executiveThank you very much, and a good morning to everyone joining us. The company issued a press release on Tuesday evening, sharing the results for fiscal second quarter 2023, which closed on September 30, 2022. That press release, as well as the presentation, is available for you in the Investor Relations area of ReNew's site, www.renewpower.in. With me on this call are Sumant Sinha, our Founder, Chairman and CEO; Kedar Upadhye, our CFO; and Vaishali Nigam Sinha, our Chief Sustainability Officer. Sumant will begin by walking through an overview of the company and the latest key highlights. Kedar is going to take us through the results next, and then Vaishali will share an ESG update; after that, Sumant will wrap up the call by talking about our guidance for fiscal year 2023. Once that's done, we'll take your questions. Just a reminder: our safe harbor statements can be found in our press release, in the presentation materials, and on our website. Those statements matter, and they apply to everything we say. Various risks and uncertainties might lead our actual results to differ materially from what forward-looking statements express or imply. So please take a look at the press release we furnished in our Form 6-K, along with the presentation on our website, for a fuller picture. You'll find certain non-IFRS figures included as well in our press release, presentation materials and annual report; we've provided reconciliations for those against the closest equivalent IFRS figures, and you can access those reconciliations on our website within the press release, presentation materials and annual report. I'm delighted at this point to pass things over to Sumant.
Sumant Sinha
executiveAbsolutely. Thanks, Nathan, and hello everyone — morning, afternoon, or evening, wherever you happen to be listening from. I'll jump straight into the deck. Beginning on Page 4. Our underlying business is essentially on course, and during the opening six months of fiscal year 2023, we're tracking right where we planned internally, leaving out what the 528 megawatt acquisition will add, since that deal is still being completed. Across that first half, revenues and EBITDA both climbed above 20% compared with a year earlier, matching strong growth in our commission capacities, which lifted the total to 7.7 gigawatts of operating capacity. Right now, capacity under construction sits at 5.7 gigawatts in total, and we're aiming to have it running by the close of the following fiscal year, taking our overall portfolio to 13.4 gigawatts as things stand today. Customer revenues were up 28% versus a year ago during the first six months of fiscal 2023, while cash flow to equity climbed 48% in H1 against last year, driven by greater revenues from operating capacities along with improving DSOs. Our accounts receivables are moving along nicely, and we're receiving steady payments from those state distribution companies carrying the largest overdues, something Kedar will walk through more thoroughly during his part. Moving to new PPA signings on Page 5; during this quarter we signed 1 gigawatt of fresh PPAs, and we've also reduced risk in our growth since under 1.5% of our 13.4 gigawatt portfolio still lacks PPAs. That figure is below 1.5%. The corporate PPA portfolio on its own expanded 41% versus Q1 and now stands at 1.5 gigawatts, nearly 247% above the same period a year ago, with plenty of further talks underway that we're hoping to turn into signed PPAs over the next few months. In the quarter ending September 30, we signed over 400 megawatts of corporate PPAs, and among our customers are prominent names like Amazon, Suzuki, Mahindra and Toyota. We think this demonstrates the distinct edge we hold in this part of the business. Corporate PPAs deliver better returns than the claims tied to our renewable energy projects, thanks to tougher barriers to entry, our capacity to work alongside corporate customers, and our ability to supply them power faster than rivals can; we're in active discussions with numerous corporate customers at present, and we're confident ReNew will hold a corporate PPA portfolio of 4 to 5 gigawatts by 2025. On the whole, the growth backdrop stays bullish, since renewables keep being the cheapest option for new power capacity in India, as Page 6 shows. More and more, our customers want sophisticated power solutions delivered reliably across the entire year, and we've developed that know-how by providing a complete suite of renewable products, layered with digitalization and proprietary AI technology; in our view, that's a genuinely distinctive offering within the renewable sector. Because power must be supplied at all hours, interest in our smart energy offerings has grown. We anticipate auctions totaling more than 5 gigawatts for complicated projects in the coming months, and a further 8 gigawatts is being discussed at SECI. Beyond that, there is a opportunity exceeding 100 gigawatts by 2030. It's crucial to remember that 1 megawatt of RTC Power in fact calls for over 3 megawatts of renewable energy power. Adding 3E, which I will discuss, brings even more distinctiveness to what we offer. Our hands-on know-how spanning renewable energy technologies, paired with a top-tier digital platform, gives us strengths that only a handful possess, and you can observe this in how few bidders are taking part in the complex RD solution auction compared with the Plain Vanilla projects. This keeps opening the door to above-average returns, and our latest 300 megawatt hybrid victory demonstrates it. Against that backdrop, I'll now discuss our fresh growth efforts. We have executed definitive agreements to buy shares of 3E, a top European SaaS platform that boosts renewable energy asset performance using analytics and AI. The deal ought to close in two stages: 40% now and 40% in 2024. At present, 3E already manages roughly 20 gigawatts of assets. Looking at today's energy complex, digitization-driven efficiencies will be essential for ongoing differentiation and stronger returns, since IPPs increasingly want tailored products. We hold enormous confidence in this company and have relied on 3E's cutting-edge software for our own assets throughout the last 4 years. The 3E platform, together with the in-house digital tools we developed across years of experience, should, we believe, turn 3E into a global leader in asset performance management covering solar, wind and storage assets. This digital platform offers numerous worldwide possibilities that can lift our returns on the extra capital we are committing to this investment; we keep seeking to improve returns on the capital you entrust to us via capital recycling. We recently formed a partnership with Norfund, the Norwegian government investment fund, focused on developing countries; and with KLP, Norway's largest pension company, to co-invest in our transmission projects, and they have signed definitive agreements to put money into the very first project. Putting money into transmission projects works in tandem with our renewable energy project development and further supports stronger returns from our core renewable energy business. Having already constructed more than 6,800 kilometers of transmission lines across the past decade, long distance transmission follows naturally from our core capabilities. When we handle the execution of transmission lines tied to our own RE projects, we can bring those renewable energy projects online faster and with better predictability, and gain chances to capture extra revenues from our renewable energy projects in the power markets. Regarding our green hydrogen efforts, you might have caught the announcement we made yesterday about signing a framework agreement with Egypt's government to build a green hydrogen facility in the Swiss Canal economic zone. Under this agreement, a final investment decision is going to be taken within the coming 12 to 18 months. Implementation of this project is planned in phases, and the initial one is a pilot phase generating 20,000 tonnes of green hydrogen plus derivatives each year. During the following phase, output of 200,000 tonnes annually of green hydrogen plus derivatives will be reached, which lifts the project's overall green hydrogen production capacity to 220,000 tonnes per year. A risk we often get questions about is inflation risk affecting CapEx along with security of supply, and that's covered on Page 7; our view is that we've handled this effectively, and at this stage there's limited risk to our CapEx budget; turbine prices have been locked in, so basically there's no material exposure on this front. We keep constructing module and cell manufacturing facilities that guarantee supply at an advantage cost relative to imports for future growth. Should module prices increase by 10% versus today's level, our CapEx would shift by only roughly 3% to 4%. Since the majority of our wind turbine prices are locked in, basically there's no material exposure on this front. Our expectation remains that our new projects — we will deliver project-level equity IRRs inside our targeted range of 16% to 20%. If it happens that any additional new project has an expected IRR beneath our minimum thresholds, we simply won't move forward. Your capital will be handled with discipline. Having said that, I'd like to hand things over to Kedar for a review of the latest quarter's financials. Kedar, over to you.
Kedar Upadhye
executiveThanks, Sumant. Greetings to everyone joining us, whether it's morning, afternoon, or evening where you are. Let's go to Page 9. We've said it repeatedly during the last twelve months: our attention has been on getting better at collecting what the straight distribution companies owe us past due, and it's a pleasure to report real headway on that front. In quarter 2 of FY '23, DSO came in better by a month versus the close of Q2 the prior year, since the DISCOMs that had fallen behind on payments — roughly half of what we're owed — have started catching up. DSO typically climbs in the second quarter for seasonal reasons, yet this time it actually came down relative to quarter 1. Andhra Pradesh's DISCOM — the AP — accounted for around 42% of overdue receivables as of March 31, and in June 2022 it consented to settle those past dues across the coming 12 months via equal monthly installments; so far it has delivered about 4 of those 12 payments. Payments have also been coming in from the other states that were behind; our expectation remains that DSO will show meaningful improvement by the time the year closes. Up through November '22, Andhra Pradesh, as I noted, has completed 4 of 12 installments toward clearing its old balances, and additional states — Madhya Pradesh, Telangana, Karnataka and Maharashtra among them — are likewise catching up on past dues; indeed, better collections during the quarter lifted our cash position by $60 million in Q2, even though this is the quarter that usually carries larger accounts receivable balances; it deserves emphasis that DSO ought to improve fundamentally over time, because a growing share of our sales will go to the central government and SECI, which it owns, and that buyer tends to pay roughly on schedule. As things stand, with 7.7 gigawatts in operation, roughly 50% of our assets sit with five DISCOMs whose DSOs are comparatively higher. Since nearly all of our committed projects are now with SECI or with corporate customers, exposure to those 5 DISCOMs will drop to approximately 33% once our 13.4 gigawatt portfolio is finished; that shift in customer mix alone would account for a gain of 55 days in our overall DSO. Now I'll turn to Slide 10, where the highlights of fiscal Q2 2023 are laid out. We brought 75 megawatts online this quarter, taking the operating total to 7.7 gigawatts; we also signed PPAs for another 1 gigawatt, lifting what's under construction to 5.7, the bulk of which ought to be running by the end of next year. Customer revenues climbed 28% year-on-year in the first half, while cash flow to equity rose 48% versus last year, driven by greater revenues from operating capacities and DSOs that keep getting better. Moving to Page 11, you'll find the reconciliation of adjusted EBITDA for quarter 2, which comes to INR 18.2 billion. The way the window played out this year was different — April and May came in stronger, which fits the usual seasonal trend, but during the second quarter things flattened out at that level. We also need to flag some timing effects related to carbon credit sales and a few other items. That revenue landed in the second quarter of last year, whereas we now expect the bulk of our carbon credit sales to be recorded in the latter half of this fiscal year. If you strip that out of last year's 2Q, EBITDA would have been up about 9% compared to the prior year. Let's turn to Slide 12. We're still working through a number of financing efforts, and in this quarter we retired a bond worth $300 million. Back in FY '23 we had USD 1 billion coming due, and the bulk of that has already been settled through a range of refinancing actions. On Slide 12 you'll also find a reconciliation of sources and uses, plus our plans for funding. Our situation is quite solid, with roughly $780 million in cash sitting on the balance sheet, and by FY '25 we anticipate generating a similar sum from internal cash flow, recycling capital, and bettering our working capital. On the CapEx side, the equity needed for the 13.4 gigawatts we plan to build is more than covered by what we generate internally and by recycling capital, based on what lenders are telling us. That also leaves us room to expand even more without issuing new shares, and issuing new shares isn't part of our plan right now. Since we can fund projects with 75% debt, and given our cash flow generation and capital recycling, once the 13.4 gigawatts is finished we anticipate carrying a larger cash balance than we have today. On the interest rate risk discussed on Page 13, keep in mind that Indian inflation remains contained and sits far under what's being seen in the U.S. When you look at long-term rates in India, they're actually more competitive than what you'd typically find around the world. We've got a meaningful amount of extra borrowing capacity sitting ready — what you might call dry powder — and our view is that we can finance everything in our current plans from domestic sources. Right now, the offers we're getting for refinancing come in at roughly 8.5% to 9% in INR terms, and that's actually lower than the average interest rates on the debt that's maturing over the next couple of years. On top of that, our exposure to interest rate risk is fairly contained: 73% of our debt carries fixed rates, and if rates were to go up by 100 basis points, the hit to our FY '23 cash flow to equity would only be about 2%. Even with rates having gone up, we anticipate being able to refinance maturing debt at levels below what we're currently paying in interest. Throughout this year we've been taking advantage of chances to save through refinancing, and we're set to refinance over $11 billion, which further demonstrates how easily we can obtain reasonably priced capital. At this point I'll hand things over to Vaishali for an update on our ESG efforts. Thanks.
Vaishali Sinha
executiveThank you, Kedar. Good day, everyone, and I appreciate you being with us on today's earnings call. Could we pull up Slide 15? From an ESG standpoint, this has been quite a year for us, since we significantly increased our efforts, and we laid out those efforts in our sustainability report covering fiscal year 2022. Because members of our community count as key stakeholders, I'm pleased to report that the report was launched at one of our CSR locations in Rajasthan, with the local community and ReNew's Global Board present. The sustainability report follows GRI standards and TCFD guidelines. Because of our NASDAQ listing, it also follows SASB. We titled the report Partnering for Transition, Progressing Sustainably, Prospering Together, since we feel that captures our sustainability approach quite well. Consistent with the notion of progressing sustainably, we have limited the carbon intensity of our electricity generation to only 32.83 grams of carbon dioxide per kilowatt hour, which is 95% below the Indian power sector average and 94% below the global average. Thanks to our clean energy operations, we have avoided 11 million tonnes of carbon dioxide and produced electricity sufficient to power 4 million Indian households. We've implemented robotic dry cleaning, allowing us to conserve 216,000 kiloliters of water, enough to cover the daily consumption of 1.6 million Indians. Intending to partner with our employees, suppliers and communities for a carbon-free future, ReNew has undertaken these initiatives; we have reduced sustainability-related risks in our supply chain and have issued a sustainability code of conduct for suppliers, which you can find on our website. Our workforce has expanded by 38% versus last year, reflecting ReNew's goal of being the employer of choice. ReNew aims to reach 30% women through multiple initiatives, such as recruiter, mentoring sessions, awareness sessions with senior experts, including our Board members. Safety trainings held during the past year rose by 41%. At ReNew, our mission is to help tackle climate change through impactful, scalable and market-driven solutions that build a sustainable and equitable future. We are also finalizing a decarbonization plan for our operations, which we will disclose in the months ahead. Beyond that, ReNew has reported Scope 3 emissions across all applicable categories for the first time in our sustainability report. Regarding community engagement, we aim to touch over 2.5 million lives by 2030 via various community development initiatives spanning women empowerment, youth engagement, providing access to clean electricity, climate literacy; and all of these align with various LTGs, LTG 5, 7, 17 and a few others. ReNew is also a signatory to UNGC and UN Women Empowerment Principles. That brings me to the last but most important element of partnering for transition. Collaboration has always been something ReNew puts its faith in, and we're cultivating mutually beneficial ties with organizations that share our outlook — universities, policy research groups, and trade bodies — so that together we can pursue one shared aim in tackling climate change. Shall we move on to Slide 16? On top of that, we've made public our goals covering ESG metrics, including this: for a second year running, we've been certified as carbon neutral when it comes to Scope 1 and 2 emissions; and we've reached 30% diversity at the Board level. Our GHG reduction targets have been handed over to SBTI for validation. Through our social responsibility initiatives, we've touched the lives of 650,000 people spanning 10 states and 250 villages. We've introduced a human rights policy along with approach notes addressing circular economy and biodiversity — all of which you can find on our website. Progress on each of these targets will be shared in upcoming sustainability reports. At this point I'll hand things back to Sumant for his closing remarks and guidance.
Sumant Sinha
executiveAppreciate that, Vaishali. Turning to the guidance we laid out on Slide 18, the company's core operations are still performing in line with expectations for this year. As noted previously, weather has worked against us so far this year, yet we accounted for that when setting our initial FY '23 guidance; beyond that, we're still pushing to finalize the acquisition we announced, and that has run into some delays. At this stage we're reaffirming our guidance, with the clear condition that full year EBITDA hinges on typical weather through the rest of the year and on the acquisition being wrapped up on schedule. For FY '23, our EBITDA guidance sits at between INR 66 billion and INR 69 billion, while cash flow to equity guidance comes in at INR 21 billion to INR 23 billion; regarding the buyback, roughly 20 million shares have been repurchased since the program began, leaving approximately $120 million of authorization still available under it; we keep seeing substantial value in our shares, given an 11% cash flow to equity yield on the portfolio we hold today. R&W likewise trades at a sizable discount relative to what we could sell assets for. Since our shares rank among the highest return investments at scale that we can pursue, we've been actively repurchasing stock whenever we think it offers the best return opportunity. I'd also like to point out that we've been added to roughly six indices during this calendar year, among them the most recent ICLN or <<inaudible>>. That doesn't just support average daily volume — it also raises awareness of RNW among a wider audience. With that, thanks for your patience, and we'll gladly take any questions you have. Thank you.
Julien Dumoulin-Smith
analystMorgan here, filling in for Julien. Great quarter — congrats. Looks like DSO came in much healthier this time around. What's your outlook for how that trends over the rest of the year? And with that extra headroom, does it shift how much room you have for putting more into investments? Any take on that.
Sumant Sinha
executiveYes. Kedar, want to handle that?
Kedar Upadhye
executiveCorrect. Correct. Thus, as we laid out, the state with the largest outstanding arrears was Andhra Pradesh; and in the balance sheet dated September 30, two of the 12 installments are in hand. Following September 30, two additional installments come due. And through March 31, which is what you asked about, 6 further ones will arrive; so altogether, across this year, roughly 8 installments of meaningful value will come in, and that lifts DSOs back to a level nearly matching pre-COVID times, and that stands in sharp relief against the heightened DSO levels observed across the last several quarters; so quoting an exact figure makes me somewhat reluctant, yet I am confident DSOs will fall to a level near 175 days or so; indeed, by October, DSO had already reached 270. So obviously that frees up cash and, as you suggest, it lets us put in more equity to support future growth, and every bit of that forms part of the plan. So the slide covering source and use of financing, which we have folded into our debt this quarter, which we mentioned in the opening remarks, reflects improvement in receivables too.
Morgan Reid
analystAnd then, I suppose, might you also discuss the co-investment announced during this quarter in the transmission projects? And how do you see such opportunities fitting into your wider capital recycling plan? Are there any intentions to keep pursuing these co-investment strategies, or any remarks on that?
Kedar Upadhye
executiveSumant, would you like to handle that question?
Sumant Sinha
executiveCertainly, certainly, I’ll take care of that. So Morgan, to this point we’ve locked in a number of transmission projects, and as I mentioned in my prepared remarks, those are highly strategic for us because they tie into the renewable energy developments we are constructing. That means they help us bring those developments online on schedule and make the timing of the overall development much more predictable. As for the financing from Norfund and the other company, KLP, basically it’s intended to partner with us and take a 49% interest in the first of those projects, with the expectation that later on they’ll continue teaming with us on further projects as well. So we do have a broader arrangement with them to join more of our transmission projects. And once we get those projects and move them to the appropriate stage, what we’d anticipate is that we’ll continue having them come in as coinvestors alongside us from the very beginning. On asset recycling, as we’ve said before, that will be central to our strategy going forward. We truly see asset recycling as a key way for us to get greater value from our own capital invested in those projects, and also to unlock capital that we can then redeploy to grow our portfolio further. On top of that, it gives us an opportunity to reshape our portfolio in ways we think could ultimately benefit us more in terms of retaining capital over a longer horizon. So recycling capital is a vital part of our overall strategy. In transmission, as we’ve noted, we’ve only just started that business, and right away we’ve brought in very high-quality partners to join us. For our other existing renewable energy assets, we’re still in talks with quite a few different investors. And as you know, for our first RTC project, Mitsui is a partner with a 49% stake; and we expect we’ll divest more assets, potentially to them and to other investors as well going forward.
Justin Clare
analystAlright, to start things off, you locked in 1 gigawatt of PPAs during the quarter that just wrapped up, which is quite a meaningful step forward. So I'm curious — has there been a notable shift in power demand, and are you finding it faster to get these PPAs over the line? Also, how widespread is that demand? And given where the market stands today, what should we assume about the lag between winning an auction and actually signing a PPA?
Sumant Sinha
executiveYeah. Justin, well, in the — yes. Apologies, I was mid-answer there. Right, so within that 1 gigawatt, 400 megawatts are corporate PPAs, the ones we've discussed; the remaining 600 megawatts came from LOAs we'd secured previously that have since been turned into PPAs. That's what makes up the 1 gigawatt — that's where the 1 gigawatt comes from. But really, I think what you're asking about is the momentum we're witnessing in the market today when it comes to power demand, and as a result, how often bids are coming out and how much they add to our portfolio. As you're aware, power demand in India has been expanding quite strongly, at roughly 6% per year at present; and over the past several months, there's been what I'd call a pretty sizable power shortfall in India, and looking ahead, that situation will probably persist. Because of that, both distribution utilities and corporates are seeking to bring on new energy sources. And since renewables are currently the least expensive way to generate electricity, they're the clear choice; now SECI is rolling out quite a few auctions. Actually, we've already put in first bids on a couple of auctions; these are all round-the-clock power style projects; meaning the more complex ones, and those bids should take place shortly, within the next month or so. Beyond that, we also see plenty of additional bids that SECI has now lined up, working alongside the states and the DISCOMs. So as we mentioned, we do expect roughly 5 gigawatts of RTC auctions to reach the market imminently. As I noted, on some of those we've already submitted first bids. Others are arriving very soon. And past those, a further 8 gigawatts of RTC auctions are on the way. So our read is that power demand is now starting to show up as bidding activity, and with the bids currently underway, SECI is running them with a fairly clear picture of the off-taker instead of bidding first and hunting for the off-taker afterward. As a result, we anticipate that the journey from bidding to PPA signing will proceed somewhat more smoothly than was the case previously. As everyone is aware, the past was obviously thrown off course by COVID. Things are now returning to normal across the board. Consequently, we anticipate that these bids will fairly quickly turn into PPAs. Before COVID, it typically required 3 months, and we think that same duration will return. Then, as you're aware, after PPAs get signed, we have 2 years in which to build the projects. So whatever bid takes place now during the rest of this financial year, FY '23, must be constructed by financial year '25. That essentially sums up where things stand at present.
Justin Clare
analystAll right, understood. Then, I suppose, regarding the level of demand you're observing, is there any increase in pressure pushing PPA prices higher, either within the corporate segment or through auctions? Is that demand causing those PPAs to rise?
Sumant Sinha
executiveJustin, the situation is that since uncertainty has grown around commodity prices and rates of interest have risen, naturally these get passed along through elevated tariffs. Consequently, tariffs broadly across the market have risen, mirroring greater costs on the input side, since clearly we pass those along to the customers who ultimately buy; that, I believe, is essentially what's taking place. The particular matter of what returns come from such bids truly depends on how fiercely competitors are bidding, which itself depends on what the bid looks like and who might be the eventual buyers; take, for instance, the corporate PPA segment, where, as we've mentioned, much hinges on what sort of tailored solution you're able to deliver. There, we observe a smaller number of companies competing. Similarly, for round-the-clock power offerings being tendered by SECI, once more only a handful of bidders participate, since these prove tougher to carry out, more intricate, and involve bigger projects, all of which suit our strengths; thus, across each of these, we anticipate IRRs that ought to fall squarely inside our 16% to 20% band. I'd rather not say whether it lands at the top or bottom of that, since clearly these bids have yet to occur. Still, I can state that we anticipate being quite comfortably inside our general IRR band for many of these upcoming bids; and indeed, power prices have climbed owing to higher input prices.
Justin Clare
analystOkay, great, that's quite useful. Now, considering the different phases of the projects you've got underway, could you discuss any significant obstacles that are still standing in the way of bringing the 13.4 gigawatts you intend to have online by the close of fiscal '24 into service? With your manufacturing scaling up, how do you feel about your situation regarding solar panel availability? And what's your read on the wind supply chain too?
Sumant Sinha
executiveYeah, so listen, when it comes to the supply chain, I'll actually address your question in a wider sense too, touching on a few other elements. On the supply chain side, obviously, as I mentioned, for wind, we've essentially secured all the turbines needed for the megawatts we need to bring online. By secured, I mean we've locked down the supply. Naturally, the turbines will arrive when we need them for installation, closer to the point when they must be installed, but basically, every turbine has been locked down. On the solar module front, several of these projects are grandfathered when it comes to custom duties. So for those projects, importing was permitted, and as a result, we've locked those in too; and for the ones we secured after April of last year, for those we were going to rely on our own module supplies. That's something we'll begin receiving from the initial section of the module facility we're bringing online around the Q1, Q2 period of next year. So even the module supply is essentially locked down too. Therefore, we don't expect any equipment problems or equipment supply problems to trigger delays in building these projects. On the financing side, I'll have Kedar address that; but I believe basically, work is proceeding at a good clip now, and at this stage, there could be the typical execution challenges we face in India related to right-of-way issues and such. Those will need to be resolved as they arise. But we expect that given everything we've accomplished so far and the ongoing work at sites, including land acquisition and so forth, we'll manage to bring the vast majority of the 13.4 gigawatts online by the close of next financial year. So we're on track to complete that. Kedar, would you like to cover the financing aspect too?
Kedar Upadhye
executiveYes, absolutely, Sumant, absolutely. So my view is that obtaining funds and making them reasonably priced is going quite smoothly at present. Our aim has been set to shift the debt portfolio increasingly toward Indian rupees. A while ago, close to 2/3 of it was denominated in dollars, whereas today it stands at roughly half. That means Indian rupees account for one portion and dollars for the other. For refinancing purposes, the majority of term sheets coming our way fall between 8.5 and 9 on a rupee basis, which genuinely assists us in creating a natural hedge. As we mentioned, access to capital within the country has gotten better. A few institutions backed by the government are stepping up to provide loans to businesses such as ours, and that too is proving helpful; so overall, things look positive where financing is concerned.
Sumant Sinha
executiveAnd the — yes, go ahead. Sorry.
Nikhil Nigania
analystFirst up, I'd like to ask about hedging packages. Could you shed some light on how swaps and options are split when it comes to dollar debt exposure? Does that cover the whole life of the debt? And if options are involved, what exchange rate is ahead there?
Sumant Sinha
executiveRight. So, Nikhil, we do use a combination of instruments. And from our perspective, when we back tested how effective our hedging practices are, it showed up as quite suitable for us. Occasionally, should the rupee depreciate in a given quarter, we end up taking an accounting charge, and that's noncash; however, from a commercial standpoint, mixing plain forwards, add the money forwards, and cross currency swaps has demonstrated its usefulness for us. I can share with you offline the sort of rates we managed to lock in, but close to half of the hedges come as plain forwards, where we lock in the prevailing rate plus a premium on a year-on-year basis. The rest is distributed across ATMF options, and as I mentioned, a few of these sit at 90 or between 90 to 95.
Nikhil Nigania
analystGot it. My follow-up concerned the round-the-clock project that's currently being built. There, word came that the debt being borrowed had been secured. So could you share some indication of what the cost of borrowing came to, and does the IRR guidance remain valid for that project?
Kedar Upadhye
executiveYes, for that one the IRR guidance remains valid. It was a sizable loan, close to $1 billion, and a consortium of over 10 banks was involved; the facility was tied to USD SOFR at roughly 9% or thereabouts, Nikhil; and we continue to sit comfortably within the IRR range we aim for — when it comes to projects of this type.
Sumant Sinha
executiveOne thing I want to mention as well, Kedar, is that once we did that farmdown with Mitsui, the IRR really has ended up being quite a bit stronger.
Nikhil Nigania
analystGot it. I just have a single additional question regarding that. That 9% figure refers to the interest rate on dollars, correct?
Kedar Upadhye
executiveYes, dollars, along with SOFR, the spread, and the cost of hedging. So that 9% represents the complete, fully loaded expense of...
Nikhil Nigania
analystUnderstood, that's useful. Alright, my final question concerns the storage opportunity. A lot of competitors have been looking into pumped storage possibilities, so I'd like to hear ReNew's perspective and whether there are any plans in that area?
Sumant Sinha
executiveRight. Pumped hydro is a business with a very lengthy gestation period. I'd say the earliest pumped hydro projects likely won't arrive until 2025, and really just one at that point, while others could take somewhat longer. That said, we do think pumped hydro can play a part in certain applications within the country, so we are evaluating pumped hydro opportunities. But as I mentioned, this is a lengthy gestation business, so bringing such projects online will require time. Our position also remains that batteries will serve a highly significant purpose when it comes to storage, and ultimately that will be rolled out at scale too. Naturally, during roughly the past year, battery costs have risen, but we sense that, with commodity pricing now easing and government policy hopefully becoming somewhat more favorable, battery costs ought to decline and become far more competitive for shorter to medium-term storage activities; so I believe batteries and pumped hydro each have distinct roles. Batteries, naturally, as I noted, can be brought online far more quickly and in a far more modular fashion, thus offering greater flexibility and being less — in certain respects, less demanding on the grid or on transmission. In fact, anything that lets you utilize transmission lines more advantageously. Pumped hydro differs somewhat, since you may need to shift power over long distances. Consequently, over the longer term, our stance remains that batteries will dominate, though I don't see it as an either-or situation — most likely both will occur to some degree. And we are evaluating pumped hydro too.
Puneet Gulati
analystMy opening question concerns the wind PLF, which once again came in surprisingly this quarter. I recall that a similar situation occurred last year, and at that time you stated your intention to revisit your wind projections. Could you tell us where things stand regarding your reassessment of those projections?
Sumant Sinha
executiveYes, Puneet, we did say — you are completely correct that we said we would hold off until this windy period, the season of strong winds, had concluded and afterward decide whether a reevaluation was warranted based on how things turned out. And I concur with you that wind performance has likewise failed to meet expectations during this year. That said, for each of the past 3 years, the gap between actual results and the long-term mean has kept getting smaller. So at minimum that trend has been occurring, yet it has not gone back to the level we took as the mean. What we intend to do across the coming few months is engage an outside firm to take another look at every long-term assessment for our wind projects and attempt to determine whether any modification to those forecasts is actually necessary. So that is the effort we are beginning right now, and I believe within the next few months we ought to receive some preliminary perspectives on it. And naturally, we would then be glad to pass those along to all of you. In the meantime, let me say that we have factored in how wind has performed across the past 2 years; we have grown, I think, considerably more — I wouldn't claim considerably more, but definitely, we have grown far more attentive to examining how wind has done in the near term across recent years whenever we put together our longer-range forecast; so we are exercising somewhat greater caution regarding the long-range forecast. Thus that adjustment for upcoming projects, one that incorporates the recent several years, is being implemented. If — ultimately, if the past 3 years turn out to be more of a deviation from the long-term mean, then all the better, since we simply ended up cautious regarding the large forecast moving forward; and naturally, should it actually represent a shift from what we believed to be the long-term mean, then at least our upcoming bids will align better. So that is genuinely where things stand.
Puneet Gulati
analystUnderstood. For my follow-up, I want to ask about the deal — the 0.5 gigawatt purchase. What is causing the hold-ups? And at this point you have also split out your EBITDA projection into what comes from the acquisition and what comes from organic business. So could there be a chance that this acquisition slips to FY '24 instead of '23?
Sumant Sinha
executiveKedar?
Kedar Upadhye
executiveCorrect. Correct. So, Puneet, right now we're working through bringing that acquisition in, and it's happening via a slump sale; with a slump sale, you're basically buying all the assets underneath — the land, the PPA, all of it — and that takes somewhat more time than buying a company would; plus, naturally, you've got to work around state-level complications and regulatory questions, which is why it's dragging on a bit. At this point, it's hard for us to say with any precision what the final figure will be for this year. That's the reason we went ahead and broke that item out separately for you. Some risk could be there, but we'll be in a much better position to give you the size and scale of it on the February call. So that's why we keep saying the guidance depends on that acquisition closing. That said, Puneet, I ought to mention that this deal's lockbox date falls in April, meaning the moment the acquisition closes, the cash is locked in. The sole open item is how it gets recognized — in the P&L on the revenue side versus on the balance sheet as a cut to capital expenditure. So that's the one addition I wanted to make: the lockbox date sits in April. So the economic interest is locked in. The only remaining piece is the accounting — whether it lands in P&L or on the balance sheet.
Puneet Gulati
analystUnderstood, that helps. My final question concerns the project. You mentioned, Sumant, that you'd abandon projects failing to deliver IRRs between 16% and 20%. So does that imply certain projects exist — or do you anticipate some within your portfolio carrying that type of risk, ones featuring tariffs as low as 2.18 or 2.35? Do you expect a moment when you'd simply drop such projects from what you hold?
Sumant Sinha
executiveNo, Puneet, allow me to clarify. My point was not about what we currently hold, but rather any upcoming bids we may enter. Should we observe tariffs dropping to a point where our usual target returns — 16% to 20% — become unattainable, we'd step away from bidding; we wouldn't proceed to develop those bids under such circumstances. Regarding assets already sitting in our portfolio, ones we secured previously, with PPAs already executed. To begin with, generally speaking, I'd note that nearly all our projects fall inside the established range, so we foresee no problems; yet should problems arise, once a PPA is signed it becomes hard for us to exit, and we likely wouldn't pursue that route; in an extreme scenario — should some adverse circumstance emerge that couldn't be predicted, someone might weigh doing so. Still, one must remain highly conscious of every consequence tied to our relationship with SECI alongside reputational concerns and similar matters. So that isn't an action we'd take casually after a PPA is executed; however, prior to entering the bidding stage itself, naturally, should projects fail to clear a hurdle rate, we won't move forward to secure them. In that regard, we are extremely disciplined, and we've stayed extremely disciplined across the past numerous years, which has actually served us well. In fact, if you perhaps — although our market share ranks largest regarding bid wins throughout the past several years. If you likewise examine the share of losses on bids not won, you'd discover we're likely among the highest there too.
Puneet Gulati
analystTake projects such as 975 megawatts, Rajasthan 4, where your tariffs were 2.18 — you still believe you're able to earn IRRs of 16% to 20% on those. Since a number of peers appear to be walking away from projects of that type that carry low tariffs. If you could also address that.
Sumant Sinha
executiveNo; so with those projects, like I mentioned, with one-off projects, a situation can arise. I can't recall the particular project you're referring to and exactly what its numbers are. It's quite possible that with one-off projects here and there. Ultimately, once you get to executing the project, the IRR comes out lower. That can happen. But on the whole, like I mentioned, we're capable of delivering what we bid for, and we only bid for 16% to 20%; and so, in the great majority of instances, we wind up delivering that amount or occasionally even more. Take, for instance, the RTC project, which illustrates this. Following the farm down, we expect to earn equity IRRs above 20% on that project; so yes, so when it comes to execution, things do tend to move one way or the other, based on particular shifts in commodity prices or interest rates or execution problems. But like I mentioned, the great majority of our projects are — every one of our projects is bid and won at somewhere between 16% and 20%, and the great majority of our projects remain inside that band after execution too.
Nathan Judge
executiveLet me jump in briefly on top of what was said. Earlier in his remarks, Sumant noted that we keep holding plenty of discussions with investors regarding capital recycling, and that in general, throughout the portfolio, there’s a chance to boost the IRRs of any given project.
Puneet Gulati
analystYes, got it. Got it. And if I could just fit in one final question. You mentioned that projects prior to April '21 are now grandfathered. From the government's side, is it now clear that this isn't a change in law, but rather grandfathering?
Sumant Sinha
executiveFour projects that were bid out before April 1, whether that's grandfathering or a change in law — Kedar, do you have any sense of that?
Kedar Upadhye
executiveActually, Sumant, let me address that particular item separately. We can discuss it away from this call, and then we'll follow up with you.
Amit Bhinde
analystI'd like to hear your thoughts on the offshore wind chance that's emerging. Word came out that tenders would be issued for 4 gigawatt in Tamil Nadu. So how do you see that chance? And how ready are we for a project like that?
Sumant Sinha
executiveYeah. Well, look, on offshore, it isn't clear right now when — and when the tender will arrive and what shape it will take. MNRE, of course, is moving toward trying to bring something forward on the offshore wind front, but nothing formal has emerged yet, not even at a discussion stage. So it's tough to say precisely what the timing would be and what a bid's contours might look like. That said, MNRE is also seeking to allocate certain blocks of the ocean floor for blocking for the future. And so that's something they are — that's likely to emerge sooner. We definitely do plan to take part in those auctions for the seabeds too. And of course, in the end, whenever an offshore win does emerge, we'll, of course, be very active participants in it. In fact, there are a number of potential partners we've been speaking with, who have been speaking with us about partnering on those kinds of bids as and when they arrive. So I think we'll probably bid for those together with our partnership with somebody who has specific experience of offshore wind in some other geographies. I should mention that when — last time when MNRE was looking at some of these things in 2018, back then, we very actively did a lot of work, and we had partnered at that time with a couple of — one European and one Japanese company to do the bid. Of course, that never progressed; so we did not go ahead either. But as and when the bid emerges, we'll of course, participate very actively.
Amit Bhinde
analystAll right, that's really helpful to hear. Now, regarding land, sir, I'd like to get a sense of what sort of land we currently have available past that 13.4 gigawatt commissioning. So, is our land supply adequate, or will we need to pursue fresh acquisitions of land, pick new sites, and so forth?
Sumant Sinha
executiveYes. So we're continuously assessing and ensuring we hold a pipeline of development assets that exceeds the PPAs already secured. And it isn't only about acquiring land — securing transmission and connectivity matters just as much. Both are handled together. And sometimes, when transmission connectivity can be obtained, buying land in that location becomes unnecessary, since you've already reserved the connectivity there; so approaches may differ when it comes to securing development pipelines for the future. Yet at any moment, an exact figure isn't something I can provide, since it naturally shifts. Still, we would generally keep a development pipeline underway that sits roughly 2 to 3 years past our contracted portfolio. So, assuming the contracted portfolio today stands at 13.4 gigawatts, we'd usually hold a development pipeline extending at least another 2, 3 years forward; and it's precisely from that development pipeline that we later bid on upcoming projects past the contracted capacity already secured. So that's quite an active initiative. We haven't discussed it previously, but it's something we're working on continuously, because in a sense, it's what grants us the right to keep expanding our business. And so, considerable effort and focus go into that area; and naturally, we also deploy development capital to ensure we keep either reserving land or transmission connectivity, whichever is suitable.
Sumant Sinha
executiveThank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete ReNew Energy Global Plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to ReNew Energy Global Plc earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in ReNew Energy Global Plc or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.