We appreciate everyone being on the line, and we’re glad to have you join the Ramelius Resources teleconference for the December 2021 quarter. Everyone attending is currently muted and can only listen. After a presentation, we will hold a question-and-answer session. <<operator_script>> At this point I’ll pass the call to the Managing Director, Mr. Mark Zeptner. Over to you.

Mark Zeptner

executive
#2

Good morning, everyone, and thanks for taking the time to join us on the call this morning. Joining me, as always, is our Chief Financial Officer, Tim Manners. In keeping with the usual format for these calls, I'll take you through the operational highlights from the quarter, and then I'll hand things over to Tim, who will dig into the numbers in more detail. After that, we'll open up the line for questions. Even though COVID-related labor shortages have become more evident within WA, Ramelius still put in another solid quarter, producing 66,919 ounces at an all-in sustaining cost of $1,493 an ounce. That landed at the lower end of guidance for the quarter, which reflected a modest decline in grade and throughput at Mt Magnet, along with an inability to haul as much ore as we had planned from the Tampia and Marda sites because of the labor shortages I mentioned earlier. Given the quarterly result, we have kept our full year guidance at 260,000 to 300,000 ounces at an all-in sustaining cost of $1,425 to $1,525, and our current expectation is that we will land within the lower end of that production range, while on all-in sustaining costs we are currently well positioned at around the midpoint of that range. That said, we have added a caveat: the actual impacts of the delayed reopening of the WA border, any potential COVID-19 infections among mine site personnel, and disruptions to the supply pipeline are difficult to assess accurately at this time.

Mark Zeptner

executive
#3

While we've factored some of these into the guidance, it's difficult to state with any real certainty how they could impact the business over the next 6 months. And I suspect we aren't alone in grappling with these issues. In the December quarter, output from Narembeen exceeded Mt Magnet for the first time since we acquired that operation in 2021. Although we were limited in how much ore we could haul from Tampia and Marda, Edna May still produced 35,367 ounces for the period, while Mt Magnet produced 31,552 ounces. It's worth noting that the labor shortages affecting all haulage capacity have led to roughly 200,000 tonnes being added to ROM stockpiles at Tampia and Marda, and those stockpiles now hold 785,000 tonnes of high-grade ore containing more than 40,000 ounces of gold. Assuming an AUD 2,500 gold price, processing this ore would generate over $60 million in incremental free cash flows. To elaborate a bit further, our haulage contractor has the trucks but not the drivers, despite significantly raising pay rates and adding a Ramelius pay for bonus system into the total package.

Mark Zeptner

executive
#4

Right now, Western Australia just doesn't have an adequate supply of truck drivers to cover the needs of both the resources sector and general freight. Sadly, we've also lost several more drivers because of the border hold-up on Feb 5 — some of them went back east before Christmas, believing they'd be able to come back, and a number of drivers based in Eastern states were mid-onboarding with a planned start date near Feb 5. We'll need to engage with the government to try to bring those drivers into the state, since the present 14-day quarantine requirement, versus the 7 days now applied on the East Coast, will serve as something of a disincentive and will additionally slow down getting those truck drivers onto our mine sites. Labor shortages at many companies have been made worse by mandatory vaccine rules brought in by the AA government. Fortunately, Ramelius has been affected only modestly — just 2.5% of our workforce, or 7 of the 300, and a reportedly comparable share of our contractor employees. We'd be glad to have these employees return if they get fully vaccinated, and some have said they're waiting for the Novavax vaccine to become available.

Mark Zeptner

executive
#5

Beyond following the vaccine requirement, we keep implementing measures to control the COVID risk and feel we're properly equipped to deal with a sudden outbreak at the site if one happens. We've obtained adequate PPE stock and rapid antigen test kits for any 4-course testing, and we've carried out on-site and corporate emergency exercises plus scenario planning aimed at reducing the chance of any disruption to operations. Regarding operations at Mt Magnet, mining activity remains centred on the Eridanus open pit, which delivered strong output from the pit, letting us preferentially mill higher-grade ore and stockpile the surplus ore. The Shannon and Hill 60 underground operations likewise kept performing strongly. Vivien attributed mill production came to 58,285 tonnes at slightly above 4 grams for nearly 7,500 recovered ounces. As the probability of deeper extensions to the Vivien ore body declines, mining will concentrate on effectively extracting the remaining reserves in any remnant resource areas, which will probably involve a final open pit cutback once all underground reserves are exhausted. At Edna May, ore sources during the quarter comprised the historic low-grade oxide stockpiles, Greenfinch, Tampia, Marda and the Edna May underground.

Mark Zeptner

executive
#6

Mining went nicely at Tampia and Marda alike, and haulage out of both sites got better too — though, as we mentioned, at a pace under what we expect, and that was mainly what drove the quarter-on-quarter production increase at Edna May. Now to project development. On that side, we finished the small Magenta pit at Penny, and a cutback started at Penny West to restore proper long-term ramp access plus a portal position in the North wall. Dewatering at Penny West has kicked off as well, with water being pumped north into the Magenta pit. Preparation of the high wall for the underground portal should take place near the close of this quarter, and we're eager to see underground mining begin and production follow soon after from this high-margin operation. Mining studies carried on, covering the Galaxy underground pre-feasibility, the Morningstar underground concept study, the St. George underground remnant study and the Hill 50 underground concept study at Mt Magnet, along with the Edna May Stage 3 open pit pre-feasibility study. A fuller update on where each of these stands will come in February. And naturally, now that the takeover of Apollo Consolidated is done, the Rebecca Gold Project, East of Kalgoorlie, has joined our roster of development projects.

Mark Zeptner

executive
#7

Work at Ramelius is set to kick off in February, and our plan is to resume the technical studies Apollo had underway as quickly as we can. For this half we've budgeted $4.6 million of spending at Rebecca, and that ought to show how aggressively we mean to push this project. The quarterly report holds a wealth of detail and exploration news, which I'll let you read through whenever suits you, though a few highlights did reach the front page — the RC and Diamond results at Bartus East, at Mt Magnet, plus fresh results from the RC program at the Mt Finnerty JV, 200 kilometers away from Edna May. The Mt Finnerty JV is a fairly recent addition for us. It's early stage, yet we believe that first round of drilling offers significant encouragement. To sum up, the returns we keep seeing from our exploration investment remain excellent. Roughly $14 million went out in the first half, and we're forecasting an even larger $18 million for the second. With that, I'll pass things to Tim.

Timothy Manners

executive
#8

Thanks, Mark. As you noted, Ramelius wasn't shielded from COVID's effects in the December quarter — especially the labor shortages you mentioned. While we stayed within guidance, output landed at the bottom of the range, with 66,919 ounces for the quarter, bringing first-half production to 132,605 ounces. Sales came in stronger during the quarter at 77,225 ounces, though that mostly reflected a reversal of the bullion buildup from the close of the previous quarter. The average price received rose to $2,357 an ounce, mirroring the runoff of lower-priced forward contracts along with a broadly higher spot price environment. Even with some of the problems that hit the company this quarter, we continue to view our all-in sustaining costs as highly competitive — ASD 1,493 an ounce for the quarter and AUD 1,473 an ounce for the half year. We've kept both production and all-in sustaining guidance unchanged for the full year, though, as Mark pointed out, we're steering toward the bottom of the production range. Projecting all-in sustaining costs for the second half is difficult given how many variables the industry is dealing with right now. Without question, as I said, cost pressures are showing up throughout the business.

Timothy Manners

executive
#9

Even so, right now we're at ease leaving the all-in sustaining cost guidance for the entire year unchanged, though we'll update the market on an exception basis as the year progresses. The December quarter also saw considerable corporate activity, with the off-market purchase of Apollo Consolidated — completing in only 36 business days during that quarter. A few hiccups notwithstanding, the deal was highly efficient and reflects great credit on everyone involved. As you'll recall, the consideration paid, carrying an equity value of roughly $150 million, included a substantial cash element — the single largest factor behind our cash and gold balance falling to $164.5 million at quarter-end, versus $273.9 million at the close of September 2021. Underlying operating cash flow stayed positive at slightly below $45 million for the quarter, of which close to $25 million went toward development at Tampia and Penny plus exploration work group-wide. Underlying cash flow from operations thus came to roughly $13 million. As noted, the Apollo transaction's net cash effect was an outflow of approximately $67 million, and together with $20.4 million of dividend payments and income tax payments covering about 1.5 years that totaled $31.6 million, we finished the quarter holding $164.5 million in cash and bullion.

Timothy Manners

executive
#10

Also, every significant payment tied to the Apollo transaction has now gone through, with the exception of stamp duty, which will be settled after it gets assessed. On top of that, since the tax payments made this quarter amounted to more than a whole year's liability, we'd anticipate smaller tax installments moving forward, assuming nothing else changes. Finally, a brief note on the hedge book. In the quarter, we delivered into contracts covering 62,500 ounces at an average of AUD 2,344 per ounce, and we added 85,000 ounces at an average of AUD 2,494 per ounce. Now that spot has climbed back above AUD 2,500 an ounce and the forward curve has gone back into contango, we seized the chance to add some positions with slightly longer dates and very attractive forward prices, which should help make sure our short- to medium-term cash management and development programs stay supported. As of the end of December, the hedge book stands at 218,500 ounces at an average of AUD 2,419 an ounce. I'll now pass things back to Harmony to open the line for questions.

Operator

operator
#11

<<operator_script>> Our initial question is from Andrew Bowler of Macquarie.

Andrew Bowler

analyst
#12

Clearly, you're referring to how hard it is to find truck drivers right now. I was wondering what the plan looks like once Penny is scheduled to arrive with trucking. Obviously, Vivien is winding down. Is it simply a matter of shifting resources from Vivien over to Penny? Or will the business face somewhat more pressure regarding satellite trucking when Penny comes online? Cheers.

Mark Zeptner

executive
#13

Thanks, Andrew. Yeah, for the most part, that shift will be a reallocation away from Vivien. At Vivien we've managed to move to what's termed a super quarter — a truck with somewhat greater tonnage — and that's going to benefit us and clearly means we'll need fewer effective trucks. And Penny, since the high-grade material there isn't high tonnage, the requirement isn't massive, unlike Tampia and Marda at roughly 2 grams per tonne, where you need considerably more trucks to move a comparable number of ounces. So we have a plan in place for that, and it will really start to take effect more in June and July, and by then we'd like to believe we'll be in a better position on all the things we've discussed as well.

Andrew Bowler

analyst
#14

Nope. This is my final question as well. You've clearly discussed certain arrangements for the point at which COVID cases rise here in Western Australia. Has the department told you anything regarding possible exemptions for mining? Obviously, with the present definitions of close contacts plus isolation rules and similar matters, I believe it's fair to state that the existing Western Australian definition is likely quite unworkable for mining. So, given the exceptionally high, 100% vaccination rate in mining, are there any exemptions you've been made aware of?

Mark Zeptner

executive
#15

From my understanding, the Disaster Council is convening today and taking a close look at that matter. Naturally, a 7-day regime would be preferable to us over 14 days, though we'll need to wait and see how that turns out. Take something like a road train driver — I never thought I'd say this, but it has turned into an essential and critical skill in which we have a shortage within WA. We will definitely be making that argument, since it extends beyond just the East Coast, which potentially again may need to draw on overseas skills to meet the needs we have at present. With iron ore prices rising again, some of these iron ore mines require 50 to 60 truck drivers for just one small iron ore mine. So they place a pretty big demand on the industry. And then we've heard about general freight and the capacity to fill shelves and similar things. I think that's the endpoint of what this shortage is showing us.

Operator

operator
#16

Mathew Collings of Morgan has the next question.

Mat Collings

analyst
#17

We seem to be stuck on mute. Mark, would you mind walking us through the schedule of works — what's been happening and what's ahead at Penny, in more detail than you gave in the intro?

Mark Zeptner

executive
#18

Thanks, Mathew. I felt I was being pretty intentional about it. As for what's going on at Penny, the small Magenta pit is now finished. The cutback has been started, and it's progressing nicely. That cutback ought to wrap up later in this quarter, and after that we'll get the high wall ready above where the portal sits, up in the northern section of the Penny West pit. An underground contract has already been handed out, and we're figuring out the mobilization schedule and similar details so that an underground crew is actually on site before this quarter ends. Early development, with production truly ramping up, comes more in the September quarter.

Mat Collings

analyst
#19

No, that was fine. It's just that my speaking isn't keeping up to speed.

Mark Zeptner

executive
#20

That's fine. To sum it up, I'd say that in today's conditions, the timeline was essentially hit — we're where we should be at Penny, and I believe the team in the field has performed really well in getting us there.

Operator

operator
#21

The following question is from Michael Scantlebury of Euroz Hartleys. And the next one is from Alex Barkley at RBC.

Alex Barkley

analyst
#22

Mark and Tim, on that point, you seem to be indicating that we'll land at the bottom end of the production guidance. How would you anticipate that revision to be distributed across the site? Is it somewhat more concentrated at Edna May, where you flagged those haulage labor issues, or is it something a little different?

Timothy Manners

executive
#23

Alex, this is Tim, I believe. Honestly, I'd say it will be fairly balanced between the two. What we're hoping is that, as you mentioned, truck driver availability gets better — and if that happens, then I think you'd see somewhat more come out of the Edna May processing center. Overall, though, the profile is fairly even. That was true at the beginning of the year, and it's still true now. So honestly, I wouldn't anticipate much of a difference from either one.

Alex Barkley

analyst
#24

All right, thanks. And one final question from my side. Turning instead to the project studies that are coming up, clearly there are labor cost pressures at the moment. I understand those studies are still underway. But if the costs and economics turn out to be temporarily unfavorable, would you possibly push things back, take another look at the studies for those cost estimates, or perhaps at when the projects would start? Do you feel the economics aren't being fairly reflected right now?

Mark Zeptner

executive
#25

Absolutely, Alex — that's exactly the situation with Edna May Stage 3. At Golden Point we've finished a portion of the drilling, and we're now gathering all the final assay results. Those will go into a model so we can see how they affect our optimization work at the open pit price we last assumed. But yes — kicking off a big open pit operation like Edna May Stage 3 while the contractor market remains this volatile is precisely the approach we're taking. Clearly, we're holding back until conditions calm down and labor isn't under as much strain as it is right now. A few of the Mt Magnet studies sit at an earlier stage, and at this point I believe we can make certain assumptions to test whether those projects have merit and can be advanced. Regarding decision-making, though, your point is entirely fair.

Alex Barkley

analyst
#26

That's fine. Actually, that background helps with what we'll see in February. Thanks a lot, everyone.

Operator

operator
#27

<<operator_script>> Our following question is from Richard Hart at Top Wheel.

Richard Hart

analyst
#28

Mark and Tim, congratulations once more on hitting guidance in spite of the conditions, since I'm certain that isn't easy. One question on trucking — everyone keeps bringing up trucking. Is there some kind of priority when it comes to getting access to trucks and drivers, or is it simply dog-eat-dog?

Mark Zeptner

executive
#29

Pretty much the latter. We've effectively pushed pay rates up several times via our contractor. A truck driver in iron ore is being offered $60 an hour plus bonuses, plus, plus, plus. They're paid quite well these days, and they're pulling people — or truck drivers — out of general freight. And the ones with the most money can pay the most, and it's pretty much a dog-eat-dog situation, you don't have any preference. And you've got the grain harvest and things like that to move around as well. So it's a pretty pale situation at the moment — that's how we're putting it to our contractors. It's pretty difficult to — right now, it's about keeping your — the truck drivers you have; getting extras at the moment is very difficult.

Analyst

analyst
#30

Okay, quick question — did we actually bring in a wheat harvest this time?

Mark Zeptner

executive
#31

This was a record-breaking year for me. Keep in mind that we discussed just how strong it was and what effect it had on our Marda haulage operations. All of that contributed to a record-setting season for the WA harvest. So there was a great deal of grain for them to transport, along with higher demand coming from the resource industry.

Analyst

analyst
#32

So what you're saying is that the wheat plan is something we actually gained from as well?

Timothy Manners

executive
#33

Indirectly.

Mark Zeptner

executive
#34

Indirectly, it's our community group that farms the area around the Tampia mine. I haven't looked at their books myself, but I'd assume they did quite well.

Richard Hart

analyst
#35

Alright, and I’ll keep this brief so I’m not taking up more of your time. Regarding the trading holder at Westar — we do have an interest there. Ramelius didn’t put out any statement. Is that not required? Is it not material enough to affect us? I was just wondering why Ramelius made no statement about Westar?

Mark Zeptner

executive
#36

Richard, I ended up on the front page — they're at an early stage, and materiality is the whole focus.

Timothy Manners

executive
#37

For us, Richard, getting into all of that isn’t material to the bottom line.

Mark Zeptner

executive
#38

Well, those are attractive early results, and our hope is that this eventually becomes a mine — but it's still early days, and we'll go from there.

Operator

operator
#39

Stuart McKinnon of The West Australian has the next question for you.

Stuart McKinnon

unknown
#40

Mark and Tim, I just want to get something straight — when you mention the truck driver shortage, does that mean road haulage specifically? Or does it cover your entire group of drivers on site as well? Is it across the board, or is it mostly limited to the road train guys?

Mark Zeptner

executive
#41

From our perspective, given that we operate a road haulage business, this really falls into that category for us. That is precisely what has hurt our capacity to move goods by truck from our satellite locations. I have no doubt that shortages exist throughout the industry, yet they are not as severe as what we are experiencing, and they have not had a larger effect than the ore haulage truck drivers have had on us lately.

Operator

operator
#42

<<operator_script>> Thanks. At this point we don’t have any more questions. That brings today’s conference to an end. We appreciate everyone for joining. You can go ahead and disconnect now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ramelius Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Ramelius Resources Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ramelius Resources Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.