operatorWe appreciate everyone being on the line, and we're glad to have you join the Ramelius Resources quarterly teleconference. <<operator_script>> At this point, I'll turn the call over to the Managing Director, Mr. Mark Zeptner. Please proceed.
Mark Zeptner
executiveGood morning, everyone, and thanks for taking the time to dial in today. As usual, CFO Tim Manners is here with me this morning. Tim and I will follow our customary format, walking through the key points from the quarterly before we open the line for questions. In the March 2021 quarter, the company delivered another strong operational performance, with gold production of 66,029 ounces at an all-in sustaining cost of AUD 1,370 an ounce, both within guidance. Mt Magnet once again anchored production, delivering 41,832 ounces. Edna May contributed 24,197 ounces, the majority of which came from the Greenfinch open pit. Tim will go into more detail on the financials shortly. It's fair to say the balance sheet is strong, and our cash reserves increased quarter-on-quarter despite a lower realized gold price and some significant one-off items, such as the FY '20 income tax payment. On the development side, our 2 key projects, Tampia and Penny, are continuing to advance well. After the acquisition of the farmland at Tampia, mobilization of the open pit mining contract has occurred and site establishment works are underway. Grade control drilling has also begun in the 100-person camp on the outskirts of Narembeen, which has been operating for several weeks now.
Mark Zeptner
executiveAt Penny, we're now fully underway with getting the required approvals, contracts and long lead items in place. We expect site works to begin next month, with open pit mining starting in the September 2021 quarter, consistent with the production schedule we've communicated before. Today we also announced that the Eridanus mineral resource has risen 52% to 760,000 ounces, based on the deeper diamond drilling we contemplated — completed over the past 2 quarters — along with a maiden resource of 220,000 ounces at the nearby Orion-Franks Tower project, both at Mt Magnet. That adds up to almost 1 million ounces of resources within 5 kilometers of the processing plant at Mt Magnet, and both are the subject of scoping studies — underground for Eridanus and open pit for Orion, respectively. The prefeasibility study looking at the potential of a Stage 3 cutback to the Edna May open pit is still on track to be completed at the end of June. It's worth reminding the audience that the Edna May study rests on an existing 1 million ounce resource industry, which highlights the growth potential at both of our primary production centers. More detail on exploration activities across the company's various projects during the quarter, where we've also seen a change in senior management, is in the full report itself, which you can read at your leisure.
Mark Zeptner
executivePeter Ruzicka, our new GM of Exploration, comes to us with extensive experience exploring for gold, copper, and base metals, both in Australia and in countries including Indonesia, China, and PNG. His most recent role was at Norton's Gold Fields Paddington operation, where he was responsible for overseeing substantial growth in the mineral resource of more than 10 million ounces. We're eager to see what he contributes here at Ramelius. Tim, over to you now.
Timothy Manners
executiveThanks, Mark, and good morning, everybody. Mark, as you noted, quarterly gold production came in at 66,029 ounces, with an all-in sustaining cost of $1,370 per ounce. Gold sales for the period were 65,420 ounces, at an average realized price of $2,242 per ounce. Our all-in sustaining cost margin declined versus the previous quarter, though it remained very strong at $872 per ounce. The main drivers of that lower margin were a 10% drop in the spot gold price and roughly a 7% rise in our all-in sustaining costs. Even so, cash flow generation remained quite healthy. In fact, underlying cash flow rose 12% quarter-on-quarter, reaching $38.7 million. For anyone interested, all-in costs for the quarter were $1,660 per ounce. The underlying cash flow from the quarter went toward funding the Tampia JV buyout and the purchase of the Tampia farmland. As Mark said, we've paid $20.3 million to the ATO. That was a one-off payment that closed out our FY '20 income tax liability. From here on, our income tax payments will follow the ATO's monthly installment regime, which is standard for a business of our size and nature.
Timothy Manners
executiveOverall, our cash and gold holdings rose by $9.1 million, reaching $230.6 million by the close of the quarter. Our debt stayed at $8.1 million, which left us with a net cash and gold position of $222.5 million at quarter end. Every bit of that outstanding debt gets paid off in June this year. Meanwhile, behind the scenes, we're busy refreshing and upsizing our syndicated facility so it can potentially back any future material growth initiatives that we identify. Before turning to the outlook, here's a quick update on the hedge book. Over the quarter, we delivered into 38,000 ounces at an average price of $2,186 per ounce, and we added 17,500 ounces at an average of $2,331 per ounce. As of the end of March, the hedge book now sits at 209,250 ounces at an average price of AUD 2,310 per ounce. So with 1 quarter of the financial year remaining, we've refined our full year guidance to 275,000 to 280,000 ounces, with an all-in sustaining cost range of $1,280 to $1,330 per ounce. We'd note that all-in sustaining costs for the June quarter are expected to come in roughly 4% higher than what was previously published, with a midpoint of $1,290 per ounce versus the $1,240 per ounce released previously.
Timothy Manners
executiveThat comes from a shift in the blend of ore sources we're processing, along with rising labor costs that are being felt across the WA resources sector. Our June quarter production guidance is still 65,000 to 70,000 ounces. CapEx for the quarter came in pretty much as expected, though we've raised our full-year forecast by 5.4% to $106.7 million. The bump reflects development of the new King Brown pit at Marda plus somewhat higher camp and ancillary construction costs at Tampia than the original feasibility study assumed. At this point I'll turn things back to the operator so we can open the line for questions.
Operator
operator<<operator_script>> Our opening question is from Andrew Hines at Shaw.
Andrew Hines
analystNice work on a solid quarter even with those outages. Tim, a quick question about your costs. The all-in sustaining cost was clearly at the top end of that range in the third quarter. Could you put a number on how much of that you figure came from the SAG mill outage? When I look at your fourth quarter guidance of $1,290, with production at pretty much the same rate as the third quarter, that's down roughly $80 an ounce. Is that about the effect you believe that SAG mill outage had on your cost base?
Timothy Manners
executiveI'd say that's a reasonable estimate, Andrew. A few factors are behind the modest cost bump. We ran a great deal of grade through the mill during the quarter, and that clearly had an effect. We also had the outage, so physical throughput at the mill came in somewhat lower. Some labor cost pressures we've mentioned previously are definitely working their way into the business, and we're plainly not the only ones facing that. Also, the ore source mix for the June quarter shows a small shift versus what was published earlier. There are several — as you know, several components that combine to produce these costs. Still, in my view each one individually contributed only a small amount to that underlying figure.
Andrew Hines
analystThanks. Clearly, what this question is getting at is simply trying to understand what's happening on an ongoing basis with the cost base as we move forward — though the cost pressures are certainly visible there — but how much of that in the quarter was a one-off impact. And I think that $80 down sounds about right. The second question is for you, Tim. On the hedge book, you're now down to only 2 years of forward hedging. I think when we first started looking at you guys, you were sort of 3 years out. Is that a deliberate shrinkage of the time lines on the hedge book? Or are you just taking advantage of whatever the market is at the time?
Timothy Manners
executiveIt's partly the latter and partly the former. We've noted on previous calls that we made a deliberate decision to reduce the quantum to roughly 200,000 ounces by the close of this financial year. We're on track to achieve that. We essentially review this position daily and weekly as things progress. The natural consequence, I suppose, given the shape of the forward curve, is that we aren't placing many ounces further out in time. Most positions, when we do establish them, tend to be short-dated. Backwardation is fairly steep right now. So that's likely a natural outcome from a timing standpoint. And the 200,000 ounce level is roughly where we're headed, and we'll pause and evaluate at that stage where we proceed from there and how the business looks going forward.
Andrew Hines
analystThanks. And this will be my last question for you, Mark. Bob Vassie has come in as the nonexec chair. By now he's been in that role through most of this year. Do you have any thoughts on how the two of you are working together, and is anything shifting when it comes to the company's strategy, M&A, different targets, a different focus, or an organic versus inorganic kind of approach to growth?
Mark Zeptner
executiveWell, Andrew, we're still at an early stage on that, but having one mining engineer keeping an eye on another certainly keeps me accountable, and Bob clearly comes with a great deal of experience. We held our strategy session not long ago. So it's clearly a good moment for him to begin digging into the nuts and bolts of the company and to assist us going forward, and now we're looking forward to his contribution.
Operator
operator<<operator_script>> The following question is from Richard Hart, representing Top Wheel.
Analyst
analystCongrats once more, everyone. It’s becoming a little repetitive, but nice work hitting guidance every single time. My first question is really about Tampia. You mentioned you’re beginning — I believe the camp has been completed. Have you actually pulled any ore at this point? And if you have, do you have any sense of what grades you’re getting?
Mark Zeptner
executiveThanks, Richard. So we've begun shifting some material, though it's really at the pit's northern end, where it's waste; a portion of that waste is needed to help finish some of the infrastructure around the site. At the same time, at the southern end of the pit in the Mates area specifically, we've got an excellent control rig. That rig is therefore running at full tilt, clearly to develop the ore blocks in that zone. So ore mining isn't far off. As a result, I can't really give a read on how that's shaping up, but that will be the first place where we actually do ore mining. And just as a reminder, I suppose, the schedule we did set out had delivery to the mill not happening until July, but if we're able to get it a bit sooner, then we will, though it won't be much sooner given where things stand right now.
Analyst
analystOkay. I understand there's some chatter going on regarding Narembeen, so I imagine you have your hands full. As for those grades, do they line up with what was expected? Is it permissible for you to comment?
Mark Zeptner
executiveSo right now at Tampia, we've essentially kicked off a grade control program. That means we don't really have sufficient results from it yet to put out a report. So as we dig some boxes down into the mill, we'll begin reporting on what those reconciliations look like, but we simply don't have enough information available at this point. And yes, quite a few folks from the accounts side were there for the first blast roughly a week ago, but they were still only far enough back to watch it, and they were quite interested, which is good for us in terms of generating some interest around town and hopefully some support around town as well.
Analyst
analystAlright. So, Orion, what I was bringing up — those grades that you currently have, a number of them are pretty impressive. Is it too soon to have even a rough sense of how that could develop? Or will it take some time before any plans take shape?
Mark Zeptner
executiveSomeone suggested that the 12 meters at 196 deserved a separate release. That intercept is fairly deep, and there aren't really holes around it to support it. So with results like that, we usually stay cautious. Orion, though, looks quite interesting for open pit potential near surface, and we've deeper hit that, hopefully, also an underground potential.
Operator
operator<<operator_script>> Our following question is from Euroz Hartleys' Michael Scantlebury.
Michael Scantlebury
analystGood job on generating cash from CapEx and tax payments this quarter. My question really concerns how you're feeling about FY '22 guidance. I know you'll be releasing your life of mine update during this quarter. Still, I'd like a sense of the pressures ahead, specifically whether an extension would help or hurt, and you mentioned Tampia here and, of course, Penny West. Then perhaps you could also address the potential Tampia throughput optimization — will your plant be running nearer to, above, or closer to present run rates? Or will you be dialing it back in order to achieve that finer grind size? Some color on that would be useful.
Mark Zeptner
executiveThanks, Michael. Vivien will clearly be in the FY '22 forecast, or guidance, as you might call it. And we're hoping we can squeeze a bit more out of Vivien, and that's looking positive. There were no drill results in this release, but we're hopeful on that front. The FY '22 plan, from a production standpoint, looks comparable when you consider the life of mine, and that's my sense of it. The team is holding budget meetings every day and working through the details. We do ground-up budgeting from the operations here, and this process goes through several reviews. On the cost profile, looking at the life of mine, it's actually higher than the year after that, and that's mainly because Penny doesn't have a significant contribution to FY '22 compared with the years that follow. So we're looking very closely at Penny and whether we can bring that in early. I'm not sure if you have any further comments on that, Tim. But the costs around the levels where we are is probably what we expect before we can get back to more of $1,100 to $1,200 an ounce, where historically, obviously, that was brought about by Penny, which is sort of $600 to $700 an ounce, which will grade that overall corporate cost down.
Timothy Manners
executiveYeah, Mark, I think that's fair. Michael, there's quite a bit of work underway right now. Obviously, we'll come out with the updated life of mine around June-July, and we'll give you some transparency at that stage.
Mark Zeptner
executiveOn the final item regarding processing Tampia ore at the Edna May mill — nothing has been run through that mill as of now. All modifications to the mill are complete, though. We installed screens, a leach, a fixnut, plus several other components, and that set us back roughly $6 million to $7 million. We're running well ahead of schedule. So that still needs to be tested. We'll be reducing the mill's speed a bit in order to achieve the finer grind, and we'll watch recoveries extremely closely. So that one really has to be handled on a case-by-case basis, Michael, and at this point I'm unable to share any results or say how it's progressing.
Operator
operatorThank you. We have no more questions right now. Today's conference ends here. We appreciate your participation. You can disconnect at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ramelius Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Ramelius Resources Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ramelius Resources Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.