Sempra (SRE) Earnings Call Transcript & Summary
May 7, 2024
Earnings Call Speaker Segments
Glen Donovan
executiveHello everyone, and thanks for joining us for Sempra's call covering results from the first quarter of 2024. You can access a live webcast of both this teleconference and the accompanying slide deck on our website, listed under Events and Presentations. Joining us on the line are a number of leaders from our management team: Jeff Martin, our Chairman and Chief Executive Officer; Karen Sedgwick, Executive Vice President and Chief Financial Officer; Trevor Mihalik, Executive Vice President and Group President of Sempra California; Justin Bird, Executive Vice President and Chief Executive Officer of Sempra Infrastructure; Allen Nye, Chief Executive Officer of Oncor; Peter Wall, Senior Vice President, Controller and Chief Accounting Officer; along with other senior leaders. Prior to getting started, please be aware that our discussion will include forward-looking statements as defined by the Private Securities Litigation Reform Act of 1995. Results we actually achieve could vary materially from what any forward-looking statement we share today projects. You can find the factors that might lead to materially different actual results described in the company's latest 10-K and 10-Q filings with the SEC. All earnings per common share figures in the presentation are presented on a diluted basis, and we will also cover certain non-GAAP financial measures. For a reconciliation of those to GAAP measures, please see the presentation slides accompanying this call. We'd also encourage you to look over our 10-Q covering the quarter that closed March 31, 2024. One more note: any forward-looking statements in this presentation are made only as of today, May 7, 2024, and it's worth noting the company takes on no obligation to update or revise any such forward-looking statements at any point in the future. With that said, please turn to Slide 4, and I'll pass the call to Jeff.
Jeffery Martin
executiveThank you, Glen, and I appreciate everyone being here today. We are happy to share the results of our first quarter. This represents an excellent beginning to the year and positions us favorably to deliver robust financial outcomes for 2024. Beyond how well we performed financially, conditions in the energy infrastructure marketplace remain highly favorable. Solid macroeconomic underpinnings are driving demand for U.S. energy, as the economy keeps expanding at a consistent rate, manufacturing output is improving, supply chain issues are loosening up, and jobs continue to be added. We have talked before about how our sector is in the middle of a growth super cycle, and we think Sempra's approach and asset mix are ideally suited to capitalize on these developments. Alongside the sustained need generated by reshoring and the shift of transportation toward electric power, AI and data centers are fueling fresh expansion in digital infrastructure, with projected requirements climbing threefold, from 2.5% of overall U.S. electricity usage to 7.5% come 2030. Texas is experiencing especially impressive growth, with ERCOT having just increased its projected peak demand for the close of this decade to more than 150 gigawatts. Notably, that figure exceeds the state's all-time high by 65 gigawatts.
Jeffery Martin
executiveAgainst the backdrop of strong industry fundamentals, Sempra offers several competitive advantages: To start, in California, we are leading the way on the energy transition, providing service to 25 million customers across the nation's biggest economy, which also ranks among the largest manufacturing hubs in the U.S. And via our general rate cases, we anticipate making fresh investments that back electrification and decarbonization, all while enhancing affordability, safety, and reliability. Now shifting to Texas, we're observing varied industrial, C&I, and residential expansion, which is generating jobs, boosting electricity demand, and calling for substantial investments to upgrade and grow the electricity grid. As the economy grows, grid safety and resilience grow even more essential, and that's partly why the system resiliency plan Oncor filed recently is so timely and significant. Allen will cover this more thoroughly afterward in today's presentation. And last, at Sempra Infrastructure, we're meeting worldwide demand for energy security and are in the middle of a second wave of LNG developments anticipated to support beyond 700 million tonnes per annum of demand by 2050. Our dual-coast LNG approach is fueling this effort with roughly 16 million tonnes per annum of new export capacity presently being built, which would more than double the LNG operating footprint we already have. The main point is we're eager about the opportunities ahead as Sempra Infrastructure aims to deliver cleaner and more dependable energy sources to its customers while setting a path for appealing built-in growth through the end of the decade; it's also worth noting that Sempra Infrastructure's growth forecasts rest only on projects that have achieved FID and are under construction and don't yet reflect anticipated upside from a series of other projects still being developed. Now moving to our financial results. We posted first quarter 2024 adjusted EPS of $1.34. Also, we're happy to reaffirm our full year 2024 adjusted EPS guidance range of $4.60 to $4.90 and 2025 EPS guidance of $4.90 to $5.25. As a reminder, if you examine our adjusted EPS guidance range from 2023 to 2025, it shows roughly 7% annual growth, which aligns with our long-term EPS growth expectations of 6% to 8%. Please go to the next slide, where I'll hand the call over to Karen for several business updates.
Karen Sedgwick
executiveThanks, Jeff. We've said before that 2024 is going to be a big year for execution across all our growth platforms, and I'm glad to share where we stand now. Over at Sempra California, the regulatory results keep looking favorable. Back in March, the CPUC put out a proposed decision backing the revised return on equity that took effect this year under the CCM trigger. The commission determined that the cost of capital mechanism is working the way it was intended, and that SDG&E's recently set return on equity of 10.65%, along with SoCalGas's 10.5%, ought to stay in effect through 2025 unless market conditions set off a trigger. What matters here is that this boosts regulatory certainty by confirming the safeguard the CCM gives both customers and shareholders; and the main point is that this marks yet another favorable data point for California's regulatory framework. Rate reform is another instance of that. Making things more affordable for every one of our utility customers sits at the top of our priorities. And I'm happy to report that in March the CPUC issued a proposed decision to put a fixed charge in place for residential electric customers. Under the proposal as it stands, this would bring volumetric rates down, back a fairer rate structure, and assist California in reaching its clean energy goals. We anticipate getting the final ruling during Q2 of 2024, after which the fixed charge should kick in around Q4 of 2025. Also in that quarter, together with the remaining California utilities, we submitted a joint application for projects that prove out mixing hydrogen into the natural gas network successfully. On isolated portions of that network, these efforts will begin blending at a rate as high as 5%, then step up the hydrogen share gradually, guided by safety considerations and technical viability. For many decades, hydrogen blending has been demonstrated as safe and dependable across the globe, and we're eager to collaborate with our partners on fresh and better approaches that advance decarbonization work within this state. Turning to the GRC, a proposed decision should arrive in Q2, with the final one landing sometime during this year. When that last decision is issued, its effect will reach back to January. To recall, securing that final decision gives us a definite regulatory route to carry out our capital plan aimed at utilities all the way through 2027. To wrap up, CAISO let SDG&E know it wouldn't be advancing on the Imperial Valley transmission line and substation. Worth pointing out that our approach to developing that bid kept financial discipline front of mind. We're eager to help the project succeed as it moves ahead, and also to get moving on the remaining transmission work CAISO handed directly to SDG&E. Now shifting to Texas: Oncor's service area keeps showing strong expansion. Only a month ago, ERCOT put out a refreshed transmission planning report projecting load in 2030 at roughly 40% above what last year's version anticipated. Then yesterday, Oncor completed its first-ever SRP filing, covering capital investments of about $3 billion. Apart from SRP, utilities across the state got a real boost from the 2023 legislative session. Here at Oncor, the benefits are already showing up in how we plan and carry out work that supports the state's goals while also improving when the company sees returns on its capital. Turning now to Sempra Infrastructure — we're genuinely excited about the opportunity to deliver cleaner energy to both our customers and our partners. Recently, we hit a positive FID on the Cimarrón Wind Expansion project. That effort demonstrates our ability to earn attractive returns by leveraging transmission capacity we already have in place to serve the California market, while also pursuing O&M efficiencies that come from our locational advantages. Beyond that, ECA LNG Phase 1 and Port Arthur LNG Phase I are both seeing solid progress. ECA is roughly 80% finished, and commercial operations should still kick off in summer 2025. Port Arthur remains on track too, with heavy construction work moving forward — including great strides in soil stabilization, newly built foundations, and the beginning of concrete pouring along with structural steel installation. Turning to marketing: LNG markets operate over long horizons, and while the DOE pause has gotten a lot of media coverage, we remain sure of our ability to complete projects that deliver secure, cleaner, long-term energy to customers. Sempra Infrastructure gains from seasoned project development teams that keep advancing critical work streams, among them permitting, engineering, and commercial negotiations. What's more, the pause just mentioned does not shake our confidence in how competitively our development projects are positioned overall, and we are deliberately using this period to methodically move our opportunities forward. Also worth noting, even if you consider only projects that have already reached FID, Sempra Infrastructure possesses remarkable built-in growth. With 16 million tonnes per annum of LNG export facilities, related infrastructure, and a new wind project now under construction, we are enhancing visibility into appealing earnings growth through the close of our planning period in 2028. And that is entirely separate from our development project pipeline, which Jeff mentioned previously and which provides meaningful upside. Let's now go to the next slide, where Allen will cover ERCOT's new planning processes.
E. Nye
executiveThanks, Karen. As we've talked about across multiple quarters, Texas keeps seeing robust demand growth. Oncor's customer base is now near 13 million, and we've moved past 4 million meters. To handle that growth, ERCOT has introduced a new planning approach, recently announced, that factors in greater anticipated power needs down the road. Back in April, ERCOT said peak load should hit 152 gigawatts by 2030 — almost twice the 85 gigawatts record from last year. Demand increases are arriving from many different industries throughout the state: new and expanded C&I, electrification of oil and gas operations, data centers, manufacturing, and residential. For context on how big this is, the shift between 2023 and 2030 would equal adding a load bigger than California's whole power market. Right now, we expect roughly 40% of that added load to land within Oncor's service territory. So for us, as one of America's leading builders of T&D infrastructure, we're eager about the chance to keep growing our electric infrastructure investments. Since 2018, Oncor has built roughly 13,000 miles of transmission and distribution lines — about 6 miles each day. We have an active planning effort in motion and feel confident we can obtain the materials and labor needed to serve our customers in the ERCOT market. Let's move to the next slide. With the state growing as it is, resiliency matters more than ever. In 2023, the Texas legislature passed House Bill 2555, letting electric utilities submit system resiliency plans that propose capital and operational expenditures aimed at improving overall grid resiliency; yesterday we submitted our first filing, covering approximately $3 billion of new capital expenditures along with just over $500 million of operating expenditures, spread across a period of 3 years; this investment would tackle overhead and underground system resiliency and modernization, a flexible and self-healing distribution system, vegetation management, wildfire mitigation, and cyber and physical security. To add some further detail, most of what we propose to spend goes toward modernizing and hardening older sections of our distribution system by adding lightning protection, stronger class poles and cross arms, and addressing parts of the grid with capacity constraints during extreme temperatures. Beyond that, we're proposing sizable technology and infrastructure investments that would help make it possible to automatically reconfigure our system when extreme storms strike, restoring service quickly to customers on undamaged segments by rerouting power intelligently. I'd also note that we've put money into wildfire mitigation for many years, including working effectively alongside industry leaders such as SDG&E and the Texas A&M Forest Service. Now, because of HB 2555, Oncor has one more opportunity to further speed up our wildfire mitigation strategies throughout our service territory. Our projection is that roughly $900 million from the overall proposed outlay, covering both CapEx and OpEx, is going to be directed toward growing our wildfire mitigation resources and putting our grid modernization and hardening initiatives into practice across areas prone to wildfires. On the procedural side, the SRP statute gives the PUCT 180 days to examine the filing, and our expectation is a decision before the year finishes. If approved, the SRP program, carrying about $3 billion in capital expenditures, would come on top of the $24.2 billion of planned CapEx Oncor announced earlier this year covering the 5-year period 2024 to 2028. Our view is that the proposed SRP opens the door to meaningfully enhancing customer reliability and overall customer service throughout and following extreme weather events, while additionally assisting in reducing other risks. At this point I'll hand the call back to Karen so she can take you through Sempra's financial update.
Karen Sedgwick
executiveAppreciate that, Allen. Sempra today posted first quarter 2024 GAAP earnings of $801 million, which works out to $1.26 per share. Against that, first quarter 2023 GAAP earnings stood at $969 million, or $1.53 per share. Turning to adjusted figures, first quarter 2024 earnings came in at $854 million, or $1.34 per share, compared with $922 million, or $1.46 per share, in the first quarter of 2023. Let's move to the following slide. The first quarter 2024 adjusted earnings variances versus the same period a year ago break down this way: at Sempra California, we saw $24 million, mostly driven by higher net interest expense and lower income tax benefits, plus $12 million of lower CPUC base operating margin, net of operating expenses, which was offset by a higher authorized cost of capital. Let's go to the following slide. The first quarter 2024 adjusted earnings variances versus the same period a year ago break down this way: Keep in mind that since our GRC remains pending, CPUC revenues for first quarter 2024 continue to reflect 2023 authorized levels. That matters because any true-up later in the year gets applied retroactively to January 1 once the final decision is approved. Moving on to Sempra Texas, we recorded $56 million of higher equity earnings tied to rate updates, increased invested capital, and consumption, partly offset by higher interest and operating expenses. Over at Sempra Infrastructure, we had $13 million of lower transportation revenues and higher O&M, partly offset by higher power results, along with $27 million of lower asset and supply optimization, partly offset by lower net interest expense from capitalized interest, lower taxes and other. One note: starting this year, waterfall numbers are shown after noncontrolling interest to improve comparability. At Sempra Parent, the $48 million quarter-over-quarter change stems mainly from higher taxes due to the interim period application of an annual forecasted consolidated effective tax rate, which we expect to reverse over the course of the year. Let's turn to the following slide. Before wrapping up our prepared remarks, I'd like to lay out Sempra's value proposition as we carry out our corporate strategy. Here at Sempra, our management team stays committed to challenging the status quo across every aspect of how we run the business; we provide exposure to growth in some of North America's largest economic markets. Our standing as a leader in infrastructure development within these markets translates into a record $48 billion capital campaign through 2028. Beyond that, we pursue energy infrastructure investments targeting attractive mid-teens returns on equity, and we recognize that disciplined capital allocation sits at the center of our success. We also recognize how important it is to return capital to our owners and expect to keep growing our dividend. Notably, we've successfully grown that dividend at a rate of roughly 7% annually over the last 10 years. That's especially worth highlighting, given the expected strength of our future earnings growth. In closing, what our industry does matters more and more to society, and here at Sempra, we feel enthusiastic about what lies in front of us. Sempra sits in a competitive spot that lets us seize opportunities, and we will keep putting money into our workforce, handle risks with care, fund our operations efficiently, and act as responsible caretakers of the capital placed in our trust; we appreciate your presence, and at this point I want to turn the line over for your questions.
Shahriar Pourreza
analystPerhaps to begin with the sort of additional positives that are beginning to accumulate relative to the plan for the fourth quarter, including at SIP and the SRP in Texas. I suppose, does the financing plan already in place have capacity to back the spending across '25 through '27? And might you consider drawing on some of SIP's balance sheet capacity to reduce possible equity requirements stemming from extra CapEx that we might see ahead?
Jeffery Martin
executiveYeah, thanks for asking that, and I'd say our balance sheet looks solid. Shar, I want to remind everybody that we've got a history of funding our expansion in an efficient way, and as you're aware, that's contributed significantly to what we've achieved since 2018; in fact, across the past 5 years, we've managed to increase our adjusted EPS at an annual growth rate of about 10%. As you know, under the plan we have right now, we expect to put roughly $48 million into investments between now and 2028. We definitely believe there are chances to keep building on that plan. But I'd also point out, Shar, that long before we made our capital plan public, we took care of our equity needs last fall; so the main point is that we're sitting in excellent shape, with no requirement for more equity. We've got strong visibility into the growth ahead of us, and I believe you mentioned a few levers available for us to use. And we've got a plan ready that ought to let us formally fund our growth.
Shahriar Pourreza
analystGreat. So the balance sheet works for you, and if there's additional CapEx on the way? That's useful, Jeff.
Jeffery Martin
executiveYes, we are.
Shahriar Pourreza
analystGreat. So, with California's cost of capital decision now confirmed, how do you intend to account for the CCM's effects? Will there be some kind of customer reinvestment program? And do you expect to share an update on California Utilities' earnings following the PD?
Jeffery Martin
executiveYeah. I believe an opportunity is going to emerge once we work through our rate case. As you remember, we anticipate receiving our proposed decision later in this quarter, plus a final decision when the year ends. Those sorts of matters would get reconciled on the earnings call that follows, possibly in Q3 at the earliest, so we can deliver genuinely clear visibility into how the rate case affects our forward earnings.
Jeremy Tonet
analystNow regarding Texas, I wanted to ask whether you could put this newest ERCOT load growth projection in context with the prior capital plan that Oncor increased. Does the amount of system investment being considered line up with that load growth? Or might there be additional upside still coming? If that's the case, when do you believe it could be incorporated into the plan?
Jeffery Martin
executiveAlright, that's really a great question. Obviously, ERCOT released its latest figures roughly a couple of weeks ago. Allen brought this up in his prepared comments, but it's pretty striking that you could look at the peak demand load in California, which is the biggest economic region in the country, and compare it with what Texas is expected to add between now and 2030. The important point Allen has made previously is that ERCOT sits right at the center of this growth narrative, correct? So when you consider where growth might come from, we believe somewhere in the range of 40% to 50% of it would land in his service territory. Allen and his group will definitely have their strategy reviewed when fall arrives.
Jeremy Tonet
analystUnderstood. That's quite useful. Then, probing a bit further on the SRP, I was simply curious whether you might roughly frame what this effort will achieve across the coming 3 years compared with the broader resiliency requirements you observe within the system.
Jeffery Martin
executiveSure, I'll offer a few remarks to set some context, then pass things along to Allen. Their first filing came in just yesterday. As you're aware from what we've shared, that's $3 billion spread across 3 years. At Sempra, one aspect we find compelling — much as with every investment we pursue throughout our various growth platforms — is that this initiative is designed to strengthen our system so it can handle severe weather, cut down how long outages last before restoration, and boost reliability as a whole. I'd add too, Jeremy, that this capital being requested sits on top of what Oncor already has in its capital plan. That said, Allen, something that could help, and I believe this gets right at the core of the question, is whether we might step back and discuss your broader $24 billion capital plan. Why does the SRP component matter so much? And perhaps I'll come back to the value proposition for your regulator.
E. Nye
executiveAbsolutely, Jeff. I appreciate the question, Jeremy. To return to what Jeff mentioned regarding our initial — our existing 5-year capital plan currently sits at $24.2 billion. Broadly speaking, that splits into roughly $5.1 billion allocated toward distribution expansion, approximately $13.5 billion directed at transmission expansion, $4.2 billion for maintenance purposes, and around $1.4 billion for technology; and once more, as I've noted previously, that shows roughly 70% of our capital plan represents growth. At least 97% of our capital plan can be recovered via our trackers, which gives us at this moment what we consider a highly robust, industry-leading rate base CAGR near 11%. Of course, that figure predates the SRP and whatever ruling the commission eventually makes regarding our SRP; we believe — we're quite enthusiastic about the plan we submitted. In my view, our team has performed excellently in crafting a very strong plan that will deliver, I believe, meaningful advantages for our customers. And if I may, I can elaborate a bit further on what we filed. Our SRP generally falls into 6 main categories. The first covers overhead and underground resiliency and modernization. That encompasses items such as new and repaired poles, cross arms, lightning protection, greater capacity for high demand days, rehabilitation or replacement of underground conductor. So within that initial category, that amounts to roughly $1.830 billion for the first category. Our second category involves continued optimization of distribution automation. What we mean there is expanding our distribution automation program via new ties, added capacity and the introduction of intelligence switches. And we have approximately $510 million in that bucket. The third category is expanded vegetation management, or VM. We'll carry that out mainly across a number of lateral circuits, and we'll utilize remote sensing capabilities like satellite and LiDAR to better steer our VM program going forward through this program; we have roughly $285 million set aside to expand the VM within this plan. Fourth category is enhancing our cyber risk management. That covers all cyber risk-related mitigation efforts along with security enhancements tied to Oncor's digital backbone. And we have approximately $525 million designated for that category. Fifth, improved physical security. Like all utilities, many across the country, we're confronting additional intrusions and risk to our physical assets. So we have roughly $80 million designated in our plan for items such as — video and event correlation systems to assist law enforcement along with general asset protective measures aimed at better safeguarding our assets and equipment. And we have approximately $80 million in that category. Lastly, we have around $900 million total in the plan, but approximately $182 million specifically tied to wildfire mitigation measures. That would encompass items such as strengthening and protection of assets in higher-risk wildfire zones, safe device deployment, advanced wildfire risk modeling, overhead and underground resiliency measures and once again, increased distribution, automation in higher wildfire risk areas. And then, as a final point on that last item, it's really an extension of the wildfire risk reduction and prevention efforts we've been pursuing for several years now. But thanks to roughly $900 million more that we've set aside for this category within this plan, we believe we can achieve genuine progress on that issue, along with the others I mentioned.
Jeffery Martin
executiveAllen, if you could, perhaps to build on what Jeremy was asking about, I don't want to speak on behalf of your regulator, but might you just lay out the value proposition that in your view this plan is going to provide?
E. Nye
executiveWell, absolutely, Jeff, and I believe you put that quite nicely. And I've mentioned on earlier calls that I see this — and I think we see this — as a once-in-a-generation chance to actually make direct changes to our system that would serve our customers in the ERCOT market well. And I think every one of these categories would deliver quite particular gains, ranging from resiliency to wildfire avoidance and prevention to improved reliability — all matters that would help our customers in a very direct way.
Jeffery Martin
executiveThank you.
Durgesh Chopra
analystCould you possibly just share what you're thinking regarding that hold on the FDA clearance, and in what way do you expect that to move forward?
Jeffery Martin
executiveAbsolutely, and thanks for bringing that up, Durgesh. Two points immediately spring to mind for me. The first one is our belief that this permitting halt is only a short-term situation, and approvals are going to come through down the road. After all, a lot of you have been tracking what was said over at CERAWeek. Secretary Granholm, as I recall, has now stated on multiple occasions that she expects this matter to be behind us sometime in early next year. The second point I'd raise is a reminder that the only real effect here lands on Port Arthur Phase 2. We already hold current Department of Energy non-FDA permits covering Cameron Phase 1, which is up and running, ECA Phase 1, and Port Arthur Phase 1 — the latter two are both being built — plus Cameron Phase 2, ECA Phase 2, and Vista Pacifico. So the direct hit here really is just Port Arthur Phase 2, and our expectation is to get that sorted out in early next year. Worth mentioning too that Justin's group keeps plugging away at moving Port Arthur Phase 2 forward, and our view remains that it carries enormous commercial worth. That said, I figured it could be useful to circle back to what we regard as the key elements of our LNG approach. We've got strong LNG development projects in the pipeline, clearly counting the Port Arthur build-out among them. Their locations give them an edge. Nobody else developing this space can tap Asia directly while also sending volumes into the Atlantic by way of the Gulf. The following 2 projects lined up benefit from sitting on brownfield land — one more cost advantage for us when it comes to Port Arthur Phase 2 and the Cameron expansion. On top of that, we're moving these forward with discipline, with our shareholders in mind. Also worth pointing out: these represent potential additional value beyond our present $48 billion capital plan, and they're likewise upside relative to our long-term growth rate.
Durgesh Chopra
analystThanks for laying all that out, Jeff. I believe you've already addressed what I was about to bring up. I wanted to know if there's a schedule we ought to keep in mind when you're evaluating a final investment decision — whether that applies to Port Arthur Phase 2 or the Cameron expansion.
Jeffery Martin
executiveAbsolutely, and there are a couple of points I want to bring up. First, for the Cameron expansion, our expected FID has been guided to the first half of 2025. As for Port Arthur Phase 2, we haven't established an FID expectation at this point. That said, I can tell you Justin's team is still moving forward at a steady pace. What I mean is, with each quarter that passes, we keep advancing and commercially developing those two projects, and I believe the momentum within our company keeps growing around their broader success.
Durgesh Chopra
analystExcellent quarter, guys.
Jeffery Martin
executiveThank you so much.
Carly Davenport
analystI'd like to circle back to the SRP filing for a moment. The level of detail provided so far is genuinely appreciated. I was hoping to understand how we ought to frame the timing and the cadence of that spending, on the assumption that the plan takes effect sometime in the 2025 time frame; and then, if you could just remind us how you expect this to unfold procedurally between now and year-end?
Jeffery Martin
executiveAbsolutely. I'll begin with the process-related item, and after that I'll hand things over to Allen so he can discuss what he anticipates happening with that capital moving ahead. Clearly, the filing was submitted yesterday, something that was envisioned under the legislative bill that was enacted last year. By law, the commission gets 180 days to examine and give approval to that filing. As things stand, then, our expectation is that we'll have it by the fourth quarter. As for how it gets deployed, that's spread across 3 years. And perhaps, Allen, you could speak to it looking forward — your view on how that capital might come in, naturally contingent on the commission's approval and the final figure.
E. Nye
executiveAbsolutely, Jeff. To put it plainly, those expenditures are essentially for the years 2025, 2026, and 2027, with a bit more weighted toward the later part.
Carly Davenport
analystUnderstood, that's helpful. Now, as a follow-up, you've discussed quite a bit these strong load growth possibilities in Texas that are backing infrastructure investment. Could you speak briefly about whether you're encountering any kind of supply chain issues or other limitations when it comes to carrying out that T&D build out at Oncor?
Jeffery Martin
executiveYeah, I touched on this during my prepared remarks. Some areas still have supply chain constraints, but overall, we're clearly seeing load growth in every market we serve, and the supply chain problem has eased somewhat. I believe Oncor especially — and Justin and I both sit on their Board of Directors — has performed really well in terms of going out into the marketplace and locking down the right contractors and hard goods. But Allen, maybe you could speak to what the team has accomplished; and across what span of time do you believe you now have everything you need secured?
E. Nye
executiveAbsolutely. Yeah, Carly, that's an excellent question. As Jeff mentioned, over at Oncor, our operations team along with the folks handling our supply chain have been preparing to carry out this plan for a good while now. We've taken several steps, such as broadening where we source from and bringing on more vendors 5 and 6 years back, which has gotten us to a point where — even though there are definitely challenges in the supply chain out there — we have a lot of confidence about the first 2 years. I've told my Board this. I'd say the first 2 years are basically locked in, in terms of what we need on the equipment side and the vendor side. We've also made really substantial headway on the remaining 3 years; right now we're filling in the gaps and holding off on handing out things like engineering studies. Those haven't been finished for the later years since we wouldn't hand them out until we know precisely what we're dealing with. Still, I think we've handled supply chain problems quite well, and we're feeling really good about our current position.
Jeffery Martin
executiveAlso, Carly, the sole additional point I'd put alongside what Allen said is to consider his base capital plan — a bit above $24 billion — which is genuinely built around expansion, and more precisely, tilted toward transmission. So about 60% of that outlay goes to transmission. That, in my view, explains why this SRP filing matters so much. It genuinely establishes another avenue for growth, one focused on adding redundancy and resiliency into the system, something just as vital for the state of Texas.
Steve Fleishman
analystOnly a single question from me. I believe Conoco may have mentioned some interest in offloading part of their Port Arthur stake, though I didn't personally come across that, so I'm just wondering what you're picking up on their end.
Jeffery Martin
executiveSure, let me offer a few thoughts on that. First, Steve, at Port Arthur, Conoco stands as a highly significant strategic ally for us. I'd point out that we hold their leadership group in considerable esteem, and we definitely enjoy excellent ties throughout both organizations, plus what I see as a solid shared alignment of interests — and that's the crucial element when it comes to both Phase 1 and Phase 2. So the question of whether they choose to commit fresh capital to Phase 2 remains undecided. That's really something I'd direct to their leadership group. Still, keep in mind that during the initial phase, they purchased about 50% of the offtake, or 5 million tonnes per annum, they hold 30% of the equity at the project level, and on top of that they serve as gas manager for that first phase. Regarding the second phase — this is vital background — I think it matters a great deal to Conoco, since Phase 2 will draw gas supply, Steve, out of the Permian Basin, which carries major strategic implications for numerous commercial players, and that holds especially true for ConocoPhillips. So I'd simply point out that this is something where we're coordinating closely with many counterparties eager to partner with us on making Phase 2 a success. And given the discussions taking place right now, we remain extremely enthusiastic about proceeding with that project.
Anthony Crowdell
analystLet me add to what Carly asked, if I may. Her question was perhaps more narrowly focused on the supply chain serving the regulated utility. When I look at the Infrastructure segment, especially regarding Port Arthur 2 and Cameron Phase 2, are there any significant shifts or revised estimates showing up in the E&C contracts that Bechtel might be examining?
Jeffery Martin
executiveSure. Anthony, it might be useful if Justin gives us a quick update on construction and also explains what’s being done to lock in some long lead time items on the projects that are focused on the near term, and that could help with his question.
Justin Bird
executiveRight, right. Hello, Anthony, and thanks, Jeff. Okay. I'll begin with construction, and after that I'll get into the core of what you asked. We're making good headway on the build at ECA Phase 1 as well as Port Arthur Phase 1. I've been able to see both locations lately. Jeff and I visited ECA only 2 weeks back to watch construction. And I was at Port Arthur not long ago for the 1-year commemorative groundbreaking. Neither project has fallen behind schedule. Supply chain problems aren't showing up for us. At ECA Phase 1, COD in the summer of 2025 is still on schedule. We've now passed 80% completion. Building work continues throughout every part of the project. Roughly 4,000 workers are stationed there, and we've logged more than 15 million hours with zero lost time incidents. At Port Arthur Phase 1, where Bechtel is involved, the construction work is coming along nicely. As Karen said in her remarks, our attention is on the foundation stage construction, soil stabilization, piling, and concrete pouring, and it's great to see that structural steel has just begun. Turning to our development projects, we're still enthusiastic about them. Market interest remains strong, and we do expect these projects to move ahead. Regarding construction contracts or progress at Port Arthur Phase 2, while we wait for our DOE non-FDA export permit, we keep working alongside Bechtel on an EPC agreement capable of optimizing efficiencies alongside the Phase 1 construction schedule. We're also still pursuing marketing efforts for offtake and equity. On Cameron Phase 2, we're presently collaborating with the Cameron partners to optimize cost through value engineering. And as Jeff noted, we're additionally looking into procuring or reserving long lead time and critical path equipment. Cameron Phase 2 is a relatively low emission project, and it's a brownfield asset sourcing low-cost gas. So we believe this matters a great deal. And as Jeff said earlier, we're pushing that forward with an eye toward taking FID in the first half of 2025. As a takeaway, I suppose, I mention the reverse Field of Dreams model: when they come and when we get the right returns, we'll build it. Following that logic, we'll only proceed with our projects once we have the right cost and risk structure and long-term contracted cash flows that back our corporate strategy, our targeted mid-teen equity returns, and create value for our shareholders.
Jeffery Martin
executiveAnthony, to get right at the core of what you're asking, our relationship with Bechtel is a strategic one. In the Gulf, they're extremely, extremely useful — pretty much the top outfit around. That's the reason Justin spoke about how important it is that we don't demobilize Phase 1 and instead move straight into a continuous build for Phase 2 at Port Arthur. I'd add as well that his team has master purchase agreements locked in with every one of the key vendors. Plus, there's considerable attention paid to ensuring we source the critical equipment and, in particular, to planning ahead for long lead time items. So all of that fits within how we handle risk, so that we deliver projects generating the proper risk reward for our owners.
Anthony Crowdell
analystSo if I could ask just one more question — I realize Cimarrón Wind represents only a tiny piece of SIP. This business has done really well when it comes to recycling capital, and a few years back it sold off a renewable portfolio. That was a very opportunistic move. So at this point, should we be expecting additional wins to show up, or more renewable assets arriving as a renewable portfolio gets rebuilt alongside SIP? I'll stop there.
Jeffery Martin
executiveSure, I can give you some background on that, since we're pretty enthusiastic about this project. Anthony, let me begin with the fact that we introduced our new corporate strategy during 2018, and at the core of it was a tighter focus on two things. The first was creating leadership and scale advantages in big economic markets. The second was investing more narrowly within the energy value chain in T&D-style infrastructure investments such as Cimarrón, where we're able to generate highly recurring cash flows. If you apply that corporate strategy to Mexico, we established a leadership position there dating back to the 1990s; it's a market with more than 130 million consumers. When I took over as CEO during 2018, Anthony, it ranked as the 15th largest economy worldwide. As of today, the IMF ranks it #12 globally, and PricewaterhouseCoopers is now projecting that by 2040 it will be #7 worldwide. It also happens to be our biggest trading partner, with an energy network that is deeply integrated with the United States. That aligns really well with our strategy along the border, and in particular the wind projects you're referring to are situated directly along the U.S. border and represent an expansion of a very large ESJ wind complex that we already own. It's electrically integrated with a high-voltage system and does serve California, and it's being constructed using SI's operating cash flows from Mexico. So I believe the main takeaway here is — and we've mentioned this multiple times in our prepared remarks — that there is a very strong built-in growth story at SI based on projects that have already reached FID, and the opportunity presented by this land position we hold next to California is to efficiently and cost effectively develop additional solar and wind to serve the California market, which is integrated with Mexico, and to fill in and keep enhancing that recurring cash flow growth story Justin has been discussing.
Craig Shere
analystI want to build a bit on what Anthony asked first regarding labor and LNG markets, and then turn that into a wider question for Justin. Over the past 2, 3 months, a few peer projects have come out with possible delays and problems finding unskilled workers. Along those same lines, you've reported growing demand across your domestic utility networks and T&D networks coming from data centers and AI, plus coal-to-gas fuel switching and other drivers. We've also observed the LNG markets steadying and bouncing back, with a sense that the digestion period everyone anticipated for the second half might turn out mild and brief, or perhaps never arrive. Given how things have shifted during these last 2, 3 months, I'm curious whether you're picking up on any difference in body language and in the appetite to seize the day with potential off-takers.
Justin Bird
executiveAppreciate that, Craig. You brought up supply chain and labor, but I want to address the core of what you asked at the end. Regarding the LNG pause, there was a window there for the market to adjust, I'd say. Some players pulled back, perhaps with somewhat less urgency than they showed during the Ukraine war. That said, as we've mentioned several times on this call, the commercial appetite for our projects, our expansion opportunities, remains strong. We've proven to be a reliable partner. So interest is robust, and at present, teams worldwide are in active commercial negotiations for long-term contracted volumes.
Jeffery Martin
executiveCraig, I'd like to add something as well — thanks for asking that. When it comes down to making the most of the moment, my money's on Justin and his group. The strides we're making with LNG have us genuinely enthusiastic, and we can't wait to share more news down the road. To begin, I want to express my gratitude to all of you for being here today. Given that there were other calls happening this morning, we're grateful you took the time to spend with us. Like Karen said, we firmly think our value proposition is a strong one, combining a solid growth narrative with income. Sempra's long-term prosperity is something our leadership is dedicated to, and we see a tremendous chance ahead to keep breaking new ground and discovering improved, more effective methods of serving customers, all while generating robust financial returns for our shareholders. Should anything else come up that you'd like to discuss, please get in touch with our IR team, and we hope to see all of you in California for AGA on May 20 and 21; that wraps up our call.
Operator
operatorThank you for your participation. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Sempra transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Sempra earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Sempra or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.