Rumo S.A. (RAIL3) Earnings Call Transcript & Summary
October 5, 2021
Earnings Call Speaker Segments
Operator
operatorGood afternoon, everyone, and thank you for waiting. Welcome to Rumo conference call to discuss the Lucas do Rio Verde and Cuiabá extension project. Today with us, we have Mr. Beto Abreu, Rumo's CEO; Mr. Ricardo Lewin, CFO and IRO; and Mr. Gustavo Rosa, Investor Relations and Treasury Director. [Operator Instructions] We also would like to inform that the conference call will be presented in English by the company's management, and there will be simultaneous translation to Portuguese. This event is also being broadcast simultaneously on the Internet via webcast. Before proceeding, we would like to mention that forward-looking statements are based on beliefs and assumptions of Rumo's management and all information currently available to the company. They involve risks, uncertainties because they relate to future events and therefore depends on circumstances that may or may not occur. Investors and analysts should understand that conditions related to macroeconomic conditions, industry and other factors could also cause results to differ materially from those expressed in such forward-looking statements. I will now turn the conference over to Mr. Ricardo Lewin. Please, Mr. Lewin, you may proceed.
Ricardo Lewin
executiveGood afternoon, everyone. In this presentation, we will be giving further details on the Lucas do Rio Verde project, which is going to be the most important driver for our future growth. We will be covering regulatory and environmental framework, project phasing, and volume and market rationale. On the next chart, I will start with the regulatory side. Over the past few years, we accomplished important milestones in our regulatory agenda. In 2019, we won the first railway auction in Brazil after a long period without new railways. In 2020, we early renewed Malha Paulista until 2058 by committing to double its capacity over the next 10 years. On September 20, we have signed with Mato Grosso state the authorization agreement, allowing us to build extensions to Cuiabá and Lucas do Rio Verde. For some years, we worked intensively to retain regulatory approval from both the federal government and the Mato Grosso state government. In October 2020, state government approved an amendment in its local constitution, allowing regional authorization for railways. After this approval, the process for the authorization of a local railway evolved quickly due to the great interest of the state in having more railways, who -- which had already been studying a potential extension project from Rondonópolis to Lucas do Rio Verde. We're the only company to present a project for the railway request by a public call by the government of Mato Grosso. This is a concrete project in addition to being regulatorily safe since along the process, Mato Grosso governor and senators signed a cooperation agreement with the federal government in order to make sure that all the parties would be working together to put this extension in place as fast as possible and enable the connection between the regional railway with the federal network. On the next chart, I will share a few features of this new regulatory model. The state authorization regulation is a new regulatory model that brings a lot of advantage when compared with traditional concession model. In this new regulatory framework, the assets are 100% private and will never return to the government. That feature gives us more agility to manage the authorization assets without stringent regulations that usually a concession requires. When it comes to the duration, we are also better off. We are authorized to operate for 45 years, and we can get multiple renewals of 45 years each, which brings almost a perpetual duration. On the economic side, there will be neither concession fee nor any kind of cap for returns, which once again will give Rumo more flexibility to manage the business in the most efficient way. Last but not least, we can also apply for SUDAM tax exemption, which could give us a 75% discount over income taxes in this new entity. On the next chart, I will share why we prefer this regulatory model over other possibilities. Several possibilities of authorization to make new railway projects feasible were or are being studied, all of them with great autonomy for the railway operator. However, the only regulatory option that can be used immediately for our extension project is the authorization from the state of Mato Grosso. The estimated timing for signing an authorization contract in other alternatives is much longer. This made the decision clear for Rumo. On the next chart, we will talk about the environmental side. In order to initiate investments, we will still need to accomplish through the environmental process. We started this project back in August 2019, and we are advancing in full compliance with all regulations. Moreover, we expect the entire licensing process to take more than 3 years from August 2019, highlighting how serious and diligent the process is and connecting well with our ESG agenda. This extension will allow us to replace trucks that today are used to bring the cargo from other areas in Mato Grosso to Rondonópolis, therefore generating significant CO2 avoidance and increasing the safety in the roads by reducing the number of trucks and accidents. We expect more than 50,000 job opportunities per year to be created by our project, bringing further development to the state of Mato Grosso. On the next chart, I will share with you how we came up with our railway course. In the early stage of this project, we have studied more than 2,500 railway courses, and we have considered more than 35 variables before getting into the final project course. By doing this, we avoided proximity with urban, indigenous and environmental areas, also making sure that the course would not go through any challenging landscape. With that, we are 100% sure that we will be optimizing our investments, reducing future operation costs and also advancing more easily with the environmental process. On the next chart, we will talk about the project phasing. We already disclosed that we are about to invest around BRL 10 billion in this project. We are still working on ways to optimize our CapEx. So this number could be reviewed as we advance with our analysis. Investments could initiate up to 180 days after we have obtained the environmental licenses. Potentially, the project could take up to 2030 to be finalized, meaning that the investment cycle will take almost 8 years. But each of the expected milestones of the project, Rumo will have a 24-month tolerance without justification. We are planning to connect with the first terminal in 2025, and this connection should already enable us to serve roughly 50% of all the volume expected for new terminals, considering both additional and volumes that will be shifting from Rondonópolis. So from this point onward, the extension might be already generating cash flow and afford the remaining investments until the completion of the project. After the connection with Nova Mutum terminal, the volumes captured will be roughly 80% of the total. Therefore, the project will be already generating some positive cash flows. On the next chart, we will see the volume buildup per terminal. In 2025, with the first terminal becoming operational, we expect roughly 50% of the volume to be at the first terminal. As we get to Nova Mutum, the first terminal should stand for 36% of the volumes and Nova Mutum for 27%. By 2030, with the project completed, we will have 14% in the first terminal, 25% in Nova Mutum and 29% at Lucas do Rio Verde. We estimate that over time, 16 million tons could be shifting from Rondonópolis to other terminals, generating additional revenue based on higher distance and competitiveness, consequence of the extended railway. On the next chart, we will be talking about the opportunities for additional volumes. To better understand the breakthrough in the competitiveness caused by the extension, we have to analyze that today, only 20% of all the exports of Mato Grosso are within a range of 200 kilometers from Rondonópolis. That means that to get a high market share, we have to go deeper in the state, lowering our tariffs to be competitive enough to attract additional volumes. After the extension and by having new terminals, we could reach roughly 64% of all the demand in the Mato Grosso within a range of 200 kilometers. This will not only allow us to increase our market share but will boost our prices because we don't need to go further in the state to get this additional volume. So we expect that potentially, we could capture 18 million tons of additional cargo with a market share of approximately 60%. On the next chart, we will talk about the changes in the competitiveness brought by the extension. As of today, we have a lower competitiveness in West, North and East areas of Mato Grosso. When we take a look in our competitiveness in Lucas do Rio Verde, for instance, the solution in the North, that includes trucks plus waterways, costs approximately BRL 273 per ton. On the other hand, whilst cargo is collected in Lucas and delivered in Rondonópolis, trucks are charging approximately BRL 102 per ton, which implies that in order to break even, Rumo could only charge BRL 171 per ton. When we look to 2030, when the extension will be fully completed, the solution through BR-163 plus waterways is going to be more expensive due to the poor roads, serving around BRL 293 per ton. Given the fact that we are going to have a terminal in Lucas, we are going to need trucks just to collect the grains in farms nearby and to deliver in our terminal in Lucas, which make the truck freight much lower than before, around BRL 20 per ton, allowing us to charge more than BRL 100 per ton to break even with the competitor solution. On the next chart, we are going to talk a bit more about the Cuiabá market potential. The connection with Cuiabá will bring some volume opportunities. The first one is to shift container volumes that we currently serve in Rondonópolis to Cuiabá, replacing costs with trucks with additional railway revenues. The second opportunity is related to additional opportunities that could be created by the arrival of the trucks in the region. Clearly, the return with this part of the extension is neither as high nor as quick as the ones we could get in Lucas do Rio Verde and Nova Mutum. On the other hand, given the lower network density, the CapEx per kilometer is going to be lower in this stretch. On the next chart, we are going to be talking about the levels of additional margins that we expect in this extension. In 2019, our margins in the North operation were 61.6%. Since then, we have been and we will continue to implement several initiatives to boost railway efficiency, reducing the cost per RTK. On the other hand, given the entrance of Central Network and the higher capacity in Malha Paulista, combined with the additional competitiveness brought by the extension, we could generate higher volumes, allowing further cost dilution alongside with additional revenues. That being said, even with potentially lower cost to producers, we expect additional EBITDA margins to be way higher than they were in 2019. Here, I finish the presentation, and together Beto Abreu and Gustavo Marder, I will be available for the Q&A. Thank you.
Operator
operator[Operator Instructions] Our first question comes from Pedro Bruno with XP Investimentos.
Pedro Bruno
analystFirst of all, congratulations on signing the authorization. We acknowledge here from our side, from the analysis side, how challenging it is to go through all of the steps to sign such a structural project. So congratulations on that. I have 2 questions. I'll go with the first one here regarding potential regulatory risks involved in the signature in the sense that how we could, let's say, help investors understand if there is any legal or regulatory risk having the authorization being done with the state rather than with the federal government. And so maybe if you can go through the process of how was the process of approval by the state and how much support you see from the federal government in this whole process. I guess it would be helpful for us to understand and gauge any potential regulatory risks that you foresee on that front. That's it from our side.
João Alberto de Abreu
executiveThank you, Bruno. This is Beto Abreu. Let me get one -- let me get the question. It's -- I think it's a very important one, by the way. And let me cover first the whole process, which started more than a year ago. And we have to take into account that firstly, what the state of Mato Grosso did was change their constitution. So they have done this exactly a year ago. After that, they complement the law of this change and then regulated. So they covered the whole process of changing the law, complementing and also regulating. And I cannot see any process more stronger than that when you look for a legal framework. So that's the first thing. But even though -- the state of Mato Grosso has also decided to build with the federal government an agreement to have all the support from the -- mainly from the infrastructure minister regarding the project. So that's why they signed it, as we mentioned in the presentation, that cooperation agreement that was signed between federal and state government exactly to support and to make sure that we were -- everyone on the state level and the federal level in the same table and the same direction. So what we will see, for sure, is something, I would say, similar to what we have already in the highways, where we have federal highways, also state highways working together in different geographies. So that's the process, in our view, very strong and with the support with both levels, the state and also the federal government. Thank you for the question, Bruno.
Operator
operatorOur next question comes from Josh Milberg with Morgan Stanley.
Joshua Milberg
analystI also wanted to congratulate you guys on this huge milestone. You guys have moved remarkably quickly with this whole project. I was skeptical. But you also, in your presentation, highlighted very clearly the incremental grain volume this extension will allow you to access and how it will expand your area of influence. And I just wanted to ask if you could talk about the whole issue of this equal concession and the potential authorization of an extension from Água Boa to Lucas. It does seem like -- and that -- the whole topic of authorizations has gotten a lot of press, I mean, in the last couple of weeks. And it just seems like that particular authorization could very much shape up the competitive landscape in the heart of Mato Grosso. And so I just wanted to hear if you're eventually as skeptical about that going forward as you were with [ the stable ground ] in the past. And if that authorization, that extension were to happen, if you think that there will be sufficient volume for both extensions.
João Alberto de Abreu
executiveYes. No. Thank you very much for the question. Let me pull this extension, this project, Água Boa to Lucas, which is the one that you mentioned. Let me call it FICO #2, okay? Because at the end of the day, it's the extension of also the other project, which is FICO #1. And I -- we have to agree firstly that this FICO #2 cannot, let's say, be a stand-alone project. We have to analyze it together. And of course, it's in our screen and we are looking to the process, but the first question for us -- and this is what we are analyzing, it's about the FICO 1 instead of phasing, timing, when will be -- when the building will start, how long it will take, when will be the action of this process because the FICO 1 is really the key one here before analyzing the FICO 2 because they are, at the end of the day, connected if they are implemented. So that's the first thing to take into account. And now -- and don't forget that we can also request the authorization of the FICO 2. It's -- what we are doing now, it's really waiting to see the regulation process moving forward. We have the provisional measure, which was issued a couple of weeks ago. We have the PLS 261, which is also under discussion in the Congress. So what we want to understand is how these both projects will converge and see how it's going to work, how it be -- how will it be regulated, and then analyze this as a project, let's say, after understanding all the rules. That's the first thing. But let's consider a scenario that we really have that project in the future despite the time that can take to be built. And what I like to say to you is that impact in our business in terms of volume is very, very low. I would say we wouldn't consider because we're going to be closer. We're going to be faster because it's 500 kilometers less distance from Santos, for instance, and we're going to be cheaper. So I am considering the scenario of arriving because again, we stopped the project 3, 4 years ago already. So next step is really having the environmental assets to start building. And this is what we are considering for that project. It's really understanding how it's going to work together because if we have the FICO 2, we're going to have rail that will cross the FICO 1. We don't know who is going to want the FICO 1. And then that is going to arrive in our rail, which is the Central Network. And there's 2 alternatives, going to the north or going to the south. So we see -- we really don't see any impact in terms of competition in our project for that. And we -- of course, we have this scenario also in our business case. But thank you very much for the question, very important one.
Joshua Milberg
analystOkay. And if you don't mind, let me just -- while on the topic of alternative authorization, if you wouldn't mind just touching on some of the other authorizations that have been announced in the market, if there are any other projects that are on your radar.
João Alberto de Abreu
executiveYes. Firstly, let me say that I think there's a very important improvement on the regulatory side going on in Brazil. So having the opportunity to have legislation, a new legal framework that can bring agility to implement projects like short lines, I think it's a very good news for the sector. So that's the first thing. But regarding the -- all the projects, again, our position at this time is really understand the process, wait to see how the regulation will be set up because it's still a lot to go on those projects under discussion in the Congress. So it's really -- and we have the experience on the state. We know that takes time. So it's really trying to understand exactly how it's going to be, the rules. But when you see at -- for instance, the PLS 261 presented to the Senate last week in Brasilia, we see as a very good project for the sector. But again, we just want to see those projects being regulated to position ourselves in terms of new request for authorization. But short lines in areas like -- I can give you an example on Três Lagoas, which is the pulp and paper, let's say, industry segment. It's a good idea to have a short line to connect those plants to our North line. So those kind of things are the kind of opportunity that those authorization can bring for us, okay?
Operator
operatorOur next question comes from Lucas Barbosa with Santander.
Lucas Barbosa
analystCongratulations on the project. I have quick 2 questions. The first one is regarding the terminals. Can you give some color on the estimated capacity for each of the 3 terminals on the stretch up to Lucas do Rio Verde? In addition, is Rumo contemplating delivering the Nova Mutum and the Lucas do Rio Verde terminals before the announced schedule? That's my first question, then I'll move to the second one afterwards.
João Alberto de Abreu
executiveThank you, Lucas. Firstly, we still -- we are still analyzing the first terminal, where exactly it's going to be. We can have 1, even 2. We are also -- we have many opportunities here to bring partners, so a lot of local players try to -- asking to be part of this. So we had a very good, let's say, experience with Caramuru in São Simão, as you know, in Goiás with a partner that can share investment and bring volume, bring value to the business. So that might be a kind of a business model for those terminals in Mato Grosso, who are really having partnerships on those. So the first terminal, we're still analyzing exactly where it will be. The capacity should be around 7 million, 8 million tons. And for Nova Mutum, we should have a bigger terminal. That will really be the heart, the biggest one. That one should be very, I would say, close to 50 million tons, will depend on the moment that we arrive. And then Lucas do Rio Verde, I'm sure that we will only decide the size of the Lucas do Rio Verde terminal after arriving, operating in Nova Mutum. We're not going to do this before because the market will be completely different at that time. Remember that by 2027, 2028, the size of the market in Mato Grosso should be around 70% bigger than it is today, so in terms of production. So we are producing something like 75 million. We're expecting by 2030 something like 120 million tons. So this is how we are planning. And there's, yes, a possibility to start operating a terminal before arriving with the rail. This is also being considered here in the plan.
Lucas Barbosa
analystPerfect. That's all very clear. If I can ask a second one regarding the SUDAM tax benefit. Can you give some details on the steps to obtain the tax incentives? For how many years is the incentive applicable? And is there any risk of not obtaining the tax incentive?
João Alberto de Abreu
executiveYes. Let me hand over to Lewin. Thank you.
Ricardo Lewin
executiveWell, SUDAM, we still do not have many details on that. What I can say is that we started conversations with SUDAM, very initial conversations obviously because before, we needed to have the project approved. So we are in initial phase of conversation. The benefit will be very similar to what we have today in Rondonópolis. That means that we would have a 75% discount on taxes. However, the term depends on the investment that's done. So we still do not have the details to provide to the market, but I can tell you that as soon as we have, we will share it with you, okay? And the probability of having -- like we are in initial conversations. So we are very positive regarding that. It's a project that has a good characteristic for SUDAM development of the area. So we are very positive in getting it.
Operator
operatorOur next question comes from Rogério Araújo with UBS.
Rogério Araújo
analystCongratulations on this development. So I have a few, actually very specific questions about the presentation, actually some doubts on what was presented. First, in terms of incremental volume, there is a slide with the expected projected volume for each year. I assume this is in ton and not RTK. Is that correct? That's the first one.
Gustavo da Rosa
executiveYes. Rogério, this is Gustavo. You're right. We present the data in tons, not in RTK.
Rogério Araújo
analystSo the second one, in terms of incremental volume of 18 million tons, can you try to break down from where these 18 million tons should come from? So maybe, I don't know, 100% from Lucas do Rio Verde, or if you could split between Terminal 1 and Nova Mutum and Lucas?
Gustavo da Rosa
executiveYes. Rogério, actually, we presented a slide. Let me check exactly the number. I think in Slide #9, that shows over time how the volume is going to be shifting from one terminal to the other. We put that, the percentage, not the real volumes. But for instance, if you look for 2025, you're going to see 51% of the volumes already in the first terminal. Meanwhile, we are going to have 49% in the volumes -- of the remaining volumes in Rondonópolis. So that means then whenever the first terminal is in place, we could reach almost the same volumes that will remain in Rondonópolis. So the mix will be roughly 50-50. What we are not answering yet, and it's because it's connected with our price strategy, is how much of this additional -- these volumes that will go for the first terminal, how much are going to be incremental volumes and how much are going to be volumes that are simply shifting from Rondonópolis to a terminal that's a bit far away, and therefore, we could have additional revenues. So the decision to set up a pricing strategy to maximize the net revenues and the cash flow generation, it's going to be made close to the initiation of this operation. So it's going to be an optimization process. And we are going to try to set tariffs in a way that could allow us to get higher returns. And therefore, the more additional volumes we could get, we are -- we could be better off. So we are not committing with these numbers right now because of that. It's going to be an optimization. And we are trying to make sure that we could maximize the revenues and the cash flow generation already in the first years of operation. So pricing will respond how much of the volume is going to be real incremental volume and how much is going to be only volumes that we were serving before in Rondonópolis, and now we are going to be shifting up through all the terminals.
Rogério Araújo
analystOkay. Thank you, Gustavo. And I'm assuming that in 2030, this breakdown includes both the current Rondonópolis volume that part of which would be shifted and also the incremental volume, correct?
Gustavo da Rosa
executiveYes. You're right. Yes.
Rogério Araújo
analystOkay. Great. And last one, it's actually related to Cuiabá rail line. I see that you put some subsectors here that you could get some volumes from. But any estimate on, in terms of million tons, how much volume could Rumo bring from this Cuiabá line?
Gustavo da Rosa
executiveRogério, as we presented in the presentation, first of all, the CapEx to do this extension is not huge. The density of the railway, it's not expected in the short term to be a huge density. So therefore, CapEx per kilometer is going to be lower, for instance, than what we are going to spend in the extension to Lucas do Rio Verde. We already have some volumes that today we serve in Rondonópolis, especially in our container business. That -- and we presented that data in the presentation. We believe that those volumes are going to be shifting to Cuiabá and therefore capturing additional revenues through higher tariffs in this process. Another thing that is kind of hard to guess right now is what could be the additional development to the region of Cuiabá that a new railway could provide. So that is expected to generate some volume but not necessarily at once or in the first year that we connect with the terminal there. So we expect those volumes to be increasing smoothly over time. And so as of now, it is hard and we wouldn't like to give any particular guidance because there is a higher degree of uncertainty with regards to that. It's not as clear as Lucas when -- where most part of the volume is already there. So it's just a method of connecting with the railways and then we could capture the volumes. In Cuiabá, we are also accounting with some market development, which is very hard to get it right over time. So the uncertainty here is a bit higher, but we believe that we could at least break even in this project. We don't believe it's going to be a negative return. But how much time it's going to take to pay off, then it's hard to really answer that question.
Rogério Araújo
analystOkay. Sounds great. And do you have any rough range of the kilometers between Rondonópolis and the first terminal, then first terminal and Nova Mutum, and last terminal, Nova Mutum to Lucas do Rio Verde, more or less according to the [ traçar ], the line that you've done?
Gustavo da Rosa
executiveYes. And Rogério, as we presented in the slide, I think it's #8, we are considering roughly to have a terminal every 200 kilometers at least. So that could change a bit, as Beto already mentioned, but we could have the first terminal 200 kilometers away from Rondonópolis. Then the second one, Nova Mutum, should be roughly 400 kilometers away from Rondonópolis. And then the end of the line, Lucas, is going to be roughly 600 kilometers. So as of now, I would say that every 200 kilometers at least, we could have a terminal. So that's how we plan to address the buildup of the volume and also our attempt to make the volumes arrive earlier than otherwise.
Rogério Araújo
analystVery clear. Thanks so much, Gustavo. Congratulations again.
Gustavo da Rosa
executiveThank you.
Operator
operatorOur next question comes from Victor Mizusaki with Bradesco BBI.
Victor Mizusaki
analystCongrats for this achievement. I have a couple of questions here as well. So the first one, why don't we take a look on Slide #8 and then your comment about project completion by like 2024 to 2025. We are talking about the company deploying like BRL 3 billion to BRL 4 billion of CapEx, right? And the project will become operational only by 2025. So I don't know if you can comp a little bit how to expect to finance this project. So if -- I mean and how we should think about the financial leverage going forward. And the second question, you also mentioned this slide about land expropriation costs. So if -- do you expect any kind of support from the state of Mato Grosso or from the federal government to implement this project?
Ricardo Lewin
executiveVictor, this is Lewin. Thank you for the question. I'll give a very complete answer in terms of everything that we think about financing, okay? So the beginning of the investment will be only in 2023, okay? So there is only a small piece in 2022 that's the executive project. So this is irrelevant, okay? So from 2023, the first 2 years, okay, to the beginning of 2025, we will not have the first terminal ready. So this will be a moment that we are spending without additional revenue from this project. So we will have -- you will see our leverage increasing a bit in these first 2 years, okay? And after that, you will see that the project will start to have its own revenues, okay? So from 2025, more or less, on -- our leverage will go down with the revenues of this project, okay? And why? Because we will be using the cash that will come from these revenues, okay? If -- so if we think about where the funding will come from, it will be something similar to what we have done in past years, Victor. It's we will be looking for diversity of pockets, okay? I always say that this is important. It generates competition between the pockets, what's important for us in terms of quality of the financing that's given for us. So we've already started to talk for example, with BNDES. We already started to talk to regional funds. So if you ask, we'll need to have any help from federal and local government maybe through these local funds. But this -- and these funds, they support projects that bring development for certain areas. We are also talking to commercial banks to see what structures they have. And we -- obviously, we count on the capital market. We have plenty of access to local market through debentures, infrastructure debentures. We have support of foreign market with bonds. And obviously, we can also talk to the external development banks. We can raise suppliers' credit. So this will come from financing and from -- we are looking for a diverse -- a huge diversity of pockets so we can always get what's better for Rumo in terms of term and in terms of price. Hope I answered your question, Victor.
Victor Mizusaki
analystLewin, so basically, I mean what -- you're saying that there's no need to raise equity, right?
Ricardo Lewin
executiveNo. We will be doing this through financing. And just to have an idea -- and again, this is -- you have your model. We have our model here. Just to have an idea, in our model, the peak of leverage will reach some -- will increase something between 0.4 or 0.6x to our baseline in the second or third year, okay? So that's not too much for a company like Rumo, taking into consideration what I always said since I became CFO that in the group, you have the policy to be -- to have a leverage around 2x. But you can go beyond that if you have a plan of deleveraging. And as I told you, after the third year, once we -- the term that we have started to work, this project will start to generate cash and then we start to deleverage the company.
Operator
operatorOur next question comes from Bruno Amorim...
Ricardo Lewin
executiveSorry. Victor, do you have any additional questions?
Victor Mizusaki
analystYes, about the land expropriation. So if -- I mean to...
Ricardo Lewin
executiveSorry, about what Victor?
Victor Mizusaki
analystMake it easier -- the land expropriation also.
Gustavo da Rosa
executiveI could take that one, Victor. This is Gustavo, Victor. Like a project -- in a huge project like this, of course, the current regulation already help us in the process of land expropriation. So we have a lot securing us because the project is -- has public interest, helping us and supporting us in this process of negotiation with the landowners. As Ricardo highlighted in the presentation, we choose very carefully our course. So we are not dealing with huge issues here. We are not going around big cities, any protected areas, environmental areas. So expropriation cost should be something easier. And we count with the support of the current law, which qualifies this project as a public -- by having a public interest. Therefore, it comes with the support of the regulation.
Operator
operatorOur next question comes from Bruno Amorim with Goldman Sachs.
Bruno Amorim
analystI have 3 questions, 2 on CapEx and 1 is just like a clarification. So the first one is how to reconcile this CapEx spend for Lucas do Rio Verde with your original long-term guidance for CapEx for Rumo. Is there something from Lucas do Rio Verde included there? Or is it really on top? Or do you consider postponing any of those projects which were initially included in the long-term CapEx plan because of this new opportunity? The second question is, what about the investments in the North and Paulista Network to support the growth in volumes coming from Lucas do Rio Verde? How much is needed if it's somehow included in that initial long-term guidance as well? And finally, just one clarification on Slide 10. And correct me if I'm wrong, please. But I understood from Slide 10 that in your view, if -- in a scenario without extension, the company would lose market share between 2025 and 2030. And so I just wanted to clarify that point. And if this is the case, is it because the northern region of Mato Grosso tends to grow more than the southern region? And if this is the case, should we expect any loss of market share from Rumo between now and 2025 before the extension starts to operate?
Gustavo da Rosa
executiveBruno, this is Gustavo. Let me try to cover the 3 questions. So first of all, our guidance until 2025 did not include any significant number or any numbers coming from this extension because by then, we weren't sure about whether or not this is going to be approved anytime soon. So right now, we are -- very likely, we're going to have to work to measure those 2 guidances that we have. So we have a specific guidance for Lucas do Rio Verde that we just shared with you guys. And we have our current guidance until 2025, which does not consider the extension to Lucas do Rio Verde. Of course, we'll have to think about leverage, as Ricardo highlighted, also the capability of our suppliers to deliver us, for instance, all the raw materials that we need to put both plans in place. So this is something that we are going to be accessing and maybe -- who knows, maybe next year, beginning of next year, we could be able to be measuring those 2 guidances. So we are planning to do that, but that's not the case right now. We still have to look to the impact of the extension figures that we just gave. And we have to remember as well that we have some triggers in this extension process, so when we are going to be obtaining the environmental licensing matters in terms of scheduling. So for instance, if we accomplished a bit earlier, it could change a bit the deployment of CapEx. The same works otherwise. So if we accomplish a bit later, we're going to have to adjust that to our timetable. So I think that's the first part of the question. Regarding the second question, investments in North and Paulista to support the project, I think here, we have no surprises. When we renewed -- when we early renewed Malha Paulista, we have committed to invest roughly BRL 6.1 billion to more than double the capacity of Malha Paulista. So from that moment onwards, the concern of the company was not anymore about the capacity in the long run but rather how could we fill up that capacity that is going to be available over time. So we could do that through pricing, so try to be more aggressive in terms of pricing to attract more demand to our network, or we could expand our footprint and which -- clearly, we choose the path of expanding the footprint. So we did the Central Network, which puts us in Goiás and Tocantins state, therefore giving us the ability to get more cargo without having to lower prices. And now we are doing the same with the extension to Lucas. So -- and already answering your third question, of course, that chart, the Chart #10, the Slide #10, it was made based on an assumption. And the assumption there was the following: As long as the market is going to be developing towards the north, if we remain only in Rondonópolis, we theoretically would have to give up on prices or reduce our prices to be more competitive and try to capture the demand more in the north. You have asked it as well about the short term. The short term, we don't think so, because -- you probably know, Bruno, but next year, we're going to have the initiation of the toll roads in BR-163. So in the short run, we have a price differential to be charged in the North Arch. So we have this -- let's say this step-up in competitiveness that could bring us the ability to grow without creating too much price pressure in the short term. But in the long run -- and I mean 5, 10 years from now, if we remain in Rondonópolis, and the market, it's already bigger in the central and in the north area of Mato Grosso, we would have to lower prices. And worse off, these lower prices doesn't mean that the producers are paying less. It's just the case that they have to pay way to -- way more to truck drivers to bring the cargo from the North region to the terminal in Rondonópolis. So indeed, we are giving away discounts without being able to lower the cost for the producers. So it's the worst kind of investments that we could be making or doing in this process. So we understand that we are much clearly better off by doing the extension, which brings us the ability to lower the cost without having to lower our prices to the producers. So that's a win-win situation. Everybody wins in this process. And then of course, our market share could be way higher because we don't need to lower tariffs to be as competitive as we are planning to be.
Bruno Amorim
analystThank you, Gustavo, for the comprehensive answer. Just to clarify one specific point, you mentioned that in the case of Paulista Network, you were already expecting to expand capacity. What about the North Network? Is there any additional investment that will be needed there or not?
Gustavo da Rosa
executiveBruno, the difference is in density. For instance, in Northern Network, we have roughly 7 trains per day, which are basically the train -- the grain train departing from Rondonópolis today. So if you think about, okay, we have to go from 7, let's say, to 10, 11 trains per day, it's not a big deal in terms of capacity especially because that network, it's very efficient. The trains are running almost at 8 kilometers per hour. We have concretized, very good tracks. So the efficiency in the network is pretty high. So if we have to do something, it would be something minor, not significant. Remember, we already extended the length of the sidings to afford the longer trains, the 120-railcar train. So we don't expect much in the north. The problem lies more in Paulista, where today, we have 25 trains per day if we count with the trains coming from other railways that access our network. So there, the density of the network is pretty high. So we have to create capacity. We have to put in significant investments in place, and that was exactly what we accomplished or what we committed back then when we early renewed the concession. So it's pretty much at the asset. I would say that the other point that we have to look also and the company is doing for a quite few time is the [ train ] capacity. So we have projects there to increase capacity, to improve the access. And we are also working to put in place more terminals there. So we announced a few times ago a potential partnership with [ DP World ]. We did a very important improvement in the access to the Port of Santos this year. We have other investments, other terminals like Terminal 39 and other terminals already seeking for their renewal, investing quite a lot there. So Santos and Paulista are the key to make sure that we are going to be accessing all the capacity that we need for the Lucas extension. And as we have already been talking to the market for a while, the company is doing all we can to make sure that those points won't -- will not be a bottleneck for us in the future.
Operator
operatorOur next question comes from Victor Mizusaki with Bradesco BBI.
Victor Mizusaki
analystJust a last one here. Lucas do Rio Verde contract has a clause of contract renewal every 45 years. Can you comment how does this work? I mean this specific contract, is there any kind of a requirement like extended rate of capacity? So I don't know if you can comment about this.
João Alberto de Abreu
executiveVictor, thank you very -- Marder, I can take this. Victor, no, it's a 45-year contract, can be renewed for another 45 years. And so it's almost, let's say, infinite contracts. So you can keep renewing the contract for 45 years. So there's no capacity or, let's say, volume to be reached as a premise to renew, okay? What we have is flexibility in terms of timing so we can change the implementation of the project for 2 years with no notice, but we can also change even more if we agree with the local government due to any specific thing that we find during the implementation. So it's -- as we can see, it's -- in terms of obligation, it's completely different from the one that we have on the concession. So that's the kind of -- that's the beauty of the authorization when we compare with the concession. So in that specific case, 45 years again renewal for equal periods successfully. There's no concession fee. It's less, let's say, stringent in terms of obligation. So it's really kind of -- the concept here is almost to be a private, let's say, asset. I think this is the concept behind here. And let me take the opportunity to close the call. So firstly, I'd like to thank all of you for the question, for the participation, for the comments. I have to say that we are also very happy with what's going on with the moment that we are living. We agree that with most of you, that is a remarkable moment for Rumo. We know that this project will transform our business. We'll also transform the logistic in terms of infrastructure not only in Mato Grosso but also in Brazil. And if we look backward in the last 3 years, so in 2019, we renewed -- we won the auction of Central Network. And then in 2020, we renewed the Paulista Network. And now 2021, we have this first private railway authorization under the Brazilian, let's say, democratic regime. Let's put it this way. So it was 3 very important steps for Rumo in the last 3 years. We're not going to come with something else next year, 2022. So we understand that we have now our portfolio to implement in the next 10 years, what we think is important to do to extract value from what we have done from those projects. So it's really a new cycle that is beginning for our company. So again, thank you for the moment. Thank you for the support. Thank you for the participation, and I hope all of you have a very good week. Bye-bye.
Operator
operatorThank you. This concludes Rumo's conference call. Thank you very much for your participation. You may disconnect, and have a good day.
This call discussed
For developers and AI pipelines
Programmatic access to Rumo S.A. earnings transcripts and 32,000+ others is available through the
EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.