At this point we’d like to turn the conference call over to the CEO and Managing Director, Mr. Bryan Quinn. Go ahead, please.

Bryan Quinn

unknown
#2

Thanks, everyone, for being on this quarterly call where we're sharing our first-quarter results. The presentation slides we'll be walking through came out in today's ASX announcement. Some of us are actually presenting from Peak Mine, and the rest are joining from Federation, based in Brisbane. With me today are Martin Cummings, our Chief Financial Officer; Andrew Graham, our Chief Development and Technical Officer; and Michelle Tracey, our Project Director for the Federation Project. Before I walk you through the quarter's results, I'd like to thank all our stakeholders and shareholders for their continued support. Since we're presenting from several locations, I pay my respects to all the traditional owners—past, present, and emerging—for our locations, and I also thank our other important landowners who host our operations. As we've said before, FY 2024 is about building a stronger Aurelia Metals by redefining the organization's vision and strategy, with a strategic focus on delivering with confidence, improving our margins, right people, right mindset, and optimizing the Cobar Basin to set up Aurelia to fill our minerals with low cost and high-grade ore, while confidently delivering our business guidance results in 2024 and beyond.

Bryan Quinn

unknown
#3

If you could please turn to slide three. Our Aurelia team and contracting partners have kept delivering the business plan and strong production results even as base metal prices have retreated somewhat. Our solid financial results were supported by production beating our quarter one plan and coming in well within guidance, along with our ongoing emphasis on cost efficiencies and cash generation across the operating assets and the corporate office. Among the highlights, revenue came in ahead of plan at AUD 70 million for the quarter. Our cash balance is strong at AUD 100 million, with current operating cash flow from the operations delivering AUD 12.6 million for the quarter. Our cost efficiencies have brought mining unit costs for Peak down to AUD 127 per tonne from AUD 180 per tonne 12 months ago, which represents roughly a 30% improvement. Our development meters across Peak and Federation keep rising quarter-on-quarter, which is de-risking the FY 2024 and FY 2025 production volumes and positioning us for further growth. Our key growth project, Federation, remains on track to deliver our first key milestone for first ore in Q1 2025, in line with our approved budget. Our exploration team kept delivering some positive results, supporting our growth plans around the Peak Mine, with high quality results as reported in the ASX last week.

Bryan Quinn

unknown
#4

We’re also continuing to reshape the corporate organization, with meaningful cost savings beginning in October, which annualizes to AUD 3 million per year. The board is moving ahead with its reduction effort in line with right-sizing, having the right skills, and lowering costs, as described in the chair letter in the FY 2023 annual report. We’re advancing our strategy to fill our minerals as soon as is practicable and are weighing commercially sensible options. The aim there has been to secure the cash flow potential from this asset and to harvest cash until the end of mine life, and Martin will walk through part of the hedging process that we’ve started. So there’s a lot of pleasing progress for the business over the quarter against my CEO 100-day plan. Looking forward, it’s pleasing to report that guidance for the rest of FY 2024 is unchanged, and inflation impacts will be offset by volumes and cost efficiency programs. I’ll now move to slide four on overall production costs. We stay focused on delivering safe and stable production with greater cost efficiencies, and the cost efficiency programs are currently forecasting better costs than within our guidance. The gold price keeps rising, and base metals remain consistent while we wait for China to release policy to improve demand.

Bryan Quinn

unknown
#5

What we're sharing today, along with the work underway as we look toward the Q2 forecast, gives clear context that we're on track to meet our commitments under the FY 2024 guidance for production and costs. In this environment of higher gold prices, the operations have delivered strong gold production, and we're positioned to lift base metal tonnes and grades over the rest of the year, consistent with guidance. We also expect the cost efficiency programs and organization changes we've planned to keep moving forward over the next couple of months, with cost efficiency benefits realized every quarter for the remainder of the year. So if we turn to slide five, safety and environment. Our underlying safety principle is that our people go home safe from whatever shift, and we minimize our impact on the environment and work with our community as a good neighbor. We had four recordable injuries in quarter one, which is far too many, and unfortunately, most of them were slips and trips. We're committed to taking the necessary steps to ensure these incidents do not happen, and our teams are ramping up efforts around field leadership, making sure our business plan is done before any work starts, and improvements in training are being rolled out for inexperienced team members as we increase our resourcing in line with our growth plans.

Bryan Quinn

unknown
#6

On top of that, our operational maintenance has been stepped up and will keep maturing across the next 12 months, becoming normalized in how we make decisions — really assessing and making sure threats to our business and operational areas are well understood and under control. We'll keep bringing in third-party expertise so we can mature at the right pace for these initiatives. Moving to slide six, Peak Operations. Peak has raised development rates considerably this quarter, with additional plans to lift those rates heading into Q2. The development improvements genuinely helped the business by giving confidence for the next 12 months to 18 months, which also keeps providing confidence in delivering our volumes and upside in FY 2024. Cost efficiencies have likewise been a priority focus at Peak, as reported in our CEO 100-day plan. Over the last 12 months, the team has delivered a 30% reduction on a cost-per-ton basis, and has continued implementing various operating efficiency initiatives identified in our Working Smarter program, which are mainly IT support on the shop floor. Overall, utilization and availability of the mine equipment have improved substantially now that Peak's resourcing is approaching target levels. The AISC — the all-in sustaining cost for Peak at $1,584 per ounce — reflects that cost efficiencies have started, and the higher expected base metal production for the remainder of the year will drive cost down as per our plans.

Bryan Quinn

unknown
#7

So for this quarter, operations have really been centered on extracting the lead-zinc stopes at the South Mine — both Kairos and Chronos — and that's delivered solid gold results. In quarter two, we finished the lead-zinc stopes that had carried over from quarter one, then shifted to copper stopes at Perseverance Deep in the South Mine and Jubilee in the North Mine. Next comes starting up high-grade lead-zinc near the end of Q2. The copper and gold stopes are a couple, and they're in production drilling right now, and all the development in the Upper Cronus is moving along nicely, which sets Q2 up well for our guidance targets. Development work is also ongoing at Jubilee and Upper Cronus right now to get ready for the Q3 copper and lead-zinc stopes, so we hit our Q3 numbers. If you turn to slide seven, Dargues operations. At Dargues, we keep sustainably maximizing the cash from this business while preparing for closure in 2025, and our current quarter two forecast shows we're well on track to hit guidance results given the planning and delivery that's underway. Development meters at Dargues have gone to plan and will wrap up in Q2. We should keep de-risking the complexity of the mine, with higher grades switching over to production, drilling, backfilling, and then mining the remaining high-grade ore pillars.

Bryan Quinn

unknown
#8

Of course, since the mine is only 12 months away from depletion, our attention is on keeping good, good people working at Dargues, and we're collaborating with our contracting partners to hold onto those people, while also using a hybrid model of employees and contractors to try to retain the best people working for Aurelia. Of course, we'll be working and seeking to keep drawing in good quality talent that we can to bring over to the Cobar region in the future, where our growth will keep happening. Turning to our critical minerals growth process at Federation, which has been reported as one of the highest-grade metals projects in Australia, with a resource grade of approximately 6.7 zinc equivalent. We've started the project well with 0 recorded injuries and are happy that we are tracking very well with development meters and construction works on the surface. In fact, I was actually there yesterday and very happy with the standards and the quality of work being achieved by Aurelia management and the Redpath team. The focus for Aurelia, under the leadership of Michelle Tracey, who's on the call today, has been to de-risk the project costs and schedule by bringing on high-quality, capable staff with expertise across various work packages of mining, shaft sinking, surface infrastructure works, and project management of construction activities, as well as commercial areas.

Bryan Quinn

unknown
#9

The team is actively looking for partners — companies with solid track records and credibility when it comes to delivering these work packages. As we showed in the presentation, every work package is underway, the scopes keep getting refined, and the end goal is to build the mine properly and hit first ore in Q1 2025 as our initial milestone. You'll also see in the presentation a green arrow marking the work finished through the end of Q1, while yellow shows what was completed as of Sunday this week. Over this quarter, we've also brought drills onto the site to evaluate potential upside from extensions to the west, and in Q2 we intend to set up a drill rig in one of the cuttings so we can begin drilling underground. Right now, we're pleased to say we remain on track to deliver the whole project within budget and on schedule, even as we handle inflationary pressures affecting the industry. Moving to slide nine, exploration. Consistent with last week's ASX release, we keep investing in exploration close to Peak, where there are many high-priority targets, and we remain pleased with what our programs deliver. For anyone familiar with the area surrounding Peak, none of this comes as much of a surprise — it keeps producing and shows the prospectivity of our business.

Bryan Quinn

unknown
#10

Over in the South Mine Corridor, we have assay results coming from Upper Cronus, Perseverance Zone A, and Perseverance Deep — areas where we've confirmed that significant mineralization keeps extending across the upper northern portion and the well-known Perseverance deposit. Those strong grade intercepts, which you can see in the presentation and the ASX release, are especially encouraging because they share striking similarities with the Cronus deposit. I acknowledge this is deep, but those grades could give us extensions to help fill our mills over the coming years. Turning to the North Mine Corridor, assay results from the Chesney South deposit have confirmed that mineralization extends south of the Cherokee deposit, very close to the recently reported maiden mineral resource at Burrabungie. This area holds significant further potential for exploration success, given that known mineralization is present. The high copper and gold grades we intersected at these near mine locations will be the focus of further exploration and evaluation work in the medium term, and they are well positioned for the existing underground infrastructure. With that, I'll hand over to Martin, who will walk through the financial slides.

Martin Cummings

unknown
#11

Thanks, Bryan. I'll be referring to slide 10. The main point I want to make here is that our balance sheet is now in very good shape. We're holding AUD 110 million in cash, and that really came from some significant milestones during the quarter, as I mentioned in the recent results call — receiving the proceeds from the retail entitlement offer and getting the cash backing returned once we achieved financial close on the Trafigura facility. We expect cash to rise further this quarter thanks to a tax refund of roughly AUD 21 million. Keep in mind that our loan note facility is still undrawn at $24 million, which gives us additional liquidity. Operationally, both Peak and Dargues got off to a solid start this year. Peak generated AUD 9.2 million in operating cash flow, helped by strong gold production along with lower operating costs and capital spending. Copper output was higher as well, and pleasingly, we managed to ship a copper shipment during the quarter. Lead and zinc production came in slightly lower, driven by grade, but as Bryan noted, we expect that to improve over the coming quarters through a combination of more ore mined and higher-grade ore.

Martin Cummings

unknown
#12

Cash flow from Dargues came in at AUD 3.4 million, below the level we saw in the previous quarter. We had expected an additional shipment to leave during this quarter, but it will now go out in the December quarter instead. Costs ran higher because of planned realigns on the crusher and ball mill, and also because of the effect of our new electricity contract, which took effect on the first of July. The rate under that new contract sits roughly 60% above the old rate, though I want to emphasize that this uplift was built into our budget and is reflected in our cost guidance. We also finished planned component replacements on our mobile fleet during the quarter, and since that fleet has a useful life after Dargues at either Peak or Federation, we will keep maintaining the equipment under the standard maintenance regimes. The Dargues team is doing excellent work to make sure we get the most cash possible out of the operation over its remaining life. At today's gold price in Australian dollars, though, it also opens an opportunity to improve those returns beyond what we had planned. To capture that opportunity, we have started a hedging program covering as much as 100% of payable gold production from Dargues through to the September 2024 quarter.

Martin Cummings

unknown
#13

So far, we've completed roughly 40% of the volumes we planned, and we intend to build on that shortly. As a bit of context, Dargues accounts for around 50% of gold output for the group, which means Peak still carries a meaningful unhedged gold position. Alongside those gold hedges, we thought it sensible to hedge a portion of base metals as well. The plan is to hedge as much as 25% of payable lead and zinc production from Peak, giving us some price protection on byproduct credits. Once more, we're considering the period through September 2024, which lines up with first stope ore from Federation. When it comes to lead and zinc, no hedges have been executed as yet, though we'll aim to put some in place soon. Turning to Federation, the project got off to a really pleasing start under Michelle's leadership. As mentioned earlier, development meters are running ahead of plan, and the team has made genuinely good progress on the other key packages — the road upgrade, ventilation, and raised boring. We spent AUD 10.6 million during the quarter, and pleasingly, that was funded by operating cash flow generated by Peak and Dargues in the quarter. Spending is set to ramp up over the coming quarters as development rates rise and we move forward on those major packages.

Martin Cummings

unknown
#14

As a quick reminder, for FY 2024 we've set capital guidance for Federation at AUD 70 million to AUD 80 million. To wrap up, operations and projects have delivered a genuinely strong beginning to the year, producing healthy cash, and honestly, we're now in a balance sheet position that can back those growth opportunities. I appreciate your time, and I'll return the call to Bryan.

Bryan Quinn

unknown
#15

Thanks — so just to recap on Q1 and look ahead to Q2, our focus is on lifting how we're performing right now on HSE, and making sure we've got firm controls around every major risk facing the business, whether that's HSE or financial. Cost efficiency at Peak — improving cash flow there and also unlocking that 90 million tonne of resource at the mine — is a big prize for us to chase. Clearly, delivering the cash flow from Dargues, and a sustainable system at that site, is paramount. Delivering the fast-paced development at Federation and the raised boring projects is well on track and remains a key focus. We keep investing in drilling, and it's producing very positive results for our future, both close to Peak and over in the Nymagee region as well. Our progress on the Great Cobar Project during this financial year is going to be a key deliverable toward the end of the year, and we'll stay active in the Cobar regions, leveraging our assets, concentrating on filling our mills with high-value ore, while also working through the various synergies and cost savings across the region to strengthen the business where it makes commercial sense. So with that, I'd like to hand over to the operator so we can move into the questions and answers part of the presentation, please.

Operator

operator
#16

Thanks. If you'd like to ask something, hit star one on your phone and hold until your name is called. To withdraw your request, hit star two. Should you be using a speakerphone, please lift the handset before posing your question. Our first question is from William Taylor at Ord Minnett. Go right ahead.

William Taylor

analyst
#17

Morning, Bryan and the team. Appreciate you hosting the call. On Federation — clearly you've flagged that development is running ahead of plan. Could you give us some detail on where the other pieces on Federation's critical path stand right now? For instance, on things such as raise bores and infrastructure, how are you seeing contract availability and timing in those areas?

Bryan Quinn

unknown
#18

Yes, thank you, Will. I’ll give a quick response and then pass it to Michelle, who can add more detail on that question. On the development side, as you mentioned, we are ahead, and that is a critical path to reaching first ore, as is having ventilation through the raised bore. Right now, the team essentially began on August 1 to issue those tenders and to look for the strongest companies to partner with—ones with solid HSEC standards, the capability to do the work, the equipment, and the resources at the right price, obviously, to make it happen. So the team has been running a fairly intensive process to get those tenders out and reach the final stage. That has covered both the raise bore and the ventilation, the ventilation band, and the roadworks as well. At this point, they are all generally progressing in the right direction and are not affecting our critical path, but that is where all of them currently stand in the work. Michelle, would you like to respond with any additional comments, or just add something?

Michelle Tracey

unknown
#19

Absolutely. Thank you, Bryan, and I appreciate the question. Regarding the raise bore rigs, we're at the last stages of getting that contract finalized. The rig is secured, the personnel are secured, and everything is ready to mobilize. Field work on the pre-construction of the raise bore collars has begun, so that's moving along well. As for the road, which sits just off the critical path, that's a significant community project for us too. We're hauling pre-crushed material onto the road, and we've seen encouraging indications of solid progress and construction getting underway.

Bryan Quinn

unknown
#20

Is that a good enough response to what you asked, all right?

William Taylor

analyst
#21

Yeah, no, it really does. Yeah, absolutely. Thanks for that color. Maybe just touching on Peak — just looking at those development rates, what's driving such an increase? Is it just a volume basis where you guys are targeting more headings, or is there kind of continuous improvement initiatives that are kind of unlocking a lot of latent capacity there?

Bryan Quinn

unknown
#22

I believe it's a mix of every factor you brought up, Will. There's clearly a push for efficiency when it comes to placing the Jumbos under the correct headings and in the proper sequence. We also now have, I suppose, a Jumbo at both the South Mine and the North Mine, which is opening up what the mine can achieve. What we're really focused on is getting meters into the plan, and that gives us solid production security across the coming 12 months-18 months. It will carry forward and keep carrying forward. A big piece of this is also getting — as you may remember, we made a transition from contractor to owner-operator early in the calendar year. Staffing, bringing the right people on board, having the right management schedules, and having the right mine plan through to the engineering team itself matters a great deal.

William Taylor

analyst
#23

All right, that's great — I'll make sure to relay it. Thanks.

Operator

operator
#24

Thanks. As a reminder, if you’d like to ask a question, press star one on your phone and hold until your name is called. Our next question is from Roy Gill, a private investor. Please proceed.

Roy Gill

unknown
#25

Hi, this is Roy. Yeah, I had a lot of interest in the Dargues plant and what happens to it once the mine shuts down. Will it be put to use somewhere else, maybe at Peak or something like that? And then a second question: with your ore body at Federation, does it change gradually from low grade near the top to high grade further down, or is it more of, you know, a sudden shift? Yeah, I'd just like those answers, thanks.

Bryan Quinn

unknown
#26

Thanks, Roy. I'll start with the response and then pass things back to Andrew for both questions. Regarding the Dargues equipment, we've clearly put together a closure project plan for Dargues. That involves examining where in the Cobar region we can best make use of the equipment, obviously. If we're able to utilize equipment that we've identified, some of it will be brought over and used at both Federation and Peak, and hopefully for future projects as well. And where it doesn't make sense, we'll obviously consider a sales process for the equipment, and I guess remediation will happen for any other equipment that's left behind. So right now there's a project underway doing an assessment and trade-off of which direction is the right one to take things, but actively looking at it. So for instance, we're asking whether, for emergency egresses out of Federation, we could use any emergency egress equipment from Dargues that will effectively be demobilized once we retrieve certain parts of the mine. So as an example, we're looking at those things on an ongoing basis to see where we can obviously use the equipment elsewhere and save money. But as I said, an overall project is being formed at this point in time, between now and Christmas, to finalize that.

Bryan Quinn

unknown
#27

Regarding the Federation ore body, what we're doing at present is examining the delineation, or possibly the extension, to the west of that ore body. We're once again placing a drill rig in the second quarter within the mine itself to carry on with that effort. Andrew, would you like to address the remaining part of the question concerning the grades that came up?

Michelle Tracey

unknown
#28

Sure, no problem, Bryan, and hello Roy. So, when the feasibility study for Federation was released, we laid out a fairly comprehensive life-of-mine schedule covering tonnage and grade. If you go back and check, it's worth locating that document on the ASX. But we're already at reasonably high grade right from the start—it isn't a situation where we begin with low grade and then wait until we're deeper to reach better grade. We do achieve strong grades from the Federation ore body. As Bryan said, through underground drilling we'll aim to get a clearer picture of things such as gold and copper. That picture won't necessarily line up perfectly with the zinc grade. Having a better grasp of it will assist us in deciding how to handle that ore and, in effect, secure the best return from it via processing options. To also address your first question, and following on from that, Bryan has just walked through it as well. As you noted, we have work underway on that front. One thing we're mindful of is avoiding forcing a round peg into a square hole.

Michelle Tracey

unknown
#29

So, for instance, simply because we happen to have a ball mill at Dargues and we're looking to find a use for it, that doesn't necessarily mean it suits what we need at Cobar. Having said that, if it does fit, and we already own one within the group, then that's definitely helpful. And, you know, when I look at the Dargues plant, it's fairly close to new. At the front end it features an excellent three-stage crushing circuit. It has a solid ball mill, decent float cells, a filter — those kinds of items — and every one of them could prove useful to us in the Cobar Basin, whether at Peak or as we consider bringing Hera back online.

Roy Gill

unknown
#30

I appreciate that.

Operator

operator
#31

Thank you. Just a reminder — if you'd like to pose a question, hit star one on your phone. We'll take a brief pause now so any last questions can come through. Thanks. Our following question is from Rodney Sweetman, a private investor. Go right ahead.

Rodney Sweetman

unknown
#32

Thanks, and good morning, everyone. I just wanted to ask about Federation—in a few of the announcements or information packages that came out earlier, there's mention of a possible dispute involving Glencore. Could you explain what that involves and what the current status is, and whether this is in any way a leftover issue from 2015? Thank you.

Martin Cummings

unknown
#33

Hi Rodney, Martin here. If you look at the equity raise presentation from 31 May, we did actually lay out some specifics about the situation. You know, opinions differ on where Federation offtake ought to go. There's a process in place to settle that, but that's likely all I can say at this point. I should emphasize, though, that just as was the case during the equity raise, our financing package with Trafigura does not hinge on how that process turns out. So, you know, we're moving ahead with developing Federation confidently, and we'll aim to get that resolved in due course.

Rodney Sweetman

unknown
#34

I appreciate that.

Operator

operator
#35

Thank you. We have no more questions right now. I will now return the call to Mr. Quinn for his closing remarks.

Bryan Quinn

unknown
#36

Well, to close, I want to give a final thank-you to every member of the Aurelia team who's joined us on the call today. I've spotted a handful of you on here, which is terrific, and the same goes for our contracting partners and the other key stakeholders. As I said at the outset, thank you for the continued backing and the effort everyone is putting in to genuinely examine how we can get Aurelia Metals creating value as we move ahead. Just as I emphasized at the beginning of this presentation, we are on a journey, and I believe the right kind of plan sits in front of us, and we are certainly on track to deliver our guidance, and all the different components inside that are on track at this moment. So I'd like to thank everybody for dialing in, and we look forward to presenting our results at the end of the second quarter, and hopefully we can have a few more conversations about some of these projects and matters underway. So thank you all for attending and for your questions. We'll speak soon.

Operator

operator
#37

This brings today's conference to a close. Thanks for joining us. You're welcome to disconnect at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Red Hill Minerals Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Red Hill Minerals Limited earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Red Hill Minerals Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.