Ramelius Resources Limited (RMS) Earnings Call Transcript & Summary

February 20, 2024

Australian Securities Exchange AU Materials Metals and Mining earnings 25 min

Earnings Call Speaker Segments

Operator

operator
#1

At this point, I'd like to turn the conference call over to Mr. Mark Zeptner, our Managing Director. Please proceed.

Mark Zeptner

executive
#2

Good morning, everyone, and thanks for taking the time to join our half year results call. With me again this morning is Acting Chief Financial Officer, Ben Ringrose. Since today's focus is on the financial accounts, I'll let Ben handle most of the talking, particularly regarding the presentation that was released to the ASX this morning, before we open up the line for questions, as always. Before I hand over, I'll give an overview of how we saw the first half. As an overall assessment, we believe this is a very competitive set of underlying results, with improvement seen pretty much in all key metrics when compared to the prior corresponding period. The company continues to be in a strong financial position, despite the continuation of a challenging labor market and inflationary pressures seen throughout the industry in the second half of 2023. In terms of production, as we announced late last month, total gold produced for the six months to 31 December came in at just over 124,000 ounces, up slightly on the prior period. Based on the half year production result and our expectation of an increasing production profile in the second half, we remain confident of meeting our upgraded full-year guidance of 265,000 ounces-280,000 ounces at the cost of between $1,750 and $1,850 an ounce.

Mark Zeptner

executive
#3

If everyone could go to slide three in the deck, that shows the five-year production profile, and right in the middle, FY 2024 is expected to be a record production year. That's record output from our asset portfolio, which you can see in the production chart breakdown on the left and, clearly, on the map on the right. Here we run a dynamic asset mix, and that same mix gives us some production flexibility. Moving on to slide four, which has the key physical production figures for the half: all tonnes mined were lower, which doesn't worry us, since we hold more than 4 million tonnes in stockpiles. More significantly, though, grades for both mining and processing have risen. Combined with slightly better mill throughput, achieved even with the CV01 conveyor repairs at Mount Magnet, that produced more gold. Another point on this slide is our second half FY 2024 guidance bars in aqua blue. There we anticipate an increase — a material increase, in fact — in gold output and a matching decline in all-in sustaining costs for the second half. I think those figures speak for themselves. With that, I'll hand things over to Ben.

Ben Ringrose

executive
#4

Thanks, Mark, and thanks once more to everyone for being with us this morning as we present Ramelius Resources' financial results covering the six months that closed in December 2023. These are genuinely robust financial numbers, since every key metric shows a favorable comparison against the equivalent period a year earlier and keeps extending the momentum of our strong second half in FY 2023. On the broader economic side, although cost increases have been rising at a slower pace, they are still elevated. Encouragingly, though, we are seeing that the labor shortages encountered previously have loosened somewhat since the new year arrived. Against that backdrop, high-grade ore sources like Penny are the ones that will distinguish themselves, and Mount Magnet stands to gain further through integrating the Cue Gold Project, which offers a rapid pathway into development and production. Given how close Cue sits to Mount Magnet, most of the infrastructure needed for Cue already exists, and our goal is to be in a position to bring out a fresh mine plan for Mount Magnet that folds in Cue during this quarter. Before I turn to the presentation, I will spend a moment on how operations performed across the half year. At Mount Magnet, open pit mining recorded significant gains not only in tonnage but in grade as well.

Ben Ringrose

executive
#5

The following comes from mining at Eridanus, our primary source of open pit ore. As we move forward, this pit has moved beyond the known lower grade section of the ore body, and we see that trend carrying on into the second half. Adding to this are the excellent deeper drill results at Eridanus, which came out in the December quarterly. Underground operations at Mount Magnet concentrated on developing the Galaxy mine, which will supply steady feed over the coming years. That had a knock-on effect on tonnages, which declined versus the prior period. Still, with Penny contributing more, the mine grade rose 50% to 5.7 grams. In fact, looking at Penny on its own, the mill grade for the period was an impressive 11.7 grams, achieved even though most of the feed was development ore. With several stoping areas coming online in the second half, we expect Penny's grade to rise to reserve levels. H2 guidance for Mount Magnet sits at roughly 85,000 ounces, up from H1, and that gives full-year guidance of 150,000 ounces. That represents a 17% gain on FY 2023, delivered through growing contributions from Penny and rising grades at Eridanus.

Ben Ringrose

executive
#6

Now shifting our focus to Edna May, where Symes was brought into production during the period, giving us an extra high-grade ore source. At Symes, mining concentrated on the shallower satellite pits, and a substantial stockpile built up. Operations have since transitioned to the deeper main pit at Symes, which together with the stockpiles will supply feed to Edna May across the whole of the 2024 calendar year. Importantly, stockpiles across the Edna May hub now stand at 1.3 million tonnes grading 1.6 grams. Underground operations at Edna May went beyond the levels we had expected, and the water problems encountered late in FY 2023 are now under control. Development work there is finished, and operations are now entirely focused on harvesting what remains of the ore body. That has produced a noticeable rise in tons mined relative to the prior reporting period. With Symes added as a third haulage route and better underground tonnages, mill throughput at Edna May rose 4% versus the prior period. Guidance for Edna May for the second half of FY 2024 sits at approximately 65,000 ounces, which is again an increase on the first half, and gives FY 2024 guidance of 122,000 ounces, an 8% increase on the prior period.

Ben Ringrose

executive
#7

Back to the presentation, slide five. There you can see Ramelius posted record half-year revenue of just under AUD 350 million, driven by strong gold output and a better gold price averaging above $2,800 an ounce. EBITDA at the group level came in at slightly more than AUD 140 million — a 40% rise versus December 2022, with an impressive 40% margin. Peer results are still coming out, but we think this will stack up very favorably. EBITDA grew as Penny's contribution expanded, and that asset delivered a margin above 70%. With an standout asset like Penny, other operations can easily be overlooked, yet it's worth highlighting here how Symes performed and how important it is to Edna May. Symes delivered EBITDA of AUD 20 million at a 65% margin — a stellar result, I'm sure you'll agree, for an asset we acquired for AUD 2 million. On to slide six, where earnings by operation show the weighting toward Mount Magnet, as we'd expect given it's our flagship asset, plus Penny's contribution. Mount Magnet's EBITDA is 54%, or more than AUD 1,500 an ounce, leaving Ramelius with a positive earnings outlook that will only be strengthened further once Cue is added.

Ben Ringrose

executive
#8

Looking at gross profit, operating costs at Mount Magnet came in at AUD 154 per ton, and that figure carried a sizable D&A charge tied to the Penny acquisition. Thanks to the higher mill grade, the cost per ounce at Mount Magnet worked out to AUD 2,000, which is a 7% reduction compared with the prior period. Still on slide six, turning to Edna May, operating costs there were AUD 121 per ton, reflecting higher costs as more tons were hauled to the mill. Cost per ounce at Edna May was AUD 2,300, and the operation keeps delivering solid returns for the business. For the group, NPAT came to AUD 41.2 million for the half year, up 42% on the prior period. Moving now to the company's cash flow on slide seven. We reported underlying cash flow of just over AUD 52 million, which includes the rise in the value of gold on hand, and that marks our second consecutive half-year period with underlying cash flow above AUD 50 million. Operational cash flows for the half year, including the larger bullion holdings, totaled AUD 121 million, and AUD 90 million of that went into mine development, exploration, and the acquisition of Cue.

Ben Ringrose

executive
#9

Once you factor in the AUD 17 million dividend paid to shareholders during the period, along with the AUD 19 million net cash outflow tied to buying Cue, we closed with a cash and gold balance of AUD 282 million. We anticipate cash flow will be especially robust through the rest of the financial year, helped by growing contributions from Penny, high-grade ore from Eridanus, and monetization of stockpiles throughout Edna May. Anyone who tracks Ramelius knows we've put money into this business wisely over the years, and we're now moving into a very powerful phase of cash generation as those earlier investments pay off. My last slide is slide eight, covering the balance sheet, which ranks among our most important assets. It has never been in better shape, and that's not just because of our cash and gold balance and our debt-free position — we also hold substantial ore stockpiles, which provide Ramelius with security of ore feed for years ahead, plus a strong outlook for cash generation. Our working capital stands at AUD 294 million, including trade and other payables of AUD 72 million, which takes in AUD 14 million of stamp duty related to the Breaker and Musgrave acquisition, an amount we expect to settle during this calendar year.

Ben Ringrose

executive
#10

That leaves us with an actual payables balance of AUD 57 million, equivalent to 36 creditors' days. Mining and haulage contractors are central to how we operate, and we take real pride in managing creditors carefully. One last balance sheet item before I move on: group net assets have increased to more than AUD 1 billion. That is quite a milestone, considering they stood at AUD 170 million when I joined in 2017. At present our hedge book stands at 192,000 ounces, at an average price above $2,900 per ounce. Going forward, you will observe a faster decrease in that position. More information will come in the next quarterly report, though we anticipate the book will be nearer 160,000 ounces by 30 June. So, before I hand back to Mark, the key financial points here are plain. AUD 282 million in cash and gold, which we expect to rise as the second half progresses, ideally finishing at roughly AUD 400 million by 30 June. We carry no debt, hold AUD 100 million in available finance facilities, and have more than 145,000 ounces of gold in stocks and in circuit, with a book value of slightly above AUD 200 million, but importantly, that will produce cash flow far beyond this figure, especially given today's gold prices.

Ben Ringrose

executive
#11

That said, I'll turn things over to Mark now for the closing summary.

Mark Zeptner

executive
#12

Thanks, Ben. I'll do my best not to lose my place again this time. We're on slide nine, and I want to summarize why we believe we're positioned so strongly, not just for 2024 but for the future as well. Briefly, the management team that has delivered such strong results for us over the years remains largely intact. I think that's quite an achievement given today's labor market. As Ben mentioned, we have the strongest balance sheet in our history, and we stay disciplined when it comes to any investment decisions. We continue to give strong support to greenfields and brownfields exploration, and we expect to keep adding to our resource base, as highlighted in the recent RIU presentation by our EGM Exploration, Peter Ruzicka. As we've mentioned for some time, watch for the new Mount Magnet mine plan this quarter and the Rebecca-Roe PFS closer to midyear. Thanks, Harmony. With that, let's open the line for questions, please.

Operator

operator
#13

Thanks. If you'd like to ask a question, hit star one on your phone and hold until your name is called. To withdraw your request, press star two. Should you be using a speakerphone, kindly lift the handset before posing your question. Our first question is from Hayden Bairstow at Argonaut. The line is yours.

Hayden Bairstow

analyst
#14

Good morning. Morning, guys. So I have just a couple of questions for myself. First, regarding Rebecca-Roe, I just want to get a sense of the range of outcomes and how feasible it is. So not so much about CapEx and all of that, but more about timing. I mean, what are your thoughts on how much work is needed on the project itself and then also the entire approvals process?

Mark Zeptner

executive
#15

Thanks, Hayden. So, at Roe, we are continuing to drill, especially the underground Tura lodes and the Northern Flat lodes. The goal is to turn inferred resources into indicated resources. As you can see, the Roe side of the project lags behind Rebecca, where a good amount of drilling has already been completed, and at Rebecca we are actually searching for water sources. On the other elements a PFS needs, we are quite far along. Work on the approvals process has already started. My belief is that we will aim to lodge it later this year. There are, broadly, two routes. We have taken the worst case as our assumption — a Part IV assessment rather than a Part V — and the gap between them is roughly 12 months. Clearly, we will be in a position to give the market much more detail on timing around the time of the PFS itself, near mid-year.

Hayden Bairstow

analyst
#16

Alright, sure. So turning to Magnet — I’d just like to get a sense, as you start working with these Cue assets, of the breakdown between tonnage from open pits and from underground, in terms of feeding that 2 million ton mill. What does that look like — is there likely to be some shift there? Obviously Penny is still delivering decent grades and remains the key focus, but I’m just keen to understand how that mix might shape up.

Mark Zeptner

executive
#17

Well, look, Hayden, without being able to quote specific figures, the highest grade obviously gets fed first, so Penny will always be first in the sequence. Cue is really — it's mostly open pits for at least the first four or five years. So those open pit tonnages will largely take the place of Eridanus and Brown Hill. Then the balance will be topped up by the underground operations at Mount Magnet, which, by the time Cue is up and running, will largely be Galaxy. So we'll be swapping out Eridanus, let's say 1.2 grams, 1.5 grams, for potentially 4-gram open pit material. Probably not at the same volumes from Cue, so there will still be some make-up tonnage from stockpiles. As I said, I can't give you the numbers, but, you know, we're looking at some very strong gold production out of Mount Magnet in FY 2025 when Cue comes in.

Hayden Bairstow

analyst
#18

Okay, that's great. Just one last thing. Could you confirm the timing for me? You may have said this at the beginning — specifically regarding when the Mount Magnet plan comes out and then the PFS for Rebecca.

Mark Zeptner

executive
#19

Yes, Hayden, for this quarter. Thanks. That's right.

Hayden Bairstow

analyst
#20

Both of them?

Mark Zeptner

executive
#21

No — for this quarter, I mean the Mount Magnet mine plan. What was the other one again? Sorry, I didn't catch it.

Hayden Bairstow

analyst
#22

Rebecca from PFS.

Mark Zeptner

executive
#23

Oh, Rebecca’s halfway through the year.

Hayden Bairstow

analyst
#24

All right, that's great. Appreciate it, everyone.

Operator

operator
#25

Appreciate it. Moving on, our following question is from Andrew Bowler at Macquarie. The line is yours.

Andrew Bowler

analyst
#26

To pick up where Hayden left off regarding Rebecca — clearly we're moving toward the PFS — I just wanted to ask how you're approaching funding for that project. Obviously, you're entering a fairly robust stretch for cash generation. Given that, and with the dividend payout of as much as 30% of free cash flow, are you thinking about keeping the dividend rhythm steady in light of the funding need coming up at Rebecca? Or are you exploring alternative routes to finance Rebecca?

Mark Zeptner

executive
#27

Honestly, right now funding hasn't really been something we've spent much time thinking about. I believe we'll be well positioned to have plenty of alternatives on that front. As for how the divvy is paced, without speaking on behalf of the board and before any choices get made on it, we'd be looking to, first, provide a sustainable dividend that we then build on. That said, with AUD 400-odd million sitting in the bank and robust cash flows coming through into FY 2025, we'll have no shortage of alternatives, including the facility Ben referred to. Those calls will get made when the time comes. The priority is to deliver the study, and make those decisions from there. Still, we do hold a number of alternatives, Andrew.

Andrew Bowler

analyst
#28

No, okay. And regarding Penny, I believe you mentioned that stoping tonnes will ramp up during the second half, and you expect grades to move toward reserve level. Could you discuss the kind of variability in grades you anticipate there over roughly the next year? Or, once you reach that reserve level, do you expect fairly consistent performance from that operation?

Mark Zeptner

executive
#29

Andrew, regrettably — and I do mean regrettably — my expectation is that the reserve grade will be the average, though you'll notice some unevenness. Some daily reports, for instance, have shown 20 grams per ton, and other days will come in at 7 grams. It hinges on the section of the ore body being mined. Mining the narrow ends gives you a lower grade. Mining directly in the core of the ore body gives you higher grades. I would love to tell you it's a steady 14 grams, 15 grams daily. Regrettably, that isn't how this ore body behaves, but we'll finish up at roughly the same point, with a few ups and downs.

Operator

operator
#30

Thanks. We'll take our next question from Paul Kaner at Ord Minnett. Please go ahead.

Paul Kaner

analyst
#31

Yeah. Hi, guys. Appreciate you taking my question. Most of them, most of them have already been answered, but maybe just one regarding Edna May Stage Three. Has anything kind of shifted in the current environment that would make you reconsider that option?

Mark Zeptner

executive
#32

Paul, Mark here — thanks for asking. I believe we said during the quarterly call — let me just verify — a couple of weeks back, that we'd release the Mount Magnet mine plan and then possibly take a look at it. And as we clarified, yeah, labor and inflationary pressures were more of a factor in the second half of last year. Obviously, with the well-documented shifts in lithium and nickel, you know, some heat has left the market, and we've seen a bit of pressure ease in the labor market. Our vacancies are at roughly two-year lows, and prices for certain items are declining, and the rise and fall isn't in contractor... Contracts aren't always climbing the way they previously seemed to. So look, we'll likely review that around March, April, and see where things stand with that project. So we have quite a bit going on. We have Mount Magnet, we have Edna May, we have Rebecca-Roe, all in this half, dealing with them.

Paul Kaner

analyst
#33

Right, got it. Maybe just one more thing about bringing Cue into the mine plan. With the approvals and permitting side of it, is there anything in particular we ought to be concerned about?

Mark Zeptner

executive
#34

There’s no reason for anyone to be concerned. We filed the mining proposal in early December, and it has already been through several rounds of back-and-forth. For us, it’s essentially an additional mine approval similar to Mount Magnet. It differs considerably from Rebecca-Roe, which is more of a greenfield site. So there are many distinctions between the two, and based on what the department has sent back, there is no cause for worry. As a matter of fact, we may receive our approvals before we have completed mining at Eridanus, which is around the middle of the year, since we intend to relocate that open pit crew once Eridanus is finished.

Paul Kaner

analyst
#35

Yeah, that's great. I'm all set. Thank you. Thanks a lot.

Mark Zeptner

executive
#36

I appreciate that, Paul.

Operator

operator
#37

Thank you. As a reminder, if you'd like to pose a question, press star one on your phone and hold until your name is called. Our following question is from Dr. Richard Hart of Top Wheel. The line is yours.

Richard Hart

analyst
#38

Oh, thank you, Mark and Ben. And thanks once more, speaking as a shareholder. Nice work, considering the conveyor belt issues, staffing difficulties, and COVID, to reach the point you have. I have to say the future excites me more, since it looks very promising. You have a real smorgasbord on your hands with the drilling at Mount Magnet and Penny, plus Cue coming online. I know I'm being impatient. I'm curious — I heard Ben mention again, the... Well, those two are intertwined, the new mine plan for Mount Magnet and the feasibility study for Cue. Should we expect them at quarter's end, sooner than that, or is that something you can't share?

Mark Zeptner

executive
#39

The team is on it. It will be released once it's ready to go, and the only commitment I've made to the market is that it will happen within this quarter, Richard. You know, we have this call, we have the BMO conference in the U.S. and things of that nature, but the moment it's ready, we will put it out to the market.

Richard Hart

analyst
#40

Thanks, Mark. That is precisely what I anticipated. I figured I would give it a shot. The other matter concerns Cue, which is an even tougher question, and you just mentioned mining Eridanus at the end. Do you have any rough sense of when the Musgrave ore could reach the ROM pad at Mount Magnet, or is that too difficult a question?

Mark Zeptner

executive
#41

No, I believe we've said that for the December 2024 quarter. Our hope is to be mining during the September quarter, with ore located fairly near the surface. In any case, first ore comes in the December quarter of 2024.

Richard Hart

analyst
#42

Well, once more, congratulations. For Mount Magnet you have a whole range of options, and drill results keep arriving. So thanks again for all your help.

Mark Zeptner

executive
#43

Appreciate that, Richard.

Operator

operator
#44

Thank you. At this point, we have no more questions. I'll now return the floor to Mr. Zeptner, who will offer some closing comments.

Mark Zeptner

executive
#45

Alright, to close things out, as a summary, I’ll just say this as well: after turning in that strong, profitable result for this half, just finished, along with an expectation of doing even better in the second half, we are in a very good position to achieve our tenth — Ben, tenth?

Ben Ringrose

executive
#46

That's right.

Mark Zeptner

executive
#47

This would mark a fourth straight year of profitability, and possibly a sixth year in a row of dividends paid later in the year. Thanks for tuning in. Have a great rest of your day, everybody.

Operator

operator
#48

Thank you. That brings today's conference to a close. We appreciate your participation. You're welcome to disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ramelius Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Ramelius Resources Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ramelius Resources Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.