Resolute Mining Limited (RSG) Earnings Call Transcript & Summary
April 23, 2026
Earnings Call Speaker Segments
Operator
operatorGood morning, everyone, and thank you for joining the Resolute Mining first quarter 2026 conference call. Right now, everyone is in a listen-only mode. Afterward, we'll hold a question-and-answer session over the phone lines, and instructions will be given at that point. If you're listening on the phone lines, the presentation is now accessible in the investor section of Resolute Mining's website. If you're watching the webcast and want to submit a written question, you can do so using the Ask a Question button on the Sparklive page. I'd like to remind everyone that this call is being recorded. I'll now hand things over to the Chief Executive Officer, Chris Eger, to open the presentation. Please go ahead.
Chris Eger
executiveThanks, and welcome to the Resolute Mining Q1 2026 activities report. I'm Chris Eger, CEO of Resolute Mining, and on today's call I'm joined by Gavin Harris, our Chief Operating Officer; Dave Jackson, our Chief Financial Officer; and Matty O'Toole, who heads up investor relations. Turning to page 4. I'm really pleased that the first part of 2026 gave us such a strong quarter. Let me walk through a handful of the operating metrics, and then we'll get into more detail on the slides ahead. On the operating metrics, we hit pretty much every target we'd set ourselves, beginning with the fact that the first quarter saw just one lost-time injury, which put our TRIFR at 0.43. Gold produced came in just under 60,000 ounces, right on target with our guidance. Group AISC stood at $2,200, a touch above what we expected, but entirely because royalty expenses ran higher in the first quarter thanks to the stronger gold price environment. Capital expenditures for the quarter came to $33 million, and $4.2 million of that was from the Doropo project. Later in the slides, our CFO Dave Jackson will give you more color on what to expect in the quarters ahead, because we do expect CapEx to begin rising as we get Doropo up and running.
Chris Eger
executiveBecause the business produced so strongly, net cash stood at a bit above $350 million when the quarter closed. Our operating cash flows came in at a healthy level, a little under $120 million. On this slide you can see that revenues and EBITDA were substantial — $337 million in revenue and $200 million in EBITDA. Once more, the start of the year has been extremely strong for the business, and I'm very happy with how the company is progressing on every front. Turning to slide 5, I want to discuss a few of the main activities in the business, though we'll cover them in greater detail on the slides ahead. Above all, at Syama, operations are going very well — on budget and on plan — with gold output of 7,000 ounces from the oxide circuit and sulfides delivering roughly 37,000 ounces. In the same way, in Senegal at our Mako operation, stockpile processing carried on precisely as planned, with gold production of 15.8 thousand ounces. Even more significantly, throughout the business, at several of the major projects we're developing, in Côte d'Ivoire at Doropo, we reached two important milestones during the first quarter — specifically, the receipt of the exploitation permit and formal FID from our board.
Chris Eger
executiveWork on the construction side has now begun, and we’ll provide a little more detail on precisely what is taking place, but activity really gets underway this month, with major work streams scheduled across May and June. In the same way, at Syama in Mali, the sulfide conversion project is still progressing on schedule and within budget. The flotation circuit has been finished, and commissioning of it is just beginning. Likewise, in Senegal, the Mako extension project is continuing to advance as anticipated. We are close to finishing a few technical studies, and we plan to apply for the mining permit for Tomboronkoto during this quarter, followed by the application for the Bantaco license in Q3. As I noted on earlier calls, we have also sharply increased spending on exploration, and we think the results from all of that exploration spending are genuinely excellent. Most notably, at the ABC project in Côte d'Ivoire, we completed the first drilling campaign successfully, with some highly encouraging drill results, which I’ll discuss in the exploration section. We also launched an exploration program at La Debo. Then in Guinea, as you may have noticed, we entered into a strategic MOU with a company named Nimba Mining Company, which is wholly owned by the Guinean government, to explore new gold licenses, and we are currently working alongside the government to determine which projects we should pursue jointly.
Chris Eger
executiveOnce more, I'll expand on this in the slides that follow. Turning to the right-hand side of the page, I'd like to discuss production for the year along with our AISC and CapEx guidance. As you can see, we hit 60,000 ounces in Q1, which sits right in the middle of our guidance. For Q2, we're anticipating similar levels, and then Q3 and Q4 should come in higher, driven by processing higher-grade sulfides once the SSCP program at Syama wraps up. On AISC guidance, we're holding the group figure at this point in the range of $2,000 to $2,200. That said, this guidance was established on a gold price of $4,000, and should the elevated gold price persist through the remainder of the year, we'll probably land at the top end of those levels, or perhaps even surpass them. We'll provide further detail on AISC guidance when we report second-quarter results in July. On CapEx, we're now solidly on track with this year's spend, and as of today we're very much holding our CapEx guidance of $310 to $360 million. As we flagged previously, we expect CapEx spending to increase sharply during the second half of the year, while also beginning to build in Q2.
Chris Eger
executiveTurning to slide 6 — we've shown this one several times already, but it's worth restating the organic growth profile of the business. In 2025, the business delivered 277,000 ounces, squarely in line with the guidance we had at the time. For both 2026 and 2027, we're aiming for 250 to 275,000 ounces, and we have strong confidence in hitting those levels. Most importantly, as I've said before, construction at Doropo is well advanced, so I firmly believe that starting at the beginning of 2028, we'll be producing more than 500,000 ounces at that point. On top of that, the business is enjoying tremendous success across the exploration portfolio, particularly at ABC and La Debo in Côte d'Ivoire. I'll go into some of that a bit later in the presentation, but today I firmly believe our fourth mine will come from one of those two assets, as we keep developing and advancing the exploration work. With that, I'll hand it over to Gavin to walk through the activities in each of the countries where we operate.
Gavin Harris
executiveThanks, Chris. First up is a status report on our Doropo project in Côte d'Ivoire, which is moving ahead quickly. In the early part of Q1, we announced that a 14-year mining permit had been granted for Doropo; it spans the planned mine life and is extendable. That extendability matters, since we see room for Doropo to grow, given the conservative $1,950 per ounce gold price we used for reserves — far under the current spot gold price. On top of that, most of the deposits remain open along strike and at depth, and we have additional exploration upside, with drilling activity getting underway in Q2. The final investment decision, or FID, came swiftly because of the project's robust economics, and we have moved rapidly into construction. The EPCM tender process wrapped up during Q1, running alongside the permitting work. Following a detailed evaluation process, the EPCM contract has gone to Lycopodium Minerals. Lycopodium was chosen because it has built most of the new gold mines in West Africa over the past decade, has a proven track record of delivering quality outcomes, and is currently active in Côte d'Ivoire on the Koné project with Montage — all of which lowers the overall risk for the Doropo project.
Gavin Harris
executiveOn the operational side, our ESG team has been putting in relentless effort alongside every stakeholder group—particularly community leaders at the local level—to secure land access for this project. Land surveys are now finished, compensation rates for land and crops have been settled, and payment structures are in place so that early works construction can get underway in April. Tenders for earthworks and early construction were likewise wrapped up in Q1 and handed to De Simone, a firm known for its track record of delivering mining projects in Côte d'Ivoire. For Resolute, Doropo represents a transformational undertaking and is still on schedule for first gold in 2028. Capitalizing on what was achieved in 2025, when the updated DFS was published and laid out a bigger operation with a longer mine life, Rob Cecchini's project team has sustained that momentum throughout Q1. Headcount on the project expanded in Q1, with more than 40 people now directly employed, adding crucial experience both on the ground at Doropo and in support roles in Abidjan. Roughly 75% of those employees work at the site, while the other 25% handle administrative support out of the regional office. At this point in the project, the main work streams are: acquiring land and compensating crops in zones beyond the early works footprint, including open-pit areas and waste dumps; clearing and building the road access network that connects the construction zones; clearing the primary construction areas and starting earthworks; upgrading the existing Danoa exploration camp so it can house construction crews; building the permanent mining accommodation camp; procuring long lead items and steel fabrication identified during FEED; and early works on the grid power connection, which includes purchasing componentry for hooking up to the grid.
Gavin Harris
executiveFor the Doropo project, we're forecasting capital expenditure of $40 to $50 million in Q2, and our total capex is still tracking inside the $170 to $190 million guidance range for 2026, with the bulk of that spend landing in the second half of the year. Thanks to a strong finish to 2025 right across our mining operations, reinforced by hitting our first quarter plans, we're heading into the Doropo construction phase sitting on a net cash position of $315 million. You can see here some recent photos from the project's initial groundbreaking ceremony, along with the team on the ground. As work advances over the life of the project, we plan to share visual updates via our social media platforms. Let's now turn to an operations update from Mali. As you may recall from the Q4 update, we made some significant changes to the management team at Syama during the second half of 2025. The new Syama team delivered a strong end to 2025 and have now followed up with another solid quarter, delivering the production plan while significantly improving quarterly site safety performance — cutting restricted work injuries by 75% versus previous quarters in 2025.
Gavin Harris
executiveGold production came in at 43,802 ounces, which was in line with expectations and at the upper end of the guidance range for Q1. The bulk of that output — 36,682 ounces — came from the underground sulfide operations, which ran efficiently during the quarter. Sulfide ore throughput rose 8% quarter-on-quarter, with strong reliability and performance at both PP1 and the roaster. Sulfide recoveries came in slightly lower as a result of the higher throughputs achieved. With the oxide plant conversion coming soon and less dependence on oxide mining, 7,120 ounces were produced from oxide stockpiles during the quarter. Feeding stockpiled oxide ore made it possible to complete further open-pit optimization work developing sulfide ore in the Syama North pits for the remainder of 2026. The higher Q1 AISC of $2,227 per ounce reflects increased royalties stemming from a high realized average gold price of $4,858 per ounce during Q1. Measured against guidance, which assumed a gold price of $4,000 per ounce, the AISC sits toward the middle of the guidance range at just under $2,100 per ounce. Although there has been some minimal impact on supply chain activities, for the most part we have not seen any disruption to operations stemming from the ongoing instability in the Middle East.
Gavin Harris
executiveTo lessen the impact of any possible supply interruptions, we've built up our stocks of key consumables to keep operations running without a break. What we've seen is that in April, fuel prices — which the government regulates — went up by roughly 40%. That rise, through Q1, will affect AISC starting in Q2. If fuel prices stay where they are now for the rest of the year, we expect the impact on AISC to be an increase of about $75 per ounce. That said, since prices are regulated, they could come down once there's more clarity on the situation in the Middle East. At Syama specifically, we've expanded storage capacity for LFO, which is used for equipment operation, and HFO, which is used for power generation. LFO inventory is currently at 80% of total capacity, which represents over 50 days of continuous operations. HFO inventory is currently above 90% of total capacity, representing over 40 days of continuous power supply. HFO is key to continued gold production, powering the underground mine, the processing plants, and other site infrastructure. Key reagent stocks on site all exceed three months, and all other goods remain in transit, with some subject to minor delays at the current time.
Gavin Harris
executiveSyama’s explosives inventory levels keep moving around, and this has not had any material effect on operations; at present, more than 30 days of operational coverage is held on site. Additional headway has been achieved in locking in a modular emulsion manufacturing plant that will be set up at the site, and we are still cooperating with the Malian authorities on the permits needed before construction and commissioning can proceed. That manufacturing facility is anticipated to be commissioned in H2. To restate the picture, the Syama sulfide conversion project—begun in 2023—installs essential infrastructure so sulfide ore can be treated through the existing oxide plant, while preserving overall flexibility to continue processing oxide ore. With project construction nearing its final phases, the work streams have been split into two stages. Stage 1 involves commissioning and operating the flotation plant and pebble crusher, handling 110 tonnes per hour of sulfide ore. Stage 2 involves commissioning the ball mill and secondary crushers, lifting total output to 215 tonnes per hour for sulfide ore. Stage 2 also covers commissioning a new electrostatic precipitator on the roaster, raising concentrate throughput by 15% so the extra sulfide concentrate being generated can be processed. Stage 1 commissioning got underway in April, and stage 2 commissioning is scheduled for Q3, once the remaining construction work has been finished.
Gavin Harris
executiveDuring Q2, the roaster is going to be down for three weeks, and that's when we'll carry out a complete internal refractory rebuild, together with mill relines and the girth gear change-out on PP1. Because we're processing oxide stockpiles in Q1, and given the longer shutdowns in Q2 needed to tie in the SSCP, the roaster upgrades, and planned maintenance in PP1, gold production will be weighted toward the second half of the year. Delivering the SSCP safely and efficiently, on time and on budget, marks another significant milestone in Syama's history. All in all, the progress we've made at Syama over the last six months has rebuilt confidence in our gold production forecasts and kept costs stable despite today's inflationary conditions, and most importantly, Syama is still on track to meet 2026 guidance. Our Mako operation in Senegal, just like Syama, turned in another dependable quarter. Q1 gold production came in at 15,801 ounces, in the middle of the guidance range for Q1, and AISC sat in the lower half of guidance at $1,669 per ounce. Mako keeps executing the production plan reliably, and although stockpile variability is always a possibility, overall gold production should hold steady through the remainder of 2026. Processing throughput of 574,000 tonnes was down quarter-on-quarter, reflecting planned maintenance shutdowns in Q1, mill relining, and recovery optimization trials at lower feed grades.
Gavin Harris
executiveWhile we haven't encountered any significant supply interruptions so far, LFO prices began climbing near the end of Q1. In Senegal, the LFO price right now sits 30% above what was anticipated, and should that trend carry through Q2, the estimate is a rise in AISC of roughly $50 per ounce across the full year. Equipment operations and power generation at Mako both depend on LFO. Inventory currently stands at 94% of total capacity, which works out to about 30 days of uninterrupted operations. Stocks of other consumables and key reagents go beyond one month, and most go beyond two months. Compared with Mali, Senegal has experienced far less supply chain disruption, since it has its own port in Dakar. To recap, the Mako Life Extension Project, or MLEP, will take the current Mako mine life out to as much as seven years, with output of 75 to 85,000 ounces of gold annually. It covers two main areas, the Tomboronkoto and Bantaco deposits, situated roughly 20 kilometers from the existing Mako operations. Our 2025 resource and reserve update declared an initial ore reserve for the Tomboronkoto deposit of 348,000 ounces at an average grade of 1.2 grams per tonne. A detailed economic evaluation of the Bantaco deposits is substantially complete, and exploitation of part of the existing resource is expected.
Gavin Harris
executiveRight now, the Bantaco resource stands at 10.8 million tonnes grading 1 gram per tonne, which works out to 351,000 ounces. The Mako processing plant is going to keep running on the remaining low-grade stockpiles through the end of 2027. Between the two MLEP deposits, we expect Bantaco to deliver mill feed before Tomboronkoto, since its socioeconomic constraints are less restrictive — mainly because Tomboronkoto village has to be relocated. As we understand the permitting timelines today, mining at the Bantaco deposits should get underway in H2 2027, while Tomboronkoto is conservatively planned to start at the close of H2 2028, with mill feed arriving in January 2029. Our key work streams over the coming quarter are pushing forward the permits for Bantaco and Tomboronkoto. We'll submit the Bantaco ESIA permit during April, and assuming no clarifications are needed, it should be validated following the 90-day consultation period under the technical services procedures of the Senegalese government. Right after the ESIA is validated — which we estimate will happen in August — we'll submit the Bantaco mining exploitation permit. Final approval of the mining license is anticipated in the first half of 2027. Mining is presently slated to begin in July 2027, which leaves some contingency within the permitting timelines.
Gavin Harris
executiveThe Tomboronkoto ESIA has already been pre-validated by the Senegalese Technical Services Departments, and it has received the support and approval of Tomboronkoto village as well as neighboring communities. We expect to file the application for the mining exploitation permit in May, with approval anticipated early in 2027. Authority to relocate Tomboronkoto village comes as part of that mining exploitation permit. Stakeholder engagement, surveys, and community consultation are all finished, and we have an agreed location for building the new village. Two further ESIA permitting work streams are currently underway. The first covers the Mako plant upgrades needed to feed the Tomboronkoto oxide ore along with the in-pit tailings management facility; those will be submitted in April. The second, to be submitted in May, covers the ore transportation route linking the new deposits to the Mako processing plant, including a bridge over the Gambia River. That improves ore transportation, though existing ESIA submissions also permit use of the RN7, a national road connecting the deposits with Mako operations. What is holding up this submission is the pre-approval needed from the Gambia River Basin Development Organization, and we submitted our application to them in March.
Gavin Harris
executiveAt present, we expect approval for both submissions to come through in September, following the 90-day consultation period. With that said, I'll pass things over to Chris, who will walk you through what's happening in our exploration activities.
Chris Eger
executiveThanks, Gavin. I'd now like to take some time to go deeper into the exploration portfolio of the business. If you turn to slide 18. On page 18, as you can see, there's a solid pipeline of exploration assets across different stages of development. In Senegal, during the first quarter, our exploration drilling was concentrated on the Laminia and Sangola licenses. That said, I should be candid: the exploration results were not particularly strong, though we remain very focused on advancing the Tomboronkoto and Bantaco projects. Most of the key exploration activities were centered on Côte d'Ivoire — at the ABC project, La Debo, and Doropo as well. I'll hold my comments on these projects for the slides coming up, since there were significant developments in the first quarter. Also, as you'd have noticed, in Guinea we carried on exploration work at Barma, but more importantly, we established a joint venture with our partner company Nimba — which is 100% state-owned — to develop new licenses in Guinea. As for our ABC licenses, on the right-hand side of the page you can see that ABC is made up of four key licenses, or permits: Faraba-Fana, located just south of the Awale-Newmont ownership company; the Koné permit; Windou; and Bemanzo.
Chris Eger
executiveThere’s already a resource of 2.2 million ounces grading 0.9 grams per tonne. One key point: that current resource relies on a 0.5 gram per tonne cut-off grade and is limited to 250 meters at depth. We see considerable upside in this deposit, which is why our drilling focus in the first quarter was at Koné. During that quarter, 64 RC holes were finished, totaling more than 11,000 meters. For the second quarter, we intend to keep up our drilling work and also to release a scoping study built on this deposit’s existing resource. I’d like to give a few illustrative examples of drill results we are seeing at the ABC project. On the right side of this page, what you’re actually looking at is the Koné South deposit, since Koné today—the 2.2 million ounces—consists of two separate zones: Koné South and Koné Central. Mineralization at Koné South, shown today in the magenta box, has a strike length of roughly 1.5 kilometers. We drilled both north and south, about 500 meters in each direction, and we’re very happy to observe consistent mineralization both to the north and to the south.
Chris Eger
executiveWe have strong confidence that the ore body extends considerably further north and south, and that the drilling work completed to date will let us grow the resource dramatically. I expect we'll put out an updated mineral resource for ABC during the second half of the year, one that is substantially bigger than what stands today. So in conclusion, what you should expect to see from ABC over the coming months is, first and foremost, the initial scoping study, which I believe will demonstrate very robust economics for what could be our fourth asset. Beyond that, we'll keep the market updated on drill results that we view as very exciting and robust, and that gives us a clear path toward an updated resource in this year's second half. If you turn to page 21, other key exploration activities in Côte d'Ivoire include our La Debo project. La Debo was acquired in 2024, and we announced its maiden resource in 2025, which appears at the bottom right of that page. We have in fact just begun kicking off drilling activities in March of this year. We completed 2,000 meters. Unfortunately, I have no key results to share today, but our focus is on drilling out G3 South, which sits in the northeast portion of the deposit, and we're concentrating on drilling it at depth and along strike, since we see it open in both directions.
Chris Eger
executiveWe're going to launch a drill program of at least 13,000 meters, and we also intend to issue a scoping study at La Debo during this year's second half, along with an updated mineral resource estimate. We really believe we can approach a million ounces, perhaps even beyond that. That's the goal we've set, and so far things look highly encouraging. If you turn to page 22, besides our ABC and La Debo exploration projects in Côte d'Ivoire, there are also some exciting key activities at Doropo. As you can imagine, when Centamin ran Doropo and was advancing the feasibility study, at a certain point Centamin halted its exploration work. Our team has been going through all the prior drilling work and thinks there are chances to grow this project and these deposits considerably. Soon, we will concentrate on drilling programs in two main areas: at Vako-Cherifso, which would be more greenfield work, but even more importantly at Kilisso Souti, located in the southwest, which is our biggest pit. We plan to drill both zones actively so as to grow the project's resource and reserve, and we're aiming for no less than 30,000 meters of drilling, with hopefully an updated resource and possibly reserve in this year's second half.
Chris Eger
executiveTo wrap up, in Côte d'Ivoire we've got genuinely excellent exploration work underway. First, I think Doropo is going to turn into a considerably larger operation with a much longer mine life. Second, given what we're observing at ABC and La Debo, my belief is that one of those two assets will end up being our fourth mine. Now, turning to page 23, I'm also quite enthusiastic about what we're doing in Guinea. As I mentioned earlier, during Q1 we signed an MOU with Nimba Mining, a state-owned mining company, aimed at evaluating possible gold opportunities across Guinea. On the joint venture, here's where things stand: we've been collaborating with Nimba to pinpoint targeted zones that we think would be the most interesting for joint exploration work. That list is now with Nimba. The next step is for Nimba to engage with the government and reach agreement that those are the right zones to begin with, and after that we'll kick off exploration activities. In closing, I'm very keen on Guinea as potentially a fourth country where we'd have operations, so it makes sense to put effort in through this joint venture as we keep cooperating with the Guinean government on developing new projects.
Chris Eger
executiveWith that, Dave Jackson will now provide a financial summary.
Dave Jackson
executiveThanks, Chris. I'll take you through the headline Q1 financials now and point out the key performance metrics. All in all, it was a very strong quarter for us, and our Q1 metrics came in line with expectations. We keep making our balance sheet stronger and are building substantial cash within the business. Turning to the financial highlights, Q1 revenue came in at an impressive $338 million, produced from selling 60,000 ounces of gold at an average realized price of $4,858 per ounce. As mentioned previously, Resolute stays fully unhedged and keeps selling all of its gold at spot prices. Net cash at quarter end was $315 million, which marks a $106 million rise from Q4. That net cash figure includes $100 million of unsold bullion, equal to nearly 22,000 ounces of gold sold shortly after the quarter closed. Group all-in sustaining cost for Q1 came to $2,210 per ounce, inside our expectation. The AISC includes the effect of higher royalties, which came to $120 an ounce because of the higher gold price realized during the quarter. As Gavin noted earlier, we are seeing fuel and other input costs rise, and those will begin flowing through from Q2 and affect all-in sustaining costs going forward.
Dave Jackson
executiveRight now, we're holding to our group all-in sustaining cost guidance of $2,000 to $2,200 an ounce. That said, we'll keep watching it closely should input costs stay elevated and gold prices remain where they are today. Let me take you through the main pieces of our cash flow summary that produced a net cash position of $315 million at the close of Q1. During the quarter, operating cash flow came in strong at $120 million, which is $34 million higher than Q4 of last year, mainly driven by stronger gold prices and greater sales volumes. CapEx for the quarter was $33 million in total. That figure includes $13 million of project capital across Syama and Mako, $8 million for SSCP, $3 million on the MLEP, $4 million for Doropo, and $5 million directed to exploration. On the whole, CapEx and exploration spending came in as expected for Q1 and remain on track toward full-year guidance of $310 to $360 million. VAT outflows during Q1 came to $9 million across Mali and Senegal. Resolute is continuing to work with local governments to settle those amounts. That said, we're glad to report that we secured $4 million of VAT mandates in Senegal in the quarter, and those will go toward settling payables in Q2.
Dave Jackson
executiveRegarding working capital, our outflow for the quarter came to $3 million. That figure stemmed entirely from a decrease in payables, which we paid down in the ordinary course of business. During the quarter, as we said before, we got the $32 million in proceeds from selling Resolute's stake in Loncor Gold. Net cash at quarter-end stood at $315 million, an increase of $106 million since the beginning of the year. With that, the business now has over $425 million in available liquidity. Right now, we hold slightly less than $100 million in available overdraft facilities across Mali and Senegal, and those can be used for working capital management or for development opportunities in the country. Looking ahead to Q2, we anticipate cash flows will decline relative to Q1 as CapEx spending on Doropo ramps up. On top of that, we expect income tax payments of roughly $50 million tied to our assets in Mali and Senegal. That stems from the strong net income performance in 2025. Backed by our continued healthy cash position and ample liquidity, the company is well-positioned to fully fund its 2026 CapEx requirements, including construction at Doropo. That will come through existing cash balances and the strong cash flows we anticipate for the remainder of the year.
Dave Jackson
executiveEven so, we keep looking at a variety of alternatives that could strengthen our balance sheet further and help move the Doropo project forward, and we expect that to be wrapped up during the year. As a reminder, we also hold a receivable tied to the sale of the Ravenswood mine, and at the close of Q1 it is valued at $52 million. That receivable comes due in 2027, though it could be paid ahead of schedule if the asset is sold. To sum up, our financial position is very solid, and we are excited about the business continuing to grow. With that, I'll turn things back to Chris.
Chris Eger
executiveThanks, Dave. Now just a few slides to wrap up our presentation today. First of all, let's turn to page 28. The key point I want to emphasize is that we are very much hitting every target we laid out at the start of the year. On the left-hand side, as you can see, in Côte d'Ivoire we've secured our mining permit for Doropo, we've reached FID, and we've begun early construction work. At Syama, our operations continue to be very much on track and on budget, both on production and on SSCP. In Senegal, we've submitted the Tomboronkoto ESIAs, and the Bantaco ESIA is nearly finished, and we expect to submit our mining application for Tomboronkoto in Q2. Also in Guinea, as I've mentioned a few times already, we've finalized an MOU with Nimba, and we're continuing our early-stage activities. The business is delivering what it said it would do, and that pleases me greatly. Looking ahead, you can see there are quite a few key milestones coming up soon that I'm very confident we will achieve over the remainder of the year. Turning to page 29. In conclusion, I couldn't be happier with how the business is performing in the first part of this year.
Chris Eger
executiveWhen it comes to production, we're solidly on course to hit the guidance range of 250 to 275,000 ounces. Across every country where we run operations, all our projects are moving forward — at this point we're solidly on course and within budget. The first quarter of the year saw us bring in a healthy amount of cash, which put our net cash position above $350 million. So what does that tell us? With the business and the assets we hold today, we have a clear trajectory to reach more than 500,000 ounces of gold production by the close of 2028. Beyond that, based on what the exploration program is showing me, I believe there's a great deal more we can accomplish by the end of this decade. With that, I'll turn it back to the operator for questions.
Operator
operatorThank you. Ladies and gentlemen, the question-and-answer portion of the call starts now. Should you be connected by phone and wish to pose a question, kindly indicate this by pressing *1 on your keypad. We'll hold briefly while the queue is put together. Our first question comes from Justin Chan at SCP Resource Finance. Please go ahead.
Justin Chan
analystHi Chris, hi Dave, and hello to the whole team. I appreciate you hosting this call, and congratulations on a solid beginning to the year. My first question concerns the ASIC guidance. You've shared quite a bit of useful detail, and I realize many variables are in play, gold price among them. To make sure I understand: setting prices aside for a moment, on the fuel side, would it be accurate to say you'd be moving toward the middle to upper end, with gold prices then added on top of that? Does that capture it fairly?
Chris Eger
executiveJustin, Chris here. Thanks for asking. Look, I'd say the number that likely carries more impact on ASIC relates to the gold price, since royalty expenses feel a meaningful effect when gold trades higher. In the first quarter, as Gavin pointed out, we came in at roughly $135 against our guidance, really owing to the gold price. Should gold sit at $4,850, my expectation is that we'd likely land above our guidance range across the full year, since that would probably mean about a $200 effect on guidance. Then, look, as we've noted, we're observing fuel prices up roughly 30% to 40%, and those are only just starting to hit during April. My guess is those figures reverse by Q3, though that's only my guess. Our maths worked like this: assuming a 30% to 40% increase that persists right through the whole year, we'd then see roughly a $75 impact on ASIC at Syama and around 50 bucks at Mako. It could reverse quite easily, which is why we'll likely take a deeper dive in Q2 and see where we land at that point.
Justin Chan
analystUnderstood, I appreciate that. Moving to tax, you did a great job highlighting the $50 million for Q2. Should we expect any additional uneven payments at other points in the year?
Chris Eger
executiveNot truly, no. That’s the item in which, during the second quarter, we settle both historical and provisional income taxes for the two operations. The separate matter that was called out was CapEx, and listen, CapEx during the latter half of the year will rise with Doropo, though the feasibility study sits on our website and that clearly shows precisely what the figure ought to be in the second half of the year. On the operating side, the main source of unevenness stems from tax payments, and those fall in Q2.
Justin Chan
analystUnderstood. Then perhaps just a single question about ABC. I suppose, how much of the resource at Koné are we talking about, and what portion comes from the satellite pits? I'm simply attempting to get a feel for what the asset looks like and where extending along strike would make sense.
Chris Eger
executiveThat's a fair question. So look, we'll post more detail on ABC to our website so folks can actually view it visually. Right now the whole resource is at Koné, and it sits in two zones: Koné Central and Koné South. I showed a map of Koné South in the presentation. Koné Central is quite similar in appearance — really it's just two ore bodies. What we've been doing is drilling north and south of both Koné Central and Koné South in order to extend the resource, and again, from what we're seeing, the mineralization is continuing in both of those areas. Beyond that, there are other satellite areas we're drilling out to the far north of the Koné license. There's one area where we've done some drilling and we may add a resource to it in the second half of this year, but the focus has been on the quick win, which is simply extending the existing resource at both Koné South and Koné Central.
Justin Chan
analystUnderstood. What’s the depth of each of those deposits? They appear to be oxides—at this point, is there a significant sulfide component?
Chris Eger
executiveNo, everything we're seeing is very much oxide and that kind of material, which is what we've kept encountering in Côte d'Ivoire. Our drilling has gone down to roughly 150 meters. Look, the way we look at it, this is a typical open-pit operation down to 150, 175 meters. It does go deeper — we've observed it carrying on — but our focus in the drilling today was putting in additional holes to the north and to the south at around 150 meters depth.
Justin Chan
analystGreat, I appreciate the preview. I’ll hand the line back over now. Many thanks, everyone.
Chris Eger
executiveAppreciate it.
Operator
operatorIf you'd like to pose a question, you can do so at any time by pressing * and then the number 1 on your phone keypad. We now have Jasper Mainwaring from Berenberg on the line. Your turn.
Jasper Mainwaring
analystHello everyone, thanks for the update. I’ve just got one question. Since the company holds such a solid net cash position, how should we view shareholder returns, and if you’re thinking about giving some of that cash back to shareholders instead of putting it toward future growth and exploration projects?
Chris Eger
executiveMorning, everyone. So, as you'd expect, given the CapEx needs at Doropo, we'll be funding our organic growth work over the next couple of years through existing cash plus cash generated from operations going forward. Then, from 2028 onward, we'll be producing substantial cash, and at that stage we'd expect to look at ways to return cash to shareholders — though we'll need to weigh that against other organic opportunities in the business. The one caveat I'd flag today is really what we're seeing at ABC. That project, as I mentioned, will probably be 3 million-plus ounces at least at some point, and the economics, I think, will demonstrate that there's a mine to be built there. Whether that's us or someone else is a question we'll settle down the road. The key point, I suppose, is that over the next couple of years we'll deploy all our cash toward the organic growth projects, and from '28 onward we'll have surplus cash to consider shareholder returns.
Jasper Mainwaring
analystAlright, thanks a lot.
Operator
operatorIf you'd like to pose a question, just hit *1 on your phone's keypad one more time. Our next question is from Richard Knights of Barrenjoey. You're up.
Richard Knights
analystHello, gentlemen, and thanks for taking the call. I have one more question about ABC. You seem fairly enthusiastic about the exploration results coming in. Does that shift how you see the project's ultimate scale, and will that revised view show up in the scoping work you plan to publish next quarter?
Chris Eger
executiveLook, it's definitely shaping how we're thinking about this, because we know the project—and the scale of that ore body—is going to end up considerably larger than the original resource that's been published. Given the time constraints, and since we wanted to get the scoping study out as fast as we could to demonstrate the economics of this exciting project, we ran the scoping study based on the original resource, the 2.2 million ounces. In the next couple of months, when we issue the scoping study, we'll make that point clear, and then we'll also keep updating on drill results. I think the scoping study will give you a sense of the plant size and the CapEx requirements, and then what happens over time as the ore body grows further is simply an extension of the mine life.
Richard Knights
analystAlright, thank you. That's fine. Perhaps just one additional question regarding explosives at Syama. Clearly, you're aiming to address that issue through the facility you plan to build on site in H2. Do you have any sense of what the timeline looks like for that permit? And also, I'd imagine, is there any risk, or how would you characterize the risks surrounding access to explosives going into the second half should that permit come through?
Chris Eger
executiveNo, I appreciate that. Well, perhaps I'll hand things off to Gavin. He'll be able to give more detail than I can. Gavin?
Gavin Harris
executiveSee, the supply picture at Syama is much steadier now than it was a year ago, and our present supplies aren't causing any interruption to operations. The main rationale for making explosives at the site is really to reduce the risk involved in moving explosive materials around Mali. That means bringing in raw materials instead of explosives shipped from regional hubs within Mali and also from Ghana and Côte d'Ivoire. Look, we've lined up a modular plant that's ready for import and is sitting in Ghana right now, just over the border and not far off. We do anticipate getting it operational in H2. The authorities have already paid a site visit, and permitting is pretty uncomplicated. We've produced explosives at that site before, in the spot we're proposing within our magazine area, so at this stage we view the chance of not going ahead as relatively low.
Richard Knights
analystAlright, thank you. That's clear. Perhaps just one additional question regarding the VAT balance owed to you in Mali. I guess, first, where does that stand right now, and second, do you remain somewhat optimistic about recovering it within a reasonable timeframe?
Chris Eger
executiveSo, regarding VAT, most of that receivable is in Mali, as we anticipated. Right now it's roughly $70 million. I was over in Mali early in March and had some solid, productive talks with the government, and they were cooperating with us to get those VATs issued. The dialogue and discussions are all heading the right way, but we still haven't gotten anything. I'm confident we'll receive them at some point. When that happens, I can't say, but this year's conversation is very different from what we've seen in earlier years. In Senegal, and even Côte d'Ivoire, we do collect VAT, though there's always a lag and we have to push hard for it. I think, as I said to wrap up, I'm confident we'll get something at some point — I just don't know when.
Richard Knights
analystAll right, that's great — I appreciate it, everyone. I'm grateful you joined the call.
Chris Eger
executiveThanks.
Operator
operatorThe following question is from Justin Chan of SCP Resource Finance. Justin, your line is open — go ahead.
Justin Chan
analystHi, apologies — my line was muted. I’ve just got two quick questions about Doropo. Could you maybe give us a sense of what you’re aiming to get done during the rainy season? It looks like the construction camp and the village. I was wondering whether you’re hoping to begin getting some water for the water storage facility in this rainy season, or is that going to be next year?
Chris Eger
executiveGavin, would you like to handle that one too?
Gavin Harris
executiveYeah, that's fine. Look, we're beginning early works construction there, and the water storage dam along with the water harvest dam are two of the main components in that area. If we don't advance far enough to hold meaningful volumes of water, we're also installing boreholes right now. We have a contract to mobilize to site for putting in bores at this point, beginning this month.
Justin Chan
analystUnderstood. Would you say that's a significant operational factor, or is it already at a decent level ahead of startup, or is it not really a big consideration?
Gavin Harris
executiveNo — our view is that by the time the following wet season arrives next year, all of the infrastructure will definitely be in place, and we expect to collect a sufficient amount during that rainy period. You've no doubt seen in the DFS update that we have in fact doubled storage capacity — this is to guard against any shortages down the road given how unpredictable wet seasons currently are in West Africa, and also to leave room for growth later on should we decide we want to take the project further.
Justin Chan
analystUnderstood. Thanks a lot.
Operator
operatorThat brings us to the end of the Q&A. We're done with today's call. Enjoy the rest of your day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Resolute Mining Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Resolute Mining Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Resolute Mining Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.