Operator
operatorWe appreciate everyone joining us and thank you for holding. This is the Ramelius Resources quarterly teleconference, and you're all very welcome. Everybody dialed in is currently muted. After a presentation, we'll hold a question-and-answer session. <<operator_script>>. At this point I'll pass things over to the Managing Director, Mr. Mark Zeptner. The floor is yours.
Mark Zeptner
executiveThank you. Good morning, everyone. I appreciate you taking the time to join us by phone this morning. Along with the quarterly report, we've released the presentation that we'll be referring to during this call. Every document has been posted on the ASX platform and will also be accessible on our website shortly. This morning, our CFO, Darren Millman, is once again with me. After I walk through the highlights and touch on operational performance as well as our development projects, Darren will give some detail on the financials. As usual, listeners will have a chance to ask questions at the end. So for those of you who have downloaded the presentation deck, I'll begin by speaking to Slide 3. On Slide 3, we generated $89 million in underlying free cash flow during the quarter, and while our cash and gold levels stayed at a similar level to last quarter at approximately $440 million, the balance does take into account our additional $97 million investment in Spartan Resources in July. Our quarterly gold production of 62,444 ounces came in at an all-in sustaining cost of $19.65 an ounce. The all-in sustaining cost, while higher than full year guidance, is in line with our plan, and it should also be noted that the all-in sustaining cost, excluding the non-cash component, would be $15.89 per ounce.
Mark Zeptner
executiveFor FY '25, we are keeping our guidance exactly where it was: 270,000 to 300,000 ounces, with an all-in sustaining cost between $1500 and $1700 per ounce, and output will be weighted toward quarter two and beyond as the higher-grade Cue ore comes in and grades at Penny keep improving. On a positive note, we achieved the quarter's production with zero lost time injuries, and we've stayed focused on that area ever since we hit the 12-month LTI 3 milestone back in May 2023. Development work at Cue is now progressing well. During the quarter we began ore mining there, and the whole Mt Magnet open pit mining fleet has now been mobilized to that project. At Key, we moved more than a million BCM in the quarter, mostly concentrated on the high-grade Break of Day pit. Exploration and resource development efforts during the quarter centered on Eridanus, given the encouraging results we are currently seeing at that deposit. If you look at Slide 4, I'd like to point you to the table on the left-hand side, which sets out quarterly production across the last 12 months. The softer production this quarter reflects our focus on developing Cue, reduced volumes from Penny stemming from mine sequencing, and lower grades from the stockpiles across Edna May, as anticipated.
Mark Zeptner
executivePenny's grades and volumes should rise over the remainder of the financial year, and combined with high-grade ore coming in from Cue, that points to higher production in the quarters ahead. Moving to Slide 5, we look at the Company's quarterly production figures. As anticipated, total tonnes mined fell versus the prior quarter as we concentrated on developing Cue. What we're planning to see, though, is how bringing in higher-grade Cue ore affects the mine grade, which rose 33% even with fewer tonnes from Penny, our highest-grade source, during the quarter. Mill throughput was held steady in the quarter by drawing down existing stockpiles across Edna May. That said, the lower stockpile grade and reduced Penny tonnes meant a lower mill grade for the quarter, which brought gold production down relative to earlier quarters. On Slide 6, we set out the operating highlights for Mt Magnet. Mt Magnet produced 41,019 ounces at an all in sustaining cost of $15.25 an ounce. Mining at the Brown Hill and Eridanus open pits wrapped up during the quarter, and the whole open pit mining fleet has now been relocated to focus on accessing the higher-grade Cue ore as mentioned earlier.
Mark Zeptner
executiveThe underground operations that supply Mt Magnet are now centered on the Galaxy and Penny mines. Following development in the prior year, the Galaxy mine is now well into commercial production, and because of that we saw tonnes mined rise by 90%, mine grade go up by 44%, and contained gold mine increase by 172% as a result. At Penny, production did fall during the quarter, which wasn't entirely unexpected given the planned development of the mine's next levels. From this quarter onwards, we expect Penny's production to improve and return to the levels seen in the second half of FY '25. Before I leave this slide, I want to point out that during the quarter we mined at an overall grade of 3.43, while the grades processed at the mill came in at 2.91 grams per tonne, roughly 20% below that. If you look back a couple of quarters to the March 2024 quarter at Mt Magnet, we processed all grades at 3.42, similar to the mine grades in the current quarter. And we achieved that at an all-in sustaining cost of $1000.30 per ounce, with operating cash flow from Mt Magnet of $79 million at an average realized gold price of just over $3,000 an ounce.
Mark Zeptner
executiveFor the March 2024 quarter, only the high-grade Penny material was included — no Cue ore at all. As things stand right now, we've got Cue ore stockpiled at grades above 10 grams per tonne, and gold spot prices are more than 35% above the realized prices we saw back in March. So we're expecting some very strong numbers out of Mt Magnet for the rest of FY 2025. I'm on Slide 7 — you'll see a photo of construction work at the intersection where the Cue access road meets the Great Northern Highway. Work is ongoing along the entire road linking Cue and Mt Magnet. That's mainly the bitumenization of this intersection, and all haulage should be starting shortly. As of today, we hold 35,000 tonnes of oxide ore grading above 10 grams, for 11,500 ounces of contained gold, just waiting on haulage and processing. Once those stockpiles start being processed, this ore will clearly generate significant cash flows. Moving to Slide 8, Edna May's highlights for the quarter: gold production came to 21,425 ounces at an all-in sustaining cost of slightly under $2,800 an ounce, with output drawn from the existing high- and low-grade stockpiles across the hub. The all-in sustaining cost, excluding the non-cash component, was $17.12 an ounce.
Mark Zeptner
executiveBy the close of the quarter, roughly 900,000 tonnes remained in both the high-grade and low-grade stockpiles, and that material will feed the mill through the March 2025 quarter. Slide 9, Eridanus. Earlier this year, we put out a mineral resource for Eridanus of 1.2 million ounces — a 64% gain over the June 2023 mineral resource, even with ongoing mining depletion. Our work on Eridanus is ongoing. We have introduced a new exploration target beyond the stated 1.2-million-ounce resource: 1.6 million to 3.7 million tonnes at between 2 grams and 2.5 grams per tonne, for between 100,000 ounces and 300,000 ounces. That new target sits beneath the open pit cutback already contemplated. On the cutback, we have set a new production target for that open pit of between 12 million and 16 million tonnes at a grade of between 1.2 grams and 1.6 grams per tonne, for between 575,000 ounces and 775,000 ounces — a 25% increase over the previous production target at the midpoint. Our mill expansion studies are now firming at around 3 million tonnes per annum. The outcomes we are targeting from these mill studies, not surprisingly, include higher gold production, lower operating cost per ton across all tonnes passing through the mill, and ideally a lower overall all-in sustaining cost for the Mt Magnet mine plan.
Mark Zeptner
executivePrior to passing things to Darren, I want to point out that additional information about the exploration and project development programs currently running at our various mines, which I haven't discussed, is available in the quarterly report itself. I'd also like to say that we're very eager to share with you the PFS results for our Rebecca-Roe project, with some encouraging RC drilling results received during the quarter further improving that project's economics. That's the highlights from my side. I'll now turn things over to Darren.
Darren Millman
executiveThanks, Mark — great to be here with everyone today. I'll start by walking through Slide 10 in the deck. Slide 10 lays out the quarter's financial highlights. For Ramelius, the September quarter was another solid one, with free cash flow of roughly $90 million. What's especially encouraging is that even with lower production in Q1, which came in as we expected, cash flow stayed very strong — a sign of the high margins this business is producing. In the quarter we sold 62,806 ounces at an average realized price of $3,359 per ounce, blending spot and committed forward sales. That gave us total sales revenue of $211 million for the quarter. Gold prices were incredibly strong over the quarter, climbing from $3,500 to $3,800, and that run has carried further into the current quarter, with spot prices now above $4,100. As we've said before, we're continuing to wind down our forward contract hedges, which now stand at 127,000 ounces at an average price of $3,123 per ounce. All-in sustaining costs came in at $19.65 per ounce for the quarter, higher than the prior quarter but in line with our internal expectations.
Darren Millman
executiveThat all-in sustaining cost figure includes a $376 per ounce charge at the group level, coming from the non-cash drawdown of existing stockpiles. If you set that non-cash charge aside, group all in sustaining cost comes to $15.89 per ounce. I'll come back to this in a moment. The all-in sustaining cost margin that results — realized gold price of $3,359 minus the all in sustaining cost of $1965 — is still strong at 42%. Cost guidance for FY '25 is unchanged, at $1500 to $1700 per ounce. If you look at Mt Magnet on its own, the all-in sustaining cost was a little above $1500 per ounce. A couple of factors drove the higher cost in the quarter. First, the emphasis on developing Cue rather than the high-grade sections of the Eridanus pit in the prior quarter. Also, less production coming from the lower cost Penny operations, and development costs for Galaxy now treated as sustaining rather than growth capital. Over the rest of the financial year, Mt Magnet production should rise and costs should fall, with better grades and tonnage from Penny and high-grade ore arriving from Cue. Cost guidance for Mt Magnet stays at $1300 to $1500 per ounce for FY '25, which leads the industry.
Darren Millman
executiveAt Edna May, all-in sustaining costs came to $2,799 per ounce, and that again matches what we had anticipated. With the gold price where it is right now, we're processing lower-grade material, and even though that carries a higher cost, it still produces meaningful cash flow. The Edna May all-in sustaining cost includes $100.87 per ounce of non-cash charge at the asset level for the drawdown of existing stockpiles across the hub. If you set that aside, Edna May's all-in sustaining cost would have come in at $15.89 per ounce. This non-cash charge is larger than what we flagged in our guidance, but we don't expect it to stay at this level through the remaining quarters, and free carry low grade stockpile has now become the source of mill feed. We continue to expect the noncash charge across FY '25 to be roughly $500 per ounce, and our cost guidance for Edna May, at $2,525 to $2,725, is unchanged. On Slides 11 and 12, we break down free cash flow metrics for the quarter and on a historical basis. Gold sales of 62,806 ounces produced operational cash flow of $111.2 million, with $68.4 million from Mt Magnet and the remaining $42.8 million from Edna May. In the quarter, $22.5 million in total was reinvested in mine development, resource definition and exploration, focused on Eridanus Cue Q development and the Roe-Rebecca project.
Darren Millman
executiveFree cash flow came in at $89.6 million for the quarter, and our closing cash and gold position stood at $438.6 million — that's after the $97.6 million investment in Spartan Resources. That closing cash and gold figure of $438.6 million, together with the new $170 million debt facility, gives us more than $600 million in available liquidity. And it isn't just our cash and gold that signals a strong balance sheet — our working capital position does too, with substantial stockpiles on hand as we move forward. Finally, from my side, I'd note that growth capital and exploration spending this quarter matched expectations, and our guidance for that spend is unchanged at $20 million to $30 million for growth capital and $40 million to $50 million for exploration. That said, spending in H2 of FY '25 depends on how the Eridanus and Mill expansion studies mentioned earlier turn out. Even so, any material spend tied to those projects realistically isn't likely to arrive before FY '26. With that, I'll pass it back to Mark.
Mark Zeptner
executiveThanks, Darren. So on this final slide, we've laid out the main priorities for FY '25, and they're basically the same as what we released before. Group wide, we'll keep lifting our safety results and meet FY '25 guidance, consistent with our core company value of we deliver and do it safely. We'll keep advancing Cue and, as planned, deliver first ore to Mt Magnet during this quarter. By December we'll finish the Eridanus underground open pit studies, plus the Mt Magnet processing facility study is due in that same window, and the Rebecca-Roe combined prefeasibility study also lands in December, and through all of it we'll step up exploration drilling at Mt Magnet, Cue Penny and, finally, Rebecca-Roe. If we could now open the line for questions, please, Darcy.
Operator
operatorThanks. <<operator_script>>. Thanks. Our opening question is from Andrew Bowler at Macquarie. The line is yours.
Andrew Bowler
analystGood day, Mark and Darren. Looking at the comments on Page 7, you mention some excellent control drilling in the lower sections of Penny, and you also discuss the northern mineralization, where you're seeing some thinner material spread out across multiple veins at Penny. I'm just wondering what that might mean for the remaining inventory at Penny, or are those changes to the modeling considered immaterial?
Mark Zeptner
executiveHi Andrew, this is Mark. Yeah, so the ore body appears somewhat more complex than what we've encountered up to now at the northern end. I believe the geology term for it is bifurcation — whether the vein has split apart in certain spots, and that wasn't appearing in the earlier drilling, so we're still working to understand it; we've only recently drilled and only recently started developing, but it seems to be stronger at the south end and might extend for a longer distance. So to grasp the full overall impact, we're not quite there yet, but there is some complication in the lower northern portion of the ore body that we hadn't anticipated, and that's what we discussed in the quarterly.
Andrew Bowler
analystThanks, Mark. And this is my last one — it might be for Darren. As far as I could tell, no cash tax was paid during the quarter, yet you guided to roughly $90 million for the year. Could you give us some sense of how that will play out? Will it be fairly even across the remaining three quarters, or does it fall more toward the back half?
Darren Millman
executiveYeah. For Q3, we're probably looking at roughly $70 million of that space. So yes, it's kind of weighted toward the back end.
Andrew Bowler
analystThat's fine. I have nothing further. Appreciate it.
Operator
operatorThanks. Our following question is from Michael Scantlebury of Euroz Hartleys. The floor is yours.
Michael Scantlebury
analystI've got a question about expanding the mill at Mt Magnet. With the expansion you're targeting to reach 3 million tonnes per annum, how should we think about the grade profile or the production profile?
Mark Zeptner
executiveI can't recall the grade right now, offhand. Of course, Eridanus averages 1.4 to 1.5, though its character is that the grade runs lower near the top, as we observed when we actually mined the current pit, and gets better as you go deeper. So that has to be factored in, but basically, if you're moving from 2 million to 3 million tonnes, that's likely an extra 1 million tonnes of Eridanus material, which carries that improving grade profile I mentioned. I don't know the grade on an overall basis, let alone a year-by-year basis, Mike, at this point.
Michael Scantlebury
analystThat's fine. Is there any detail you can share about CapEx, or must we hold off until the study is done? Clearly, you're aiming toward that 3 million tonnes, and you went through several items that need work at the plant to reach it.
Mark Zeptner
executiveYes, we’re working with <<inaudible>> on that right now. At this stage we don’t want to put numbers out there, but we think it’s not too exciting. Maybe looking at what Capricorn has done will give you some kind of indication of where we’re probably thinking, and broadly, if you’re doubling production, you’re building a new mill, that’s probably going to cost you $200 million, so it’s less than that, but as you know, it doesn’t come for free.
Michael Scantlebury
analystThat makes sense, that makes sense. And then am I hearing it right regarding when the spending would land — that it would be in FY '26?
Mark Zeptner
executiveYeah, that’s the sense of it. If we’re pleased with what we’re saying by the end of the year, and even if you’re pressing buttons and getting board approvals and you get things moving with permitting and contractors, I can’t see much spending in the second half of FY ’25 — it would mostly be material in FY ’26. So, whether another $20 million or $25 million or so gets spent in the second half, that’s why we’ve always framed growth capital by pointing to FY ’25 being very similar to the roughly $50 million we spent in FY ’24. We can’t see that changing.
Michael Scantlebury
analystOkay, that's clear to me. I'll relay that message. Thanks, everyone.
Operator
operatorOur following question is from Alex Barkley at RBC. Your line is open.
Alex Barkley
analystMorning Mark and Darren. I have another question about Eridanus. I appreciate what you said regarding the production target and the exploration target. There are a couple of things I'd like to ask. Is there any reason why the grade for the production target comes in somewhat below the resource? Is dilution the only factor there? And on the exploration target, I'm curious about how that could factor in. Might it be incorporated into a cutback design prior to your final decision on the mine and the mill? Basically, what's the timing for how that would come in? Thank you.
Mark Zeptner
executiveThanks, Alex. Mark here. I have to disagree about the exploration target having a lower grade — it falls between 2 and 2.5. The production target is not as deep. The exploration target basically lies beneath the pit shell you're seeing, and consistent with the improving greater depth, the deeper you go, the higher the grade you get. So yes, the actual cutback production target at 1.4, 1.5 is below the midpoint of 2.25, but that isn't surprising given the nature of the ore body as we understand it, and sorry, what was your second question, Alex?
Alex Barkley
analystOn the exploration target, which is at somewhat lower confidence in resource terms, what's the timing for when that might convert into a resource, and does that factor into how you're making decisions?
Mark Zeptner
executiveYeah, look, ideally Alex, that arrives alongside the mineral resource update in December. When we ideally turn that exploration target — most likely — into an inferred resource, given how deep it sits and how many drill holes we have. I believe there are roughly a dozen holes in it. So I think we could get that into the classified category.
Alex Barkley
analystAll right, that's great. Thank you so much, everyone.
Operator
operatorThanks. <<operator_script>>. Our next question is from Paul Kaner at Ord Minnett. Go ahead, please.
Paul Kaner
analystYeah. Hi, guys. Appreciate you taking my questions. I've got another one about the mill expansion at Mt Magnet. You said the 3 million tonne per annum option looks most likely. Could you expand on that a little more? I suppose, what's holding you at 3 million tonnes per annum rather than going beyond that — is it all-in constraints, space constraints, or a capital issue?
Mark Zeptner
executiveI'd say capital is the bigger factor there, Paul. And clearly we're working through that right now, but you reach a stage where, instead of adding or upgrading particular sections of the mill, you hit a point where pump sizes and conveyor sizes have to be examined — and at that stage you're essentially constructing a second mill. So CapEx takes a step change, and that certainly helps shape the decision you make.
Paul Kaner
analystYes, got it. And then regarding Cue mining, I realize it's still fairly early stages there, but that material you've extracted — is it, I suppose, arriving at a higher grade than you'd anticipated?
Mark Zeptner
executiveI'd say it's reasonable to put the Break of Day pit average grade at 4.5. Alongside that, a lower-grade stockpile exists — another 35,000 tonnes at, I believe, 1.7, sitting next to the high-grade stockpile, even though it was up there last week and, funnily enough, you can't distinguish the two. On that 4.5 average grade, my own guess is that the high-grade portion is doing better than that, and we did note that if any ore body were to outperform, it would be the high-grade portions of Cue, given the top cuts and, I suppose, how conservative we are in our resource-to-reserve processes. So some uplift could be there, but it's early days — I'll caution on that.
Paul Kaner
analystAnd how much of that do you figure will actually flow through in the next quarter, coming from those stockpiles?
Mark Zeptner
executiveWe're clearly going to start hauling very soon—we just wrapped up work at the intersection. We will need to haul through the Mt Magnet turn and then turn right to head out toward the Mt Magnet Mill. So we may not be running at maximum production rates, but we'd like to believe we'll get that high grade portion into the mill by the end of the quarter.
Paul Kaner
analystAll right, fantastic. I'm done with my questions. Many thanks, everyone.
Operator
operatorOur following question is from Rob Wolf, who is a private investor. You may proceed.
Rob Wolf
unknownHey Mark, good to talk. I’ve just got a couple of quick questions about the potential expansion of the mill at Mt Magnet. The first is about grind size. Obviously, with the gold price high, will a finer grind be considered to try to get that tiny bit of extra recovery? And the second question, LinkedIn really is, will the large stockpiles of low grade and reasonably low grade at Mt Magnet be included in that 3 million tonne expansion for later in the processing option for that mill?
Mark Zeptner
executiveThanks Rob, good to hear from you. One of the key outcomes — I did mention it verbally, but it's in the release — was to maintain our recoveries, which last time I checked were pretty handy, around 95%. You're starting to push the nets to get much more than that. Obviously, we don't really think we need to find a grind beyond what we currently have. We're reasonably fortunate with our ore sources, but we'll always keep an eye on those recoveries. On the stockpiles, I think they're 0.9 grams or 3 million tonnes on average. They'll find a place in the mine plan that suits best, and at this point in time I think it's at the end of the mine plan. Unfortunately, they'll have to wait, because we've got higher grade to put in first.
Rob Wolf
unknownThat works for me. Appreciate it, Mark.
Operator
operatorThank you. At this point, we have no additional questions. I will now return the floor to Mr. Zeptner for his closing comments.
Mark Zeptner
executiveThanks so much, everybody, for tuning in. Hope the remainder of your day treats you well. Appreciate it.
Operator
operatorThanks. That brings today’s conference to a close. <<operator_signoff>>.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ramelius Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to Ramelius Resources Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ramelius Resources Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.