RGC Resources, Inc. (RGCO) Earnings Call Transcript & Summary

February 10, 2023

NASDAQ US Utilities Gas Utilities earnings 21 min

Earnings Call Speaker Segments

Paul Nester

executive
#1

Good morning, everyone, and thanks for joining RGC Resources' 2023 first quarter earnings call. I'm Paul Nester, and I serve as President and CEO of RGC Resources. Before we begin, a few housekeeping notes: every line has been muted, and we ask that everyone stay muted throughout. Once the presentation and our prepared comments wrap up, we'll open the floor for questions. You can find the link to today's presentation on the Investor and Financial Information page of our website, www.rgcresources.com. Here with me this morning are Jason Field, our Chief Financial Officer, Tommy Oliver, Senior Vice President of Regulatory and External Affairs, and Kelsey Davenport, Director of Finance. Turning now to slide one, I want to note that this presentation includes forecasts and projections. Our forward-looking statements appear on Slide 1. The agenda for today's call is shown on the second slide. As we typically do, we'll go over operational and financial highlights from the first quarter, discuss our fiscal 2023 outlook, and then, as I said, we'll gladly take your questions once the call concludes. Now to slide three: our customer growth remains solid. On that bar chart, you'll see the customer count dipped slightly versus 2021. As you may recall, we talked at length going back to 2020 about the moratorium placed on utility disconnects and how it impacted our customer counts. Come March of 2022, we could restart collection processes for non-pay turnoffs, and so, with colder weather arriving this winter, we've managed to bring back a number of those customers. Just under 63,000 is where our total customer count sits. That figure makes us quite pleased. We absolutely anticipate crossing 63,000 within the next few months. It was a solid first quarter, with new services added along with main extension, plus another 1.1 miles of main; in our view, housing development across the greater Roanoke Valley remains robust. Once again this year, we look to bring on roughly 500 to 600 new customers. Jason, please take us through delivered volumes, our financial statements, and capital spending for the first quarter.

Jason Field

executive
#2

Absolutely, Paul. Thanks. We're looking at slide four. In the first quarter, our delivered volumes rose by roughly 620,000 dekatherms versus the first quarter of 2022. That works out to a 23% gain, mostly because the weather was colder than usual relative to a year earlier. Heating degrees came in 31 higher than the prior year. On top of that, we kept seeing the benefit of more transportation and interruptible volumes thanks to our single multi-fuel customer, which maintained elevated natural gas usage throughout the quarter. Turning to slide five, we highlight our financial results. For the quarter, operating income came to $5,544,000, an increase of roughly $166,000 from the prior year. Operating revenues, adjusted for normal weather, were higher, while non-gas operating expenses for the quarter surpassed the previous year because of greater spending on contracted services, bad debt expense, and personnel costs. Interest expense for the quarter rose versus last year, driven by higher rates on our variable rate debt, mainly at our midstream affiliate. All told, net income fell by approximately $329,000 relative to the first quarter of last year. On an earnings per share basis, we posted $0.33 per share, a decline of about $0.10 per share, reflecting the dilutive impact of the equity offering from March of 2022 along with the modest drop in net income. Comparing our 12-month operating results through December 31st, 2022 is tough because of the impairments we recorded — again at our midstream affiliate, related to the Mountain Valley Pipeline; we've adjusted for that impairment on slide six. If you go to slide six, you'll see our underlying net income, which strips out the after-tax effect of those impairments and shows underlying net income of $8,851,000. As you remember, we recorded those in the second and fourth quarters of 2022. This figure is down $112,000 versus the 12 months in 2022. On the whole, we're happy with that financial performance. When it comes to managing costs in this inflationary environment, we believe we did well. We'll talk a bit later about the non-gas rate case filing, which we submitted in early December, and which we expect to ease some of those cost pressures over the rest of the year. Moving on to slide seven, you'll see that Roanoke Gas Company made strong investments in utility property during these first three months of the fiscal year. In total, we invested approximately $7.5 million in utility property, which was up by about $1.8 million compared to the first quarter of last year. This rise came mainly from investments in the RNG project and SAVE eligible renewal projects. Paul and Tommy will now cover the outlook for the rest of fiscal 2023.

Paul Nester

executive
#3

Thank you, Jason. Before we go through the fiscal year forecast, I want to offer a single remark regarding the first quarter. Our Roanoke Gas operation and the quarter overall have me feeling genuinely pleased, yet what truly has me excited and filled with pride are the efforts during mid-December, in the days before Christmas, when that severe cold weather hit the part of Virginia where we operate. The people and teams on our side did a superb job. Not one customer was lost, and that is something we take great pride in and feel very good about. When we turn to the 2023 forecast, we'll examine the capital investment projection covering the entire year. Tommy will provide additional specifics regarding the filing for our non-gas base rate case; we will discuss the projection for earnings per share, after which Tommy will wrap up with a fine update concerning the project for our RNG facility. Turning to slide nine, you'll observe that capital investment continues to be led by $6.8 million in SAVE spending. One quick note on that. Tommy will address it shortly, but essentially that spending is renewal-related; put differently, we remain engaged in renewing pre-1973 Aldyl A plastic pipe. Roughly that amount has been our yearly outlay across the last three or four years. Through the rest of this year, we will stay on that same path. Beyond the RNG facility, we actually have a few other notable projects I want to bring you up to date on. An Enterprise Resource Planning, or ERP, system upgrade is currently underway. For this fiscal year, we expect to spend roughly $1.4 million on it. Our existing system has reached the end of its life. In fact, it is 30 years old. It has served us very well, but the moment has come to modernize and bring in a new tool. Right now, our teams across finance, IT, and operations are working their way through that project. We intend to invest around $1.7 million in the Carilion and Virginia Tech Carilion Medical School area to back the growth that simply keeps expanding there. Roanoke Memorial Hospital has a new addition, and the medical school is putting up another building as well. To strengthen the distribution system in that section of downtown Roanoke, we're going to install a large 8-inch plastic main. We also have roughly $2 million in projects tied to the Virginia Department of Transportation. What these amount to is this: over the last five years especially, our general assembly has restored funding, so to speak, for road infrastructure projects that are important and necessary; a fairly major bridge replacement is taking place, along with other road maintenance that obliges us to relocate gas mains that already exist. We prefer to seize those chances to make the mains either bigger for added capacity or, in fact, safer. The bridge main is one illustration. Rather than hanging on the bridge as it does at present, we're going to place that main underground. Once again, those are solid projects. That benefits the community when it comes to getting around, and it also helps us make the system safer and more dependable. Tommy, walk us through some specifics of the rate case we filed recently.

Tommy Oliver

executive
#4

Okay, thanks Paul. Good morning, everyone; we're looking at slide 10. During last quarter's earnings call, we noted that the company filed for a rate increase with the Virginia Commission back in December of 2022, and those rates went into effect on an interim basis as of January 1, 2023. We sought an increase in non-gas base rates of roughly $8.55 million, and about $4.5 million of that is being recovered through the SAVE rider. Because we're now collecting costs tied to our SAVE plan via interim rates, we did terminate the SAVE rider as of January one. As Paul said, we keep spending on renewals, and those costs will be recovered through our base rates. Later this year, we'll file for approval of a new SAVE plan so rates can take effect October one. This non-gas base rate increase means the typical residential customer's monthly bill will go up by $5.78. Since early winter, natural gas commodity prices have been falling and are currently under $2.50 per dekatherm for the prompt month. We began factoring in these lower gas costs in our gas rates on January 1st and then again February first. Thanks to these changes, or these adjustments, customers are now seeing an overall decrease in their bills of roughly 19%. With the roll-in of our SAVE year capital spend of about $22 million, our total net rate base coming out of the rate case will be around $190 million. Paul will now go over our earnings outlook for the rest of the fiscal year.

Paul Nester

executive
#5

Thanks, Tommy. Only to repeat, our most recent request for a non-gas base rate hike went in during October 2018, and the Commission issued its final order on that in January 2020. That's roughly 3 years now, isn't it, Tommy?

Tommy Oliver

executive
#6

It has been.

Paul Nester

executive
#7

Starting from the most recent rate case, and we're looking at slide 11 here, our EPS guidance for fiscal 2023 remains unchanged from what we gave last quarter. Once more, to remind everyone, fiscal 2022, like Jason said before, reflects adjustment for that non-cash impairment loss taken at the midstream subsidiary. Looking at 2023, we expect a loss of $0.20 per share at the midstream subsidiary, largely driven by interest costs, which have climbed substantially because of the higher interest rate environment all of us are currently in, plus the absence of offsetting operating income from the Mountain Valley Pipeline. As a quick update, the MVP joint venture right now is cooperating with the relevant agencies to get the necessary permits reissued, so that construction can ideally restart very soon. Roanoke Gas, as our update probably makes clear, is positioned to deliver yet another strong year, though naturally this depends on how the rate case turns out along with other broader economic conditions. We want to point out that the dilution impact stemming from the March 2022 equity offering comes to roughly $0.07 per share. We'd like to wrap up with something that truly ranks among the great stories in this company's history, and it will likely become even greater as we keep progressing toward final project completion and placing it in service. Tommy, bring us up to date on what's going on with our renewable natural gas facility project.

Tommy Oliver

executive
#8

Okay, Paul. If you go to slide 12, the RNG initiative is something we've discussed for a while, and at last it has become a reality. In January of this year, we obtained Commission sign-off for the project, along with authorization to recover costs via a separate rider. Right now we're pursuing administrative approval of the project's rates and tariff, and we anticipate having all elements ready so that billing can begin on March first. The rates are going to be set up so they recover expenses tied to running and upkeep of the facility, plus a return on the $7.7 million that was invested. Building work has moved forward mostly within schedule and within budget, and we anticipate the project entering service in March as well. Across the company, this effort has occupied us for roughly two years, and the result makes us quite happy, and I think a line from the Commission's order captures the project nicely. As the Commission wrote in that order, "Roanoke Gas's project has the potential to achieve a rare combination of increasing local fuel supply, reducing greenhouse gas emissions, and increasing the utility's profit, while also lowering customers' rates." Now I'll hand things back to Paul.

Paul Nester

executive
#9

Thanks, Tommy. Tommy, his group, and the rest of the folks across the company who backed the filing with the Virginia State Corporation Commission truly deserve the credit for this. This marks, in fact, the first approval of its kind for a project in Virginia granted to a gas utility, and while we haven't run the exhaustive research, it may also be a first for the East Coast of the United States. We're extremely proud to have that order, and of what it means for our company and the community. Western Virginia Water Authority, our partner on this project, has performed wonderfully, and we're delighted to have them alongside us, and we can't wait to turn the switch on, Tommy, in roughly 45 to 60 days. That wraps up our prepared remarks. Should you have questions, please dial pound pound or hashtag hashtag to unmute your line. Pound pound to unmute your line.

Mike Gaugler

analyst
#10

Good morning, all.

Paul Nester

executive
#11

Mike, hello there. How are things with you this morning?

Mike Gaugler

analyst
#12

Warmer than it should be for this time of year. I'll accept that.

Paul Nester

executive
#13

Honestly, today in Southwest Virginia it resembles North Florida more than anything. Things have been quite mild around here. As a matter of fact, we're in the process of closing out the January books right now, and January came in at roughly — wouldn't you say, Jason? — 240 heating degree days above the typical level, making it among the hottest Januarys ever recorded. That pattern has carried on into February. Mike, days like these aren't favorable for gas, though they are favorable for building; we do our best to find the upside in whatever the weather brings.

Mike Gaugler

analyst
#14

Alright, so honestly there was just a single item I wanted to ask about, and it concerned the RNG facility, which you devoted quite a bit of time to. I'm curious, once that one is finished — and it's roughly 2 weeks off — do you have any other things within your geographic footprint that you're considering pursuing, when it comes to renewable projects broadly? Not only RNG, but whatever else you might be seeing.

Tommy Oliver

executive
#15

Mike, a few organizations have reached out to us, and they're exploring RNG projects around here. A number of them simply want to put gas into our system. We're in discussions with those folks. Others would like us to build pipelines so they can be interconnected, and we're assessing all of it and will reach a conclusion grounded in the economics at the point when that decision has to be made.

Mike Gaugler

analyst
#16

Alright. Given that you're located in a very mountainous area, at least in certain sections, is there any advantage solar could offer you? Does that seem practical?

Paul Nester

executive
#17

Yes. Over roughly the past 2 years, Mike, there's been some activity — mainly from the large electric companies — toward placing solar installations in this area. Should you locate a suitable plot of land that faces south, as you mentioned, it likely could be viable. You're correct that in our region, because of the mountainous landscape, such plots of land are rather scarce. Since installing the solar setup on our headquarters building back in 2021, we haven't devoted much effort to investigating solar. Regarding Tommy's excellent point from earlier, with this RNG project now wrapping up, we'll have both the time and the chance to look into some of those other possibilities.

Mike Gaugler

analyst
#18

Alright. That's about everything I had. Here's hoping it gets colder for you.

Paul Nester

executive
#19

Thanks. We'd be happy to see a bit more cold before winter officially ends. I'd just tack on one more thing regarding your solar question. There's press on this — this isn't necessarily my own view. As we've observed with the Mountain Valley and other infrastructure projects, the solar projects proposed in this area by our electric provider are running into tough opposition when it comes to permitting and siting. Getting them permitted and sited is nearly impossible. You know, going back to the permitting reform that was bubbling up in the United States Congress in the fall of 2022, that need still exists. It applies not only to Mountain Valley Pipeline and other natural gas infrastructure, but to renewable infrastructure as well.

Mike Gaugler

analyst
#20

Honestly, I'm hoping for the best for you with Mountain Valley; seeing them actually return to work out there would be fantastic.

Paul Nester

executive
#21

Yes, that's what we want as well. Being in a position to finish this project on a timely basis is, without a doubt, something that matters most — I believe — for this area, for our nation overall, and getting that right of way put back in place is likewise the most environmentally sound approach; we are doing all we can to advocate for it and assist in moving it forward.

Mike Gaugler

analyst
#22

Alright. Make the most of the rest of your day.

Paul Nester

executive
#23

Thanks, Mike. We appreciate your joining us today. Are there any further questions out there? To unmute your line, just dial pound pound or hashtag hashtag — either works. Well, it appears there are no additional questions at this point. Once more, we want to express our gratitude for your participation. We sincerely hope every one of you enjoys a safe and pleasant weekend. That wraps up our first quarter earnings call. We very much look forward to connecting with you again in May, when we'll talk through our second quarter results. Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete RGC Resources, Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to RGC Resources, Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in RGC Resources, Inc. or any ticker on your watchlist.