larry Somma

executive
#58

Right, Brian, I was about to mention, the key point here involves our doctor along with the bond trustee and that trustee's legal team; and like Dustin hinted at, rather than battling to argue that they made a mistake, we made a mistake. Honestly, what we'll do is simply swap them out, and that's the fastest and finest approach, and it brings our fresh agreements in line with the market, which benefits us greatly.

Brian Butler

analyst
#59

Great. Thank you.

Thomas Boyes

analyst
#60

Appreciate it. Yeah, the majority of what I wanted to ask has already been covered. I suppose there are just a handful of isolated items left. Regarding that critical passing item <<inaudible>>, are there a pair of them? Do both serve as executors? From going through a few of the more recent reports, I'm aware there was a knockout pot <<inaudible>> that you're also awaiting. I simply wanted to confirm whether this is in series, or whether these represent two critical process items running in parallel?

Dustin Olson

executive
#61

Yes. I mean, a knockout pot did raise concerns earlier on in the project, but at this point it isn't the critical path on this project. As you can imagine, there are several simultaneous critical paths, correct? Once you resolve one, another appears—you're perpetually managing whatever's most critical. So right now, the thing on the critical path is the extruder that's arriving from Germany. And listen, we're on it actively. Ultimately, what remains for this plant essentially boils down to piping plus a bit of low-voltage wiring that still needs completing before it can run. Every piece of major equipment has been installed, with the extruder being the exception. So I'd say that's genuinely the final critical delivery we're awaiting; however, once it shows up, there's additional work we'll need to perform afterward. Because of that, we're seeing some lingering effects, though the current timeline already accounts for all of them.

Thomas Boyes

analyst
#62

Great. And given how many pieces are in motion here, could you perhaps address — specifically, what you expect for CapEx next year? My thinking is that those figures might come in a bit lower than before, since the timeline has shifted for some of the pre-cut facilities, which should now line up better with when Augusta comes online, so does that shape your thinking there?

Dustin Olson

executive
#63

Well, look, we see tremendous appetite for expanding our technology, all right. There's a definitive joint venture agreement in place with SK; so conversations regarding financing and CapEx outlays will — those conversations are beginning already, and we'll add structure to that effort early next year and eventually settle on a CapEx plan. The same holds for Europe. I mean we've got a strong plan taking shape in Europe that will also call for a CapEx strategy. And so, look, we have to complete Augusta's initial round of financing, which will pave the way for everything else we intend to do, but it's hard to say, for instance, how the CapEx trajectory would look for the company at this point until Augusta's financing is secured, but you can be sure that once this is finished, the growth pipeline we keep referencing is genuine, all right? It's genuine. With South Korea and with Europe, those represent two genuine projects that are lined up and ready to move, and we're developing the project right now and we'll develop the CapEx forecast in parallel with that?

Larry Somma

executive
#64

Right, and one more point from me. What matters most to us is making sure our wish to put together a CapEx plan doesn’t push us into a spot where we’re committing before the money is coming in, so to speak. Where the funds come from and where they go—that’s what occupies our minds daily. So Dustin nailed it. After we clear this capital hurdle, we can then provide a clearer picture of how 2023 capital will shape up.

Thomas Boyes

analyst
#65

Understood. That's completely logical. Here's another thing — clearly, you've shown movement on both the feedstock side and the offtake side for Augusta line one and line two. In decks you shared before, you pointed to some of the visibility you have into more feedstock as well as conversations with active customers. I just wanted to ask whether you've had a chance to give an update on that?

Dustin Olson

executive
#66

Honestly, nothing new has happened on either feedstock or offtake. Where feedstock is concerned, our energy footprint for making a purified product is far smaller than what competing options require. That gives us an advantage when it comes to variable costs. Our method of cleaning the feedstock is far more basic than what those other processes rely on. As a result, we're able to purchase feed streams nobody else is able to work with, and then purify them, all right. Turning to offtake, brands care a great deal about product quality, all right. To produce a shampoo bottle, consistency in the product is essential. Everyone globally would like to use sustainable materials, but when they attempt it, quality variation — colors and odors in certain instances — shifts around; managing that is extremely hard for a converter who needs to build the shampoo bottle identically each and every time; so our product, since we take out the color, since we take out the odor, since we accomplish it at a cheaper cost point, delivers — honestly, it delivers something simpler for customers to handle. Beyond that, there's our lifecycle analysis. We're aware that our lifecycle analysis is very strong, and honestly it will be even stronger at Augusta, all right; brands care about that as well. They need to know the material they're buying is sustainable. That's check mark number one; they need to know it has a solid carbon footprint, since they're invested in that narrative for their own brand too. After that, they want things to be simpler for them with the converters. And honestly, that's where we succeed on the offtake side; we'll hand customers a solution that is simply simpler for them to handle. They don't need to stress about it; demonstrating the LCA is good is straightforward. Demonstrating it's sustainable is straightforward, and dealing with it is straightforward for them since we take out color and odor. So this is what — look, I mean, with the Augusta project, clearly, we're running a bit behind on the financing. It'll arrive, we'll sort it out, and we'll get that project moving. Yet when everything is said and done, our feedstock supply is oversubscribed, and our offtake demand is oversubscribed as well, and that ought to attract attention, since it will in the end shape the site's economics along with the platform's expansion and provide the brands with what they require to meet their customers.

Larry Somma

executive
#67

Yeah, one more point I want to mention, Thomas. Dustin brought up the European site. He said nothing whatsoever regarding what's happening out of public view when it comes to forming feedstock alliances across Europe. That is genuinely, genuinely thrilling. And once more, we won't be sharing details on that today, but keep watching for it, since the alliances we're putting together for Europe so we can guarantee sufficient speed at economic target figures, and so forth, will truly demonstrate that we're accomplishing something remarkably one-of-a-kind.

Dustin Olson

executive
#68

Absolutely, I'll add to what Larry said there. That was a really strong observation on his part. The whole reason we kicked off this presentation by asking where we stand right now is simply to give everyone a refresher on our narrative — and that narrative hasn't changed. Alright. It remains exactly the same: there's an enormous market opportunity tied to the value our product delivers. What sets us apart in the marketplace is our capability when it comes to feedstock, and the world genuinely requires it. So every single factor that has made people enthusiastic about PureCycle before is still very much in place. And honestly, we're seeing substantial momentum with genuine partners all over the world, alright. Think about it — you wouldn't begin discussions about Europe without first putting together a feedstock strategy; that's already been accomplished. Likewise, you wouldn't even start conversations with SK, or build any momentum with them, unless they had come to value, acknowledge, comprehend, and concur that the technology holds up, plus have both a feedstock arrangement and an offtake plan in place. Alright, so this idea of PureCycle within the industry is genuine, and serious participants in the market are paying attention, and they're forming lines to join forces with us for upcoming expansion. So look, we understand we need to get Ironton operational; that's going to happen. We understand Augusta has to secure financing, and that's going to happen too. But immediately following those 2 temporal items lies a growth strategy that involves far more than just PCT doing the talking — it's partners queuing up behind us to collaborate in building something truly extraordinary on a global scale.

Thomas Boyes

analyst
#69

Understood. So I believe there's simply a <<inaudible>>. It sounds as though, when we look at the prior quarter's 938 pounds of feedstock under discussion, that figure ends up larger. Out of the 345 million pounds of early offtake talks, the number exceeds that — it's as if everything keeps speeding up. Is that a <<inaudible>>?

Dustin Olson

executive
#70

All right, let's return to a few basics. During 2018, China was importing 10 billion pounds annually of feedstock from around the globe. Roughly 50% of it originated in the U.S. And, say, 50% of that consisted of polypropylene. Right. So between 2.5 billion and 3 billion of polypropylene was heading to China. During 2018, they halted it; the flow flipped and began going into landfills. Therefore, plenty of volume exists out there, even if you only consider the United States. The problem we address through our infrastructure strategy is that we must go obtain it, we must extract it, we must gather it, we must feed it into the system so that we can purify it; that identical approach replicates itself globally; throughout Europe, an enormous quantity of plastic headed for incineration gets labeled as recycled. We are able to remove it from incineration and purify it for a superior value proposition. Throughout Asia, abundant feed exists there. It simply hasn't been tapped, and whenever people examine it, they conclude, fine, this represents a terrific opportunity, yet we wish to pursue it using the proper technology. Whenever they search globally for technologies appearing most sensible regarding LCA, value, consistency, and quality, they arrive at peer cycle. Thus, indeed, I'd concur with what you're saying. Is it expanding? I believe the response is affirmative. As people discover increasingly more about what PureCycle can accomplish, and as we prove our capacity to scale the technology, opportunities will pour open regarding what we're capable of doing going forward. Consequently, indeed, I believe tremendous demand exists for our product. A tremendous amount of feed simply sits out there, waiting for someone to retrieve and purify it, and I believe we occupy a distinctive position to accomplish that. Plus all of it appears more promising to people the nearer we come to Ironton completion and Augusta financing, which is what we observe in today's market.

Thomas Boyes

analyst
#71

Understood. Perhaps just one final item. Regarding the feedstock plus pricing piece, can you give a rough idea of what share of the contracted offtake for lines one and two that accounts for? Clearly, a few quarters back you ran a solid scenario analysis and outlined the effect of that.

Dustin Olson

executive
#72

Sure. When it comes to Augusta lines one and two, that figure is roughly 80%. Another thing worth pointing out about Augusta is that our offtake is oversubscribed, yet we are not over committed. Right. Our contracts contain min’s and max’s, with the min fixed at a certain level and the max available at our discretion up to the highest level. Right, so we carry a min of roughly 160 million to 170 million that we must deliver on, and a max of somewhere around 300, 290, 300 or so, all right. What this affords us is the flexibility to shift our offtake toward those customers who are ready for it and who want it. Okay. And who are the most successful at developing applications that brands ultimately desire. So we hold considerable flexibility in that regard. And as I mentioned, the bulk of it sits at feedstock plus roughly 80%. One more thing worth noting is that on the Ironton contract, we're switching to a feedstock plus structure for the replacement. So even under the Ironton contract arrangement, that cuts a substantial amount of risk for the overall Ironton project, since it's now tied to market pricing for number five bales, along with feedstock plus pricing for the offtake.

Thomas Boyes

analyst
#73

Excellent, and I appreciate hearing your perspective. Those were all my questions.

Dustin Olson

executive
#74

Many thanks.

Dustin Olson

executive
#75

Right. So first off, I'd like to express my appreciation to each of you for dialing into this call today, and even more so for sticking with PureCycle throughout this journey, all right; we're right at the point where Ironton is nearly finished and we're about to get this technology up and running, and that's what people have been talking about for the past 6 years; so we're close to getting there. So stay with us just a bit more, we'll have that facility operational and then we can demonstrate to the entire world just what PCT can truly do. Appreciate you being here, and I'm looking forward to speaking with all of you within the coming 2 months or so.

Operator

operator
#76

That wraps up the presentation for today, everyone. You're welcome to leave the call now, and I hope the rest of your day is great.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete PureCycle Technologies, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to PureCycle Technologies, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in PureCycle Technologies, Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.