This is the RWE conference call. Markus Krebber, who serves as CEO of RWE AG, along with Michael Muller, CFO of RWE AG, will brief you on how fiscal year 2024 unfolded. At this point, Thomas Denny will take over. Over to you.

Thomas Denny

executive
#2

Thank you, and good afternoon, ladies and gentlemen. I appreciate your joining the RWE Conference Call on Full Year 2024. Markus Krebber, our CEO, along with Michael Muller, our CFO, will begin by walking you through our presentation, after which we'll open our Q&A session. With that, I hand over to you, Marcus.

Markus Krebber

executive
#3

Okay, thanks Thomas, and a warm welcome to all of you. Even with certain headwinds caused by a steep drop in European commodity prices early in '24, we kept the commitments we made. Our solid business portfolio has allowed us to achieve a robust operational and financial performance. We've also demonstrated that we can deleverage quickly and return capital to shareholders, through launching a €1.5 billion share buyback program in Q4 of last year. Although market fundamentals for power demand look promising and substantial investments in extra power generation capacity are required across all our core markets, we're seeing greater uncertainty in the investment climate. So we will be even more cautious when it comes to further investment commitments. We'll aim for the leverage ratio at the conservative end of our range, so as to keep a strong balance sheet during more uncertain and volatile times. We have raised our return requirements across every technology and market. And we'll apply stricter investment criteria, particularly in the US. As a result, we have considerably reduced our 2030 investment program. For the years '25 to 2030, we've lowered our planned investments by 25%, or €10 billion euro, relative to our Capital Markets Day 2023.

Markus Krebber

executive
#4

A key element of how we're optimizing CapEx is a strategy of actively selling down and bringing in partners for our offshore portfolio, which lightens the load of capital tied up in projects still under construction. Right now, with 12.5 gigawatts of projects under construction across every technology, our committed net cash investments total €13 billion. Those projects are going to generate attractive returns. Our planned investments for '25 are fully committed, but from '26 onward we have a lot of flexibility when it comes to allocating capital. Our financial targets are confirmed. From '25 to '27, we expect EPS to grow at a CAGR of 18%, reaching €3 per share. We also reaffirm the long-term target of €4 in adjusted earnings per share in 2030. We confirm the dividend increase for 2024 and are targeting a further rise of $0.10, to €1.2 per share, for 2025, and our existing share buyback program of €1.5 billion continues through Q2 '26. Let's take a quick look back at 2024. We turned in strong financial and operational results, thanks to how robust our integrated generation portfolio is. Adjusted EBITDA came in at €5.7 billion, above the midpoint of our guidance range. Adjusted earnings per share were €3.1, which also clearly beat the guidance midpoint. Alongside that, we've continued making headway on decarbonization.

Markus Krebber

executive
#5

During '24, our CO2 emissions fell by 13% more versus the year before. Across the past 12 months, six lignite plants totaling 2.4 gigawatt of capacity were shut down, and we've switched our Dutch facility Amer over so it runs entirely on 100% biomass. Following a detailed review in December, the Science Based Target initiative verified that RWE's climate goals for cutting emissions align with the 1.5-degree pathway. In light of recent market shifts, we've revised our capital allocation plans through 2030. First, fundamentals remain robust in Europe and the US for the power sector. Demand for power should rise considerably, propelled by broader electrification and the growing need for more data centers to support artificial intelligence research. Additional supply will come from renewable generation paired with batteries, backed up by gas. Across all our core markets, substantial investment is required in renewables, batteries and gas generation. That said, a stable and dependable investment framework is essential for large-scale investment, and regrettably, uncertainties here are considerably greater. Uncertainty around US energy policy direction, along with wider geopolitical tensions, could affect international trade.

Markus Krebber

executive
#6

Our future investment choices have to take this environment into account, so we are now proceeding more cautiously. Our return targets have been raised. Stricter investment criteria have been brought in, particularly in the US. In today's conditions we will keep our balance sheet strong and aim for the more conservative end of our leverage range. As a result, our 2030 investment program has been adjusted, and planned net investments have been cut by roughly 25%, or €10 billion. For the period '25 to '30, we now intend to invest €35 billion net. Active portfolio management of our offshore wind business is one element of our optimized capital allocation. Here too we aim to lessen the burden from capital employed for projects under construction. Our approach is systematic. We examine projects across all three phases — development, construction or commercial operation. Based on risk and capital intensity, we determine the optimal timing for farming down a project and the size involved. In certain cases, we see value in retaining a majority in the project in order to deconsolidate and allow for project finance respectively. Page seven shows what we have already implemented and what we plan to do. We have successfully farmed down a minority stake in our 3-gigawatt UK Dogger Bank South project to Masdar, with the goal of partnering early and reducing capital needs on our balance sheet.

Markus Krebber

executive
#7

We’ve also teamed up with TotalEnergies on our 800-megawatt OranjeWind offshore project in the Netherlands, and on our 4-gigawatt Windbostel development project off the German coast — and there will be more to come. We intend to farm down additional stakes in projects that are under construction. Things are moving along well on the sell-downs of Thor and Nordseecluster, and we anticipate being able to share a positive announcement soon. As for the Norfolk portfolio, our plan is to farm down ahead of FID, along with project finance once a CFD has been secured. And lastly, we’ll farm down a 49% stake in Sofia, our highly attractive project, which comes online next year. Under the new investment plan, we expect net cash investment of around €19 billion from ’25 to ’27. As you’d expect, for the current year our net investments are committed. Starting in ’26, the proportion of uncommitted investments will rise substantially. That leaves us with a great deal of flexibility in how we allocate capital. Carrying out the outright farm downs of Sofia and Norfolk will add even more flexibility beyond what’s shown on page eight. Additional share buybacks are part of any capital allocation discussion as we move forward. We’ll settle on the optimal capital allocation for the flexible portion early next year, when we expect to have clarity on future US and German investments.

Markus Krebber

executive
#8

Now let's turn to page nine and examine our running investment program more closely. At present, capacity under construction stands at 12.5 gigawatt, and it is well balanced across both technologies and regions. On the investment decisions we have taken, the average IRR achieved at FID comes to 8.3, which clearly beats the 8% target we had previously set. We also manage risk actively across our construction projects. Every one of our offshore and onshore wind projects is on time and on budget, and we keep lowering merchant offshore exposure by locking in attractive offtakes. For our Nordseecluster offshore wind projects, the first 400 megawatts are already secured. A PPA has been signed with Tesla for the supply of clean electricity from a Pan European wind portfolio that includes 100-megawatt from Nordseecluster. Beyond that, an agreement has been signed with TotalEnergies covering 30,000 metric tons of green hydrogen annually for its refinery in Leuna starting in 2030. That hydrogen will be produced by our 300-megawatt electrolyzer, which is currently under construction in Lingen, with plans to use renewable electricity from our Nordseecluster offshore wind farm. As a result, we have not only implicitly hedged 300-megawatt of offshore wind but also contracted our H2 production from the electrolyzer investment. The supply chain for our US onshore wind project is largely derisked.

Markus Krebber

executive
#9

For projects currently under construction, the equipment is locked in, which we can attribute to long-standing relationships with domestic suppliers. Tariff exposure appears minimal in our view. Since every required permit has been obtained, federal permitting poses no risk to us. Looking across our entire construction portfolio for onshore wind and PV, over 95% has offtake secured. When it comes to any future investment decisions, our return thresholds have been raised. The spread over WACC has gone up by 50 basis points, bringing it to a new range of 150 to 350. As a result, our new average target IRR is going to exceed 8.5%. In addition, given the present market conditions, we've put in place very stringent criteria for investments in the US. Only projects where every federal permit has been secured, all relevant tariff risk has been mitigated, offtake has been locked in, and tax credits are safe harbor will be taken to FID. Notwithstanding the market shifts we've discussed and our scaled-back investment plans, we remain on track to hit our earnings targets. Our '27 and 2030 adjusted EPS targets, which were laid out at our Capital Markets Day in '23, are reaffirmed. Thanks to our robust existing portfolio, the attractive returns from investments we've already committed to, and the flexibility we'll have in capital allocation moving forward, we will achieve an adjusted earnings per share CAGR of 18% from '25 to '27.

Markus Krebber

executive
#10

We provide appealing midterm returns for shareholders, with a dividend yield right now near 4% and a goal of raising that dividend 5% to 10% each year, driven by bottom line earnings growth featuring an 18% EPS CAGR through '27, alongside our existing €1.5 billion share buyback program, which runs until Q2 '26. Through dividends plus the buyback, we will return nearly €4 billion of capital to shareholders through '27. To sum up: RWE stands as a highly attractive investment, with meaningful upside versus its present valuation. Our operational and financial performance record is strong. Across the last five years, we beat our guidance annually. The investments we have committed will generate appealing returns, and we maintain a clear emphasis on capital allocation discipline, with substantial flexibility starting in '26. Visibility into our EPS growth is clear, and we have reaffirmed our mid and long-term EPS targets for '27 and '30. Lastly, shareholder remuneration is highly attractive thanks to continuous dividend growth, and our current share buyback program will keep going until next year. With that, I pass things to Michael.

Michael Müller

executive
#11

Okay, and thanks, Markus. And hello from me as well. Let's begin by taking a closer look at the 2024 financials. We turned in a strong financial performance in 2024 and came in above what we had expected back in November. Adjusted EBITDA came to €5.7 billion, helped by a strong showing in our Flexible Generation and Supply & Trading businesses. Depreciation was minus €2.1 billion, reflecting a one-off effect on US assets that were commissioned prior to the RV E.ON assets swap. Our adjusted financial results got better thanks to lower tax, interest and interest provisions. On top of that, interest during construction had a positive effect. At the bottom line, adjusted EPS came in above the midpoint of the guidance range. 2025 will be the earnings trough as earnings in flexible generation and trading normalize. Between '25 and '27, earnings will grow on the back of all investments. For offshore wind, we expect 2025 EBITDA to land in the range of €1.3 billion to €1.7 billion, which is comparable to '24. From 2025 to '27, the offshore EBITDA CAGR amounts to 24%, driven by the commissioning of new assets. All our projects under construction are well underway, on time and on budget. The most advanced project is Sofia. We expect COD in the second half of 2026.

Michael Müller

executive
#12

As of today, over 50% of the offshore foundations are installed. The offshore converter station, the onshore substation, and both the onshore and offshore export cables are now in place. Last week, the turbine installation vessel arrived, and installation will begin shortly. Also, the first 150 recyclable plates have been produced and are ready to go in. We anticipate the first revenue generation later this year. Once commissioned, the project will benefit from a 15-year inflation-linked CFD. Beyond that, our Nordseecluster project in Germany is moving along well, and all major supplier contracts are signed. Foundation and substation fabrication is advancing nicely, and initial offshore work to prepare for foundation installation has begun. We plan to bring that project online in 2027. Thor, our 1.1-gigawatt Danish offshore project, is likewise on track. Onshore construction is well advanced, and 50% of the foundations have already been delivered to Eemshaven port. Installation of those will happen this summer. We expect to commission the project in 2027. 2027 EBITDA is also driven by the lease accounting effect from the long-term charter of installation vessels. At the EBIT level, that effect is neutral. Our guidance does not include any book gains.

Michael Müller

executive
#13

Now let's move on to onshore wind and solar. Organic growth is what's fueling the rise in our '25 earnings. Adjusted EBITDA should land somewhere between €1.65 billion and €2.15 billion, and we anticipate additional expansion over the next several years. For 2027, EBITDA is projected in the €2.5 billion to €3 billion range. That works out to an implied yearly growth rate of 20%. The main forces behind the trajectory from 2025 to '27 are growth stemming from our current asset base that's already in construction, plus we anticipate earnings from projects that haven't yet reached construction. Naturally, those FIDs remain contingent on our rigorous investment standards, heightened return expectations, and how we allocate capital. Falling power prices will partially offset that earnings growth. Much like our offshore guidance, no book gains were factored into the guidance for onshore solar. In recent years, our flexible generation business has gained from elevated power prices and volatility. Going forward, we're assuming normalized levels for both of those drivers. Adjusted EBITDA for 2025 should come in between €1 billion and €1.4 billion, consistent with the midterm average we laid out a year ago. Within the Flexible Generation segment, we've put in place an EBITDA earnings floor. That floor is made up of capacity payments and regulated incomes, along with margins we've already locked in or that are highly certain.

Michael Müller

executive
#14

When we look at 2025, the EBITDA floor comes in at €900 million. For 2027, adjusted EBITDA is projected to land somewhere between €1.1 billion and €1.6 billion. That works out to a yearly growth rate of 6% across 2025 to '27, powered especially by increased capacity payments in the UK and battery projects going into service in Germany. That said, our fresh EBITDA target sits below what was expected at the CMD, reflecting softer margins and reduced investments. The 2027 EBITDA floor is €1 billion, supported by greater capacity and regulated payments. I should point out that these secured payments will run for an extended period. Only last week, we locked in over 6.4 gigawatt in the UK T-4 capacity auction for the delivery year beginning October 2028. That gives us income of approximately £400 million plus inflation. During 2024, our existing operations produced an adjusted operating cash flow of €5.9 billion. Even with weaker EBITDA in '25, the business is going to keep generating robust cash flows down the road. Over the next few years, we anticipate an adjusted operating cash flow averaging €5 billion. This reflects a solid cash contribution from our expanding core business. Adjusted operating cash flow also takes in the cash flow from our phaseout business, along with cash financial result and cash taxes.

Michael Müller

executive
#15

Between 2025 and '27, we anticipate benefits from working capital as well. Given the market conditions we're seeing now, our strong balance sheet will be preserved. So we'll aim toward the more conservative side of our 3.0 to 3.5 leverage range. At the close of '24, our net to adjusted EBITDA leverage factor was 2.0. During 2025, we'll move nearer to 3.0. And our solid investment rating — Baa2 from Moody's and BBB+ from Fitch — will be kept. Let me recap. In 2024 we achieved strong operational and financial results, with adjusted EBITDA and net income both above the midpoint of the guidance range. That came from a robust portfolio and especially from the strong showing of Flexible Generation and Supply & Trading, with high visibility on our earnings growth in every segment through 2027. Supported by our robust portfolio, we'll produce €5 billion of cash on average across the years 2025 to '27. And our strong balance sheet and solid investment grade rating will be maintained. With that, I'll hand back to Thomas for Q&A.

Thomas Denny

executive
#16

Thanks, Michael. That kicks off our Q&A session. Operator, would you please get it started?

Operator

operator
#17

Thanks. <<operator_script>> Our first question comes from Peter Bisztyga at Bank of America. Go right ahead — your line is open.

Peter Bisztyga

analyst
#18

Good afternoon, this is Peter Bisztyga. I have two questions, if that's alright. The first concerns the 20 gigawatts of CCGT that the German government—or the incoming one—has been discussing: could you outline how much of that might involve RWE installations? Roughly what level of CapEx could that potentially mean for you? How fast could you move to start construction? And what kind of framework would you need from the government in order to make that investment? Second, on data centers: digitization also features in the new German coalition strategy. I'm wondering whether you could discuss how you view the chance to monetize data centers—where you stand in terms of conversations about using your land, with connections, to site data centers. That would be very helpful. Thank you.

Markus Krebber

executive
#19

Yes. Thanks, Peter. I'll take the first question about the 20 gigawatts. I believe we're in a strong position to secure that, provided the framework comes through. And the incoming coalition has shown real readiness to move on it quickly and in a pragmatic way. So my expectation is that it will likely be straightforward gas plants, with no extra decarbonization burden. It really hinges on how successful we turn out to be, but I'd say our planning is quite far along. We hold excellent sites. We've signed precontracts with suppliers, meaning turbine slots are reserved. And right now our share of the German market stands at 20%. That may give you some sense of it. Ultimately, though, we'll only invest when returns are very good, particularly in that business. I'd anticipate quite attractive business cases, since competition isn't that heavy. Turning to data centers, we approach that from three angles. First, we sell substantial PPA volumes to data center providers — measured in gigawatts over the last year — and that continues, so we're seeing solid demand and active talks on additional PPAs. Second, where we hold land we don't intend to use going forward, where we don't see strong opportunities to develop batteries, gas backup or the like, we can sell it.

Markus Krebber

executive
#20

The third angle involves pursuing more advanced solutions that leverage our existing infrastructure, making those available, perhaps supporting them with round-the-clock power and green PPAs. However, selling that land is not something we would do—we'd lease it on a long-term basis, since we view it as an appealing opportunity looking ahead. And it wouldn't surprise me if additional announcements across all three angles come this year, though we won't make any promises. What we will do is report on the delivery.

Peter Bisztyga

analyst
#21

All right, thanks so much.

Thomas Denny

executive
#22

Thanks, Peter.

Operator

operator
#23

Thanks. Next up is a question from Alberto Gandolfi at Goldman Sachs. Go right ahead. Your line is open.

Alberto Gandolfi

analyst
#24

Good afternoon, and thanks for the opportunity to ask. I've got two questions. The first is fairly detailed and concerns earnings. Michael, as I understand it, the '27 EPS figure contains no gain from asset rotation. Is it correct that in the 2023 CMD you assumed roughly €250 million of asset rotation gains for 2027? That works out to about $0.30 of EPS. So what I'm hoping to clarify is, first, whether that's right, and second, it looks like there's an underlying upgrade of 10% compared with the prior plan on a like-for-like basis, without — excluding asset rotation. So where does that come from? Is it purely the buyback, or is there something else you could walk us through below the EBITDA line? My second question concerns capital allocation. You announced a buyback just recently for the first time in your history, so I wasn't expecting you to have anything new to say today. Still, if possible, could you be a bit more specific about how you rank your share buyback against other opportunities, for instance the Germany infrastructure plan? Can your balance sheet handle both incremental investment and/or buyback, and/or is there a share price at which you would put share buyback at the top of the list?

Alberto Gandolfi

analyst
#25

Whether the stock is under €35, I can't say. I mean, we will certainly grow the buyback, and if the shares are higher, we need to think it through. Is that the way you're looking at it, or what's your reasoning, please? Thank you very much.

Markus Krebber

executive
#26

Yeah, Alberto. Let me begin with the first one. So your assumption is correct. The CMD originally included about €300 million in book gains in the figures, and those are no longer included now.

Michael Müller

executive
#27

Turning to the share buyback question, Alberto — let me put a couple of questions to you. The first was: what is the balance sheet good for when it comes to additional investments? I mean, first, in this more unstable environment, we said we would move to the conservative end of our leverage target range. Of course, should the situation improve, we can go for higher leverage again, but not for the time being. I mean, that may be a decision for the future. Then, if you look at this chart where we show how much uncommitted capital CapEx we have until — from '26 onwards, this is significant, and it does not yet include the planned farm downs from Sofia and the Norfolk project. So, if we are successful on that next year, it will mean even more flexibility and headroom for flexible capital allocation decisions from '26 onwards. Now, what is the metric? Of course, we don't have a formula, but you already touched up on the relevant questions. We need to achieve higher returns than in the current market environment. If we don't achieve higher returns for new capital commitments, then we will return the capital to the shareholders.

Michael Müller

executive
#28

Is there a particular share price? No, though it does factor into the consideration. But to give you a sense of it, if you had to make that decision in today's market conditions, with the stock sitting at 26 right now given the flexibility, in the current market environment we would opt for an additional share buyback.

Alberto Gandolfi

analyst
#29

That’s very clear. Thanks.

Thomas Denny

executive
#30

Appreciate it, Alberto.

Operator

operator
#31

Our following questioner is Deepa Venkateswaran of Bernstein. The floor is yours.

Deepa Venkateswaran

analyst
#32

Thanks for taking my questions. I have two. First, on the 2030 EPS, I'm wondering how you're confident about hitting €4 per share. Although CapEx is incrementally €8.5 billion lower in today's announcement, I'm already assuming the one and a half before in the nine-month stage with the buyback. So that's my first question: what are the levers to still keep the EPS for 2030? And the second question is on the subsidy free offshore wind projects, Thor and Nordseecluster — you mention you would be farming it down and maybe something imminently in '25. Could I check whether your partners are therefore happy to take the PPA risk, or are you signaling that you could be signing even more PPAs to make this farm down more attractive? If you could just talk about how that would work and maybe it's more risk sharing rather than gains for those projects. Thank you.

Michael Müller

executive
#33

Okay, Deepa, let me begin with the questions about the 2030 EPS. Well, to start with, one clear lever is our elevated return expectations, which ought to translate into a higher EPS as well. The second one is — well, in practice you can strike a balance involving investments alongside a mix of share buybacks, as we mentioned. So you either gain on the side where you simply hold fewer shares, and then clearly the less you invest, the less you end up with, let's say, in depreciation and financing costs. And we would probably also need to examine the platform and trim some of the direct P&L. That would therefore have an effect. Or, going the other way, should the environment become attractive, you would in fact maintain the investments and deliver the return through appealing investments. In the end, it comes down to that balance. And since we're talking about 2030, we clearly see enough flexibility to steer toward that figure. On the second question regarding Thor and Nordseecluster, well, please forgive us that no details can be disclosed at this point. Conversations are underway, and as soon as we have greater clarity, we will of course also walk you through the deal in more depth.

Deepa Venkateswaran

analyst
#34

Thank you.

Thomas Denny

executive
#35

Thanks, Deepa.

Operator

operator
#36

Thanks. And our next question comes from Ahmed Fahrman at Jefferies. Go ahead, please.

Ahmed Fahrman

unknown
#37

Yes, hello, and thanks. I have two questions. First, regarding the €9 billion CapEx reduction program: could you break that down into, say, the gross CapEx reduction versus how much comes from farm downs and disposals? And I suppose a sub-question to that: can you give any sense of how much of those farm down and disposal proceeds you expect to come through by 2027? My second question concerns AR7 and the potential CCGTs in Germany. If those investments were to go ahead, would they make a meaningful difference to the CapEx profile through 2027, or would that fall beyond that period? Thank you.

Michael Müller

executive
#38

Ahmed, I’ll take both questions. On CapEx, we still report net CapEx, and you can already see where our investment will be smaller. First, what we announced on the prior call: US offshore. During the planned period, we anticipate no US offshore spending. We will also cut our hydrogen investments substantially—already announced last call—and we see that continuing going forward. We also expect materially lower CapEx at least across the coming years, with no additional committed CapEx in the US over those years until we have clarity on energy policy, environment, permits, and tariff risks. And we also expect notably less net offshore CapEx. That partly reflects the farm downs already announced, but also, given the environment—you’ve followed the auction in Denmark; in the Netherlands there is no willingness to take additional merchant risk under current conditions—so we expect those investments to be lower as well. And the second part of the question I interpreted as: what we announced as capital—a flexible capital location sufficient even for a very successful AR7 and a good investment framework in the German gas plant build out.

Michael Müller

executive
#39

And yes, that’s the answer. So that would go into the capital — the flexible capital location we’ve announced.

Ahmed Fahrman

unknown
#40

Thanks.

Thomas Denny

executive
#41

Thanks, Ahmed.

Operator

operator
#42

Thank you. Now we'll take a question from Wanda Serwinowska at UBS. Go right ahead. Your line is open.

Wanda Serwinowska

analyst
#43

Hello. This is Wanda Serwinowska from UBS, and I have two questions. The first one concerns mainly the UK. Could you give us your view on the wake and blockage effects? Disputes are continuing between the developers — how does that affect your LCOE assumptions? And if we look at UK offshore wind generation year-to-date, it appears that Triton Ore, for instance, is down 30% or 40% year-to-date compared with last year. Is low wind speed the reason, or what is going on in the UK? My second question is about German policy. There is a lot of noise around the climate fund, the infra funds, the infrastructure fund and so on. But apart from the CCGT no longer being hydrogen ready, how can RWE benefit from the new energy policy? Thanks.

Markus Krebber

executive
#44

Wanda, I’ll take the last question first. So I think the obvious encouraging signal is that the incoming German government has put restoring the economy to health as one of the central pillars of its upcoming agenda. And we can anticipate substantial government spending itself by easing the debt brake. And we can anticipate that the government will back energy-intensive industry so it remains competitive in international markets. Both are clear positive signals for future energy and power demand in Germany, where we stand to benefit the most. And the third point is the clear intention to resolve supply security issues through a build-out plan of 20 gigawatt of gas. Here I think no government money is really required; we simply need a sound investment framework, and then private capital will handle it. But I think the first — so I don’t expect any, let’s say, competition from infrastructure funds for our potential investments, but I think the overall business environment should be considerably better given the substantial spending from the German government, its willingness to support energy-intensive industries and, of course, all the other measures that have been announced which make our product cheaper.

Markus Krebber

executive
#45

Basically, bringing power taxes down as far as they can go and helping with grid charges, that kind of thing. On the other matter, the wake and blockage one, I'll take that — I believe Michael handles a particular one concerning the asset. There's a great deal of chatter right now, and in the specific, say, renewable releases, you're seeing it nearly daily. Honestly, it's overblown. For us it isn't a major issue. I mean, we understand the possible wake and blockage impact. We've taken those into account. It isn't anything new. I think we're certainly, with the whole of our assessment, what we also observe when we speak with partners, on the cautious side of that. I'd say the current chatter you're seeing, particularly since the legal basis, how to resolve it and how to handle it, remains unclear. That's the reason everyone is staking out a position at the moment. But for our investments, for the assets we already hold, we believe we know the worst case that could occur. And it has been factored in.

Michael Müller

executive
#46

Yeah. Regarding the wind <<inaudible>>, all of the wind. So Q4 also experienced low winds, and in fact the first quarter has begun with weaker wind as well. So that's a reasonable assessment.

Wanda Serwinowska

analyst
#47

Thanks. Could I just ask one — one quick follow-up about German politics? Marcus, from what I understand, the CDU and the SPD were considering moving assets out of the strategic reserve, or out of the reserve capacity, and putting them back into the merchant market in order to bring the power price down. How likely do you think that is to happen? And is there anything else that others could put on the table?

Markus Krebber

executive
#48

At this point, this is political guesswork, and normally I decline to get into that kind of discussion. Still, let me be very clear. In my view this is not a great idea, and I have made that clear to the decision makers as well. On the surface, bringing back these plans sounds great, but you're going to create significant negative effects, because you would immediately dampen the investment appetite to go for batteries. But batteries are also needed not only for the high price, it also needed for the negative prices to carry the power into the hours where it is needed. Second, you would give an incentive to close even more plants. That's definitely not wanted by the government, because we could even think about closing our plants. You get a guaranteed cost coverage and then you can put them into the market and earn additional margin. I think bad idea. And last, bad incentive from that idea is you disincentivize long-term power purchase agreements because everybody who is a long-term contract doesn't suffer from the high prices. So only those who speculate short term suffer from the prices. And I think that incentive is also not wanted. So, in a nutshell, I would be very surprised if that idea comes to life.

Wanda Serwinowska

analyst
#49

Much appreciated.

Thomas Denny

executive
#50

Appreciate it, Wanda.

Operator

operator
#51

Thanks. And moving on to Deutsche Bank, our next question comes from Olly Jeffery. Go ahead, please.

Olly Jeffery

analyst
#52

The first question I have is this: you’ve already stated that part of why net investments are €10 billion lower — or why you’re cutting €10 billion, sorry — relates to expectations in the US. What I’m trying to understand is whether, if you now invest more onshore in the US, with more committed in 2025 and ’26, and under a reasonable assumption for a reasonable outcome from the German gas auction and the investment level you think you might need there, plus any investment you might need under AR7 under a reasonable outcome — do you still believe, in that scenario, that you’d have the balance sheet capacity to carry out buybacks at least as large as the €1.5 billion you announced for ’26 and ’27? I’m just trying to get a sense of whether, given the reasonable outcome of the investments you expect, you think you would still have balance sheet capacity to do buybacks if you wanted to. And then, just on AR7, do you have any indication of its potential size? And when might we expect to hear any views, and when might we get further details on the AR7 auction and the parameters in it?

Olly Jeffery

analyst
#53

Appreciate it.

Markus Krebber

executive
#54

Right, Olly, perhaps regarding the largest piece, the Norfolk projects, what we indicated today is that farming down is our aim ahead of FID, so no additional CapEx commitment will be made until that farm-down happens. Our target is to farm down to 50% and deconsolidate, which means at CfD award we can pursue project finance. That already signals the net CapEx involved isn't very significant within our net CapEx. On the US gas plan, well, how much you choose to do at this point is speculation. The question of capital location will be answered based on the drivers we outlined, and share price plus the returns we can expect form one part of that. That answer will come in -0- when it's due, once we have capital allocation flexibility, which is in '26. So we'll decide later this year or early next year.

Olly Jeffery

analyst
#55

And when do you expect to hear something from the AR7 process, potentially the potential…?

Markus Krebber

executive
#56

Yeah, sorry — I skipped that one. So the consolidation is, I think, still in full swing, still very much underway. The Ministry is talking it over with all the relevant parties. From what I understand, they'll reach a conclusion soon, and based on every indication I'm getting, they don't intend to delay the auction into the last quarter. So we'll likely see it in Q3, which means we should have clarity perhaps before the summer break.

Olly Jeffery

analyst
#57

Appreciate it.

Thomas Denny

executive
#58

Thank you, Olly.

Operator

operator
#59

Thanks. Next in the queue is Harry Wyburd from BNP Paribas Exane. Your line's open, so please proceed.

Harry Wyburd

analyst
#60

Hello. Thank you so much for the question. Two fairly basic ones, then. The first concerns something the sector no longer discusses much, based on what I've noticed — namely, installed costs for renewables. What are you observing right now? When we last paid attention to these installed costs — chiefly onshore and offshore wind, in my mind — they had more or less flattened out and settled down, and inflation concerned us less. You brought up the Danish and Dutch auctions, with developers reluctant to bear merchant price risk. Yet a major element here is clearly whether installed costs will decline, and could that increase the odds those auctions succeed down the road? So I'd like your perspective on where installed costs are heading, covering both turbine prices and the balance of spend. That's the first. The second is on new-build gas and the supply chain. How do you see the supply chain there? You hear from other utilities, in both the UK and US, that the supply chain is already rather stretched. With new-build gas, there's talk that some components tie in with defense procurement too.

Harry Wyburd

analyst
#61

Could the construction of those 20 gigawatts of CCGTs end up taking more time and costing more money than we presently anticipate? And how much danger is there that we see a repeat of the kind of non-productive capital employed situation we experienced in offshore wind starting to show up with CCGTs, should they take longer to build or should you find it difficult to secure critical components? Thanks.

Markus Krebber

executive
#62

Harry, on the cost side, what we're seeing right now when we purchase is that it's flattening out. It is certainly not climbing any further. If I look ahead, I'd actually anticipate some relief in the supply chain, given the deceleration in the US and, in fact, a halt of US offshore wind. So on the wind side overall, I'd expect the supply picture to become somewhat easier. That said, I don't think it will lead to developers being ready to shoulder meaningfully greater merchant risk. We've consistently said that the merchant risk you're able to take depends on how large the market is and how deep the PPA market runs. So the gigawatt in Denmark and the Netherlands is fine by us, but we won't go beyond that, and in Germany we've likely already hit the ceiling of what we're prepared to take on — and we also farm down on an ongoing basis. So overall, in this uncertain environment, what I'm hearing in the market — and our view matches it — is that appetite for merchant risk, or for additional merchant risk that's been auctioned in offshore, is very, very limited. And I think policymakers — this is what we tell them — need to adjust; it has to shift toward — I mean, I believe an inflation adjusted double sided CfD model is needed to secure the investments.

Markus Krebber

executive
#63

You'd bring down investment returns as well. And I think particularly now that you move to the UK, they're going in the right direction, since part of the consultation is even about extending the CfD period from 15 to 25 years. And a 25-year inflation-adjusted, government-guaranteed income stream is, of course, far better, and it would lower cost for consumers too, because you can go for higher leverage. On the new gas side, it's also a very, very interesting situation. I mean, what I heard at CERAWeek last week from the big suppliers is that if you want to buy a gas turbine, you probably have a delivery date now of '28. So it actually fits a bit with the German schedule if you are fast. But as I already said in reply to a previous question, we have reserved certain product slots. So I think for what we want to buy — for what we want to build, we have the supply chain secured. And I think that's more on a side note: if we would release these production slots, we could even make a bargain today.

Harry Wyburd

analyst
#64

All right, thanks. That’s pretty interesting. In effect, your build slots give you a competitive edge. And do you figure that’s something your rivals in the potential new-build CCGT market also have? Or do you believe you could use that to essentially earn higher returns? It sounds like you could, correct?

Markus Krebber

executive
#65

That's speculation, sure. Still, I don't think we'd hand over that advantage. That much is certain. What I mean is the upside that comes from actively running the supply chain — we've done the same thing offshore in certain cases, as you're aware, when it came to securing equipment there. We intend to hold onto that advantage ourselves. I mean, that much is certain.

Harry Wyburd

analyst
#66

Yes. That makes sense. All right, thanks a lot.

Operator

operator
#67

Thanks. We’ll take our next question from Rob Pulleyn at Morgan Stanley. Go ahead—your line is open.

Rob Pulleyn

analyst
#68

Thank you. Thanks for taking our questions. At least a few remain. First, I haven't heard Amprion mentioned in any of the materials or on the call so far. The last we heard, you began a sales process to divest the 25.1% stake, and I believe some media articles said you were just receiving or had already received bids, so maybe just an update on that. And is that capital, so to speak, earmarked in the plan you've presented today, or is it, shall we say, unallocated capital that could go toward additional distribution or toward committing to some of these other CapEx plans that might firm up in due course? That's the first question. The second is, as we look at 2027 guidance and accept that, obviously, EPS is the same and the cap gains have changed. Within the EBITDA range, there are two fairly significant changes. One is FlexGen, where HPG has come down by roughly a 400 million delta at both the top and the bottom end, while offshore wind has risen by around 200. Could you perhaps give a bit of color on what's happening there? Thank you.

Markus Krebber

executive
#69

Yes. Rob, I’ll handle the first question. Michael will cover the earnings profile. Regarding Amprion, we’ve consistently stated that because of the substantial capital requirements there, we will examine every option to identify solutions, since our view is that RWE should not be the one funding the TSO business here. Still, we prefer to keep our cards close and preserve all alternatives. So yes, we are in the market — that is accurate — and we are currently working through what the best solution would be. That could also result in a partial sell-down. It doesn’t have to, but it could. We are clear that we no longer want to make investments into that, and we want to find solutions for it. If we do partly sell it down and receive proceeds, those proceeds are not yet reflected in the net CapEx shown in the presentation.

Michael Müller

executive
#70

Yes. Rob, regarding EBITDA '27, that's a fair point. FlexGen is indeed lower because we expect lower prices in flexible generation. In offshore, there are essentially three main drivers. First, at the CMD we still assumed OranjeWind would be fully consolidated. That is no longer the case. As you know, we sold it to 50% with TotalEnergies, so that leads to a lower EBITDA. And on the positive side, there are two effects. One is an accounting treatment around our lease ships. What happens is that the lease itself, since it's capitalized, flows through the EBITDA. So there's a positive EBITDA effect, but at the same time the leases result in higher depreciation, so the positive EBITDA effect is then fully offset by higher depreciation, so the EBIT effect is the same as we had at the Capital Markets Day. And the third positive effect — the third effect is a positive one from Thor, where we now take those lease payments that are paid through a kind of CfD mechanism in the first one and two years. And what we've done now is we will distribute them as a lease payment over the entire life cycle of the project, and that leads to a slightly higher EBITDA effect in '27 and '28 in Thor.

Rob Pulleyn

analyst
#71

That is quite clear. Many thanks.

Markus Krebber

executive
#72

At the core, nothing is different.

Michael Müller

executive
#73

Right. That’s the main point.

Rob Pulleyn

analyst
#74

Understood, understood. My apologies, Marcus — while you're taking follow-ups, just on that first one, with every option on the TSO situation still on the table, if proceeds were to come in, might those funds support larger returns to shareholders, in the sense of revisiting the share buyback and/or the dividend policy?

Markus Krebber

executive
#75

We’re not looking for that direct link from €1 to that or that — I mean, but as we’ve said, the proceeds aren’t included in what you might call the flexible capital allocation portion we have. So if we receive some, that would increase it. What we do with it has to be decided at the moment we have it, and a decision has to be made, but there’s no automatism.

Rob Pulleyn

analyst
#76

That's reasonable. I'll hand it over to you. Thank you so much.

Thomas Denny

executive
#77

Thanks, Rob.

Operator

operator
#78

Thanks. And our next question comes from Meike Becker at HSBC. Please go ahead.

Meike Becker

analyst
#79

Yes. Hi, everyone, and thanks for taking my question. Perhaps moving a bit closer to the end of the year, this is a qualitative one. How conservative do you believe your plan is at this point? I mean, among some of your peers, we have seen several rounds of downgrades. In your case, on the strongly positive side, there don't appear to be any execution problems. I mean, your offshore execution seems to be going very well, and you seem quite confident about the PPA signing. But regarding future CapEx, how confident are you that this is now the conservative plan and that we won't see further downgrades? That would be my first question. And the second one, just one topic we haven't yet touched on is battery development. What do your current plans look like, and which markets are you currently considering for your battery ambitions? Thank you.

Markus Krebber

executive
#80

Micheal?

Michael Müller

executive
#81

Yeah. So, Meike, I'll take that first question. I mean, I think your summary of the situation was fair. I mean, we haven't run into any difficulties with our offshore business. It's coming along well. And I also made that clear in my speech — on all the current offshore projects we're on budget and on time, so I'm very confident we'll deliver that. And with that said, we're very confident that we'll deliver the plan as well. I mean, by the way, if you also look at how we performed in 2024, at the beginning of the year we took a more conservative stance given the commodity price environment. But you also saw that by the end of the year, we actually turned out to be above consensus, which also demonstrates the robustness of our portfolio and our ability to deliver.

Markus Krebber

executive
#82

Regarding the CapEx plan and the batteries, perhaps starting with the CapEx plan and whether it's conservative or not. What we're trying to get across, I think, is that we will be disciplined with CapEx, and we are willing — if the environment isn't there and the investments aren't attractive enough, we will reduce. And we announced a share buyback on the last call. Now we announced that we're going for lower CapEx through 2030 because we see higher risk and require higher returns. And let me use that opportunity to say a bit about the market and then I'll address your battery question. We're actually in what you could call a very interesting but also contradictory environment. There are three elements. One is the fundamental growth of the product. Power is there. You've got to see power demand rising in all markets. That means significant investments are needed. What I also observe is that competition is actually easing. People are exiting — you can talk about big oil or others exiting — and we also see some peers struggling under financial stress. But on the other hand, the investment environment isn't one where you like making big investments, because you have tariff risk, permitting <<inaudible>> risk, energy policy uncertainty.

Markus Krebber

executive
#83

This is a conflicting kind of market. What that really means is that a business such as ours, with the balance sheet to put capital to work, has to stay very disciplined. And we will be pushing our teams to seek better returns. We have to earn better returns. If we can't earn them in this market climate, then we shouldn't be putting money in. That leads perfectly into batteries, an investment area we're quite fond of right now, including based on how those players behave in the market and the returns they generate. Our main battery markets include Germany, where we brought a substantial amount of battery capacity online this past week — more than 200 megawatts. We've announced further investments totaling 600 megawatts. So expect additional battery investments there. We also invest in batteries in the UK. And in the US we colocate battery investments as well, particularly alongside solar. And that's one area where, so far, we haven't trimmed our investment plans.

Meike Becker

analyst
#84

That's great. That really helps. Thanks.

Thomas Denny

executive
#85

Appreciate it, Meike.

Operator

operator
#86

Thank you. And our next question comes from Piotr Dzieciolowski at Citi. Go ahead, please — your line is open.

Piotr Dzieciolowski

analyst
#87

Hello there, and good afternoon, everyone. There are a couple of things I'd like to ask. First, I wanted to ask about what this higher return threshold you announced means for the long-term targets. You gave us a rule of thumb of over 10 times the contribution of whatever euro you spend on 2030, or as you go — is that multiple now lower? So, nine times, and this €36 billion you have left to spend will contribute more. Can you say how much? And then, does this — assuming you get a lower CapEx, does this have any implication for your OpEx? You build up quite a machine to develop new projects, and it seems some of the pipeline may not meet your threshold, but maybe you can reduce some of the costs. Like we've seen the headline on the US Offshore that you — is it meaningful, or is that not meaningful at all? Thank you.

Markus Krebber

executive
#88

Yes, Piotr, thanks for that question. What you're raising is, of course, fully reflected in the figures. It ties back to what Deepa asked right at the start: why do you feel confident about hitting the 2030 numbers? Well, that's precisely the trade-off you'll observe. Fewer investment opportunities would clearly affect the overall cost structure as well, including in development. So that part is quite clear.

Piotr Dzieciolowski

analyst
#89

All right, thanks so much.

Operator

operator
#90

Thanks, and now we’ll take a question from Ingo Becker at Kepler Cheuvreux. Please go ahead—your line is open.

Ingo Becker

analyst
#91

Yes, thanks, and good afternoon. I have a couple of questions too. The first concerns your Supply & Trading business, where the guidance remains €100 million to €500 million in EBITDA. Since you've materially beaten that figure for many years running, I'm curious how we should think about that guidance. My understanding was that the trading guidance is deliberately kept conservative so it can serve as an offset if something goes wrong in renewables — and in that case, in a normal environment, there's a solid chance you'd keep exceeding it. That's question one. Second, on slide 18, may I ask about the '25 guidance, where you give a range of €1 billion to €1.4 billion and a floor of 900? What precisely separates the range's low end from the floor that sits a bit lower still? And tied to that, you guide to €1.27 billion as a floor again, plus a higher range of €1.1 billion to €1.6 billion including additional expected earnings. Can I just clarify — I believe your earlier distinction was between existing earnings and earnings from new assets, which would point to investments.

Ingo Becker

analyst
#92

But now you're mentioning extra earnings. Take, for instance, the 2 points you're raising regarding capacity payments. That's extra income arriving without any CapEx spend. I suppose commissioning your battery projects does involve some CapEx. May I simply ask, if nothing were spent on expansion within that segment, what range should we expect for 2027, if you can say. Thank you.

Michael Müller

executive
#93

Okay, Ingo, I'll begin with Supply & Trading. I could simply offer the usual response here. What we guide to is consistently rooted in the long-term earnings expectations for that business. As we've consistently stated, when market conditions are favorable, the numbers can come in higher. Still, that's the guidance we've maintained over recent years. And as you're aware, recent years have delivered very attractive actuals, yet guidance remains this 100 to 500, and nothing about this year's guidance has changed. On your second question about Flexible Generation — what outcome should be expected for the Flex segment? That is precisely the guidance range. So for '25 we expect 100 to 400, and for '27, we expect <<inaudible>>. During the roadshow, people often asked how best to model it. So we thought it might be helpful to provide an earnings floor. That figure reflects a very conservative assessment. We went through the margins and pinpointed those positions we consider highly certain.

Michael Müller

executive
#94

When you look across the various positions, what's clearly been secured is capacity revenues in Germany and the UK. There are also other regulated revenues within the business. On top of that, obviously, hedge margins factor in, along with those revenue streams where we're quite confident they'll come through as actuals. That gets you to the 900. But just as you rightly pointed out, a delta exists, and clearly the bottom end of what we actually expect as an outcome sits higher, since we do believe some of those positions that aren't yet fully certain will deliver, at least within the lower part of the guidance range. That said, there's plainly upside too, particularly when markets tighten. Which is why the range comes out at 1 to 1.4 in '25 and 1.1 to 1.6 in '27. And of course the figures capture the upper end as well, including those investments we've made. So the additional battery investments Markus mentioned are baked into those numbers.

Ingo Becker

analyst
#95

Thanks. Michael, could I ask about the higher capacity payments in the UK — are those included in the €1 billion floor figure for '27?

Michael Müller

executive
#96

Those figures are part of the €1 billion. Yet when you look from '25 through '27, '25 clearly already carries a larger portion of hedged income. So even though capacity market income exceeds €100 million — in fact it's around €200 million, perhaps a bit above that, which reflects the UK capacity market increase — you simultaneously have fewer margins being hedged, and that's the reason the uplift comes to just €100 million. Still, that alone should signal to you that this really represents the cautious low end of the range. It's a floor. An extremely cautious floor.

Ingo Becker

analyst
#97

Much appreciated.

Thomas Denny

executive
#98

Thanks, Ingo.

Operator

operator
#99

Thanks. We’ve got a few follow-ups, and the first one comes from Alberto Gandolfi at Goldman Sachs. Go ahead.

Alberto Gandolfi

analyst
#100

Thanks for waiting. And those two are, I think, for Michael once more. First, I’m somewhat taken aback by your claim that nothing fundamental has changed, since unless I’m misremembering, at EBITDA you stated that roughly €300 million is being taken out of asset rotation gains. Yet my suspicion is that the lease impact comes to somewhere between 100 and 150, and at the EBIT level it’s entirely removed, as the DNA rises. So — that really is on an underlying basis. To me that sounds like an upgrade. Is there something I’m overlooking or misconstruing? That’s the first one. The second, please: when you mention your three times leverage, you don’t appear to be factoring in your E.ON stake, which stands at €5 billion. May I ask whether, at some point, if E.ON keeps performing very strongly and RWE lags behind, you shouldn’t simply sell your own stock in order to buy back your own stock? But more broadly, how are you thinking about E.ON? Because your three times leverage, if I actually adjust for this, which is the monetizable asset, is far lower than that. So again, am I right? How are you thinking about it?

Alberto Gandolfi

analyst
#101

I really appreciate it.

Michael Müller

executive
#102

All right, so let me give you my take on this. At the core, nothing is different. I mean, you're correct that €300 million represents a shift, but it isn't purely offshore. So that came from every one of the segments. And then the leasing piece — I mean, that's purely an accounting treatment. So, when you look at the EBITDA figure, nothing has changed. So this leasing impact is purely an accounting effect that produces a higher EBITDA, but then higher depreciation as well. So on EBITDA, the impact came out neutral.

Alberto Gandolfi

analyst
#103

Got it, that's very clear. So if you do still hit €3 EPS, then somewhere there has to be an upgrade — it's below the line, but an upgrade exists somewhere, because otherwise the EPS would be a lot lower.

Michael Müller

executive
#104

Right.

Alberto Gandolfi

analyst
#105

Thanks.

Markus Krebber

executive
#106

Alberto, regarding the E.ON stake, as you're aware, the lignite provisions fall outside how we define net debt, since the E.ON stake sits against them as an offset. So if you sell E.ON, those provisions have to come into our net debt, and that's the ring fence approach we describe — we intend to fund the lignite provisions from the state claim we still hold, under which we receive annual payments. Those payments will offset a portion of the negative cash flow from that business, and once we begin drawing on the provisions, we have the E.ON stake. So in a sense it's a virtual CTA — not a formal one, but a virtual one. It's a closed box of financial assets, with E.ON offsetting the lignite provisions.

Alberto Gandolfi

analyst
#107

Thank you, and I appreciate everyone waiting.

Thomas Denny

executive
#108

Appreciate that, Alberto.

Operator

operator
#109

Our next question comes from Ahmed Fahrman at Jefferies. Please go ahead.

Ahmed Fahrman

unknown
#110

Yes, thank you. Thanks for the chance to follow up. I have just one question from my end. Marcus, when you answered one of the questions about buybacks versus CapEx, it sounded to me as though you were implying that market conditions would have to get better before that uncommitted CapEx shown on slide eight could turn into committed CapEx. So my question is this: are there any particular clearing events you have in mind over the next 12 months that would help us — that would help you make those calls about shifting from the uncommitted, flexible portion to the committed portion? Thank you.

Markus Krebber

executive
#111

I'd say there are three factors that matter here beyond the share price, Ahmed. As you correctly noted, before we shift from uncommitted to committed CapEx, we need to see those higher returns. We must have clear visibility that returns will be better than they are today. The second one is uncertainty — the risk side of things. Right now it's very hard to make investment decisions in parts of our business where permitting risk, tariff risk and so on are looming. So if the environment is more stable and you can see ahead for the next 12 months, you feel more comfortable. Even when returns are higher, we won't accept significantly more risk. That trade-off doesn't work. And the third element is how our disposal program is progressing. So, we have the plans. We're very far along with two of the disposals where we said you can expect an announcement shortly. And we're not talking quarters here — we're talking weeks. That gives us greater confidence about headroom and, of course, also about how we're doing and when we deliver Sofia and the Norfolk farm now, because that would actually increase the uncommitted net CapEx.

Ahmed Fahrman

unknown
#112

Got it, thanks.

Operator

operator
#113

Thanks. We’ve got our last question for today from Peter Bisztyga at Bank of America. Go right ahead — your line is open.

Peter Bisztyga

analyst
#114

Okay, I have two final questions, please. First, regarding the UK, what is your perspective on locational pricing? And should the government choose to pursue that, what might the consequences be for your assets? Second, has your thinking shifted at all on the value of putting money into US CCGT? Do you see any potentially interesting opportunities arising in that area? And is there any — could that be somewhere you might deploy some of your flex? Thank you.

Markus Krebber

executive
#115

Yeah. Thanks, Peter, for those questions. Regarding the UK, our overall stance is — and we've signed that industry letter as well — we believe that in a situation where billions of investment are required in the system to shift from one pricing regime to another, the timing is poor. I don't have a view on what would be a superior system if it could be brought in overnight. But the issue is whether this is the right moment, because you generate substantial uncertainty if you go from a single price zone to zonal pricing over the next year. So, I think it's a bad idea. What would it mean for us? Well, it hinges on the specifics, but perhaps two observations. One is clearly that the UK government wants to make sure that investments take place. That's why part of the consultation for offshore for the AR7 also concerns what kind of protection you need in case we opt for solar pricing. So, I would assume that all renewable investments are immunized against changes in solar pricing. And when you look at the map on the non-renewable assets, you're going to see that all our CCGTs sit in the south, so in the probably higher price.

Markus Krebber

executive
#116

I won't speculate on that, because fundamentally, even if you'd gain relatively versus others, we believe shifting from one system to another at this moment creates enormous disruption, actually puts investment at risk, and should not be done. Now, regarding the US CCGT side, I mean, you can observe the valuation level of CCGTs in the US. And I can state plainly that on our side there is no plan for any M&A transaction—not just for CCGTs, but for anything else either. So M&A is not on the table.

Peter Bisztyga

analyst
#117

That couldn’t be clearer. Thanks so much, Markus.

Thomas Denny

executive
#118

Thanks, Peters.

Operator

operator
#119

Thank you. And since there are no more questions waiting in the queue, I'd like to return the call to you, Mr. Denny, for any additional or closing remarks.

Thomas Denny

executive
#120

Thanks, operator, and thanks to all of you for joining us today. I appreciate Marcus and Michael for taking the time. As you're aware, the IR team is available to you at any point — we look forward, first, to hearing your questions and, second, to seeing many of you at the roadshows we've lined up over the next few weeks. Enjoy the rest of your day. Bye-bye.

Operator

operator
#121

I appreciate everyone being on today’s call. Ladies and gentlemen, at this point you’re welcome to hang up.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete RWE Aktiengesellschaft transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to RWE Aktiengesellschaft earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in RWE Aktiengesellschaft or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.