Operator

operator
#1

I appreciate everyone joining us today. Good afternoon. I'm Ina, and I'll be serving as your conference operator for this session. Right now, I'd like to extend a welcome to all of you on behalf of Silvercorp as we present the First Quarter Fiscal 2027 Financial Results Conference Call. <<operator_script>> At this point, I'll hand the conference over to Lon Shaver, President of Silvercorp. Please go ahead.

Lon Shaver

executive
#2

Thanks, Ina. Silvercorp would like to express appreciation to all of you for being on today's call to go over the financial results for Q1 of fiscal 2027, which we released yesterday afternoon. The news release, the MD&A and the financial statements can all be found on SEDAR+. Before we begin, please be aware that some statements made on this call will include forward-looking information as defined under securities laws. In addition, we ask that you review the cautionary statements contained in our news release and the risk factors outlined in our latest regulatory filings. Let's begin with the financial results. We posted a strong first quarter even with the temporary production slowdown at our Chinese operations tied to the safety upgrades that started in June. Revenue climbed 70% year-over-year to $139 million, while cash flow from operating activities and free cash flow came in at nearly $62 million and $29 million, respectively, which was up 28% and 27% from the prior year. This performance was primarily driven by a 135% rise in the realized selling price of silver, which averaged above $69 an ounce after smelter deductions. And silver made up 77% of our revenue in Q1. We reported net income of $59.4 million for the quarter, or $0.27 per share.

Lon Shaver

executive
#3

That figure includes an $11 million gain on investments plus a $6 million gain from selling the Santa Barbara project in Ecuador. Taking out noncash and nonrecurring items, adjusted net income for the quarter came to $53.9 million, or $0.24 per share, versus $21 million and $0.10 in the comparative quarter. Cash flow from operating activities before changes in noncash working capital was strong at $70.4 million, an 82% increase over last year. In the quarter, roughly $22 million was spent and capitalized at our China operations, $12 million at the El Domo project in Ecuador, and $2.6 million at the Chaarat ZAAV project in Kyrgyzstan. Also, in May we paid $60 million in cash to the Kyrgyzstan government after the new mining license and license agreement for ZAAV were issued, which adds 20 years to the license term, extending it to June of 2062. Our strong balance sheet gives us significant financial flexibility as we move forward on our growth strategy. We closed the quarter with $387 million in cash, excluding investments in associates and other companies, whose combined market value was $304 million as of June 30. Additional funding is available to us through the RMB denominated term loan facilities we signed, totaling approximately USD 220 million, which remain undrawn.

Lon Shaver

executive
#4

Turning now to a review of the operating results we announced in July. In the first quarter, we generated roughly 1.5 million ounces of silver, more than 2,500 ounces of gold, 13 million ounces of lead, and 4 million pounds of zinc. Gold output rose 24% versus last year, whereas silver, lead, and zinc production fell 17%, 15%, and 15%, respectively. At Ying, production was affected by lower head grades, which reflect greater dilution tied to the move toward more shrinkage mining. Additionally, on June 29, we announced a voluntary suspension of operations at both Ying and GC so that a comprehensive safety self-review could be completed. That decision came after new nationwide safety requirements were rolled out across China's mining industry following a major accident in the country in May. Through this process, we pinpointed areas needing upgrades to comply with the new regulations and brought on 5 certified vendors to carry out the 6 major underground safety system upgrades. Safety has consistently been our highest priority. Although these upgrades are temporarily affecting production, they represent an important investment in our operations, and we anticipate coming out of this process with mines that are even stronger and safer. Consolidated mining operating income for the quarter was $84.8 million, with Ying contributing $80.1 million, or approximately 95% of the total.

Lon Shaver

executive
#5

Now on to costs. At Ying, production costs came to an average of $87 per tonne, which was 5% higher year-over-year. The main factor behind this rise was a 6% depreciation of the RMB relative to the U.S. dollar. Even so, production costs stayed under our annual guidance range of $88 to $90 per tonne. Ying's cash cost per ounce of silver, net of by-product credits, was $2.45, versus $1.26 in the prior year quarter. That's mainly because silver sold in the quarter fell 15% and because of the stronger RMB I mentioned, partly offset by a $3.8 million increase in byproduct credits. All-in sustaining production costs at Ying were $130 per tonne, essentially flat year-over-year and below our annual guidance range of $155 to $160 per tonne. On a per ounce basis, Ying's all-in sustaining cost, net of by-products, was $13.94 an ounce. That's up 30% year-over-year, and the increase reflected the same factors impacting cash costs but also a 60% -- 68% increase in government taxes, which was driven by the higher revenue that we reported. Turning to our growth projects. At Ying, capital expenditures totaled over $16 million in Q1 for underground development and drilling, mainly aimed at improving underground access and material handling to boost productivity.

Lon Shaver

executive
#6

Work at the Kuanping Project, located north of Ying, centered on underground advancement to reach the ore. That project holds a permit allowing output of as much as 200,000 tonnes of ore annually. During this fiscal year, we'll send a portion of nominal development ore to be milled at yen. Thanks to capacity expansions across the existing Ying permit areas in Kuanping, our permitted mining capacity will reach roughly 1.5 million tonnes per year. Preparing for greater mine output, we've started building a new mill — the #3 mill. Capex came to $300,000 for the quarter, with foundation treatments and the elevated water tank now underway. That mill should contribute 3,000 tonnes per day of capacity and is slated for commissioning in Q1 of fiscal 2028. Turning to Ecuador. At El Domo, construction kept moving forward in Q1 even with unusually heavy rainfall. On infrastructure, the noncontact water channel, processing plant foundation work and the initial tailings storage facility dam construction all advanced, with over 600,000 cubic meters of earthworks finished. At the same time, open pit pre-stripping is in progress, and efficiency is rising through added large-scale equipment, expanded operating areas and road upgrades. Beyond that, major equipment for the processing plant and water treatment plant has been purchased and is being shipped to Ecuador.

Lon Shaver

executive
#7

T.G.J.A. has been given the construction contract for the plant; it's a contractor with solid experience that completed the 80,000 tonne per day flotation mill at the Mirador copper-gold mine in southern Ecuador not long ago. Now turning to Condor. Permitting work is ongoing, and the formal consultation process with the communities directly impacted is currently in progress. That represents the last step needed to obtain the small-scale environmental license, which we anticipate receiving later this quarter. After we get it, development will begin on two 1,500-meter exploration tunnels at the Camp and Los Cuyes deposits, which will support underground drilling and move exploration and resource definition forward. In Kyrgyzstan, we've also achieved substantial progress since acquiring Chaarat ZAAV in January. That's a joint venture company holding the Tulkubash and Kyzyltash gold projects, and it is 70% owned by Silvercorp, with us serving as operator, while the remaining 30% is held by the state mining company, Kyrgyzaltyn. At Tulkubash, a fully permitted oxide project, construction of the temporary camp and associated facilities is in progress. We've engaged CRCC 19, which is on site right now constructing access roads to the future open pit and waste rock storage areas and getting the foundation ready for the heap leach pad.

Lon Shaver

executive
#8

CRCC 19 already has operating know-how in Kyrgyzstan, and that same company serves as our mining contractor at El Domo. We expect the updated feasibility study for Tulkubash to arrive later this month. In our June budget release, we laid out a plan to put $166 million into building a 4 million tonne per year open pit heap leach operation at Tulkubash, with $42 million in capital expenditures budgeted for fiscal 2027. Over at the nearby Kyzyltash sulfide project, we had finished close to 13,000 meters of drilling by the end of the quarter, and 16 rigs are turning right now, with assays still pending. That work forms part of the 50,000-meter drill program we are running this year, which targets both infilling the deposit to upgrade resources and stepping out to extend mineralization and make new discoveries. This program will underpin completion of a PEA next year, and after that comes a further 60,000-meter drill campaign to support feasibility level studies and detailed engineering design for construction. We look forward to sharing more updates as our growth projects keep moving ahead. With that, operator, I'd like to open the call for questions.

Operator

operator
#9

<<operator_script>> Our initial question is from Kevin O'Halloran at BMO Capital Markets.

Kevin O'Halloran

analyst
#10

Beginning with the guidance, do you remain at ease with the production forecast despite the temporary shutdowns? Or might we expect those figures to be reassessed once you move through roughly the coming quarter and gain a clearer picture of how these shutdowns have hit? And then, in a similar vein on costs, you came in under the dollar-per-tonne band for cash costs and for AISC at Ying. Could that likewise hold some possible upside that you may revisit as you work through these shutdowns?

Lon Shaver

executive
#11

I mean, one quarter clearly doesn't add up to a full year—both when it comes to the negative side we discussed and dealt with through the protection curtailment, and also because some of the positive figures we're seeing in a given quarter might not be what ends up applying to the budget for the whole year, simply depending on which activities take place at various points during the year. On top of that, we're obviously dealing with some RMB strength, which had an effect—costs would have come out even better had we not seen that during the past quarter. But to return to the first part of your question, it's too early to begin making projections right now and then have to revise them multiple times. So I think we'll hold off and see how this quarter plays out. We're clearly seeing production return online gradually. We remain comfortable with the target we provided in that news release—40% to 50% of target for this quarter. And I think once we gain better visibility on that, we'll be in a stronger position to offer a comment on guidance for the year.

Kevin O'Halloran

analyst
#12

Yes, that's a fair point, and I appreciate it. Perhaps we could turn to El Domo in Ecuador for a moment. Spending came in somewhat lower during this quarter. It sounds like that's likely due to the rainy season in that region. But I'm just wondering, what's the cadence of the remaining capital spend that you expect, and what you would need to spend to get yourselves on track for production next summer?

Lon Shaver

executive
#13

Yeah, I mean, the figures alone don't give you the complete picture, since there are expenditures and deposits on equipment, and those clearly make up a significant portion of CapEx without showing up in the actual CapEx spending for the quarter. So work has been done on that side of things. And then, just given how the build is structured, it was always going to lean toward the back end, based on assembling the equipment at the process plant and carrying on with stripping at the pit. So right now, even though we might be somewhat behind the original spending budget, we don't view that as a problem. Much of that work, like I said, was back-end weighted in any case. And with some of it, we had a bit of room in the schedule when it came to earthmoving and certain stripping work. Our contractor had been pretty confident that our schedule was very conservative and that they can accomplish a lot more in a much shorter time frame. So we'll be holding them to that commitment for the rest of this year and the fiscal year.

Kevin O'Halloran

analyst
#14

All right, that’s wonderful to hear. This is my last question. Turning to Condor: I saw that your stake went up over the quarter. Did that involve any payments, royalties, or other consideration?

Lon Shaver

executive
#15

The payment was quite nominal, and really it amounted to just tidying up what was, in essence, a more legacy-style ownership stake in the corporation held by a government agency.

Operator

operator
#16

The following question is from Joseph Reagor of ROTH Capital Partners.

Joseph Reagor

analyst
#17

I think you mentioned this only briefly, but could you share anything more about how the safety upgrades are progressing? And is there any possibility whatsoever that this extends into fiscal Q3?

Lon Shaver

executive
#18

I mean, based on where we stand right now and what we've already disclosed, we're comfortable with that. And obviously, production has started up again at Ying, though at a reduced rate. But it is up and running, as we disclosed, and GC is still awaiting some approvals before we can get that going. But at present we're comfortable with our projection and our target for Q2 of being roughly 40% to 50% of the original plan.

Joseph Reagor

analyst
#19

Okay. And then regarding Q2, I saw some discussion in the release about shifting it from a lead-zinc operation into a silver mine, and that this would affect the number of production levels you're able to have — is that a sign that you'll soon be announcing some sort of expansion at the mill or in throughput there?

Lon Shaver

executive
#20

So that's a required piece if we were to take that path and give it consideration. Clearly, how much output and expansion we could plan from GC has been constrained. There are further zones where we know mineralization exists, but given the present restriction, thinking about planning for them or incorporating them has been somewhat academic. Taking this away, then, lets us view the mine in a more holistic way and put together some longer-term plans, and if expanding at that point makes sense, we will. Right now we have no plans for expansion, but this provides us the flexibility later on.

Operator

operator
#21

<<operator_script>> The following question is from Matthew O’Keefe with Cantor Fitzgerald.

Matthew O'Keefe

analyst
#22

Turning to Condor — it’s quietly progressing quite well. Could you remind us? I know you brought it up in the press release and in your remarks here as well, but it sounds like you’re getting nearer to carrying out some development there and getting a portal in. Can you walk me through the timeline for that? And then the next steps, I mean, as far as advancing toward production. Will that portal mainly serve resource development and confirmation, or will it actually be a precursor to some production?

Lon Shaver

executive
#23

Okay, so with the permit now received, our goal is to push forward on essentially two big projects at the same time. The first is the tunnels, which, as you said, we figure would take roughly a year to finish. So if we got started on them in Q4, then about a year out from that you'd be expecting to be into the ore zones. But what that lets us do sooner is begin putting in drill stations so we can drill off at greater density. The other effort underway at the moment involves reviewing a plan and detailed engineering for a surface plant operation at a smaller scale to begin with, along with a tailings facility and process plant, roughly 900 to 1,000 tonnes per day, which could treat some initial high-grade ores that we've managed to pull from our deposits, and also toll treat a portion of the ores that smaller-scale miners in the region are producing. So that's being worked on right now, in terms of detailed planning and a budget for what it would cost. And once we have those details assembled and are proceeding with the concrete expenditures for it, naturally we'll provide more disclosure at that point.

Matthew O'Keefe

analyst
#24

All right. So that mining or processing rate is lower than the one in the PEA — is that meant as an interim step, or is it simply constrained by permits?

Lon Shaver

executive
#25

The way this works is that it would be attached to the small-scale mining permit, and we would get it up and running. And regardless of whether it's initial or interim, we'd see that as a stepping stone — produce some cash flow and also be in a position to return to the regulators with a successful start of operations, and then modify that permit so the throughput rate increases, instead of entering a larger scale mining permit process that would definitely take longer before any cash flow would be seen.

Operator

operator
#26

That brings the Q&A portion to an end. At this point, I'd like to hand the conference back to management so they can offer any closing comments.

Lon Shaver

executive
#27

Okay, that's excellent. Thanks to the operator, and thank you all for being with us today and for those questions. Should anyone have further questions, we're clearly around and reachable to take calls or e-mails and help with them. Thanks once more, and enjoy your day.

Operator

operator
#28

That brings us to the end of today's conference call. You're welcome to disconnect your lines now. Thanks for joining us, and we hope you have a wonderful day. Bye.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Silvercorp Metals Inc. transcript — plus 130,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Silvercorp Metals Inc. earnings transcripts and 130,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Silvercorp Metals Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.