Ramelius Resources Limited (RMS) Earnings Call Transcript & Summary

August 25, 2025

Australian Securities Exchange AU Materials Metals and Mining earnings

Earnings Call Speaker Segments

Darren Millman

executive
#1

Thank you, and good morning, everyone. Sadly, Mark Zeptner had to pull out late this morning. He was cheering on his beloved West Coast Eagles this morning, or last night. So it falls to me today. Thanks for taking the time to dial into our FY2025 Results Conference Call. With me is our General Manager of Finance, Ben Ringrose, who will drill down into the numbers after I've covered off on the highlights. We have uploaded to the ASX platform, along with our website, a number of documents including our FY2025 financial results summary, audited statutory financial report, and the presentation we'll be speaking to today. Starting on slide 4, we set out our plans to grow the business on the back of an exceptional FY2025, which you saw us establish a strong platform to build from with the release of our 17-year Mount Magnet mine plan, the Rebecca PFS, and significant cash reserves, which were $784 million post the net payment of $71.3 million on the close of the Spartan transaction. Our focus for the coming year is to integrate Dalgaranga into our Mount Magnet Hub and enhance our portfolio with an aggressive exploration plan that will see us spend between $80 million-$100 million focusing on defining additional high grade resources and making new discoveries.

Darren Millman

executive
#2

We’re eager to bring the market up to date in the December quarter with our five-year plan that includes Dalgaranga and lays out an obvious route to reaching 500,000 oz of production by 2030. Detailed guidance for FY2026 will also be part of that plan. Turning to slide 5, here are the year’s mining and production highlights. Operationally, the clear standout is record gold output of 302,000 oz, driven by Kew open pits beating expectations and better grades from Penning. We managed that even though fewer tonnes were milled during the year as Edna May moved to care and maintenance. Without taking too much away from Ben, I want to point out our industry-leading all-in sustaining cost of $1,551 per ounce and realized gold price of $3,963 per ounce, leaving a margin of $2,400 per ounce sold; the effect shows in the exceptional cash generation we delivered across the year. With that, I’ll pass things to Ben to walk through the numbers in more detail.

Ben Ringrose

executive
#3

Thanks, Darren, for following up on the presentation. To start, I'll be referring to Slide 6 and discussing our earnings for the year. At the risk of repeating myself too much this morning, let me say right away that on just about every metric reported, these financial results represent record returns to the business. That's even more impressive when you consider we were sitting here 12 months ago saying the same thing. Revenue from the sale of 303,000 oz exceeded $1.2 billion and rose 36% compared with the prior year. Revenue gained not only from a strong gold price but also from reducing hedge book commitments at a higher average price. Gross profit for the year came to $695 million, an increase of 122%, which reflects both the high gold price and the lower cost per ounce that high grade ore delivers. At the group level, the mill grade rose 23%, with the two operations telling very different stories. At Mount Magnet, the mill grade went up 53% to 4.48 g/ton, while at Edna May the mill grade fell 41% to 1.19 g/ton as that operation transitioned to care and maintenance. As the old saying goes, grade is king, and even more so when it comes from a shallow open pit like those at Kew.

Ben Ringrose

executive
#4

Underneath gross profit, most other lines matched the previous year, except for $4.1 million of care and maintenance expense at Edna May. That figure takes in employee redundancy costs, so it shouldn't be viewed as representing the continuing care and maintenance expense for the operation. Group EBITDA — which adds back depreciation and amortization — came to $819 million, an impressive 68% margin. On a reported basis, EBITDA rose 81% versus the prior year, while the margin was up 33%. Income tax expense for the year totaled $196 million, giving an effective tax rate of 29%. Income tax actually paid and payable relating to FY2025 was $158 million, equivalent to a cash tax rate of 23%. As of June 30, $130 million of tax on FY2025 earnings remained outstanding, with most of that amount falling due in December this year. Since we're now required to make monthly tax instalments, we don't expect these sizable one-off tax payments to keep occurring going forward. Group NPAT came to $440.474 million, more than double the prior year, for a net profit margin of 39%.

Ben Ringrose

executive
#5

That worked out to $0.41 in earnings per share. Now let's turn to Slide 7, EBITDA broken down by operation. This slide matters quite a bit, because it isolates Mount Magnet and highlights the exceptional margins there. Mount Magnet's EBITDA came in at an extraordinary 80%, which is $3,159 for each ounce sold. While Edna May's earnings were solid and did generate cash, they do weigh on the group's earnings metrics. In fact, you'd struggle to locate any production center across Australia that delivered stronger returns in FY2025 than Mount Magnet did. And this powerhouse will only get a further boost once Dalgaranga ore is added into the feed. Turning now to slides 8 and 9, we've provided somewhat more detail on the Mount Magnet operations and then on Edna May. I won't spend too long on these, but a couple of key highlights deserve mention. First, at Mount Magnet, the grade of Q material milled during the year came in at 10.66 g/ton. That's a pretty strong grade for an underground mine, never mind an open pit mine, and its effect on FY2025 earnings is plainly visible. Second, at Edna May, the operation produced $123 million of cash earnings for the year.

Ben Ringrose

executive
#6

Given that the stockpiles did better than we had anticipated considering the gold price we saw during the year, we extracted every last bit we possibly could from Edna May. And yes, while that brought the group margins down as a percentage, the cash we generated made it well worth doing. While a 940,000 oz resource still exists in connection with the Stage 3 cutback at Edna May, our near-term priorities lie with Mount Magnet, Dalgaranga and Rebecca. We plan to revisit the options at Edna May early in the 2026 calendar year, and we're now turning our attention to what it's all really about, cash, which gets discussed on slide 10. There are certainly some impressive figures here, beginning with underlying free cash flow of $694.9 million, which works out to $2,304 per ounce produced and places Ramelius well ahead of our peer group. Total cash flow for the year came to $359.4 million, more than double last year's figure, giving us a closing cash and gold position of $809.7 million. Slide 7 highlights a few key cash items, among them total cash returned to shareholders for the year through the FY2024 dividend and the maiden FY2025 interim dividend of $70.3 million.

Ben Ringrose

executive
#7

When dividend reinvestments are factored in, the total return to shareholders rises to $92 million. Capital investment across the year came to $328 million, which is 36% higher than the previous year, and that figure covers mine development, exploration, plus our 19.9% stake in Spartan. Lastly, I'd point you to the chart at the bottom left of the slide. From when Kew was introduced in the December quarter, we've delivered strong cash flows on a consistent basis, averaging more than $200 million each quarter. Now turning to slide 12 and the balance sheet. Ramelius's working capital position, which accounts for the current stockpile and current payables, rose 70% to $689 million, while the net asset position grew to $1.9 billion, up 43% on the prior year. That increase reflected the strong earnings for the year along with the fair value increase in our investment in Spartan. Total liquidity of just under $1 billion, including our undrawn but committed $175 million finance facility, means we are fully funded for the future development of Rebecca, the integration of Dalgaranga, and continued returns to our shareholders. The transformational combination with Spartan will materially change our balance sheet in FY2026.

Ben Ringrose

executive
#8

While the valuation work for the acquisition is still underway, I'd like to point you to note 26 in our financial report, which gives some provisional detail on the purchase consideration and the fair value of the assets and liabilities acquired. The $2.8 billion purchase consideration is going to be allocated across the assets and liabilities acquired, and we expect the bulk of that value to sit within the mill infrastructure, mine development, and exploration assets. As at the completion date, and after taking into account the cash payment to Spartan shareholders, total cash and gold for the combined group stood at $784 million, and while the valuation work is still in progress, we do expect stamp duty on the transaction to land between $130 million and $140 million, which we assume will fall due sometime in the second half of FY2026 and will affect earnings in that year. These works are expected to be finished by the end of this calendar year, with a half year financial report that includes all relevant information on the acquisition and fair values. We very much look forward to sharing our five year plan with the market in the December quarter. It will not only set out our path to reaching 500,000 oz per annum by FY2030 but also the synergies available to the combined group, including tax synergies that are real and immediate, with our tax instalments already reduced as a result.

Ben Ringrose

executive
#9

All of this will be quantified when we release the five year plan, and as Darren mentioned, that release will also contain detailed guidance for FY2026. Before I hand things back to Darren, I want to point out that the appendices to the presentation contain detailed information and reconciliations, as well as the five year history of our operations, earnings, and cash generation. I trust you will find these useful. With that, back to you, Darren.

Darren Millman

executive
#10

Thanks, Ben. Turning your attention to Slide 13, I'd like to cover the final dividend we've declared for FY2025. Our dividend history is something we take pride in, and as of today we're declaring a seventh final dividend in a row — $0.05 per share on this occasion, fully franked. Combined with the maiden interim dividend that was paid in April, dividends across FY2025 come to $0.08 per share in total, which is a 60% rise versus the prior year. Delivering that kind of growth in returns to our shareholders is a pleasing outcome, and it's especially so when you factor in the larger share count following the addition of Spartan. As a proportion of free cash flow, the FY2025 total dividend comes out at 29%, which stays faithful to the 30% of free cash flow we target as a return to shareholders. When the Board approved this final dividend, it weighed up future capital commitments as well as the doubling of our exploration budget to $80 million-$100 million in FY2026. On the basis of the 30 June 2025 share price, the total dividend equates to a 3.2% yield, and over the last five years it equates to a total return of 9.5% per annum. In per-ounce terms, it amounts to a total return to shareholders of $430 per ounce sold — more than twice the $195 per ounce noted last year.

Darren Millman

executive
#11

Our dividend reinvestment plan is now firmly in place, and for the FY2025 interim dividend the participation rate stands at 23%. Shareholders will again have the chance to take part this year, with the share price set at a 2% discount to the 10-day VWAP measured from the election date. The dividend paid last year came to $57.2 million in cash and reinvestment. This year, with the maiden interim dividend included, we will return up to $130.3 million in total — a 128% increase. The final dividend goes out in October. To close, I'd point you to Slide 14, where the investment case still sits. You are a reliable operator that does what we say we will do. We have met guidance on both production and costs over the past five years, and we have consistently paid dividends, doing so for the past seven years. Through our transformational combination with Spartan, we could enter the ASX 100 this calendar year. We lead the sector on cash flow generation per ounce and hold a long life asset in Mount Magnet and Rebecca. We have a credible pathway to 500,000 oz per annum, which will make us the third largest Australian gold producer.

Darren Millman

executive
#12

Our exploration efforts have grown twofold, thanks to a collection of quality brownfield targets sitting in our portfolio. For Ramelius, the close of the calendar year promises to be both exciting and busy, with the Rebecca DFS coming up, along with the integration study and five year plan for the Mount Magnet Dalgaranga. There is plenty of exciting news headed your way over the coming weeks. We intend to give you a progress update on our integration studies and the activities tied to them, on mine development progress, and on exploration at Dalgaranga. As I see it, everything is progressing to plan. That brings our presentation to a close. I will now hand it back to the operator so the line can be opened for questions.

Operator

operator
#13

Thank you, sir. To ask a question, please press Star followed by one on your telephone keypad and wait until your name is announced. To cancel your request, press Star followed by two. If you are using a speakerphone, please lift your handset now so you can ask your question. We will pause for a moment while we assemble our queue. Our first question comes from Alistair Harvey of JPMorgan. Please go ahead.

Alistair Harvey

analyst
#14

Morning, team. Just a quick clarification. Regarding the FY2026 guidance, I believe at the quarterly you mentioned it might land roughly six weeks after Diggers, so around mid-September. I simply wanted to clarify what you said in your opening remarks. That FY2026 guide will be released alongside the integration study in the December quarter. Both are expected within the next couple of months.

Darren Millman

executive
#15

Yeah, thanks Al. So really, what we're aiming to do is present that five-year plan in the December quarter. In an ideal world, we'd sort of lay it out by early November, but the studies will be done when they're done. The network has been coming in, and we're starting to narrow down some of those eight options that are under review. We'll probably be targeting — in an ideal world — late October, but mid-November is probably that range. That's when we want to get that full picture out there to show both the capital needs going forward, just so shareholders have the complete picture.

Alistair Harvey

analyst
#16

My understanding is that we still anticipate news on the Rebecca DFS results during the September quarter. How is that trial progressing?

Darren Millman

executive
#17

Right, so that's still kind of what we're monitoring. Again, we might hold off somewhat just to get the complete capital picture once we see what Mount Magnet Hub will require in terms of capital needs, and then clearly layer on top of that what Rebecca needs. More likely than not, there's a scenario where both arrive at the same point in time. From that point, we'll make those calls on capital spending across the next several years.

Alistair Harvey

analyst
#18

Much appreciated, Darren.

Operator

operator
#19

Alex Barkley from RBC is up next.

Alex Barkley

analyst
#20

Thanks. Good morning. Morning Darren and Ben — regarding the Spartan deal, you said the cost stamp duty is likely to be expensed next year. Are there any other items flowing through the P&L, such as transaction costs, or any capital gains on the stake you already held in Spartan? I'm just trying to understand what might be expensed. Thanks.

Ben Ringrose

executive
#21

Thanks, Alex. This is Ben speaking. Regarding our initial 19.9% stake, there are no capital gains or anything of that kind. As for the other costs running through earnings, those will be fairly small. I mean roughly $2 million-$3 million in addition to that stamp duty—not much beyond that.

Alex Barkley

analyst
#22

Sure, that makes sense. Capitalized lease liabilities did go up somewhat. You had very little on the books a year ago. The amount isn't a big jump, but is there a specific reason worth flagging there?

Darren Millman

executive
#23

There are also a few other items to mention. Clearly, we reached, more or less, the conclusion of the lease we held here in Perth. We signed a fresh lease in Perth proper rather than East Perth. We incurred some extra expenses too when we committed to our new power generation setup. As you're aware, we're shifting from gas to solar and afterward making the transition to wind at site. That accounted for the sizable rise you will notice there, and what we expect is that we may have expanded that power generation source as we prepare to bring Dalgaranga on board. Mainly, the power generation.

Alex Barkley

analyst
#24

Alright, thank you. This is my final question. You said the pay-as-you-go tax for FY2025 may have come in somewhat low. Do you have any sense of what a catch-up payment could look like?

Darren Millman

executive
#25

Regarding the first half of next year — yeah, I believe Ben mentioned roughly $130 million on our balance sheet. That comes due in December of this year. As for installments, if you look at the figures from before, we're likely a bit above 8% monthly, and that's probably landing somewhere just over 4%. That's the immediate effect Ben referred to regarding our relief from the Spartan acquisition. That's the factor being revenue — you know, revenue multiplied by that factor. Yeah, yeah. Okay.

Alex Barkley

analyst
#26

Okay, thank you so much, everyone.

Darren Millman

executive
#27

Thanks, Alex. Operator, are there any additional questions? I’m just checking the webinar here, folks. A few may be on the way. One question we received: when will the first gold bar be poured at Dalgaranga? That will be settled through the final integration studies. We do anticipate that some ore will be included in FY2026, while we work through those final numbers, and after that it will increase annually as we reach depth at the Dalgaranga deposit. The grade goes up, and the width goes up. We’ll have some minor material coming through in FY2026, but there will be another step up in FY2027 and a fairly substantial step up as we move into FY2028. That’s all from the webinar, operator. Any additional questions on the...

Operator

operator
#28

Sorry, everyone. There does appear to be a small problem with the questions coming in by phone. Kindly wait a moment. It really does look like our phone questions are experiencing an issue. Our apologies for that. Anyone who has questions by phone, we would ask to reach the company through a different method, and then we will hand things back to Ramelius for the closing remarks. Thank you.

Darren Millman

executive
#29

Thank you, everyone. I can see — and I know — that two questions are coming through from participants. I'll ring you right after this. So with that, thanks to all of you for joining the call. In my view, it was a solid result with which to finish FY2025. Genuinely exciting as we move toward FY2026. There's plenty of money invested in the ground on the exploration side, so we're aiming to provide the market with substantial detail as that comes through. As I mentioned before, we'll deliver an update on Dalgaranga's progress, its integration, and the studies in a few weeks as things advance. We're looking forward to the period from now until the end of the calendar year in terms of information flow, and to getting us to that 500,000 oz producer by FY2030. Everything looks positive from where I sit. I'm looking forward to catching up with a few of you over the coming days on the east coast alongside Mark and Ben. Talk soon, everyone, and thanks for joining. Thank you, operator.

Operator

operator
#30

The presentation for today is now finished. Thanks for joining us. You can go ahead and disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ramelius Resources Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to Ramelius Resources Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Ramelius Resources Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.