Ramelius Resources Limited (RMS) Earnings Call Transcript & Summary

July 28, 2022

Australian Securities Exchange AU Materials Metals and Mining earnings 22 min

Earnings Call Speaker Segments

Operator

operator
#1

We appreciate everyone holding on, and we’re glad to have you join the Ramelius Resources quarterly teleconference. Everyone attending is currently in a listen-only mode. A presentation will come first, and after that we’ll hold a question-and-answer session. Should you want to pose a question, please press the star key and then the number 1 on your telephone keypad. At this point I’d like to pass the conference to Mr. Mark Zeptner, Managing Director. Please proceed.

Mark Zeptner

executive
#2

Good morning, everyone, and thanks for taking the time to join us on the call today. As always, Chief Financial Officer Tim Manners is here with me. We'll follow our usual sequence: I'll walk through the operational highlights for the quarter, then hand things to Tim for a more detailed look at the numbers. After that, we'll open the lines for questions. As you'll have seen, this morning we reported group production of 258,625 ounces for the financial year 2022. Within that result, a revised guidance range of 255,000 to 260,000 ounces was issued just over a month ago, only marginally below the original guidance we posted this time last year. As a reminder, that production guidance revision was needed largely because of some untimely rain events that affected haulage routes, along with continuing staff shortages tied to the labor market itself, COVID-19, and the flu season. All-in sustaining costs for the full year came in at AUD 1,523 an ounce, right at the top end of guidance, as the team did an admirable job in an obviously inflationary environment that has become more difficult each quarter. Turning to the June quarterly performance, the company produced 67,418 ounces at an all-in sustaining cost of AUD 1,564 per ounce for the period.

Mark Zeptner

executive
#3

In fact, it was the strongest production quarter across the entire financial year. Output was divided between the two production hubs as follows: Mount Magnet contributed 31,413 ounces at an all-in sustaining cost of AUD 1,374, while Edna May produced 36,005 ounces at an all-in sustaining cost of AUD 1,737. Now, when the Western Australian border reopened in early March, road train driver availability did improve as a result, and that led to a 20% quarter-on-quarter rise in all haulage rates from Marda and Tampia to the Edna May plant. As we know, that border reopening also came with a surge of COVID-19 infections, and this played a part in our haulage forecast for the June quarter coming in slightly below target. We've assumed haulage rates will ramp up gradually from these levels in FY 2023. To give some perspective on how COVID-19 affected staffing during the June quarter, we recorded almost 300 positive cases, plus another 88 close contacts who had to isolate for 7 days. That's out of a total workforce of around 1,000. So roughly 60-odd% of the workforce is still yet to be affected. Given the recent reports of short turnaround reinfections, working through this is gonna take some time.

Mark Zeptner

executive
#4

Turning to project development, we today revealed the inaugural mineral resource for the Rebecca Project, generated by Ramelius, located east of Kalgoorlie; that project came via the acquisition of Apollo Consolidated through the takeover completed earlier this year. Drawing on only 9,070 meters of infill drilling finished since February, Rebecca along with its satellite deposits, Duke and Duchess, is now estimated to hold 31 million tons grading 1.2 grams per ton, equating to 1.2 million ounces. Bearing in mind that we are merely partway through the drill program, with emphasis thus far placed more on infill holes than on extensional ones, we look forward to finishing the broader program so as to test the full potential of the Rebecca tenement package. This new resource does amount to a modest 9% lift in overall ounces, yet importantly, 85% of those ounces now sit in the indicated category, which I note has risen by some 22%. Confidence in the integrity of the resource is high. We still regard the wider Rebecca project as underexplored and anticipate further discoveries as our geological understanding develops. At Penny, capital development is progressing well following the portal firing in April. We are now nearing the first ore level of the Penny lode, and first production is expected this quarter.

Mark Zeptner

executive
#5

You might have noticed we got a nice surprise as development of the uppermost access drive moved forward, hitting a quartz vein 1 to 1.5 meters wide that we interpret as the southern continuation of the Penny North lode. Coarse visible gold was seen once within that vein. More work is needed to determine whether it is economic, but it sits roughly 90 meters south of where the resource boundary currently stands. It's a good problem to have, even if unanticipated, and we'll evaluate it down the track once our underground drill rig is on site. Turning to our mining studies, work continues on the Hill 50 underground scoping study at Mount Magnet, and geotechnical results so far have been encouraging. Regarding Edna May Stage 3, we carried out a review this March of the inputs used for the PFS during 2021, and the higher fuel price is, not surprisingly, a notable added cost burden. A new mine design has been produced, with the aim of obtaining pricing for this open pit from contracting and equipment leasing groups. That process should wrap up later this year, and a decision on where the project stands for development will follow. Development work on Stage 3 has to start in 2023 so we can meet the mine plan schedule delivered last year, under which meaningful production must reach the mill by FY 2026.

Mark Zeptner

executive
#6

Moving on to exploration. At the Bartus East Prospect at Mount Magnet, RC and diamond drilling keeps producing robust results, which points toward underground potential there. We should note that assay results are still pending from the deepest hole, which had visible gold in it. Over at our Galaxy project, specifically beneath the Saturn mine plan, recent drilling indicates the kinds of extensions we anticipate within the BIFs. The BIF units showing 6 meters at 6.8 grams, and the bottom of the hole also continues to cut a broader BIF breccia zone of 72 meters at 1.84, including 25 meters at 3.8, which could very well be the top of our new bulk mining zone. Lastly, before I pass things to Tim, guidance for FY 2023 has been set at 240,000 to 280,000 ounces at an all-in sustaining cost of AUD 790-AUD 990. At the midpoint of that range, Mount Magnet will contribute 150,000 ounces, and Edna May 110,000 ounces. In the current environment, we want to provide a wider range than previously on costs, while we've used a similar range for production as last year, to allow for what no doubt will be another somewhat unpredictable period ahead. I want to stress that we are working hard to maintain our margins in the face of inflationary pressures.

Mark Zeptner

executive
#7

For a number of years now, we've been ahead of our peers on this front, and letting go of our cost discipline mindset is not something we plan to do lightly. Tim will certainly have more to say about that. With that, I'll hand things over to you, Tim.

Tim Manners

executive
#8

Thanks, Mark. With the industry as a whole facing the very difficult operating conditions Mark described, it's good to see Ramelius turn in a strong Q4. Output of 67,480 ounces during the quarter brought full-year production to 258,625 ounces, landing us within 0.5% of the guidance we originally set, as Mark pointed out. Considering how heavily COVID and other knock-on events affected the business, we remain very pleased with that outcome. On top of that, we finished the year at an all-in sustaining cost of AUD 1,523 per ounce, keeping us within the upper end of our annual cost guidance. Once more, credit goes to every team across all our sites and here in the Perth office for another great result under these conditions. Reading the quarterly reports our peers have released so far makes one thing plain: the cost environment has genuinely shifted. That won't be news to anyone, but the real question, I suppose, is how long these elevated costs will persist and what we can actually do about them. Anecdotally, there is certainly evidence that costs have peaked, though only time will tell.

Tim Manners

executive
#9

We have built a strong record as one of Australia's lowest-cost gold-only producers, and I believe once this reporting season wraps up, our all-in sustaining cost will remain close to the bottom of that curve. Keeping that record intact over the coming years is the challenge, since inflationary pressures are making the near- to medium-term cost picture highly unpredictable, though with a clear upward underlying trend. Over recent years, Ramelius has put substantial effort into concentrating on the costs within our control. I mean the genuine underlying costs, not per-ounce costs, since grade will always sway those more than any other input cost. Considerable good work has gone into managing costs, and that effort must carry on. Grade is king and always will be, and its effect on every financial metric is plainly substantial. Mount Magnet has demonstrated this well, where alongside active cost management, a high-grade ore source has consistently featured in the blend, delivering those additional ounces and holding unit costs at the low end of industry figures. Vivian has provided a steady supply of low-cost ore at Mount Magnet for several years now, as more recently has the Shannon underground.

Tim Manners

executive
#10

We also saw some very good cost results as Eridanus got off to a stronger start than we had anticipated. The Edna May Stage Two open pit likewise turned out to be a really solid asset that beat our expectations when it wrapped up a year or two back. That let the processing hub stay cost competitive over a stretch of time, which in turn allowed us to add Marda and Tampia and lengthen the asset life. Against a backdrop of these elevated underlying input costs, grade remains the factor that comes to the fore and gives you the means to push unit costs lower, lift margins, and set one asset apart from another. For us, that asset is Penny. Even though we are guiding to higher all-in sustaining costs in FY 2023, those costs will probably be greater in the first half than in the second, since higher-cost development ore from Penny in H1 gives way in H2 to steady state development and stoping production cycles, which deliver very high-grade ore to the Mount Magnet mill. The genuine payoff, though, shows up in FY 2024 and 2025, when output from Penny is expected to nearly double the figure forecast for FY 2023.

Tim Manners

executive
#11

Since this will rank among Australia's best-grade, cheapest mines, we have confidence that Mount Magnet's all-in sustaining cost profile is going to come down and get back to the levels we're more used to. Now turning to revenue. During the quarter we sold 67,632 ounces, at an average price of AUD 2,508 per ounce. That average received price is a bit more than AUD 100 an ounce above the prior quarter, and it keeps reflecting two things: lower priced forward contracts running off, plus a spot price environment that remains strong. On cash flow, the operations contributed slightly under AUD 40 million of operating cash flow, along with underlying cash generation of AUD 12 million once CapEx, exploration, and resource definition drilling are accounted for. Consequently, closing cash and gold balance rose 5% to AUD 173 million. A quick hedge book update: over the quarter we brought total commitments down to roughly 196,000 ounces, carrying an average forward price of AUD 2,512 per ounce. RMS is still well-funded, with a healthy cash balance, more than 120,000 ounces of gold held in ROM stocks and GIC, and an undrawn corporate debt facility of AUD 100 million.

Tim Manners

executive
#12

We're still quite busy evaluating several business development options aimed at growing and enhancing the asset portfolio, and right now the emphasis is squarely on the possibility of picking up a third production center. With that said, I'll turn things back over to Mark now.

Mark Zeptner

executive
#13

Thanks, Tim. Before we take questions from the line, I'd like to briefly go over a few things. Ramelius delivered a strong FY22 result, with all-in sustaining costs that were competitive despite a difficult backdrop — both where cost inflation is concerned and on the labor shortage front. We expect FY23 output to be at comparable levels, though all-in sustaining costs will be higher, since some high grade feed sources are dropping off and there is a slight lag before the new low-cost Penny mine ramps up. In FY24 and 25 we will see the full benefit of Penny production, and we expect all-in sustaining costs to return to roughly FY22 levels. Exploration at Mt Magnet keeps delivering success, particularly at Bartus and the Galaxy project, and the new Rebecca project has seen a 9% increase in resources following relatively few new infill drill holes. Darcy, could you please open the line for questions?

Operator

operator
#14

Thank you. Should you like to pose a question, kindly press star 1 on your phone and hold until your name is called. To withdraw your request, press star 2 instead. In case you are on a speakerphone, please lift the handset before asking your question. Our first question is from Andrew Bowler of Macquarie. Please proceed.

Andrew Bowler

analyst
#15

Yes, thanks, guys. I believe you addressed my question regarding the early signs that inflation appears to have peaked. So, on to the next one: clearly, you discussed the way COVID affected trucking from satellite pits throughout the year. You also mentioned that reinfections might lead to a somewhat prolonged recovery from this skilled labor shortage. What amount of impact, or what amount of recovery in trucking rates, are you factoring in for FY23, or do you assume it stays fairly flat versus the Q4 exit rate from this year — in other words, that things won't improve much? Cheers.

Mark Zeptner

executive
#16

Thanks, Andrew. This is Mark. What we've done is take our actual results for quarter four as the starting point, with a steady increase over the course of FY23, and that's already reflected in the production figures we've given for FY23. Our expectation is that things will improve, though at a slow pace.

Andrew Bowler

analyst
#17

Right, I understand. Penny, as you laid out quite clearly, that should have a fairly significant effect on group costs. Is there any room to accelerate any of that, or is development at full capacity right now?

Mark Zeptner

executive
#18

We're going to be operating at maximum capacity. My expectation is we'll produce roughly 50,000 ounces in this year. Next year it's nearly twice that amount. That's simply how mining works and how the mining method we're required to use works — you have to complete the development first, and stoping follows after that. The team is dialed in. They understand how vital they are to this business, and they'll be extracting ore as fast, as efficiently, and as safely as they possibly can.

Andrew Bowler

analyst
#19

Nope, I'm finished. Appreciate it, Zeptner.

Mark Zeptner

executive
#20

Appreciate that, Andrew.

Operator

operator
#21

Thanks. Just a reminder — to ask a question, hit star 1 on your phone and hold until your name is called. Our next question is from Alex Barkley at RBC. Go ahead.

Alex Barkley

analyst
#22

Thanks. Morning, Mark Zeptner and Tim Manners. My question concerns next year's cost guidance. Clearly you performed strongly in this financial year and ended Q4 on a good note, which was certainly a solid result compared with some peers. We've noticed that increase in the FY 2023 guidance, I suppose, roughly 30% above the level you set 12 months ago. I'm just curious why that year's guidance shifted, even though, you know, you've done fairly well across the past 12 months.

Tim Manners

executive
#23

Alex, this is Tim. I appreciate the question. It's clearly a highly relevant one and something we care deeply about. Look, as you're aware, our business has several moving pieces. I'd say the primary factors are, of course, an ongoing—and we've built in an ongoing—elevated cost setting of this kind. Even so, I think, you know, there's anecdotal evidence suggesting it may have topped out. Hard to say. Our assumption is that it persists. That said, we do—we forfeit the advantage we previously enjoyed from having ore sources, as I noted, such as Vivian. At Magnet, we no longer have, you know, the genuinely high-grade Vivian ore in the blend. What's left of the underground is roughly a modest 3 to 4 g/t. We don't have Shannon underground, which we had last year and especially the year before, and that was truly a massive contributor to our unit costs. As you know, look, the leverage that grade provides is fairly substantial. Remove those from the operation, and even so, you substitute development ore from Penny, and you observe those costs genuinely starting to take effect. As we said, Penny will—we will reduce those unit costs in the second half compared with the first, as Penny really begins to find its rhythm.

Tim Manners

executive
#24

As we've mentioned, it won't be until FY 2024 and 2025 that Penny truly takes effect, and those costs will drop back down to what we're more accustomed to, I suppose. It's a mix of ongoing cost pressure and the loss, if you will, of one or two high-grade, low-cost sources.

Alex Barkley

analyst
#25

Alright, so when you established that FY 2023 figure a year ago, I mean, my assumption is you'd have been relying somewhat on the reserve life at Shannon and Vivian, which has the potential to extend. My guess is you basically stopped at the reserve. Were you forecasting somewhat more gold for FY 2023 than has actually turned out to be the case? I mean, I would simply have presumed that you already were aware of the gold declining in FY23. In fact, your gold projection for next year is essentially the same in guidance and level year over year. So I'm just curious how — is that a change?

Tim Manners

executive
#26

I mean, it comes down more to what products we're mixing, I'd say. And it's also the situation, you know, with certain operations — especially at Edna May — where we're genuinely beginning to reduce those stockpiles. There's what you might call a non-cash element embedded in those all-in sustaining costs as we work through those inventories. It's difficult to really spell out and disclose that kind of thing in documents like these, but we do have to account for those costs that benefited us previously. Look, these are small adjustments across several areas, honestly.

Alex Barkley

analyst
#27

All right, just one final question. Roughly when could you release a revised life-of-mine plan, so that we might get some updated figures within the next few years? Is that probably going to be scheduled alongside the Edna May PFS publication, simply so you have a clearer sense of what is going on at Edna May?

Mark Zeptner

executive
#28

Alex, following what you said last time, we're likely a bit cautious about releasing any fresh mine plans, since you'd return twelve months later and highlight the spots where we got it wrong. Now, look, that's something we're working on. I can't really offer a timing. Obviously, not a lot of folks have published beyond that. A few have even published for six months. Certain companies haven't even released forecasts at all. In today's volatile environment, we're probably somewhat wary of putting out something about which people will ask, "Well, how can you be sure that's going to be correct? What assumptions have you used?" That's something we're working on constantly behind the scenes, and then we'll inform you and the market once we're ready to release something. Hopefully at some point, this calendar year.

Alex Barkley

analyst
#29

All right, thank you so much, everyone.

Mark Zeptner

executive
#30

Appreciate that, Alex.

Operator

operator
#31

Thank you. As a reminder, should you want to pose a question, hit star 1 on your phone and hold until your name is called. We're going to take a brief pause now so any last questions can come in. At this point, we have no more questions. That brings today's conference to a close. Thanks for joining us. You're free to disconnect now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ramelius Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Ramelius Resources Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ramelius Resources Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.