Ramelius Resources Limited (RMS) Earnings Call Transcript & Summary

October 26, 2022

Australian Securities Exchange AU Materials Metals and Mining earnings 22 min

Earnings Call Speaker Segments

Operator

operator
#1

We appreciate everyone holding, and you’re welcome to the Ramelius Resources quarterly teleconference. Everyone joining is currently in listen-only mode. A presentation will come first, and after that we’ll hold a question and answer session. Should you want to pose a question, press the star key and then the number one on your telephone keypad. At this point I’d like to pass the conference to Mr. Mark Zeptner, Managing Director. Please proceed.

Mark Zeptner

executive
#2

Morning, everyone, and thanks for joining us on the call today. Chief Financial Officer Tim Manners is here with me, as he always is. We'll stick to our usual format. I'll walk you through the operational highlights for the quarter, drawing on the quarterly activities report that came out earlier this morning, and then I'll hand things over to Tim, who will dig into the numbers in more detail. After that, we'll open up the lines for questions. As you'll have noticed, we reported solid group production of 61,244 ounces for the September 2022 quarter, which matches what our internal forecasters had projected and keeps us firmly on track to hit our FY 2023 guidance range of 240,000 to 280,000 ounces. All-in sustaining costs for the quarter were AUD 1,930 an ounce, near the upper end of guidance, and this figure reflects a scheduled mill shutdown at Mt Magnet during the quarter as well as some meaningful sustaining-related development costs, which Tim will address shortly. Production was split between our two hubs as follows: 28,440 ounces recovered from Mt Magnet at an all-in sustaining cost of AUD 2,043, and 32,804 ounces recovered from Edna May at an all-in sustaining cost of AUD 1,833.

Mark Zeptner

executive
#3

In the quarter, we chose to take a number of subcontracted double road trains out of the haulage fleet based at Edna May. Those units had been there for several months, but their cost per ton was higher than the triple road train configuration we prefer, which our main haulage contractor supplies. Taking them out did cause a short-term capacity reduction in September, in particular. Happily, the haulage rate under our preferred, cheaper configuration has improved markedly since then. October is presently on course for a record of almost 138,000 tons, which will put us back above the rate that was planned at this stage in FY 2023. Hopefully the graph in the quarterly supports what I'm saying here. On COVID-19, we recorded 183 positive cases during the quarter, a 40% drop from the June quarter. In line with government advice, we saw certain requirements, including social distancing, pre-commute testing, and screening, relaxed late in the quarter, and our contact tracing system was switched off. It has been switched off, but we can easily turn it back on again if required. From a safety perspective, it was pleasing to see a further 13.4% drop in our total recordable injury frequency rate during the quarter.

Mark Zeptner

executive
#4

The safety initiatives we launched during the last twelve months are starting to pay off. It's a positive trend, but the two fatalities that happened recently at WA mine sites are a painful reminder that we can never be too vigilant in this area when it comes to ensuring a safe workplace. Our thoughts do go out to the family and friends of those two men. Turning to production, although Mt Magnet was slightly below that of Edna May in the September quarter, that balance will change over the course of the year as ore from Penny starts to factor into the mix in a bigger way. At the midpoint of guidance, we expect Mt Magnet to contribute 150,000 ounces this financial year, while Edna May will contribute the remaining 110,000 ounces. Development at Penny continues to progress well, with our quarter seeing commencement of the first ore drive level on the 1,390-meter RL. By the end of the quarter, the 1,390 north ore drive had progressed well past the known resource boundary, with grades averaging 11 grams per ton in the core of the resource and visible gold noted on a regular basis within the quartz lode. Decline development has continued, and we're now down to the second ore drive level and expect the ore body to get better as we get deeper.

Mark Zeptner

executive
#5

Rehabilitation work is declining at the Galaxy underground at Mt Magnet, and that brings us to quarter-end, close to where new development starts in order to reach the Mars ore body. A new long section has been put together for the Galaxy mine, showing Mars, Saturn, and the historic Hill 50 decline that we are using for access. With luck, that comes across more clearly for you. Several mining studies were progressed over the quarter, as is typical, and we acknowledge that interest is likely greatest in Edna May Stage 3. An open pit data package has been handed to a number of reputable mining contractors, and we anticipate responses during this December quarter. From that point we will reach a final development decision, since essentially the remainder of the PFS is finished at a satisfactory standard. Naturally, we are quite conscious that activity needs to get underway at some stage next year so the production schedule given in 2021 can be met. Review of the Hill 50 underground scoping study is at its final stage, and it will also be published this quarter. Turning to Mt Magnet, Vera's is developing well as one more possible way of extending mine life there. Assay results from recent drilling have all now come in, and that drilling included a substantial share of diamond drilling, which generally takes more time because of the core cutting that is required.

Mark Zeptner

executive
#6

Those results featured a refreshed resource model along with a mineral resource that increased by more than 800%, reaching 230,000 ounces overall. Roughly 150,000 ounces of that total sits within the higher grade core, which will likely be mined via bulk underground methods down the road. At Bardoc, we intend to speed up both drilling and study work, since at this stage it appears to offer a superior underground choice compared with Eridanus — partly because no open pit is being mined concurrently. Lastly, at Rebecca, our advanced exploration project, encouraging results keep coming in, and drilling continues there with one to two rigs at any given time. In a similar vein, we've reported some strong results at Hesperus, 11 meters at 55, at Magnet and Symes' Find, among them 5 meters at seven and 14 meters at nearly six close to Edna May. More specifics on all of that appear within the body of the quarterly report. With that said, Tim, over to you.

Tim Manners

executive
#7

Thanks, Mark. I think you could say Ramelius has had a strong beginning to the new financial year, with quarterly gold output of 61,244 ounces, which, as Mark mentioned, matched our internal expectations and positions us favorably regarding our FY 2023 production guidance. That output came at an all-in sustaining cost of AUD 1,930 per ounce, inside our cost guidance. Although at the top end of the range, that was anticipated given a planned mill shutdown during the quarter and substantial sustaining development spending at Mt Magnet tied to building the Orion pit, which will deliver valuable oxide feed to the plant. The Orion development costs on their own contributed AUD 275 per ounce to Mt Magnet's all-in sustaining costs for the quarter. That worked out to AUD 134 an ounce for group all-in sustaining costs. Because the Orion pit is comparatively small, the development costs under the guidance note for the all-in sustaining cost standard mean we must treat those costs as sustaining capital. Turning to revenue. Sales for the quarter totaled 59,750 ounces at an average price of AUD 2,460.

Tim Manners

executive
#8

That price came in a bit below the previous quarter's level, as spot prices moved downward late in the September quarter. In October, though, the spot price climbed back toward where it had been in the prior quarter. On cash flow, cash and gold rose by AUD 4.3 million across the quarter, with underlying cash outflow of AUD 2.2 million following investment of AUD 19.4 million in mine development and AUD 7.1 million in exploration. RMS is still well-funded, holding a healthy cash balance, roughly 130,000 ounces of gold contained in ROM stocks and GIC, and an undrawn corporate debt facility of AUD 100 million. Finally, a quick hedge book update. Committed ounces stayed fairly static through the quarter, with 193,250 ounces committed at quarter end at an average forward price of AUD 2,549 per ounce. With that, I'll hand back to Mark.

Mark Zeptner

executive
#9

Thanks, Tim. Andrew, could we go ahead and open up the lines for questions?

Operator

operator
#10

Thanks. To ask a question, hit star then one on your phone and wait for us to announce your name. To withdraw your request, press star and then two. Should you be using a speakerphone, lift the handset before posing your question. Our first question comes from Alex Barkley at RBC. Go ahead.

Alex Barkley

analyst
#11

Thank you. Good morning, Mark and Tim. Regarding that Bardoc resource, you're consistently reaching a fairly solid scale there. What kind of timeline do you have in mind as you move through the studies, and perhaps when might you be able to enter production? And could you possibly offer a remark about the grades you're observing there? It's 1.7 across the entire resource, 2.1 for that central higher-grade zone. Clearly it's early days, but, you know, is that sort of level sufficient on the economics to get it across the line? Thanks.

Mark Zeptner

executive
#12

Thanks, Alex. Yeah, we're still at a pretty early stage. That's the magic of geostats and resource models — they can take a mix of results and produce a grade that might come out a bit lower than you'd expect. We prefer to view our models as conservative, and that gives us a baseline to achieve against. On timing, I'd like to think maybe the same, around the middle of next year. By the end of the financial year, we'll sort of have some economics, some mine designs, and some further answers from new drilling. Then we shift into development decisions later next year. You'll need an open pit above the underground to provide portal access. It's really an underground target that we like to think remains open at depth and will keep growing from here.

Alex Barkley

analyst
#13

All right, that clears things up quite a bit. Appreciate it.

Mark Zeptner

executive
#14

Appreciate that, Alex.

Tim Manners

executive
#15

Appreciate that, Alex.

Operator

operator
#16

John Macdonald from Argonaut has the next question. Go ahead, John — your line is open, though you're muted on your side.

Mark Zeptner

executive
#17

I'm not getting that, Andrew.

Operator

operator
#18

Richard Hart from Top Wheel has our next question. Please proceed.

Richard Hart

analyst
#19

Thank you very much. Mark and Tim, thanks for the presentation. It's always a pleasure, and congratulations on the results you achieved during these difficult times. Regarding ongoing all-in costs, I'm just curious about where you stand. Well, there are two issues. I mean, there's power, and there's fuel. Do you have any hedging or contracts set up that offer us some protection on those, or are you simply at the mercy of the market?

Tim Manners

executive
#20

Richard, it's Tim. Right now we're examining whether it makes sense to hedge part of our diesel exposure. The forward curve for diesel is in backwardation, meaning forward prices sit below spot. So there's a chance to save some money, so to speak, compared with the internal diesel price estimates we're using today. That's a timely item we'll be taking up with the board tomorrow. As of now, no, we don't. We're fully exposed on those fronts, though it's something we're actively looking into.

Richard Hart

analyst
#21

Okay, so in a way, from where I sit, that's excellent. You know, I've consistently appreciated the conservative approach you take with hedging. Certain people might call it excessive, while others would argue it isn't sufficient. From an external perspective, it strikes me that the more you're able to at least grasp some of those variables, the more beneficial that could be. Then, if I may ask a second thing, it concerns Rebecca. I realize we're discussing production that's a couple of years out. For processing in that region, are we counting on an acquisition, or is that perhaps something you're unable to address? What I'm getting at is that right now it appears quite remote from anywhere, so eventually we ought to consider processing. Can anything be shared regarding that?

Mark Zeptner

executive
#22

Regarding that, Richard, the only thing I'll mention is that we bought Rebecca with the view that it could stand alone as a project. That's the assumption behind our numbers. Ideally, we'd want to expand the project — through exploration success in and around the tenements — so it reaches the sort of critical mass we think amounts to a million ounces that can be mined. Right now, we hold a million ounces in indicated. Not every bit of that is going to convert, but our exploration program is still only partway done, and it's aimed at building up what we believe can be a standalone project.

Richard Hart

analyst
#23

Wow, that's really impressive. So going standalone remains on the table. Thank you.

Mark Zeptner

executive
#24

Appreciate it.

Richard Hart

analyst
#25

I’ll stop there and not use up any more of your time. It was great speaking with you, and thank you for your presentation.

Tim Manners

executive
#26

Thank you, Richard. Appreciate it, Richard.

Operator

operator
#27

Larry Hill from Ames Asset Management has the next question. Go right ahead.

Larry Hill

analyst
#28

Morning, Mark and Tim. Great work on the quarter. Could you walk us through a little more of what sits on the critical path at Penny? Just pulling together that infrastructure and, you know, the decline — is that the critical path, and where would you sort of want to be in order to be scoping out first ore? Thanks.

Mark Zeptner

executive
#29

As we mentioned during the quarter — thank you, Larry — we've been mining the top ore drive quite effectively, and at this point we've moved down to the level of the second ore drive. So, as you know, the approach is top-down, and we're also currently upgrading the haul road so it meets the standard needed to run our preferred triple road trains with 100 ton capacity. That work is taking place this quarter. As a result, not much tonnage will come through in Q2. Q1 saw zero tons. Once you connect a couple of levels, you'll see stoping in the new year, and at that point you can establish your first stoping fronts. On the infrastructure side, you'll find the airport finished, along with all the surface infrastructure, and a primary fan is being installed right now. It's essentially complete. The camp has been up for some time, so at Penny we're ready to rock and roll.

Larry Hill

analyst
#30

Good. With the ventilation, is it running at capacity for your maximum tonnage, or does it ramp up as that comes online?

Mark Zeptner

executive
#31

From what I understand, the main fan will be required for the entire mine life as you presently envision it at Penny North. Clearly, we’ll need to extend our electrical reticulation system. The first underground substation is being installed shortly. As for ventilation, this isn’t a particularly deep mine. It won’t require a huge amount of ventilation. The primary fan we’re installing ought to last for the life of mine.

Larry Hill

analyst
#32

All right. Also on exploration spending, perhaps in relation to guidance. I realize you’ve had just one quarter so far, but will that more or less remain as you laid it out, without being affected by the somewhat weaker gold price?

Mark Zeptner

executive
#33

Nothing's shifted on that as of now. The AUD 25 million figure remains on schedule. We continue to hit gold. We'll carry on drilling holes. One thing I'm certain of: you won't discover anything without drilling holes. At this point, we're going to stay with our budget, Larry.

Larry Hill

analyst
#34

Alright. Thanks, everyone. Best of luck.

Mark Zeptner

executive
#35

Appreciate that, Larry.

Tim Manners

executive
#36

Appreciate that, Larry.

Operator

operator
#37

Ord Minnett's William Barlow has the next question. The floor is yours.

William Barlow

analyst
#38

Yeah. Morning, Mark and Tim. Appreciate you taking the call. Look, just to follow up on those questions about Penny, I was hoping you might give us a little more detail on the forage roadworks and, I guess, where— Along with, I suppose, being able to run your preferred triple road trucks, whether that haul road would likely hold up a bit better against any bad weather down the track.

Mark Zeptner

executive
#39

Yes, thanks—and thanks, Will. Unfortunately, roughly 100 km out of the 160 km route from Penny to Magnet is gravel. Making the entire stretch all-weather isn't realistic. At times, a storm or the tail end of a cyclone passing through will halt haulage briefly. The upgrade we're discussing concerns that 100 km. Within that 100 km, I believe around 70 km is already rated at the appropriate level to support those road trains. There's a brief 30 km section that will essentially need to be raised to that same standard and then receive approval from the shire and main roads. As you know, we have trucks on hand. Not many trucks are needed given the high grades involved. I think just two trucks will cover this requirement. It's simply a matter of completing those upgrade works, securing the sign-off, and getting started, which we anticipate happening during the quarter.

William Barlow

analyst
#40

Alright, thank you very much, Mark. Could you share any specifics regarding how much ore that involves?

Mark Zeptner

executive
#41

Based on what we see in development, it's roughly 10,000 tons. One could make the case that this material likely could have gone through the mill and might have given our quarter one result a modest lift, but we'd rather finish the road upgrade first so we aren't forced to haul using a shorter road train, which in effect raises your cost per ton. Where possible, we try to steer clear of that scenario. We do hold a small stockpile, yet going forward we'll generally operate the way we do at Vivian, so that at month's end, or especially at quarter's end, no high grade material stockpiles remain at the mine.

William Barlow

analyst
#42

Alright. That's great. Thanks a lot.

Mark Zeptner

executive
#43

Appreciate that, Will.

Tim Manners

executive
#44

Appreciate that, Will.

Operator

operator
#45

To repeat, should you wish to pose a question, press star followed by one, then hold until your name is called. We have no more questions at this point. I will return the call to Mr. Zeptner now for his closing remarks.

Mark Zeptner

executive
#46

Thanks, Andrea. Just to close things out quickly, Ramelius has delivered a strong quarterly result, and its cash and gold reserve have actually gone up compared with what isn't expected to be our strongest quarter in FY 2023. All-in sustaining costs, and CapEx too, are both projected to come down in the second half as the high-grade Penny operation shifts into stope production, which puts the company in a very strong position as we head toward the end of the calendar year. Exploration success continues across the portfolio, and as always we'll keep the market informed about progress on our mining study. Thanks for tuning in this morning, and enjoy the rest of your day.

Operator

operator
#47

That brings today's conference to a close. We appreciate your participation, and you're welcome to disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ramelius Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Ramelius Resources Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ramelius Resources Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.