ReNew Energy Global Plc (RNW) Earnings Call Transcript & Summary

June 7, 2023

NASDAQ US Utilities Independent Power and Renewable Electricity Producers earnings 45 min

Earnings Call Speaker Segments

Nathan Judge

executive
#1

Thanks, Darcy, and hello everyone, good morning — we appreciate you being here. The company put out a press release on Tuesday evening covering results for the fiscal fourth quarter, which closed on March 31, 2023. You can find both that press release and the presentation in the Investors Relations area of ReNew's site, www.renew.com. Joining me now are Sumant Sinha, our Founder, Chairman and CEO, along with Kedar Upadhye, our CFO. Once the prepared remarks wrap up, the line will be opened so you can ask questions. Just a note that our safe harbor statements appear in the press release, the presentation materials, and the materials posted on our website. Those statements matter and form an essential part of everything we say, and risks and uncertainties exist that might lead our results to come out materially different from what such forward-looking statements express or imply; therefore we urge you to look over the press release furnished in our Form 6-K along with the presentation on our site to get a fuller picture. Our press release, presentation materials and Annual Report also include certain non-IFRS measures, which we reconcile against the most comparable IFRS measures, and those reconciliations can likewise be found on our website within the press release, presentation materials and Annual Report. I'm glad now to turn things over to Sumant.

Sumant Sinha

executive
#2

Thanks, Nathan. Greetings of the day to everyone joining us — morning, evening, or afternoon. It's a pleasure to have all of you with us on this call for ReNew's Q4 FY '23 results. To kick things off, I'd like to lay out 3 key points. First, the renewable energy sector in India keeps gaining momentum, with some very heartening progress seen of late. The Ministry of New and Renewable Energy — the body responsible for India's renewable sector — has tripled the speed of its auctions, taking them to 50 gigawatts for FY '24 and beyond, beginning this April. What matters more is that most of that added volume should come through complex and wind auctions, areas where our competitive strengths are well established. In fact, across the initial set of these auctions, we have encouraging news to share — a complex bid one with a fairly healthy IRR. Naturally, we'll share more on this, along with certain corporate and state-level bids, once the PTAs are signed. We're also happy to share that we've formed a joint venture with Gentari, the renewable energy arm of Petronas, covering our Peak Power project. As you're aware, we see capital recycling as one of the pillars for boosting shareholder value. Beyond these bright spots, regulators have taken several measures to make life easier for companies such as ours, among them the Late Payment Surcharge scheme continuing successfully, which has brought our DSOs down considerably, to 138 days as of March 31. These and other shifts genuinely give us the confidence to keep building our growth path in this market. Second, as you know, ReNew will mark 2 years since listing on the NASDAQ within the coming couple of months. Over that stretch, we've expanded our organizational footprint and capabilities in the key areas needed to capture the global climate transition opportunity. We've strengthened our talent bench by bringing in several key leaders across crucial functions — project execution, regulatory, business development, digital, and solar manufacturing — along with 4 additions to our highest-level management committee, drawn from diverse global backgrounds. We've taken numerous steps to sharpen our readiness for what lies ahead. For instance, we're seeing solid momentum in our solar manufacturing operation, which delivers critical supply security and cost advantages to our core renewable energy development business. During this same period, we've also reinforced our in-house wind EPC capabilities so we can deliver projects at scale. We remain engaged with stakeholders, and our sustainability ratings have gained good traction. As you're also aware, CPPIB, our largest investor, has raised its economic stake in the company to 52%. All of these important milestones firmly place us as a stronger climate transition leader. Third, on page 6, we keep executing well on the other key building block — financing. In fiscal year 2023, amid a challenging borrowing landscape, we managed to refinance over $1 billion of maturities, bringing down interest expenses by shifting toward loans denominated in rupees. As I noted before, we've entered into a joint venture agreement with Petronas, a company eager to expand its footprint in renewables, and we've already received the initial installment of their equity investment for the Peak Power project. We anticipate growing this partnership even more. Simultaneously, we're looking into ways to monetize the assets we hold. Our plan is to systematically pursue asset recycling efforts as a means of boosting shareholder value; this also allows us to improve returns, secure funding at multiples greater than what our stock price suggests, which in turn backs focused expansion at solid returns without the need to issue additional shares. If you turn to page 7; MNRE's latest effort to speed up the yearly auction rate to 50 gigawatts — roughly triple what was auctioned annually in the past two years — along with a move toward a larger share of intricate projects, opens up major market possibilities for us. Meanwhile, we're observing reduced competition, which is driving up tariffs in recent auctions, and when combined with our unique capacity to handle complex projects, the IRRs from auctions we've recently secured rank among the best we've witnessed in many years. For example, a recent auction for peak power supply took place, and we emerged as one of the largest victors. Although I'm aware that the PPA hasn't been signed yet, this is an intricate project that will demand a substantial amount of wind capacity to satisfy the daily dual peak and high PLF delivery needs; this intricacy obviously led to considerably higher tariff offers from our rivals; actually, among the — among the 12 bidders, most ended up with final tariffs that were 10% to 20% above the level where we prevailed, which we think demonstrates that we have succeeded as, if not the cheapest provider for complex projects in the nation. The tariff we achieved came in roughly 35% above the tariff from our prior RTC project, even though CapEx isn't anticipated to be significantly greater on a normalized basis. To put it differently, this project and others like it should generate IRRs that exceed even the top end of our intended IRR range. In short, as shown on page 8, ReNew holds a major competitive edge in complex auctions. We're among the handful of Indian IPPs possessing in-house wind EPC, fully integrated solar execution, and a JV partner with robust credentials in battery storage systems. The exclusive wind-related data we've amassed over time, paired with our digital platforms, puts us in a favorable position. There's a shortage of EPC and operational expertise in India for wind at scale, and even fewer can deliver wind, solar, and storage seamlessly. We're pleased with the result and look forward to signing the PPA later this year. Just keep in mind, we don't put winds into the portfolio before a PPA has been signed. If you look at page 9, we're glad to report that for financial year '24, we anticipate finishing between 1.75 gigawatts and 2.25 gigawatts of execution, with the rest — 3.5 gigawatts to 4 gigawatts of under construction capacity — coming through in FY '25. Keep in mind that although execution will be distributed across the year, a significant portion of that capacity should come online in the final quarters of each fiscal year, which constrains the profit contribution during the year of commissioning; since we last spoke with you, we've further derisked our growth in FY '25, because our 2 biggest power projects — the round-the-clock and the peak power projects — are well advanced across multiple stages and on track to be completed by the end of the current fiscal year. Also note that cost savings have materialized compared to late last year, when we would have needed to purchase modules to deliver these projects on the timelines originally discussed. These 2 projects account for the largest portion of our 35% plus growth in adjusted EBITDA in FY '25. Our manufacturing facility should begin production by early next quarter and deliver much needed security of supply, given the supply side challenges in solar module sourcing in India currently; with that, I'd like to hand it over to Kedar, our CFO, to walk through the latest financials. Kedar?

Kedar Upadhye

executive
#3

Thank you, Sumant. Let's turn to slide 11 now, where we've laid out the key points for fiscal year 2023. Across this fiscal year, our portfolio grew from 10.7 gigawatts up to 13.7 gigawatts — that works out to a 28% jump versus the year before. On the top line, total income of revenues for fiscal '23 climbed from $912 million to $1.1 billion, which is a 29% rise on a Y-o-Y basis. Adjusted EBITDA for FY '23 came in 12.4% higher across the fiscal compared with the previous year, while cash flow to equity was up 18%. Wind PLF and solar PLF sit at approximately the same levels we saw a year earlier. That said, per a recent wind resource study carried out by the industry expert syndicate, the thinking is that there's a strong likelihood the unusually weak wind resource seen across the last several years will return to normal over the years ahead. If you go to page 12, you'll find a reconciliation of adjusted EBITDA, which lands at $753 million, or 12% above last year — and that's in spite of weak wind resource and carbon credit sales that were comparatively lower than a year ago. You might have picked up on the fact that at the overall company level, our EBITDA margin is lower than in earlier periods. The truth is, for our core business the EBITDA margin is comparable, at roughly 80.3%. Accounting for our transmission projects distorts the reported overall EBITDA margin somewhat, since we're required to comply with the requirements of IFRS standard IFRIC 12 on Service Concession Agreements; this contributed roughly INR 27.5 million to income and INR 7 billion to cost of goods sold, so the effect on adjusted EBITDA was capped at INR 0.4 billion. Such reporting applies while transmission assets are being constructed, after which the annual income under the PPA gets reported. Now on page 13, we're still working hard to boost collections and recover past due receivables from the state distribution companies. As Sumant pointed out, year-end DSO got better by almost 50% versus last year, dropping to just 138 days. Discoms keep paying down overdue amounts, and over time we still anticipate further gains in our DSOs. With a growing share of our sales going to Central Government-owned authorities, which <<inaudible>> around time. Running through a summary of our balance sheet, liquidity stands at close to INR 77 billion, counting cash and bank balances, which is quite healthy. In the current quarter we brought in approximately $600 million of debt, and net debt currently sits at INR 455 billion; with that, let me go to page 16 and discuss our ESG initiatives. Our Chief Sustainability Officer, Mrs. Vaishali Sinha, couldn't join the call today because of her travels; we remain committed to setting new benchmarks across every aspect of ESG vision, performance and transparency. To start, we're very excited to share that the near-term target and the net zero goal for 2040 at ReNew have now been formally validated by the well-regarded Science Based Targets Initiatives, or SBTi. As everyone knows, the SBTi gives recognition to companies that establish bold targets for cutting emissions consistent with the most current climate science. This strengthens how ReNew lines up with the Paris Agreement and connects what we aim to achieve with work to cap global warming at 1.5 degrees Celsius above pre-industrial levels. Regarding the net zero goal, ReNew pledges to achieve net zero GHG emissions throughout our value chain by fiscal 2040, and we pledge to cut our absolute Scope 1, 2 and 3 GHG emissions by 29.4% by fiscal '27, using fiscal '22 as the base year. Our most recent ESG ratings and scores stand as proof of our work on performance and transparency. As confirmation of our commitment and results in ESG, we recently got a rating of 11.6% from Sustainalytics, a global ESG ratings company. That places ReNew at number 10 worldwide in the utilities category and at number 7 worldwide in the renewable energy category. In addition, ReNew got a rating of A minus for its supplier engagement rating for 2022 from CDP, which places us in the leadership bank. ReNew's ACR exceeds the Asia regional average of C and exceeds the renewable power generation sector average of B minus. A new minus rating from the CDP ACR for ReNew shows that the company is putting current base practices into action to speed up progress on supply chain emissions. With that, I'll hand things over to our CEO, Sumant, for his comments on our FY '21 guidance.

Sumant Sinha

executive
#4

Absolutely, Kedar, thank you. Turning to the guidance we laid out on slide 18 for FY '24, our expectation is adjusted EBITDA somewhere between INR 60 billion and INR 66 billion. Since we're determined to hit what we've committed to, the assumptions we've baked in are conservative — ongoing bad weather, project completion, and essentially zero contribution from M&A along with carbon credit sales, plus other elements. Looking at FY '25, we do anticipate adjusted EBITDA growing versus FY '24 by roughly 35%. After that, in FY '26 we arrive at our portfolio run rate EBITDA, which as things stand is basically fully contracted. On cash flow to equity, we're looking at somewhere around INR 6 billion to INR 8 billion for FY '24. The drop versus FY '23 comes from the additional debt sitting on our balance sheet tied to delivering the 5.7 gigawatts currently under construction. Our 13.7 gigawatt run rate CFe is unchanged from before; as for debt, our view is that coverage ratios will hit their peak this year, which is typical when large-scale commissioning is underway, and improvement should start showing up as revenues begin to be booked; we'll also capture the upside from the capital recycling efforts we have going; we anticipate net-debt-to-adjusted EBITDA getting better by close to one turn by the time the 13.7 gigawatt portfolio reaches completion. On the buyback, we've now repurchased 32.1 million shares as of today, amounting to roughly 30% of our free float. We still view our shares as among the highest return investments of scale within our portfolio. The remaining INR 50 million of authorization works out to about 10% to 15% more of the total free float; with that said, we're glad to take questions, and thanks for listening to us. Nathan, over to you.

Nathan Judge

executive
#5

Hi Darcy, can you please open the call open for questions, please?

Justin Clare

analyst
#6

To start with, regarding this quarter, you brought CMB back for the projects you have. I was curious whether you might discuss what has driven the better visibility you now have on commissioning schedules. And then, about the uncertainties that originally resulted in the <<inaudible>>, and how have those changed?

Sumant Sinha

executive
#7

Apologies, Justin, I didn't catch the second portion of your question. The first portion concerned why we possess greater certainty regarding commissioning, correct; and what did the second question ask?

Justin Clare

analyst
#8

Yeah, that's correct. It all comes down to the better visibility you now have regarding project commissioning. And honestly, that's the core piece of what I was hoping to get into with my question.

Sumant Sinha

executive
#9

Alright, understood. Yes, yes, absolutely; so here's the thing — the reason our confidence has gone up is clearly that even though we brought fewer megawatts online during the last year, plenty of effort was underway on project commissioning and construction across the projects we had in progress. As you're aware, take the RTC project — on the financing side, for instance, we completed the tie-up with Mitsui. We additionally closed a syndicated loan worth more than $1 billion involving 12 international lenders, and 6 of those were lending into India for the very first time. The machines have been ordered, the land has been secured; so substantial work has taken place on both the RTC project and the Peak Power project, and both are now at fairly advanced stages of commissioning; and you will — because of that, we feel confident that in the coming months, you'll begin to progressively watch those projects come online; so what I'd say is that our confidence behind the commissioning figures we're providing you at this moment truly stems from the progress we've genuinely achieved on the ground across a number of our projects currently underway. So that's genuinely the source of that confidence. And it really centers on financing, as I mentioned, for some of the projects — on the Peak Power project, as you can see, we've also by now announced the joint venture with Petronas, so both of these large projects, which together represent almost 2-odd-gigawatts of our portfolio. We have the financing locked in. And like I said, there's been considerable progress made on the ground when it comes to land acquisition, securing the turbine, ordering the equipment, and plenty of work on the transmission side too.

Justin Clare

analyst
#10

All right, understood. That's useful. Now, regarding the expedited auction program MNRE made public, I'm curious how you view the volume of capacity you could potentially obtain through auctions over the next few years, particularly if IRRs turn out to be highly appealing? So are you expecting to significantly scale up the capacity you submit bids for and possibly secure — I'm just curious what the constraints on growth would be if the set of opportunities has gotten bigger?

Sumant Sinha

executive
#11

Yes, Justin. Excellent question. So here's the thing — the truth is that our nation is currently conducting roughly 15 gigawatts of auctions annually. The government aims to raise that figure to 50 gigawatts. And MNRE has issued a detailed note confirming this; they've brought in 3 additional bidding agencies alongside SECI. As you're aware, Solar Energy Corporation handled the bidding until now, but they've added 3 new agencies. These are power companies owned by the central government — NTPC, another firm named SJVN, and a third one named NHPC. So these organizations have now been given the responsibility of conducting auctions, selling the electricity, and so forth. And MNRE has additionally released a quite specific list of which types of auctions will take place during this quarter. So it's a rather detailed plan they've now put out. And within that plan, they've also sorted out which categories of bids will occur. And it's evident that most of the bids there are shifting toward complex auctions. That's the reason we brought up that specific topic. But returning to what you asked — therefore, if the goal is to reach as much as 50 gigawatts, whether or not we hit that target number, there's going to be a very significant increase in how many auctions take place. And so what we need to figure out is how much of that we wish to capture and how much we're capable of capturing. So I'd say our primary criterion is that we clearly intend to keep IRRs elevated; and we're seeing a chance here to boost the level of IRRs we can generate on these projects owing to the factors I mentioned, namely the expertise and so forth that we now possess. The limiting elements, though, include first financing, since there's only a certain amount we're prepared to push our balance sheet to. And we've provided you with quite explicit parameters regarding how much debt we intend to carry on our balance sheet. And we wish to hold it at a specific ceiling; so that's plainly one element. And the second element is obviously execution capability as well; and when it comes to execution capability, multiple elements come into play. First, there's our ability to actually carry out projects from an EPC standpoint, and second, securing the right equipment at the right price. So we simply want to ensure we handle all of this as optimally as possible, and that we don't take on too many projects that we then can't execute properly. Those are the things we'll keep monitoring. On top of that, we want to ensure that anything we win ultimately delivers the maximum or highest possible IRRs. So as we see it right now, Justin, to answer your question, we plan to do roughly 3 gigawatts to 4 gigawatts each year; exceeding that isn't likely. And once we gain comfort around our execution capability over the next 2 to 3 years at that megawatt level, then maybe in future years we can consider scaling up the megawatts we handle. But for the near term, our focus will be doing roughly 3 gigawatts to 4 gigawatts each year. And for FY '24 and FY '25, meaning the current year and the next one, we already have a pipeline and we already have an execution plan in place. So really, it's FY '26 onwards where we'd begin at somewhere between 3 and 4 gigawatts and then possibly look to scale it up, depending on how all these factors develop. That said, I definitely see an opportunity for us to be choosier and far more selective regarding projects, and to truly win the ones that maximize our IRR. So I believe our capacity to deliver higher IRRs, all things considered, will rise even if our market share possibly declines somewhat.

Morgan Reid

analyst
#12

Hello, Morgan Reid here, filling in for Julien. Your remarks about recent successes on complex projects were truly fascinating. Could you discuss the growing opportunity you see in that area? Presumably, the most recent auction victory along with any later wins will be reflected in FY '26, exactly as you were describing. So could you explain where we ought to look for the upside relative to the present development pipeline within this complex project segment, and when we might begin to see that contributing to the 3 gigawatts to 4 gigawatts of development you mentioned earlier?

Sumant Sinha

executive
#13

Yes, certainly. Regarding complex auctions, given everything I have already explained, we are — the government is plainly heading in that direction, since it is far simpler for grids and utilities to take in power that satisfies a specific generation profile. It becomes just as easy for them to absorb that electricity. Consequently, they are in a sense shifting onto us the duty of shaping the generation profile. That suits us fine, because it lets us perform that shaping and deliver a power source, or a profile, suited to the utility while remaining less expensive than the next best option, which is coal based power. Coal based power currently runs at roughly INR 5 to INR 6 and above. Should they purchase electricity through the markets on a merchant basis, those rates climb even higher. Thus, for them, obtaining anything under INR 5 for this managed profile represents an excellent outcome for the utilities. As for the tariffs at which we secured the latest auction — which, incidentally, we have not yet added to our committed pipeline, because, as you noted repeatedly, we will do so only after the PPA is signed — but purely as a signal of the course we are taking from an auction and bidding perspective, we won that tariff, and we won a further tariff of INR 4.69 or approximately that amount. That was — it stands in some comparison with the tariff from our initial round the clock power project, which was nearer to about INR 3.50. Naturally, much hinges on the shaping needed for the generation profile, and hence on the quantities of wind, solar and storage required, so they cannot truly be compared on a like-to-like basis. Still, it definitely provides a signal that for such projects and such generation profiles, utilities are prepared to accept a greater tariff. So I believe that is essentially what will, in terms of trajectory, deliver improved IRRs for us. In these tenders, the number of bidders we're seeing is smaller, since a big share of the work needs wind plus the ability to execute wind projects in India, and as we've often said, that capability there is in short supply. Good EPC contractors are basically not available, whereas we possess a full in-house EPC organization numbering over 300 individuals. Another factor, which we've likewise mentioned many times previously, that acts as a limiting element, is the supply of solar modules. Government rules have tightened how easily solar modules can be obtained in India, and that's making it difficult for a number of our rivals to place bids in these auctions. This is precisely the situation where our very own solar production facility, which is now — which is due to be commissioned later this summer — proves extremely useful. What's being commissioned at present is a plant for modules with 4 gigawatts of capacity, and therefore we can already feel far more assured about securing solar modules. So given every action we've taken previously — and I'm aware many of you felt doubts when we moved into manufacturing solar — it was for these reasons, and we expect this to occur within the Indian market and that it would provide us with substantial security. Thus the ability to do wind, the ability to identify the proper approaches for combining, and the ability to have our own solar supply chain at this point is what lets us achieve significantly better IRRs in a market that's currently facing some difficulty.

Morgan Reid

analyst
#14

Understood. So when we discuss the strategic priorities — I get that FY '23 was hit by a few of those postponements everyone has mentioned regarding resource, which we all grasp. Then as we move toward FY '24, there are certain subtleties involving project data while you wrap up the remaining development work. Could you — where should we be looking regarding the strategic priorities from here onward, and where ought investors seek a bit more reassurance across the coming 2 years, recognizing that currently the conversation centers on FY '26 execution? What would you highlight to build confidence about the next 2 years, and are there any openings currently available?

Sumant Sinha

executive
#15

Sure, Morgan, I'd direct your attention to a few items. First, naturally, and most importantly — the same subject Justin raised — is project commissioning. Clearly, that will be essential for reinforcing everyone's trust in the business even more. So that's definitely something worth watching, and we'll keep supplying that data going forward. That should give you assurance regarding our '24 — FY '24 and FY '25 figures, and consequently provide reassurance about the eventual run rate in FY '26, which will become evident during that year. Second, you ought to watch bid wins. Regarding bid wins — typically we don't discuss them since, unless, as I mentioned before, they convert into a PPA, we don't ordinarily include them; we don't place them into a pipeline. However, you can follow the auctions taking place in India, since they're publicly accessible. There could be a delay between winning a bid and signing the actual PPA, and at that moment the bid wins we hold will appear in our committed pipeline — but at minimum you can begin monitoring the bid wins. That way you'll gain a sense of the direction things are moving. Still, to restate the point: for us, market and growth aren't limiting factors, because sufficient auctions will take place. Furthermore, as you're aware, the corporate PPA market is performing quite strongly too. So right now we're somewhat spoiled for choice concerning how much capacity we wish to win. Given that, we can be highly selective about which — how to maximize IRRs. That's something you obviously won't be able to observe directly. Yet I believe that when the quantity of offers increases, you can reasonably expect that the projects we end up winning will consequently deliver a greater IRR, simply because we now have the ability to be pickier. So those are the two items I would direct your attention toward.

Morgan Reid

analyst
#16

Sure, please continue.

Sumant Sinha

executive
#17

Right, right — the third item, clearly, is asset recycling. So because of that, you should expect additional announcements and the like as we move ahead on that side.

Puneet Gulati

analyst
#18

To start off, I'd like some insight into what's behind the postponement of commissioning, and it also appears there might be savings on costs. Could you put a figure on the sort of savings involved — whether from lower module prices or any shift in wind turbine expenses, and so on?

Sumant Sinha

executive
#19

Right, Puneet. Now regarding the — pardon me, the latter portion of what you asked concerned cost savings. What did the earlier portion cover?

Puneet Gulati

analyst
#20

What was the main factor behind the postponement of commissioning? I mean, the initial timeline called for completing it in the first half, correct?

Sumant Sinha

executive
#21

Yeah, yeah. Correct. Correct. So, you know, I'd say the factors behind our choice to push things back included, naturally, certain natural causes, like a few transmission substations that were meant to be ready — those slipped. We also faced a few problems with equipment supplies; however, the largest factor, I'd say, was truly the matter of the government giving us a 1-year extension on commissioning deadlines; and second, the reality that module prices rose, and so we were kind of in a position — definitely anticipating a decline, because of polysilicon additions that were being built in China. And so what we really had to ask ourselves was whether to commission projects 6 months early at potentially higher CapEx on a per-module basis, $0.03 to $0.04 more, or to hold off for 6 months and then commission at a reduced cost; now — in fact, that's precisely what unfolded, in the sense that polysilicon prices fell owing to all the poly capacity that has been brought online in China. And because of that, module prices dropped by $0.03 to $0.04; so that is enabling us, as a result, to bring our CapEx down by nearly — close to around 7% to 8% for solar projects. Now — so that's genuinely the gain we managed to achieve by having this 6-to-9-month postponement in project commissioning.

Puneet Gulati

analyst
#22

Okay, and could you give us a feel for the sort of module pricing you're securing for shipments around October and November?

Sumant Sinha

executive
#23

So the module prices we're currently seeing — look, it truly hinges, Puneet, on the origin of those modules, since three separate origins are available to you at this moment for October and November. One option is bringing them in from China at roughly $0.20 to $0.21. So in China, at least, pricing has fallen back to the levels seen previously. However, as you're aware, a 40% customs duty has to be paid on that. The second origin is purchasing out of Southeast Asia, where pricing runs a bit cheaper, roughly $0.26 to $0.27 versus China plus import duties, which lands nearer $0.28 to $0.29. And a third route is bringing in the cells and performing tolling within India, and in that case, with cell prices having declined as well, you can achieve a price of roughly $0.25 to $0.26. So if you possess module capacity, bringing in cells and tolling them in India is, in certain respects, now the optimal approach. Sourcing from Southeast Asia is fairly constrained since, as you're aware, the bulk of that capacity is directed toward China — toward the U.S., pardon me. So actually obtaining modules from there is quite difficult. Thus, I'd say today's price levels hinge on your sourcing or the origin from which you're procuring the modules. And at present the least expensive route is proving to be importing cells and turning them into modules within India, which explains why having access to module capacity production capability in India matters greatly, because as you're also aware, Puneet, plenty of Indian modules are being shipped into the U.S. too, on account of the higher pricing there. So it isn't the case that the whole module capacity — India is open for sales within India. So that, I believe, is what's generating difficulties for plenty of folks right now; but as I mentioned, luckily, our own plant is coming on stream by this — by the middle of this year, by the summer; and so we'll begin obtaining a great deal of our own capacity from the module at roughly, let's say, $0.25 to $0.26.

Puneet Gulati

analyst
#24

Also, when you purchase from your own capacity instead of bringing in from China with the duty modified, would you still receive the change in law advantage there?

Sumant Sinha

executive
#25

Yes, so Puneet, that hinges on the timing of when those bids take place. Bids that occurred, as you're aware, before 1st, April 2021, I believe — those are grandfathered, meaning change in law applies to them. Consequently, for those you're still able to import from China and cover the capital duty, provided you're ready to hold that working capital stock for a period, since, as you know, securing that refund takes time; however, for projects whose bid came in afterward, clearly that advantage isn't available; therefore, the India option then becomes what you must choose as the following solution.

Puneet Gulati

analyst
#26

All right, I get it.

Sumant Sinha

executive
#27

That's essentially what took place. And what I'd say is this: for the majority of our projects that are being commissioned — the ones getting commissioned at this moment, such as RTC and Peak Power — every one of those was bid previously. As a result, those have protection against change built in. A number of the other bids we came out on top on lacked that protection, so what you're looking at is a combination of the two.

Puneet Gulati

analyst
#28

So when it comes to a change in law, you'd still rather source from your own plant or from India than bring in goods from China? Given what would take place, is that still the preferable option?

Sumant Sinha

executive
#29

No. In the case of a change in law, or anywhere you're protected, bringing in from China remains the better choice, since the price there is still $0.20, $0.21, and even after you factor in the higher working capital and all the associated cost of that, you'd likely still land at around $0.23, $0.24; that means it's still $0.01 or $0.02 less expensive than doing the tooling in India.

Puneet Gulati

analyst
#30

Got it, that's quite useful. Then, if you could also say something about what we earn from selling carbon credits — that was a fairly solid figure up until last year, and this time around, in the other expenses line, it looks like you actually recorded some impairment. So what caused that shift?

Sumant Sinha

executive
#31

Right, I believe Kedar is going to address that one.

Kedar Upadhye

executive
#32

Sure, Puneet — for us, carbon credit revenue mostly comes by way of RE credits. And in the prior year, we actually built up registrations across the bulk of our projects that qualified for such credits, and cumulative income recognition occurred then for the first time. So on a year-over-year basis, I'd say it — the way it was structured meant a somewhat lower reflection. That's why this time, on the revenue line, you're seeing a decline versus the prior year, and that was intentional. Then on the expense side, there's an impairment, since prices have fallen. As you're aware, with no additionality in play, pricing on RE credits is facing some pressure. We had therefore carried out inventory accounting through September and December, so we were to some degree obliged to make adjustments to those prices. Yet every bit of that was taken into account and sits within the broader $62 billion guidance we provided for FY '23, $61 billion to $63 billion; so those adjustments were all incorporated there. To put it briefly, though, I believe RE credit pricing is the thing reflected in that other expense impairment?

Puneet Gulati

analyst
#33

Alright, that's quite useful. Just quickly while we're on this call, regarding a single balance sheet item, contract FX showed a shift and it was negative, even though your receivables actually declined. What's the right way to interpret that?

Kedar Upadhye

executive
#34

I can — Puneet, could you say again which particular line you mean?

Puneet Gulati

analyst
#35

On the balance sheet, then, there's a shift in contract assets, and that appears on the cash flow statement as roughly INR 7.5 billion of reduction in noncurrent assets.

Kedar Upadhye

executive
#36

Yeah, yeah. That likely relates to how we handle transmission accounting. What I touched on briefly in my remarks, the transcript, is that we now apply IFRIC 12 transcript accounting, so whatever CapEx goes into transmission projects gets treated as a sale and a cost right away within that same period. That means we book an EPC margin of perhaps 3% to 4%. Then the receivables tied to it are gathered in later periods from PGCIL under the usual PPA accounting. During the period when we build those projects, though, you'll see revenue and you'll see cost, and the net margin ends up quite thin in the P&L, yet a receivable gets created, and that will be collected over the support period. So this is a book entry; our cash flows aren't truly affected by it.

Amit Bhinde

analyst
#37

Hi there. I only have a single item to raise, which is that previously we were steering toward a net debt to adjusted EBITDA run rate of 5.1 through quarter 3 PPD. And at this point we've raised that figure to 5.1 to 5.3 at the project level. On top of that, we've added 0.4 to 0.7 for corporate debt. So that lands somewhere between 5.5 and 6. So what's shifting in our debt assumptions, especially given that working capital should decline as receivables start coming in now? So why would the sale assumption go higher?

Sumant Sinha

executive
#38

Yes. I'd say it's moved up somewhat, though not significantly, since what we're focused on is discipline at the project level, and the tracking of DACR, it's an increase, quite robust. So we'll hold to what we told you before at that level. So that piece isn't shifting. The corporate layer on top is needed so we can put money into newer businesses. So as you're aware, we're doing initial directs. We're doing initial businesses. We're doing manufacturing investments. Now the EBITDA from those isn't included here, so in an ideal case, if you take the EBITDA from manufacturing, once we secure certifications, and we begin exporting; and you're aware there's a scarcity premium tied to how modules are priced. If you include the EBITDA from that, I believe this would be considerably lower, but getting that visibility will take us some time. So you should mainly focus on the green portion on slide 18, which references 5.1 at the lower end. And the extra top up is needed so we can make contextual investments during that period to build new businesses, which will generate EBITDA in a later period.

Operator

operator
#39

Thanks so much. At this point, we don't have any more questions. That brings today's conference to an end. We appreciate everyone for joining in. You're welcome to disconnect now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete ReNew Energy Global Plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to ReNew Energy Global Plc earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in ReNew Energy Global Plc or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.