executiveGood morning, everyone. Paul Nester here, President and CEO of RGC Resources. I appreciate you spending part of your Friday with us for the call covering our fourth quarter and fiscal 2021 earnings; the weather is lovely today in Roanoke, Virginia, and I trust conditions are just as nice wherever you're listening from. To begin, a handful of housekeeping notes. <<operator_script>> Once the presentation wraps up, we'll open the lines for questions. You can find the link to today's presentation on the Investor and Financial Information page of our website, www.rgcresources.com. All right. Let's begin. Slide 1 contains our forward-looking statements disclaimer. Forecasts and projections do appear in this presentation. Slide 2 shows the agenda for today's call. So, like I said, we're going to walk through the operational and financial highlights. I should've mentioned this sooner — with me today are Tommy Oliver, our CFO, and David Garcia, who heads up Finance. You all know that Tommy and David join us for every call, and we'll also spend some time on what we expect for 2022. And just to repeat, we'll take questions at the very end. Let's move to Slide 3. The Roanoke Gas utility had a fantastic fiscal 2021 when it came to bringing on new customers. We brought in about 600. If I remember correctly, the exact number for the fiscal year was 597, and that topped 2020 by 8%. We've talked about main extension miles on previous calls. We wrapped up 2.5 more miles in Q4. That covered the second phase of the Blue Ridge build-out. With that, our full-year figure reached 7 miles. It's a fantastic outcome, and it represents growth of 71% versus 2020. Let's move to Slide 4. Q4 volumes looked pretty strong overall. On the residential side, we saw a decline of 5%. September 2021 came in far warmer than the same month a year earlier. Actually, heating degree days fell 77% during September. Yet the shift in residential volumes, measured in absolute decatherms, amounted to only 9,000. That means the 5% figure can be a bit deceptive. All things considered, it wasn't so bad. Industrial volumes stayed lower throughout Q4, largely due to the big customer that switched from natural gas to another fuel back in 2020. Like we mentioned earlier, in 2021 this particular customer went back to using coal. You've heard us talk about it all fiscal year — our volumes so far are higher and showing more strength. That big account I just brought up has definitely dragged down industrial volumes for the year to date. Still, when you consider our ten biggest customers, mostly a blend of industrial and commercial, eight of them used more gas in 2021. We keep seeing clear gains over last year among building suppliers, auto parts manufacturers, and makers of consumer products. Now turning to capital spending, which is on Slide 6: we came in roughly $3 million under 2020. That stems from the way projects are scheduled, which we've covered on earlier calls, along with the kinds of projects we're taking on. Shortly, you'll notice that this $3 million is going to carry over into what we're projecting for capital in 2022, or our capital budget. During both the previous year and this one, we devoted a lot of time to talking about the initiative we refer to as our signature project for 2020, the Blue Ridge main extension. Blue Ridge's Phase 2 did begin in July. In fact, it wrapped up only a couple of weeks ago, around mid-November, and that's great. In 2021, we had two initiatives that mattered a great deal to us. One was the support project for the Carilion expansion, where we invested about $1 million. The other was the renewal of Mason Station, which ran through our SAVE Rider and totaled $0.75 million. Both wrapped up during the fourth quarter. As for customer growth and main extensions, we've already addressed those. The amount connected to the figures we reviewed earlier reached $5.9 million, which marks a 70% increase compared with 2020. That $5.9 million does not include the Blue Ridge project. Tommy is now going to take a few minutes to walk us through the income statement for our fourth quarter and fiscal 2021.
Lawrence Oliver
executiveOkay, thanks, Paul, and good morning, everyone. Our condensed consolidated statements of income can be found on Slide 7. I'll walk through the financial results for each of our 2 operating segments separately — our Roanoke Gas utility and RGC Midstream. Let me begin with how Roanoke Gas performed in the fourth quarter. Operating income came in roughly $1.5 million above what we saw in the same quarter a year earlier. As we've mentioned on previous earnings calls, the fourth quarter of 2020 included several sizable expenses. Specifically, those were bad debt and the accelerated recovery of certain regulatory assets; we also pointed out that a moratorium on disconnecting customers for nonpayment was in place for all Virginia utilities. We're happy to say that moratorium, along with the uncertainty surrounding it, came to an end in late August 2021. Following the moratorium's conclusion, in October the company received an award of $858,000 in ARPA funds from the Virginia State Corporation Commission. Those funds carried a specific designation and, I should add, went toward assisting our customers with their arrearage balances. These ARPA funds had a favorable effect on our fourth quarter 2021 results. In fact, they boosted earnings by $0.06 per share. Without the ARPA funds, we would have posted a loss for the fourth quarter of 2021, since we accelerated the recovery of our deferred COVID-related expenses and also incurred other sizable expenses tied to outside professional services, among other things. It's worth pointing out that following the write-down of the COVID-related deferrals, as of September 30, 2021, we no longer carry regulatory assets on our books that are subject to the earnings test. Now let me move on to RGC Midstream. Midstream again saw a substantial quarterly year-over-year drop in equity and earnings from the Mountain Valley partnership. Equity and earnings fell by more than $1.1 million quarter-over-quarter. Even with that drop, earnings per share for the fourth quarter of 2021 were flat, compared with a loss of $0.04 per share in the fourth quarter of 2020. For fiscal year 2021, operating income rose 18% year-over-year, mostly driven by SAVE revenues and customer growth, which Paul covered on an earlier slide regarding our main extensions and new customer additions; beyond the effect of the ARPA funds on earnings, during the fourth quarter we recorded — the company also had received $400,000 of CARES Act money earlier in the fiscal year, which dramatically lowered our bad debt expense as well. The solid fiscal year earnings at Roanoke Gas were offset by a year-over-year $3.1 million decline in equity and earnings from the Midstream's — from investment in the MVP, producing $1.22 in earnings per share on a consolidated basis.
Paul Nester
executiveThanks, Tommy. Our 2021 financial results were truly exceptional. At this same point a year ago, a great deal of uncertainty remained, especially regarding the pandemic; and as everyone is aware, the vaccine wasn't obtainable until the beginning of 2022. So finishing this fiscal year with those earnings ranges really reflects well on our team members and how committed they are to our business and the people we serve. That $1.22 figure makes us extremely pleased. All right. Now let's shift to 2022, and there are 4 items we'd like to address. Capital comes first. Once again, capital remains the engine behind our earnings growth. We'll provide an MVP update. I believe the timing is right for Tommy to share some details regarding a few of our ESG efforts and the work we've done in that area; we feel now is a good moment to inform you about it, and after that we'll wrap up with our earnings per share projection. All right. Our capital plan for 2022 sits at $25.4 million, as you can see — the biggest capital budget in this company's history. Momentum keeps building on main extensions and adding new customers. I believe we already mentioned that phase 2 has now finished up over in Blue Ridge. Phase 3 has begun, and we've allocated close to $6 million toward that category. That's the biggest sum we've ever set aside for main extensions and new customers. A single gate station remains to be renewed, and we're aiming to finish it during 2022; that work will go through our SAVE plan. And once again, that's genuinely something for this company, our customers, and our shareholders to take pride in. Back in 2014, we began the effort of renewing our gate stations under the SAVE plan, and this final one — named Brown Farm, which we intend to finish this year — will be exactly that, our last; at that point every one of our gate stations will be renewed and modernized. We're quite pleased about it; we're moving ahead with phase 3 in Blue Ridge. That should require roughly a $1 million investment to extend approximately another 1.5 miles to 2 miles of main across that region. And last, we have a sizable special project totaling about $5 million within this capital budget. We're hoping to make a public announcement about it within the next few weeks. It's — in our view it's simply a fantastic, fantastic opportunity and project. There's an ESG dimension to it, and we look forward to announcing it once the timing is appropriate, but it's also factored into this number. All right. Let's spend a few minutes discussing the Mountain Valley Pipeline. Mountain Valley has concluded its 2021 construction; they've demobilized from the field. Naturally, they continue monitoring environmental impacts and the right of way as mandated. They truly performed well—or even excellently—during 2021 when it came to building, making headway, and carrying out what they'd planned for that year; we're genuinely pleased with their efforts. When it comes to the whole project, it's actually roughly 94% finished. On the slide, you'll notice we showed a figure above 90%. That figure is accurate as well; however, once you factor in the compressor stations, every one of the interconnects, and the pipeline itself, the number really falls within that 94% range. We're eager for Mountain Valley to reach completion during 2022. It's very nearly finished. We're looking forward to that, along with the gas it will deliver to the Roanoke Valley. Tommy, give us a brief overview of ESG.
Lawrence Oliver
executiveAbsolutely, Paul. Let me take you back a bit through our company's timeline. Back in 1992, we became the initial utility within the state to receive approval for an infrastructure rider, which allowed us to recoup expenses for swapping out bare steel and cast iron mains and services without going through a rate case. Thanks to that rider and the SAVE riders that came later and remain active, by 2016 we had finished replacing every one of our bare steel and cast iron mains and services. That work has sharply cut our greenhouse gas emissions and simultaneously made our network far safer and more dependable. In 2021 — that is, fiscal year 2021 — we carried on with our methane reduction work via the SAVE program. We replaced close to 8 miles of main, more than 600 services, and an additional city gate transfer station, as Paul referenced. It's important to point out that our solar installation just hit its 1-year mark of being operational. From the time it entered service, the company has generated more than 106-megawatt hours of power, which has taken away 63 tons of CO2 emissions. We also became a member of ONE Future not long ago. For anyone who doesn't know ONE Future, it consists of 50 natural gas companies collaborating to lower methane emissions throughout the natural gas value chain. Our website has further details about these and other ESG efforts.
Paul Nester
executiveYes. Thank you, Tommy. As Tommy mentioned at the start — I appreciate him taking us back a bit. Our track record is long when it comes to acting properly and putting in extra effort so that our effect on the environment stays limited, or, once more, so that we do positive things for the community. Naturally, we intend to keep that going. What we've accomplished over the past 12 months makes me very pleased. And once more, there are several efforts underway that we're developing across the coming 12 to 24 months. All right. Let's close by looking again at our earnings per share. Once more, the figure for 2021 stood out; and specifically, you're able to see the shift in those blue bars, which was truly powered by the Roanoke Gas utility. And as Tommy discussed, the — we did experience a fairly substantial onetime effect from pandemic stimulus funds; we don't anticipate receiving that relief or seeing that effect during 2022. So we have reduced, specifically, the Roanoke Gas utility earnings only marginally compared with the prior year. Should you take out the onetime effect of those stimulus funds, Roanoke Gas is still expanding, naturally. And in a cautious manner, we've set the earnings from our Midstream investments at basically breakeven. So once more, we anticipate a tremendous 2022, and the Board is pleased with that earnings projection. That brings our prepared remarks to an end. We'd be glad to take any questions. <<operator_script>> Mike, how are you?
Mike Gaugler
analystI'm well, thanks. And you?
Paul Nester
executiveThings are great on our end. Today it's like we're in Florida, here in Roanoke. The temperature has reached 60 degrees already, and it's expected to get near 70.
Mike Gaugler
analystStill, that doesn't bode well where gas volumes are concerned.
Paul Nester
executiveFor construction it's a plus, yet for throughput it isn't. Exactly.
Mike Gaugler
analystOnly a single item from me, everyone. I came across a piece in S&P Global. According to it, MVP Southgate has been running into certain permitting problems across the Carolinas. I figured perhaps you might shed a bit more light on that, plus what the partners are thinking regarding this matter.
Paul Nester
executiveSure. Thanks for asking, Mike; and only as — a quick reminder for everyone else listening in, Southgate constitutes the extension running from Station 165 off the MVP mainline, turning back at the Virginia and North Carolina border and basically forming a dogleg returning toward the broader Greensboro region, roughly speaking. That project spans about 70 miles. The pipe diameter is somewhat smaller, 24 and 16 inches compared with the main line's 42 inches. Still, it truly is an excellent project; and should anyone know that section of North Carolina, especially, it's an area of strong growth when viewed through an economic development lens. So perhaps the — maybe the straightforward response to what you asked, Mike, is that clearly, since the MVP mainline has gone through certain delays, especially across the last 24 months, Southgate's delays have tracked right alongside that. As I see it, the project continues to move through permitting on Southgate. Nothing strikes me as what you'd call seriously concerning right now. It's, I believe, what all of us have witnessed over the last 5 years when it comes to pipeline projects. Clearing the permitting obstacles is tough, yet I believe they will eventually get there successfully.
Mike Gaugler
analystAlright, that is definitely welcome information. That project is something that's needed.
Paul Nester
executiveDoes anyone else have something they'd like to ask?
Analyst
analystPaul, it's Jack.
Paul Nester
executiveJack, how are you?
Analyst
analystAll right, I'm good. A couple of things. First, regarding the debt level — how much debt has been taken on because of MVP?
Paul Nester
executiveYeah, that's a fair question, Jack. As things stand, if you go back to that slide showing what we've put into MVP, every bit of that funding has come from debt so far. I believe David is there on a slide, Slide #10. When 2021 came to a close, the capital costs we've spent on the project — our cash investment — comes to a bit more than $50 million. So as of now, debt has covered all of those capital costs.
Analyst
analystAll right. Could you also share your perspective on, I suppose, the overall regulatory hurdles facing the MVP?
Paul Nester
executiveSure, happy to provide some detail on where things stand as of December 3. The upcoming item on the schedule is the Virginia State Water Control Board hearing set for December 14, when they will review the application for water crossing permits within Virginia. Tommy, along with 2 or 3 other colleagues from our company and myself, took part in the public hearings concerning those permits. Back in the fourth quarter of 2021, we shared our views and the facts, I should mention, regarding why the Mountain Valley is needed for the Roanoke region and, indeed, for Roanoke Gas Company. Jack, in response to your excellent question, the customer growth we're experiencing here and the economic development happening in the greater Roanoke Valley are significant, and we're delighted to back that, yet we genuinely require the Mountain Valley to keep supporting it. Our expectation is that we'll bring on another 600 customers, possibly even more than that during 2022. Once more, there's such strong momentum carrying over from 2021, yet the necessity for the Mountain Valley has never been more urgent. Still, as has been made public, not just by us but by the other project partners, the water crossing permits represent the major obstacle at present. Once again, we ought to learn more regarding those within the next 60 days while Virginia and West Virginia carry out their planned work on it. The Army Corps follows right after Virginia and West Virginia when it comes to additional approval. And in the end, the FERC must likewise grant approvals tied to the water crossing. So I hope that addressed your question. Are there any other questions right now? <<operator_script>> Well, once more, thank you very much for spending time this morning on the call. And from everyone here at the company and on behalf of our employees and customers, I'd like to wish you a joyful holiday season and a very merry Christmas; and we look forward to joining you again to go over our first quarter results around late January or early February. I hope everybody has a safe and pleasant weekend. Thank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete RGC Resources, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to RGC Resources, Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in RGC Resources, Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.