Sarda Energy & Minerals Limited (504614) Earnings Call Transcript & Summary

August 3, 2026

BSE IN Materials Metals and Mining earnings 46 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day, and welcome to Sarda Energy & Minerals Limited Q1 FY '27 Earnings Conference Call. [Operator Instructions] Please note that this conference is being recorded. I now hand the conference over to Mr. Parth Chauhan from AdFactors PR. Thank you, and over to you, sir.

Unknown Attendee

analyst
#2

Good evening, everyone, and thank you for joining us today to discuss the Q1 FY '27 business performance of Sarda Energy & Minerals Limited. We have with us Mr. Pankaj Sarda, Managing Director; Mr. Manish Sarda, Deputy Managing Director; Mr. Padam Kumar Jain, Director and Chief Financial Officer; and Mr. Nilay Joshi, Executive Director. Before we proceed with this call, I would like to mention that some of the statements made on this call may be forward-looking in nature and may involve risks and uncertainties that are difficult to predict. The company undertakes no obligation to update any forward-looking statement to reflect developments that occur after the statement is made. Documents related to the company's financial performance, including the investor presentation have been uploaded on the stock exchanges and company website. I now hand over the conference to Mr. Pankaj Sarda. Thank you, and over to you, sir.

Pankaj Sarda

executive
#3

Thank you, Parth. Good afternoon, and thank you all for joining us on the Q1 FY '27 earnings call. I hope you have had a chance to go through the financial results and investor presentation uploaded on the exchanges and our company website. Q1 FY '27 stands as testament to the series of decisions we have taken over the last few years to build a diversified integrated business model, one that has continued to help us navigate external challenges. Following a record FY '26, we have begun the new financial year with continued progress across our strategic priorities, strengthening our integrated business model through disciplined execution, strengthening expansion pipelines through disciplined capital allocation and improving efficiencies. Let me now walk you through the key highlights of the quarter. Despite a combination of planned maintenance shutdowns, unplanned outages and seasonal factors, Q1 FY '27 financial performance remained robust with the highest ever quarterly EBITDA and PAT. Q1 total income stood at INR 1,717 crores, EBITDA at INR 762 crores and PAT at INR 478 crores, a growth of 9.4% Y-o-Y. Net profit included a onetime net benefit worth INR 110 crores, mainly relating to the regulatory approval of final project cost for 113-megawatt Sikkim hydropower plant. Moving to the operational performance. Our energy business remained the key growth driver, contributing nearly 70% of consolidated EBITDA and providing stability to overall earnings. We have secured medium- and long-term power supply agreements for over 380 megawatts out of the total 710-megawatt salable power capacity, which meaningfully improves revenue visibility and earnings stability for our power business going forward. During the quarter, generation at the 600-megawatt thermal power plant continued to be steady during the quarter with an average PLF of 85.9%. Generation across our small hydropower plants was affected by delayed monsoon conditions during Q1. However, we are encouraged by the early trends in July and are hopeful of a better momentum in Q2. Separately, as previously announced in stock exchange intimation, our 113-megawatt Sikkim hydropower project was shut from 18th June to 5th July, following the collapse of a transmission tower caused by heavy rainfall and landslide. The plant has resumed operations fully and is functioning at normal level. On the metals front, while iron ore pellet production supported our operating performance, but the consolidated revenue for the steel and ferro alloys segments declined Q-o-Q as the production was impacted by several planned outages. Firstly, the planned replacement of 30-megawatt captive power plant unit at Raipur, along with improvements works across steel and ferro alloys facilities temporarily impacted production. This resulted in a temporary Y-o-Y decline in production of billets, wire rod, et cetera. However, the new 30-megawatt unit is ready for trial operations. We expect stable commercial operations to begin by the middle of this month. Secondly, at Vizag, the captive power plant underwent scheduled maintenance for 23 days, affecting ferro alloys production. Additionally, one of the ferro alloys units at Siltara was also under shutdown for 53 days for refurbishment. On the realization front, the steel prices remained largely range bound with a mild negative bias during the quarter, while ferro alloys prices saw a modest improvement, the price realization from sale of power was lower Y-o-Y. Moving on to the updates on our ongoing capacity expansion. Execution across our major expansion initiatives continues to progress as planned. The regulatory approval process for expanding our thermal power capacity at SKS from 600 megawatts to 1,200 megawatt is on track. The brownfield expansion remains one of the most capital-efficient growth opportunities available to us, backed by existing land, water, material handling system and evacuation infrastructure. Approval process for our 3 small hydro projects in Chhattisgarh, 74-megawatt aggregate is progressing as scheduled. Commissioning of our 50-megawatt captive solar project has been delayed due to right-of-way issues on the transmission line. We now expect commissioning before the end of the next quarter. For our recently acquired 66-megawatt hydropower project in Arunachal Pradesh, most key statutory approvals are in hand and critical land acquisition is complete. Work for approach road started. We remain confident of hitting our planned time lines on this project. On mining, development of the Shahpur West high-grade coal mine remains on schedule with commissioning targeted before the end of FY '27. The Bartunga Hill coal mine is expected to be opened by the end of next financial year, while regulatory approvals for the Gare Palma 4/5 and Sinduri coal blocks continue to progress as planned. Additionally, as part of our sustainability agenda, we are investing approximately INR 300 crores. The project includes a waste heat recovery power plant at Vizag with an aim to improve energy efficiency and resource utilization. As committed earlier, we continue to be very prudent about our balance sheet while undertaking all these expansions. All ongoing expansion projects continue to be funded through internal accruals. We are now net debt-free on both a stand-alone and consolidated basis with a strong balance sheet and healthy liquidity of more than INR 2,500 crores as of 30th June 2026, giving us significant flexibility to execute our long-term growth plans. Looking ahead, our focus remains on disciplined execution of the expansion pipeline, timely commissioning of ongoing projects, deepening the integration from mining to energy to metal and further strengthen the balance sheet. We are confident these initiatives will continue to enhance earnings visibility, improve operating efficiency and support sustainable value creation for all our stakeholders. With that, I'll hand over to Mr. Manish Sarda to walk you through the industry environment and outlook.

Manish Sarda

executive
#4

Good afternoon, everyone, and thank you for joining us.

Pankaj Sarda

executive
#5

Manish, over to you.

Manish Sarda

executive
#6

Good afternoon, everyone. Can you hear me?

Operator

operator
#7

Yes, sir.

Manish Sarda

executive
#8

Can you hear me?

Operator

operator
#9

Yes, sir, we can hear you loud and clear.

Manish Sarda

executive
#10

Energy sector demand..

Pankaj Sarda

executive
#11

Manish, you are not audible.

Manish Sarda

executive
#12

Not audible?

Operator

operator
#13

Sir, it is very much audible.

Manish Sarda

executive
#14

Okay. So let me go ahead then. India's power generation grew 9.4% year-on-year to around 5%.....

Pankaj Sarda

executive
#15

Talking about energy sector demand India's... Hello, are you there?

Manish Sarda

executive
#16

Yes, I'm there very much.

Unknown Executive

executive
#17

I can hear both of you.

Pankaj Sarda

executive
#18

Talking about energy sector demand.

Unknown Executive

executive
#19

I think they are unable to hear us.

Pankaj Sarda

executive
#20

Am I audible?

Unknown Executive

executive
#21

Yes, you are audible.

Operator

operator
#22

Manish sir, you may continue.

Manish Sarda

executive
#23

So India's power generation grew 9.4% year-on-year to around 523 billion units during the quarter. Thermal generation grew 7.5% and continue to account for close to 70% of the country's total generation, while renewable generation, including large hydro grew approximately 15%. Delayed monsoon conditions weighed on hydropower with small hydropower generation declining roughly 30% year-on-year and large hydropower generation declining 7% -- this was more than offset by a sharp 45% increase in solar generation. Average prices on the day ahead market held broadly stable at INR 3.85 per unit compared to INR 3.92 per unit in the corresponding period last year. However, prices in July have moved up from INR 4.19 to INR 5 per unit year-on-year. The government continues to prioritize energy security by promoting domestic energy resources and reducing dependence on imported coal and oil, reflecting global supply disruptions, higher logistics costs from geopolitical tensions and Indonesia's export restrictions, the Indian coal index for June 2026 was minus 21% higher than June 2025 and minus 11% higher than March 2026. Steel sector. India continued to outperform major global steel producers through the first half of calendar year 2026. Domestic crude steel production grew over 7.5%, even as China and several other major producers saw declines. The weak domestic Chinese real estate demand continued to push exports into global market at about 10 million tonnes per month. Amidst this, India's apparent steel consumption grew year-on-year, though momentum moderated sequentially. Imports have once again exceeded exports after 2 quarters, partly on the back of free trade agreements with partner countries. We welcome the government's antidumping investigations, which should help address unfair imports and support domestic producers. The ongoing conflict in West Asia has raised input costs and created supply chain disruptions. Elevated oil prices could inflationary pressure and affect demand in certain end-use sectors, including steel. While we remain in a wait-and-watch position, given India's predominantly domestic demand-driven economy, we expect to overall impact to remain manageable. Government initiatives under Viksit Bharat 2047, Make in India and Atmanirbhar Bharat continue to drive investment across manufacturing, logistics, electronics, semiconductors, data centers and industrial infrastructure, creating sustained long-term demand for reliable, competitively priced power as well as metal sector. How is SEML's positioning? Against the backdrop, -- we believe SEML is well placed to capture these structural opportunities through our integrated presence across mining, energy and metals. Our diversified and calibrated expansion pipeline is well aligned with India's long-term priorities of energy security, manufacturing-led growth and economic self-reliance. With plans to quadruple our mining capacity and double our energy generation capacity, we are entering the next phase of growth with a strong balance sheet, improving operating momentum and clearly defined road map. We remain confident that our integrated model, disciplined capital allocation and continued execution focus will drive sustainable growth and enduring value for all stakeholders. With that, we'd be happy to take your questions. Thank you.

Operator

operator
#24

[Operator Instructions] The first question is from the line of from [Sugandh Haria] from [GreenEdge Wealth].

Unknown Analyst

analyst
#25

See, my first question is on our IPP, the power sale, and power realization. If I just back calculate the numbers, in this quarter, we earned almost INR 8 a unit on our power sale. Now, I heard on the call that almost 370 MW of our capacity, we have some long-term PPAs or mid-term PPAs for that, and I’m sure the rates for PPAs would be between INR 5 to INR 6. Is it fair to say that going ahead, as more and more PPAs are signed by us, the revenue per unit of power will keep declining? Hello, am I audible?

Unknown Executive

executive
#26

Yes, you are audible. Just hold on. I think Raipur disconnected. Can you connect them, please?

Operator

operator
#27

Yes, sir. I’ll just connect them again. Hello, sir. Am I audible?

Pankaj Sarda

executive
#28

Hello. Can’t hear you.

Operator

operator
#29

Hello. Am I audible to you, sir? Sir, I think the Raipur team is unable to hear us.

Unknown Executive

executive
#30

So then you do one thing. You may be...

Unknown Analyst

analyst
#31

Are they on mobile or are they on landline?

Unknown Executive

executive
#32

No, no. See you connect on the mobile. I'll just give you the number. Wait.

Operator

operator
#33

[Operator Instructions] Ladies and gentlemen, we have the management connected. Sir, you may proceed.

Unknown Analyst

analyst
#34

This is [Sugandh Haria]. Should I ask my question?

Unknown Executive

executive
#35

Yes, please.

Unknown Analyst

analyst
#36

Yes. Sir, my question is on the power -- on our power business. See, when I back calculate, I get that we have earned around INR 8 a unit on an average for this quarter, which is quite a good realization. But I heard on the call that almost 378 megawatts of our power plant capacity is going to be on long-term PPAs. And the rates there may be in that INR 5 to INR 6 unit. So would our revenue from this power plant keep declining as we sign more and more long-term PPAs?

Padam Jain

executive
#37

I think there is some understanding our current period income also includes the previous year adjustments. So the average realization calculated by you is not a correct one.

Unknown Analyst

analyst
#38

Okay.

Unknown Executive

executive
#39

Reverse calculation will not work because we have certain income for the previous period also.

Unknown Analyst

analyst
#40

Okay. Okay. Got it. Sir, but then going ahead, like we should generally assume for the full year, like INR 5 to INR 6 a unit on whatever electricity is generated and sold by us?

Unknown Executive

executive
#41

Yes, yes. It will be in between -- and over a period of time, it will go up. Over a period of time, as the inflation goes up and peak demand goes up, this will increase, particularly for the hydropower side.

Unknown Analyst

analyst
#42

Okay. Okay. Okay. Sir, and just I think this summer, it said that there was a lot of solar power in the daytime and which is why the daytime rates did not go up at all despite very high demand. So as Sarda Energy, how do you see this whole situation of excess solar capacity coming? And like will it hit us or that is precisely the reason why we are doing these long-term PPAs?

Unknown Executive

executive
#43

No. As the solar is increasing, at the same time, this BESS is also coming up. And there will be certain policy changes at the government level also when they may also give concessional power tariff during day hours to the industry or maybe charging stations and all those things, policy initiatives will also happen. So over a period of time, things will get balanced. But yes, definitely for the present time, during day hours, because of solar, power is excessive. And during the peak hours, the gas has gone up. So we are getting much higher prices during peak hours. And peak hour period has gone up from 5 hours to maybe 8 hours, 10 hours like that.

Unknown Analyst

analyst
#44

Got it. Got it. Got it. Okay. Okay. And in case of our hydropower, wherever our hydropower projects are, is there enough water like has it rained in the reservoirs which are there around our hydropower plants?

Unknown Executive

executive
#45

In case of our large hydropower plant of 113 megawatts, we have generated higher than the last year. We are at par even after closure of the unit for almost 13 days. So indirectly, we can say we have generated better than the previous year. But in case of smaller hydropower plants, there was a shortfall of water because there was a delay in the rainfall. Our generation was hardly 1% lesser than the previous year.

Unknown Analyst

analyst
#46

Yes. Sir, but next quarter, this -- like this quarter is the largest for our hydropower. So I was just checking if there has been anything.

Unknown Executive

executive
#47

Can you repeat your question?

Unknown Analyst

analyst
#48

Yes. My question is that, see, quarter 2 is the largest quarter for our hydropower generation. So I just wanted to ask if -- have the rains come and is the water adequate in the reservoirs from where this hydropower will be generated?

Unknown Executive

executive
#49

Yes, Rains are good. And July, we are getting far better rains in the smaller hydropower projects also.

Unknown Analyst

analyst
#50

Okay. Okay. Okay. Got it. And then my last question will be for this year, which is financial year '27, what will lead to, say, a growth in revenue or EBITDA? Because whatever projects we have on the coal mining side or in the power side, a lot of them are probably going to come later on. So is there any -- can we expect any growth in this current year?

Unknown Executive

executive
#51

One will definitely be the improvement in the power price realizations. Another is the improvement in the power capacity utilization in our IPP. These are 2 primary factors. And with the commissioning of our 30-megawatt power plant, there will be improvement in the generation.

Unknown Analyst

analyst
#52

Okay. And sir, you don't see any improvement on the metal side, like any.

Unknown Executive

executive
#53

Metal side, the production will go up with the commissioning of the 30-megawatt new power plant. Our total power generation will go up. That will definitely help in increased production of the steel side.

Operator

operator
#54

The next question is from the line of Manav Gogia from Yes Securities.

Manav Gogia

analyst
#55

Sir, my first question is pertaining to the INR 110 crore impact on the net profit that we have witnessed this quarter. Just wanted to get a sense of if you could give me the number of what the actual impact was on the top line and on the EBITDA level?

Unknown Executive

executive
#56

In the top line, in the revenue, it was INR 162.64 crore was added in the revenue side.

Manav Gogia

analyst
#57

Okay and...

Unknown Executive

executive
#58

There was an increase of about INR 18 crores on the other income in the form of interest. At EBITDA level, it I'll just give you the figures. Before tax, you can directly reduce -- add up 25% to the INR 110 crores. That is the EBITDA level effect.

Manav Gogia

analyst
#59

Okay. Net of tax, right?

Unknown Executive

executive
#60

Net of tax.

Manav Gogia

analyst
#61

Got it. Sir, just a follow-up. This INR 18 crores is the only number which is coming in to the other income because sequentially, we have seen a good jump in the other income from roughly INR 4 crores, INR 5 crores. So...

Unknown Executive

executive
#62

No, INR 18 crores is basically interest awarded along with the tariff. So that is added in the other income.

Manav Gogia

analyst
#63

Okay. Got it. So that is quite helpful. Second question, sir, comes pertaining to the PPAs. So out of 380 megawatts of PPAs that you already have in place, how -- what megawatt capacity would it be pertaining to SKS, roughly 200 megawatts, if I'm not wrong?

Unknown Executive

executive
#64

No, 330 megawatts approximately.

Manav Gogia

analyst
#65

Okay. 330 for SKS. And would you be able to give us a sense on what the tariff would be?

Unknown Executive

executive
#66

It is in between 5 and 6.

Manav Gogia

analyst
#67

Okay, between 5 to 6. Okay. And the maximum capacity that we are looking for PPAs for SKS, is it going to be 400, 500, or are we going to keep something as probably open quantity over there as well for sale?

Unknown Executive

executive
#68

Maximum quantity is 540 megawatt.

Manav Gogia

analyst
#69

Okay.

Unknown Executive

executive
#70

Now it's a call we have to take it to what extent we have to commit.

Manav Gogia

analyst
#71

Sure. Got it. That is helpful. So one last question I had was on the mining front. The PPT states that we are going to be reaching a coal mining capacity of 7.1 million, which includes the 2.1 million from Bartunga. My question arises the 5 million tonne target that we plan to achieve, what all mines would be there? Is it Gare Palma 4/7 is what we are aiming for? And if you could also give me the time line at which what procedures will be go from 1.8 million to 5 million?

Unknown Executive

executive
#72

So Gare Palma 4/7 is 1.8 million tonnes. 0.6 million tonnes will be from Shahpur West. 0.6 million will be from Sinduri approximate. This is provisional because it is under exploration. That may change. But assuming on the initial side, 0.6 million and 2 million will be from 4/5.

Manav Gogia

analyst
#73

Okay. Got it. And did not -- we didn't have any...

Unknown Executive

executive
#74

This has been in our presentation also. In our presentation at Slide #23, all details are made available.

Manav Gogia

analyst
#75

Yes, yes. No, no. That I'm aware of. I wanted to get a sense of -- because you were planning to expand Gare Palma 4/7 from 1.8 million to 5 million. I just wanted to get a sense of how that expansion is going to take place.

Unknown Executive

executive
#76

No. As of now, we are not considering in the immediate future. That is because we have got new mines with a better quality of coal, compared to the Gare Palma 4/7. For the time being, we are focusing on the new mines.

Manav Gogia

analyst
#77

Okay. And these new mines will be operational only post FY '28, right? Not no prior.

Unknown Executive

executive
#78

Shahpur will start in -- by end of current financial year. FY '27 by end of current financial year. FY '27.

Manav Gogia

analyst
#79

Okay. And the coal from Shahpur West will be usable for our SKS power plants or no?

Unknown Executive

executive
#80

No. That will be for our Sponge iron and ferro alloy plant, because that is high grade coal. For power plant, we don’t require high grade coal.

Manav Gogia

analyst
#81

Okay.

Nilay Joshi

executive
#82

Just to clarify, Manav, all the new mines, they are all high-grade coal mines. And Shahpur is like already told is starting in the current financial year. And Bartunga, we will open in the next financial year -- end of next financial year.

Operator

operator
#83

The next question is from the line of Deepika Rathore from NG Security.

Unknown Analyst

analyst
#84

Could you share the latest -- Hello.

Unknown Executive

executive
#85

Yes, we can hear you.

Unknown Analyst

analyst
#86

Could you share the latest update on the environmental clearance for the 600-megawatt brownfield expansion for SKS? And when do you expect construction to commence?

Pankaj Sarda

executive
#87

So the study that is required to submit our TOR is already over. We are in the final stages of making TOR. And as soon as we submit it, maybe in another 3 months, they will accept it looks like. And then maybe we have to go for a public hearing or -- and post public hearing, so maybe we have another 6 months to 8 months to get a final environment clearances. And post that, we'll be able to -- in the 6 to 8 months, we'll appoint a consultant also for the same. And then all the procedures will start.

Operator

operator
#88

The next question is from the line of Rajesh Bhandari from Nakoda Engineers.

Rajesh Bhandari

analyst
#89

[Foreign Language]

Unknown Executive

executive
#90

[Foreign Language] We are expecting to complete by FY '31. FY '31. So then we expect our turnover to be more than double, sir? Should be by the time.

Operator

operator
#91

The next question is from the line of Ashish from Bonanza.

Unknown Analyst

analyst
#92

Yes. So my question was regarding the Sikkim project. That was disrupted due to the transmission line. Has that project normalized post the restoration of the transmission line? Also, do you expect any.

Unknown Executive

executive
#93

Yes. We are producing at full capacity.

Unknown Analyst

analyst
#94

Okay. So there won't be any -- is there any residual impact during Q2, expected residual impact on Q2?

Unknown Executive

executive
#95

No, sir, it doesn't look like.

Operator

operator
#96

[Operator Instructions] The next question is from the line of Ashwini from [indiscernible].

Unknown Analyst

analyst
#97

I just had one question. Steel prices remained range bound during this quarter, while ferro alloy prices had improved modestly. So how do you see the pricing environment evolving in the second half of FY '27?

Unknown Executive

executive
#98

So both steel and ferro alloys prices, they look and they -- like we personally believe that they will be stable. And the margins may look to be a little more decent in terms of ferro alloys. And steel, it looks that it will be stable. And if so that we have a complete settlement in the West Asia region, we might see prices also going up because there will be demand pickup and more stable production centers in West Asia region as well.

Unknown Analyst

analyst
#99

Okay. Understood. Understood. Also, I had one more question. What were the specific right-of-way of challenges for the 50-megawatt solar project? And is there any execution risk beyond the revised commissioning time line?

Pankaj Sarda

executive
#100

There is a railway line coming in that region for which they are acquiring a lot of land. So we assume it has been notified already in that area. They are acquiring land. And I think in next 1 to 2 months, we should get permission from the railways for the same.

Unknown Analyst

analyst
#101

Okay. Okay. One last thing. I wanted to understand like guidance for PAT and EBITDA for FY '27, if you could just help with that as well?

Unknown Executive

executive
#102

Generally, we don't give any forward guidance. We have given the industry scenario and our project has already stated the current period -- current quarter prices are also better. As stated in our opening address also, July prices in the power have been better. So we are in a volatile market. So giving any guidance on the specific numbers is not advisable.

Operator

operator
#103

The next question is from the line of Vishal Patel from Patel Investments.

Unknown Analyst

analyst
#104

Firstly, sir, congratulations on good set of numbers. So I have a couple of questions. First is, excluding the impact of one-off items during quarter 1, how should we think about the normalized quarterly EBITDA run rate over the balance of the FY '27 as operational?

Unknown Executive

executive
#105

So second quarter is definitely better because of hydro generation. And we -- as stated, power prices are better, have been better in July, at least, whatever has already gone up as against last year INR 4.20 -- this year, it was INR 5 in IEX itself. So we expect the power prices to be better. Beyond that, it's very difficult to comment on the profitability side. Otherwise, as I already stated, with the commissioning of the 30-megawatt power, our steel volumes will also go up.

Unknown Analyst

analyst
#106

Okay. Sure. Sir, my second question is, with improving power demand and additional PPAs, how do you see PLFs and merchant realization evolving over the next few quarters?

Unknown Executive

executive
#107

PLF should definitely, if you see PLF at the annual level, PLF for the whole year for IPP shall be better than the previous year. This is what we expect. Last year, I think we had INR 415 crores. This time, we should be able to cross that with a reasonable margin.

Unknown Analyst

analyst
#108

Okay. Sir, could you quantify a little bit about this?

Unknown Executive

executive
#109

Pardon?

Unknown Analyst

analyst
#110

Could you quantify as in just surpass or like with a healthy growth?

Unknown Executive

executive
#111

As I stated, in case of IPP, last year, we had generated about INR 415 crores of units. This year, generation will be better than the previous year. And in case of captive power plant also with the commissioning of the 30-megawatt new generator, our capacity utilization will be better as compared to the previous year. In case of hydro, it depends solely on the rainfall. And as of June, our generation was almost at par with the previous year.

Operator

operator
#112

Okay, sir. The next question is from the line of Deepika Rathore from NG Securities.

Unknown Analyst

analyst
#113

So sir, with most of your major projects progressing as planned, what do you see as the biggest execution risk to achieving your FY '30 growth road map?

Unknown Executive

executive
#114

What is the biggest risk? As of now, there is no material risk we see, except there may be slight here and there because of the regulatory approvals. Otherwise, more or less the things are moving as what we have planned.

Operator

operator
#115

The next question is from the line of Reena Kaur from Starlome Investments.

Unknown Analyst

analyst
#116

So I just have 2 questions. One was now since everything is on track, like the 30-megawatt turbine replacement is commissioned, the Sikkim hydro project resumes normal operations and the maintenance shutdowns have also concluded. What do we expect earnings in Q2 becoming half yearly for FY '27?

Manish Sarda

executive
#117

As stated, we don't give any forward-looking profitability. because it depends on a variety of factors, rainfall data, power demand supply. There are multiple -- and in case of steel also prices are volatile because of the developments. So giving any specific number will be very difficult. But we have already stated on the operational front, we have already clarified. Operationally, it should be better. This is what we can tell.

Unknown Analyst

analyst
#118

Okay. And also on the steel prices, the steel prices remained range bound during the quarter, while ferro alloy prices improved modestly. So going forward, how do you see the pricing environment evolving in the second half of FY '27?

Manish Sarda

executive
#119

The prices will remain stable for both ferro alloys and steel. And in fact, the margins may be a little higher in the Ferroalloys segment as we are seeing some softening of raw material prices. And for steel, I think once the West Asia matter is completely settled and they have a peace accord, which is in reality in place, then we might see some uptick in the steel pricing as well. Plus overall, the steel demand looks to be very good because of domestic developments as well. We have very strong and robust domestic demand and with new developments of data centers and many other infrastructure projects, especially after monsoon, we see that the prices go up.

Operator

operator
#120

[Operator Instructions] The next question is from the line of [indiscernible] from Sunidhi Investments.

Unknown Analyst

analyst
#121

So I wanted to ask you on the Arunachal project. So actually, most of the approval has been received for 66 megawatts. So when do you expect construction to begin? And what do you think will be the expected time line for it?

Manish Sarda

executive
#122

So we are undergoing all the drilling and soil investigation. And we have also appointed a consultant. So as soon as those data are available, detailed engineering will commence.

Unknown Analyst

analyst
#123

Do you expect from this year or from the beginning of next year?

Manish Sarda

executive
#124

This year itself.

Operator

operator
#125

The next question is from the line of Priyansh, an investor.

Unknown Attendee

analyst
#126

I'm sorry if this question has been asked already, but I wanted to know that regarding the transmission tower that was recently lost, what is the loss that has been incurred in electricity generation pertaining to this? And consequently, what is the additional cost that was incurred to build it again? And are there any, let's say, steps in place to prevent this from happening again?

Unknown Executive

executive
#127

There is no material cost incurred on the restoration of the tower. Nominal cost is incurred and most of that will also be covered except the minimum excess loss that will be covered through insurance. Yes. But whatever generation we have lost for a few days, that was the real loss what we have incurred, which is already covered in the first quarter results broadly because started again. So there is an impact of 5 days generation in case of July. Otherwise, everything is already covered. And amount is not substantial. restoration cost is negligible, and that is also fully covered in the insurance.

Unknown Attendee

analyst
#128

Okay. Got it. And my second question was regarding the mineral wool project. What was the revenue of the mineral wool? And what is the sales and EBITDA target of mineral wool for the Q2 and the full financial year FY '27?

Manish Sarda

executive
#129

Can you repeat the question, please?

Unknown Attendee

analyst
#130

Sure. My question -- second question is regarding the mineral wool project. So what was the revenue of Mineral wool? And what is the sales and EBITDA target for the same for Q2 and the full financial year '27 -- FY '27?

Manish Sarda

executive
#131

So we have started and ramp -- we've been ramping up our production in the mineral wool. And in mineral wool, we are now touching almost 60%, 65% of our capacity. And once we achieve the full capacity in the coming year, in the next 3 to 6 months, we'll be achieving that full capacity, we should be able to give out the exact numbers. Right now, we are still identifying a few issues, and we are trying to resolve those issues. So right now, the project is not making any profits at the moment.

Unknown Attendee

analyst
#132

Got it. But is it making sales or not at this moment?

Manish Sarda

executive
#133

Yes. We are doing sales. There is a huge demand. There's a huge demand and there is -- we are making good sales. In fact, we are lagging in sales. The demand is more and our production is not ramping up due to certain imported equipments and machineries, which are stuck due to West Asia crisis and all. But we should be getting that in order. And probably in the next 6 months, we should be achieving full production.

Unknown Attendee

analyst
#134

Okay. But do we have any revenue figures right now?

Manish Sarda

executive
#135

We are expecting '27 -- for the year '27, we should be achieving around INR 90 crores.

Unknown Attendee

analyst
#136

INR 90 crores. Okay. And for Q2...

Manish Sarda

executive
#137

For Q2, it's very difficult to comment right now.

Unknown Attendee

analyst
#138

Okay. So the projection is the capacity utilization should ramp up from.

Manish Sarda

executive
#139

Ramp up in the next -- yes, in the next 2 quarters, and we should be able to achieve in FY '27, anywhere between INR 90 crores to INR 110 crores.

Operator

operator
#140

Thank you, everyone. That was the last question. Thank you, everyone. Thank you, management speakers. On behalf of Sarda Energy & Minerals Limited, that concludes this conference. Thank you for joining us, and you may now disconnect your lines.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Sarda Energy & Minerals Limited transcript — plus 251,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Sarda Energy & Minerals Limited earnings transcripts and 251,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.