Ramelius Resources Limited (RMS) Earnings Call Transcript & Summary
January 24, 2023
Earnings Call Speaker Segments
Operator
operatorWe appreciate everyone holding on, and we’re glad to have you join the Ramelius Resources December 2022 Quarterly Teleconference. <<operator_script>> At this point I’ll pass the call to Mr. Mark Zeptner, Managing Director. Please continue.
Mark Zeptner
executiveThanks, Winnie. Morning, everybody. Appreciate you joining us a bit earlier today. We hope this timing doesn't put us up against too many other calls. Chief Financial Officer Tim Manners is here with me again. As usual, I'll walk through the operational highlights for the quarter, referring to the December 2022 quarterly activities report that was released on the platform this morning, and then I'll hand things to Tim to dig into the numbers in more detail. After that, we'll take questions from the line and wrap up with some closing remarks. As most of you, if not all, will know, earlier this week we also put out a significant announcement regarding the deferral of the Stage 3 open pit at Edna May. As we said at the time, that decision came down to keeping a disciplined approach to capital investment rather than simply looking to fill out a production profile with ounces that fail to meet our financial return criteria. By carrying on with the environmental permitting processes for the project, we stay ready to revisit it if key economic variables shift, which gives the company optionality over a large mineral resource right beside an operating mill.
Mark Zeptner
executiveShould you have any questions regarding any of the specifics shared about the Stage 3 announcement, we'd urge you to raise them with us once the line becomes available later during this call. To repeat, postponing the Stage 3 project has no impact on the 3-year production outlook the company published in November last year, which demonstrates a steady output profile of 240,000 to 290,000 ounces of gold annually and likewise reflects our declining all-in sustaining cost trajectory. Returning to the quarter now. Strong gold production for the period reached 56,756 ounces at an all-in sustaining cost of AUD 2,153 per ounce, and gold sales ran 4% above the prior quarter at slightly more than 62,000 ounces. Operating costs rose at both of our production centers during the quarter, with Mt Magnet hit negatively because fewer higher grade feed sources were available as the Shannon and Vivien underground operations wound down, combined with the continuing ramp-up of haulage from Penny, and Edna May was affected by lower grades from the underground plus the greater sustaining capital spent on the plant. Mill throughput at Mt Magnet rose as anticipated in the prior quarter thanks to the introduction of oxide feed from the Orion open pit, and 458,000 tonnes in total was processed.
Mark Zeptner
executiveAt Edna May, milling volumes came in below the prior quarter—roughly 493,000 tonnes processed—because the historic low-grade stockpiles close to the mill have been depleted. As we've noted before, all-in sustaining costs should improve in the second half of the financial year, helped by more ore tonnes coming from the high-grade Penny mine. That effect really begins to take hold after the haul road upgrade wraps up in February, which will let triple road trains move bigger ore loads to Mt Magnet for processing. So far, less than 10,000 tonnes of ore was hauled from Penny during the quarter using smaller double road trains, and that barely reduced the stockpile last quarter—the stockpile will keep building until triple road trains come in later this quarter. We note that 7,000 ounces of gold at Penny are currently ready for hauling to Mt Magnet. At a gold price of $2,750, that comes to about $17 million in net revenue, which has not yet shown up in cash flows. Still on the topic of ore haulage.
Mark Zeptner
executiveOn a positive note, ore hauled from Tampia and Marda to Edna May rose 13% versus the September 2022 quarter, even with a Christmas-period slowdown tied largely to that familiar culprit, COVID, which flared up late in the quarter. So far in January, haulage has picked up markedly from December, and extra drivers will soon be available from the Vivien haulage route as well, which is a good sign for the second half. In fact, the extrapolated number shown in the quarterly's chart draws on the average daily haulage rate through the 22nd -- sorry, the 23rd of January -- to produce a monthly figure comparable to what was achieved in October '22. Should we instead apply the daily average from haulage's final week, we would come in exactly at our budget rates of roughly 140,000 tonnes, shown as the dotted line for anyone with access to the report. Also worth flagging is that Tampia beat expectations in the December quarter, with the operation posting its strongest quarterly mining result: 457,000 tonnes at 2.26 mined, for more than 35,000 ounces of contained gold. And by quarter's end, nearly 1 million tonnes of ore feed sat stockpiled at the mine, ready to be hauled to Edna May.
Mark Zeptner
executiveMining-wise, Vivien and Penny also deserve a mention. Vivien was run for 7 years—far beyond what was originally intended—and on the 11th of January it hauled its final truckload of ore up to surface. By month's end, the surface stockpiles will be moved to Mt Magnet, and reclamation of the surface has begun. On a provisional basis, 260,000 ounces have come out of Vivien, which began with an ore reserve only slightly above 100,000 ounces. More reconciled figures will be given next quarter, but we wanted to express thanks to the Vivien team—many of them have retired within the business—for their work at what has effectively been a great mine for the company. We think Penny will do even better. In fact, many management and technical staff have very recently shifted from Vivien over to Penny. While ore driving is still underway at Penny at present, we're stoping to Vivien shortly. It's encouraging for all of us to see 21-gram faces such as the 1 in the quarterly. On the project side, development of the Galaxy Mine at Mt Magnet continues, with lateral development now commenced across to the Mars hallway, along with upgrades completed on the power and pumping systems.
Mark Zeptner
executiveWe’re speeding up the Symes project near Edna May to the greatest extent we can, and applications for the mining lease and mining proposal are still pending. In addition, work is proceeding on the Rebecca project pre-feasibility study, and within the next 5 to 6 months we’ll be in a position to give a clearer timeline for ultimately developing that project. With that, I’ll now pass things over to Tim.
Timothy Manners
executiveThanks, Mark. As you noted, quarterly gold output came to 56,756 ounces, while gold sales totaled slightly more than 62,000 ounces. Those ounces went out the door at an all-in sustaining cost of $2,153 per ounce. Now, even though the physicals fell short of what we had expected internally and costs came in higher, we're still on track to hit our full-year guidance on both of those key metrics. Obviously, we'll need a strong second half, but that's been the story all along for FY '23, and our latest internal forecasts reinforce our confidence that guidance will be met. As Mike said, in quarter 2, Mt Magnet was affected a bit by delays at Penny — specifically the haul road upgrade — but mostly because of the shrinking contribution from 2 high-grade, highly profitable sources, Shannon and Vivien, which are now essentially finished. While a full life of mine review of these mines hasn't been carried out yet, we know both delivered substantial financial returns to the company. And although Penny will be an asset that more than makes up for their completion, the high-grade underground isn't quite ready to deliver that contribution. The Penny mine, though, is coming along nicely, and the ore body seems to be performing as expected.
Timothy Manners
executiveLike we've mentioned before, we're currently hauling material to the mill at Mt Magnet, though right now that's happening at a slower pace as work continues on upgrading the haul road. We expect the volume of Penny ore hauled and processed at Magnet to rise in quarter 3, then climb again in quarter 4, reaching what we'd anticipate as the steady ongoing rate of roughly 20,000 tonnes each month. Costs this quarter came in above both the previous quarter and our internal forecasts. Although cost pressure has eased somewhat on certain inputs, diesel being one example, the largest single source of cost pressure is still people — having enough of them available, plus the inefficiencies and disruptions caused by the turnover levels that we, our peers, and our contractors are all dealing with. On a brighter note, the gold price is trending favorably. And while broader market and economic conditions still support an optimistic outlook on the U.S. dollar gold price, the U.S. dollar's own strength is less helpful and arguably harder to predict. So how the AUD gold price behaves across the short to medium term is still tough to call. That said, RMS's achieved sales price climbed 4% versus the prior quarter, hitting $2,536 per ounce — reflecting both better spot pricing and improved hedge book deliveries during the quarter.
Timothy Manners
executiveWe keep actively managing our price risk by settling each hedge contract progressively as it comes due, and by adding ounces whenever we observe the AUD gold price moving upward. Because of that, hedged physical, which has stayed fairly steady for roughly 18 months now, stood at 202,000 ounces at the close of December. Even so, our average price keeps climbing. By the end of December, the hedge book's average price was $2,606 per ounce. The majority of contracts added lately have fallen in the $2,850 to $2,950 per ounce band. That underpins a main rationale for hedging: letting our operations and technical teams plan and design new projects with greater certainty about a minimum achievable gold price. And my final point: the cash balance for the quarter declined $10.8 million, and the value of gold on hand dropped by about $12.4 million. Although the operations produced roughly $15 million of cash flow, several key expenditure items offset that. $7.2 million went to shareholders as a fully franked dividend for the last financial year. A bit under $20 million was used for nonsustaining capital, covering things like Die Hardy, the next open pit at Marda, and also at Penny; almost $8 million went to exploration and resource definition; and working capital also came down slightly, which a tax refund of a similar size offset.
Timothy Manners
executiveEven though we saw a modest decline in cash and gold, our financial position is still very strong, with $154 million in cash and gold and a fully committed, undrawn debt facility of $100 million. That's quite healthy, but we still look forward to strengthening that cash position through a better second half of this financial year. Thank you everyone for tuning in today. I'll now return you to the operator for any questions. Thank you.
Operator
operator<<operator_script>> Our first question is from Paul Kaner at Ord Minnett.
Paul Kaner
analystRegarding the different elements in play at Edna May, I'm simply trying to get a feel for how the production profile will shape up during the second half of this financial year. I mean, grades declined somewhat this quarter. But perhaps you could just comment on what you expect grades and throughput to do over the second half of this financial year?
Timothy Manners
executivePaul, Tim here. I believe we indicated during the quarter that we still expect Edna May to deliver roughly 110,000 ounces for the full year, which is, I suppose, the midpoint of our guidance. It's produced, I guess, 60,000, I think, for the first 6 months. You're looking at about 50-odd for a midpoint second half. I think the -- you'll probably get a similar sort of trend, I think, as Mark mentioned, largely depleted the low-grade stockpiles at Edna May. So the feed really does comprise Marda, Tampia and the underground. I don't have the exact numbers in front of me, but I will be working off sort of a similar -- maybe a slightly lower tonnage figure and a similar grade as we've seen in the first half. I don't think there'll be a dramatic difference from that first 6 months to the second half.
Paul Kaner
analystThat's right, pretty straightforward. And then we may simply shift over to Mt Magnet, with Penny ramping up properly there once the haul road is finished. My recollection is that you mentioned 20,000 tonnes a month coming from Penny after that haul road completion.
Mark Zeptner
executiveYeah, that's right, Paul. The full production rate sits at roughly 20,000 tonnes each month, and from a mining standpoint that ought to be in place by March, with haulage coming in a little after that. So yes, you should be looking at hauling 60,000 tonnes and mining 50,000 tonnes, more or less, per quarter from Penny. We clearly hauled 10,000 during the last quarter, so I'm just pointing out what lies ahead for Penny and how big that's going to be.
Paul Kaner
analystRight. So for the March quarter, once that haul road is finished in February, you'd be looking at 20,000 tonnes there. And then, from the haulage that's already in place, how much would you have now?
Timothy Manners
executiveAs things stand, we're operating at roughly that 10,000 to 15,000 tonne type rate. So once the upgrade finishes, you're correct. We'll move essentially to triple road trains, and on an annualized basis we'll be running at that 240,000 tonnes per annum rate. I suppose the question hinges on when we switch from doubles to triples as the road gets completed and approved. It's hard to say with certainty precisely when that date will land, but I think we'll see that through Q3, we'll keep running doubles for as long as we can and bring triples in as soon as we can. And then Q4 will be, I'd imagine, a purely triple structure at that 20,000 tonne per month rate.
Mark Zeptner
executiveTo clarify that point, Paul: doubles aren’t two-thirds of a triple. In effect, a double carries a 50-tonne load, while a triple carries 100. That means with triple road trains you can move twice the tonnage. So for quarter 3, we could do 30,000 tonnes rather than 60,000 with triples. We did 10,000 last quarter because we began hauling the doubles in December, at roughly the same time the road update started. So that gives you a bit of color there.
Paul Kaner
analystYes. No, that's really helpful context.
Operator
operatorOur following question is from Andrew Hines at Shaw and Partners.
Andrew Hines
analystI have a couple of questions. First, regarding Mt Magnet and the Penny ore that's coming in — is the Penny ore body fairly consistent when it comes to grade? Or should we expect some grade variability as you ramp up, with either higher or lower grade early on? Second, about the choice not to proceed with Stage 3 at Mt Edna, I see that your 3-year plan is obviously unchanged and this doesn't affect it. But clearly there are some implications here for Edna May beyond '25. And obviously it's still a fair way off, but I'd be interested in your early thinking on what options you have to keep that mill and that infrastructure full if you don't move ahead with that Stage 3.
Mark Zeptner
executiveOn the grade at Penny, I'd say it's about as uniform as a gold ore body gets—which isn't saying much. You'll notice that the larger tonnage hauled to Mt Magnet so far, along with the stockpile grade, runs a bit below the reserve average, and that comes down to being at the top and on the edges of the ore body with your ore driving. So you're picking up more dilution, typically, than you would from a stoping perspective. That's what we'd expect in this early phase. Once we're fully into stoping, we ought to be sitting around 15 grams per tonne. Right now we're closer to 10 or 11, but I take encouragement from the 20-plus-gram faces starting to show up just on the third level down, if you look back at the long section. On Stage 3, yes, look, we did have some time, and we did—we will examine options in the area to extend life, both within our own portfolios at Holleton and elsewhere in the region. Southern Cross isn't too far away, for instance. We did make the comment—I believe we were asked the other day—that Edna May Stage 3 currently offers the longest life potential, but that doesn't mean we won't look to add a year or 2 here and there, which again buys more time for Edna May Stage 3 to potentially return at a later date under the right economic conditions.
Operator
operatorThe following question is from Stephen Matthews at Westcap.
Steven Matthews
analystReaching a native title agreement is often a fraught process. Could you give us some clarity on Rebecca and the reference to progress on a native title review and application?
Mark Zeptner
executiveAt Rebecca, we have 2 mining leases. One of them has already been granted, and the second — effectively a much smaller extension to the lease that's been granted — is subject to native title. So we're in the process of building a relationship with the native title group and working through that process, and all of that will form part of the sort of Gantt chart timeline for developing the Rebecca project. So no agreement is in place, and we didn't inherit one, but we'll be working toward having one going forward.
Operator
operator<<operator_script>> Our following question is from Richard Hart of Top View.
Richard Hart
analystOnly a single question from me. I noticed the numbers that came out this morning from the Mt Finnerty joint venture. I know laboratories have been facing substantial hold-ups. So first, I'm curious whether that situation is getting any better at all. Second, could you give me a general sense of which findings you're still waiting for that stand out as especially important?
Mark Zeptner
executiveThanks, Richard. This is Mark. I don’t really have the sense that the sample turnaround has improved all that much. When you’re going to drill a diamond drill hole, you have to drill it, get a cut, get it to the lab, and you’re talking about something like a 24-month process. Obviously, I’m not aware of significant results that are coming. We don’t release them for every hole we get; instead, we release them in what I’d call reasonable batches. Otherwise, we’d be updating the market for pretty much every hole. We don’t think that makes sense. But I’m not aware of. And I think it’s outstanding that they’ll come in from all parts of the portfolio as they come in, but there’s quite a lag, as you’d appreciate.
Analyst
analystRight, okay. When I mentioned that significant ones come in, obviously you can't know something is significant until it shows up. I was only attempting to get a sense of whether there was anything you folks were especially excited about and waiting on that result for. But I'd guess you won't tell me, so that's fine.
Operator
operator<<operator_script>>
Mark Zeptner
executiveIt seems there are no further questions. So thank you, Winnie. As we close, I want to highlight three things. First, Ramelius reported a quarterly result broadly in line with Q1, as we anticipated, though the absence of hauling and processing of Penny material gave an appearance that was worse than the underlying reality. At Penny, we have roughly $17 million of ore that is ready for trucking to Mt Magnet, and by Q4 we will reach full mining and hauling run rates. On haulage rates — this concerns Edna May haulage rates — although Q2 was an improvement over Q1, a rather weak December took some of the shine off. Even so, figures for January to date indicate, or back up, that we are back on track, and shortages of road train drivers are steadily becoming less of a problem. And third, we have demonstrated capital discipline through our recent choice to defer Edna May. With our mission of delivering superior returns, we believe this provides investors the certainty they were seeking and lets us concentrate on delivering the cash flows anticipated from the existing portfolio. Thank you for joining us today, and enjoy the rest of your day.
Operator
operatorThat brings today's conference to a close. We appreciate everyone for joining in. You're welcome to disconnect at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ramelius Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Ramelius Resources Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ramelius Resources Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.