ReNew Energy Global Plc (RNW) Earnings Call Transcript & Summary
August 14, 2025
Earnings Call Speaker Segments
Anunay Shahi
executiveThanks so much. Good morning to all of you, and we appreciate your participation today. Yesterday evening we issued a press release sharing the results for the first quarter of fiscal 2026, which closed on June 30, 2025. You can find that press release along with the earnings presentation in the Investor Relations area of ReNew's site, www.renew.com. Joining me on this call are Sumant Sinha, our Founder, Chairman and CEO; Kailash Vaswani, our CFO; and Vaishali Nigam Sinha, Co-Founder and Chairperson, Sustainability. Following our prepared remarks — which we anticipate will run roughly 30 minutes — we'll take your questions. Kindly be aware that safe harbor statements appear in our press release, the presentation materials, and the materials posted on our website; those statements matter and form an essential part of everything we say. Certain risks and uncertainties might lead our actual results to diverge materially from those conveyed or furnished or implied, pardon me, through such forward-looking statements. Therefore, we urge you to look over the press release we furnished in our Form 6-K as well as the presentation on our website to get a fuller picture. Also included in our press release, presentation materials, and annual report are specific non-IFRS measures that we reconcile against the most comparable IFRS measures, and those reconciliations can likewise be found on our website within the press release, presentation materials, and our annual report. At this point, I'm delighted to turn things over to our CEO, Sumant Sinha.
Sumant Sinha
executiveYes. Thanks, Anunay. Good morning, good afternoon, and good evening, everyone — great to have all of you joining us on this earnings call covering the first quarter of fiscal 2026. Our pursuit of excellence carries on, and our vision remains that of becoming a global leader in clean energy. We recently filed our 20-F along with our second integrated report, which underscores our steadfast dedication to transparency and sustainability. Looking toward the year ahead, nothing is being left on the table as we aim to outperform prior years. Certain factors will always lie outside our control, but our emphasis on bettering margins and maintaining capital discipline will keep generating shareholder value. A number of the investments made across the last few years, our manufacturing business among them, have begun to yield results for us. Moving to the quarter's highlights. Starting from July of last year, we brought roughly 2.2 gigawatts of renewable energy capacity into commission, which represents 23% growth in our portfolio once asset sales are adjusted for. We keep growing our committed portfolio as well, having signed PPAs covering 3.7 gigawatts of installed renewable energy capacity, for projects expected to deliver returns at the higher end of our targeted IRR range — or possibly beyond it. We restate our FY '26 megawatt guidance, staying on course to finish construction on 1.6 to 2.4 gigawatts of capacity during fiscal 2026. During fiscal 2026, we likewise anticipate that a number of the unsigned PPAs will get signed, giving us a still clearer path past the present 18.2 gigawatts of committed portfolio, together with clarity on execution time lines. Our approach to bidding for future growth will stay disciplined and highly selective, and we aim to lock in projects carrying lower risk and a higher return profile. Moving to our financial highlights: we posted superior performance this quarter, with adjusted EBITDA of INR 27.2 billion, representing 43% growth year-over-year. For the first quarter of fiscal 2026, our profit after tax came to INR 5.1 billion, exceeding the profit recorded across the entire fiscal 2025. We have likewise meaningfully enhanced our leverage metrics for operational projects, and we reaffirm our FY '26 guidance. Our manufacturing business — made up of an operational capacity of 6.4 gigawatts of modules and 2.5 gigawatts of cells — is fully stabilized and turned out 900 megawatts of modules and 400 megawatts of cells this quarter. Manufacturing likewise contributed a meaningful INR 5.3 billion toward adjusted EBITDA for the quarter. Additionally, we are raising our FY '26 adjusted EBITDA guidance for the manufacturing business to INR 8 billion to INR 10 billion. Our ESG commitments remain firm, and the second edition of our integrated report stands as proof of the standards we hold ourselves to. To cite just a few, over the year we successfully cut our Scope 1 and Scope 2 emissions by 18.2% against the FY '22 baseline, exceeding our 12.6% target, and conserved 540,372 cubic meters of water, which marks a 51% improvement. Now moving to Page 9. For us, execution stands as the number one priority and a major point of differentiation; across roughly the past 12 months, we've brought more than 2.2 gigawatts of capacity online, and we restate our guidance of finishing construction on 1.6 to 2.4 gigawatts during fiscal 2026. So far this year, upwards of 700 megawatts have been commissioned, divided between over 650 megawatts from solar and roughly 50 megawatts from wind. On top of that, we've commissioned more than 500 megawatts of wind plus around 300 megawatts of solar that are already erected, and these will let us reach our construction goals for this year. We remain optimistic as well about signing PPAs from the pipeline we currently hold during this fiscal year. Now to Page 10. Our solar manufacturing plants are running at full ramp, and right now they turn out in excess of 10 megawatts of modules and 5 megawatts of cells every day; during the first quarter of this year, we turned out more than 900 megawatts of modules while running at high utilization and efficiency levels. As of today, we hold third-party orders to sell roughly 800 megawatts additionally this fiscal, with nearly 1.9 gigawatts delivered so far. In May of this year, we landed a marquee investment from British International Investments worth more than USD 100 million, granting an approximately 10% stake in the solar manufacturing business, and we anticipate the deal will close before the second quarter of fiscal 2026 ends. Together with that, we're happy to report that construction of our new 4-gigawatt TOPCon cell facility is progressing well, with land acquisition finished and civil works already begun. By posting an adjusted EBITDA of INR 5.3 billion this quarter at a margin exceeding 40%, our manufacturing business has begun adding meaningfully to the consolidated P&L. This quarter's EBITDA contribution came in somewhat above the usual level, since the bulk of production was directed toward external sales. That share might — should come down to some degree over the coming few quarters. Beyond that, margins ran a bit higher thanks to certain cost advantages and some early procurement, which could partially normalize; with that, I'll pass things to Kailash so he can discuss the finance highlights in more detail.
Kailash Vaswani
executiveAppreciate it, Sumant. Let’s move to Page 12. We keep delivering steady expansion in every one of our performance metrics. Compared with the same point a year ago, we've built more than 2.2 gigawatts of projects — that's a 23% rise in operating capacity once you account for the 600 megawatts we divested over the trailing 12 months. Our cost optimization programs keep paying off, with EBITDA margins in the IPP business climbing from 80.7% to just about 82%. Profit after tax is at 13x versus Q1 FY '25, mostly fueled by added megawatts, a higher PLF that we achieved quarter year-on-year, a substantial lift from the manufacturing business, and our cost optimization efforts. Now to Page 13 and the EBITDA walk. We did see muted solar PLFs this quarter because of weaker irradiation stemming from the early arrival of monsoons; even so, stronger wind PLFs offset what solar lost us, producing a net favorable effect of INR 1.4 billion on EBITDA year-over-year. The fresh projects we brought online during the last 12 months added INR 1.8 billion to EBITDA, whereas the manufacturing business delivered INR 5.3 billion. During the past year, we divested more than 600 megawatts of solar assets plus the transmission line, which cost us roughly INR 300 million of EBITDA this quarter. Leverage at the operating asset level remains comfortably under the 6x ceiling we've established. Measured on a trailing 12-month basis, leverage came to approximately 5.7x EBITDA, leaving out our under construction portfolio and the convertible debt contribution from our JV partners. Cash flow generated by our manufacturing business has likewise played a significant role in bringing our leverage levels down. As our portfolio keeps expanding, the share of under construction projects relative to the total portfolio ought to decline and will enhance the ratios, on top of our push to stay disciplined about how we deploy capital. A quick update on the consortium's offer: we disclosed that ReNew had gotten a final revised nonbinding offer at USD 8 on 3rd of July. Talks involving the consortium and the special committee are continuing, and the special committee has said an update will go to the shareholders no later than 30th September 2025. I'll now pass it to Vaishali for her remarks on ESG.
Vaishali Sinha
executiveThanks, Kailash. Let's move on to Page 15. It's a pleasure to share that we've put out ReNew's second annual integrated report, covering fiscal year '25. This demonstrates how dedicated we are to being transparent, accountable, and a leader when it comes to ESG reporting. Taking the solid base from our first edition, the FY '25 report established fresh standards for our ESG vision, performance, and disclosures. The report was put together following IIRC, GRI, SASB, IFRS S2, UNGC, along with other worldwide reporting frameworks. We've made notable improvements compared with last year's report, such as incorporating the business responsibility and sustainability report, known as the BRSR framework, to meet Indian regulatory needs, tighter connections between financial and nonfinancial metrics, and a more thorough explanation of how the 6 capitals interact — specifically financial, manufacturing, natural, social relationship, and intellectual capital. We've also brought in something new: an AI chat box that allows smooth navigation and makes it easier to learn about the integrated report, which makes the fiscal year '25 report a smart report unlike any other. External assurance for the financial and nonfinancial metrics for FY '24 and '25 was provided by SR Batliboy & Company LLP and E&Y, respectively. Turning to ReNew's FY '25 ESG performance highlights: during FY '24 and '25, ReNew made major progress in its ESG work, demonstrating a firm dedication to safety, sustainability, and social responsibility. On the environment side, we cut our Scope 1 and 2 emissions by 18.2% compared with the FY '22 baseline, beating our 12.6% goal, and conserved 540,372 millimeter cube of water — a 51% gain. Within our operations, 76% of electricity came from green sources, above our '25 target of 50%, and we reached carbon neutrality for Scope 1 and 2 emissions for the fifth year in a row. When it comes to social impact, our socioeconomic program has benefited more than 1.7 million lives, with CSR spending of INR 320 million this year. Our workforce currently shows a 16% gender diversity rate, with women holding roughly 12% of STEM roles; we recorded a lost time injury frequency rate, LTIFR, of 0.21, which is a 5% decrease from the prior year and also for the second year running. 100% of our critical suppliers underwent assessment against ESG criteria, a major move forward in our supply chain commitment. On governance, our Board composition shows our dedication to diversity and independence, with women making up 40% and independent directors accounting for 60% of the Board; on Page 16, we point out the key value additions from this year's annual integrated report. The main value we've added this year is our voluntary alignment with BRSR. As I noted, that's India's sustainability reporting framework, highlighting our commitment to boosting ESG transparency in step with national and global expectations. Also for the first time, we've linked material ESG issues to our ERM, the enterprise risk management framework, which is a major move toward weaving sustainability into our enterprise-wide risk strategy. We've also put in a thorough showcase of progress measured against our company-wide sustainability goals, which strengthens accountability and shows how serious we are about delivering. On top of that, we broadened our decarb approach so it now covers manufacturing operations, and we stayed aligned with the EU taxonomy; let's move to Page 17 now to go over what's been achieved on our ESG targets. Our commitment to the broader sustainability targets hasn't changed. We finished the LCA — that's the life cycle assessment for the solar module we make in Jaipur — and we put out a verified EPD, meaning the environment product declaration under the International EPD system. Also, 2 of our locations have earned certification as water positive for operational water, in line with Niti Aayog's Water Neutrality Standard for Indian industry. Social responsibility sits at the heart of what we're trying to do. We've reached more than 1.7 million lives so far, with a goal of 2.5 million by 2030. So we're on track. We've teamed up with IIT and ISM Dhanbad to help coal mine workers build skills in green technologies. Our CDP A rating for supplier engagement shows we lead when it comes to value chain sustainability. Looking ahead, we stay devoted to weaving resilience, responsibility and impact into all our work. I'll hand things over now to Kailash.
Kailash Vaswani
executiveThanks, Vaishali. Now for our outlook on the fiscal year that concludes on March 31, 2026. What we shared before still stands. Assuming weather conditions remain favorable through the remainder of the year and asset divestments materialize as we anticipate, we anticipate landing at the upper portion of our adjusted EBITDA guidance, which spans INR 87 billion to INR 93 billion; additionally, our expectation remains that we will build between 1.6 and 2.4 gigawatts of projects over this period and produce cash flow to equity in the range of INR 14 billion to INR 17 billion. So far this year, though Q1 brought a favorable weather comparison against the prior year, we've since experienced modest shortfalls in both wind and solar, which erased the bulk of that first-quarter weather benefit. Because of how the first quarter performed, we've raised our EBITDA contribution guidance from the manufacturing segment to between INR 8 million and INR 10 million; with that covered, we're ready to address your questions.
Justin Clare
analystI wanted to begin with the manufacturing side of things. So in your prepared remarks, you mentioned that during fiscal Q1, production volume mostly went toward external sales, and it seems like volumes might drop over the next few quarters. So I was curious whether you could tell us the number of megawatts that were delivered in fiscal Q1? And then could you also tell us the number of megawatts you expect to deliver across the rest of the quarters in fiscal 2026? I'm aware that you have a backlog of 800 megawatts, but I'm also curious whether you expect to book more volumes with delivery anticipated in fiscal '26.
Kailash Vaswani
executiveJustin, I appreciate the question. To respond to that, during Q1 FY '26, we sold nearly 700 megawatts of modules to third parties. The remainder was essentially utilized for our own internal consumption. For the most part, profit and margins are generated by our cell business, which is mainly focused on third parties. Within that, we sold nearly 1.2 megawatts through direct sales of cells to third parties; and therefore there was a bit of upside tied to that.
Justin Clare
analystUnderstood. Alright. Could you share what you're expecting for the second half of the year? Do you believe there's room to sell or book additional volume this year for delivery? Or would you say your capacity for the year has basically been maxed out? What's the right way for us to frame that?
Kailash Vaswani
executiveThe reason we adjusted our guidance for the EBITDA contribution coming from the manufacturing business is that we keep seeing third-party sales contributing during the rest of the year as well. Exactly how large that will be is something we'll find out as we move through the year. As things stand today, though, we have reasonable visibility into the guidance we've provided.
Justin Clare
analystUnderstood. Understood. All right. Then only one additional item. I was hoping you might give us an update regarding how appealing the current bidding landscape looks. In what direction is it moving? Do any specific segments stand out as especially appealing at this moment? And beyond that, how aggressive do you intend to be during fiscal '26 for the rest of the year as you evaluate new projects?
Kailash Vaswani
executiveYes. So what I'd say is that bidding conditions keep progressing at a stable pace. The government has set a goal of reaching as much as 500 gigawatt by 2030; therefore they intend to auction 50 to 70 gigawatt annually, and whatever projects go up for auction, we take part in those. What I'd say is that our success rate has come in somewhat below, let's say, fiscal '24 and a portion of '25, since competition has turned somewhat, I'd say, unreasonable in certain respects. And we observe players genuinely accepting far smaller return expectations; our approach to bidding is extremely disciplined, as we've shown across the past several years. And therefore, unless we achieve the rate of return we require, which serves as our hurdle rate, we are perfectly fine with winning no capacity at all. However, what I'd also say is that we possess a quite strong pipeline sitting there. So we feel no pressure whatsoever to add capacity at reduced returns.
Nikhil Nigania
analystIt's encouraging to watch both the figures and the plan come through as you concentrate on manufacturing and batteries rather than pumped storage. Let me start with how the renewables work is being carried out. Once more, the results have been solid, but I was hoping you might offer a bit of insight into the main challenges that peers, and perhaps the industry as a whole, are running into — be it grid access, right-of-way problems, or transformer scarcity. So where do things stand on that front?
Kailash Vaswani
executiveSumant, please take it.
Sumant Sinha
executiveAlright, so honestly, when I look at capacity additions, overall I'd describe the pace as fairly reasonable. Now and then you run into shortages — really more like holdups involving certain transmission infrastructure, which can occasionally fall behind the generation capacity being brought online. Still, that amounts to a matter of a few months in one place or another, nothing bigger than that. As far as transformer availability goes, typically, provided you're fairly disciplined about placing orders early, which is generally our approach, you can find a way around it. So in my view, this isn't really restraining execution. What I'd say does tend to restrain execution is the standard set of challenges surrounding land acquisition and similar matters, more so than anything else.
Nikhil Nigania
analystGot it. I recall what you mentioned before, I believe it was during one of the calls a couple of sessions ago, particularly regarding wind — you noted that given the difficulties related to land or evacuation, seeing India exceed 5 gigawatts of wind annually would catch you off guard. Do you still feel the same way? Or do you think that area is also getting better?
Sumant Sinha
executiveShould we go beyond 5, it might only be slightly higher. That figure won't be surpassed in the current year, incidentally. Perhaps down the road, should a greater number of players take on wind projects, the total could rise somewhat. Still, reaching 10 gigawatts, or anything along those lines, isn't something I foresee; so perhaps 5 becomes 6 or thereabouts. Yet in the prior year, as an illustration, we observed roughly 4 gigawatts being accomplished. It could be 5 this year, and in years ahead, it might stay roughly at that level, from what I sense.
Nikhil Nigania
analystUnderstood, Sumant. Then my next question concerns the solar manufacturing operation, which appears to be performing quite strongly. It caught me off guard to learn about a 0.8 gigawatt TOPCon site. My understanding had been that all 2.4 was Mono PERC. Could you therefore shed some light on this, and are there any intentions to switch the whole site over to TOPCon down the line?
Sumant Sinha
executiveNo. Nikhil, that 2.4 is in fact Mono PERC. If it came across that 800 megawatts of TOPCon was involved, that isn't accurate. Every bit of the tunnel facility is Mono PERC, not TOPCon. However, the fresh site we're building, all of the new 4 gigawatts, is a TOPCon facility. Regarding modules, incidentally, when it comes to modules, incidentally, we have 4 gigawatts, and the whole Jaipur plant has been switched over to TOPCon modules.
Nikhil Nigania
analystI see. That makes sense. I must have approached it incorrectly. Thanks for clarifying. Also, is there anything planned regarding Ingot Wafer, since a few of your competitors are moving in that direction, or...
Sumant Sinha
executiveOn that front, our approach will be to let the government take the lead. Government policy, as you're aware, has truly been what's been pushing the rollout of manufacturing capacity. Right now, we'll need to wait and observe if they introduce something comparable to ALM for wafers, or if they begin signaling that to us. So as things stand, those discussions haven't reached a stage where we'd feel confident launching anything on the wafer side. If that were to change, though, then absolutely, wafers would be something we'd consider too.
Nikhil Nigania
analystUnderstood, that makes sense. One final item from my side concerns the ammonia tenders that came up recently. Could you give us a bit of detail — did ReNew take part, or did the bid terms simply come across as too aggressive for it to be worthwhile for ReNew?
Sumant Sinha
executiveRight. No, we stayed out, and the reason is that in our view those contracts simply weren't put together properly. To begin with, the PPAs, or green ammonia purchase contracts, run for just 10 years. That struck us as far too brief. What becomes of your whole plant once that decade is up simply wasn't spelled out. And then there's a second point — certain other structural problems exist within those contracts, such as the absence of any change in law pass-through, among others. So for that reason, we made the decision to stay away from that tender. Because, to repeat what Kailash mentioned earlier, we aren't in a position where we're desperate to enter any new bids. We're able to be highly selective regarding the quality of bids we take on and the returns we secure from them. So in our assessment, the green ammonia tender simply wasn't structured properly, which is why we chose not to take part. And beyond that, looking at a few of the tariffs that others have secured, those appear quite low as well, particularly considering all the risks at play and the level of contracting detail required in that instance.
Operator
operatorThat brings us to the end of the Q&A portion. With that, I'd like to wrap up both the question-and-answer session and today's conference call. We appreciate everyone for joining, and you're free to disconnect at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete ReNew Energy Global Plc transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to ReNew Energy Global Plc earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in ReNew Energy Global Plc or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.