SJVN Limited (SJVN) Earnings Call Transcript & Summary

May 15, 2026

NSEI IN Utilities Electric Utilities earnings 33 min

Earnings Call Speaker Segments

Operator

operator
#1

Ladies and gentlemen, good day, and welcome to SJVN Limited Q4 FY '26 Earnings Conference Call hosted by Elara Securities. [Operator Instructions] I now hand the conference over to Mr. Rupesh Sankhe from Elara Securities. Thank you, and over to you, sir.

Rupesh Sankhe

analyst
#2

Good afternoon, everyone. On behalf of Elara Securities, we welcome you all for the Q4 FY '26 Conference Call of SJVN. I take this opportunity to welcome the management of SJVN, represented by Mr. Bhupender Gupta, Chairman and Managing Director; Mr. Parthajit De, Director of Finance. So we will begin the call with a brief overview by the management followed by Q&A session. I will now hand over the call to Mr. Bhupender Gupta, sir, for opening remarks. Over to you, sir.

Bhupender Gupta

executive
#3

Thank you so much. Good afternoon to all. I'm Bhupender Gupta CMD, SJVNL. I am accompanied by my Director, Personnel, Ajay Kumar Sharma; Director of Finance, Shri Parthajit De; and Director, Projects, Shri Adhikari. It gives me immense pleasure to share with you some key highlights and significant developments from the financial year '25-'26, along with the important milestones achieved during the ongoing quarter. We are delighted to highlight the strong and consistent operational and generation performance of our hydropower stations during the financial year '25-'26. Our flagship project, Nathpa Jhakri Hydroelectric Station, 1,500 megawatts, as you all are aware, achieved a remarkable generation of 7,506 million units in FY '25-'26 as compared to 7,421 during the corresponding year -- previous year. Similarly, Rampur Hydro Power Station, which is 412 megawatt, recorded a generation of 2,108 million units as compared to 2,074 achieved in the previous year, which reflects a sustained operational excellence across our hydro portfolio. During the financial year, total generation from all our power stations stands at 13,302 million units as compared to 10,646 million units during '24-'25, which is reflecting an increase of growth of 2,656 million units, approximately 25% higher than the previous year. On the capacity addition side, during the financial year '25-'26, I'm delighted to share the following major milestone. We commissioned first unit of 660 megawatt of 1,320-megawatt Buxar Thermal Power Plant, which went for commercial operation on 14th of November 2025, marking a significant journey for SJVN in the thermal power sector. I'm also pleased to inform that Unit-2 of the project is successfully synchronized with the national grid on 8th of May 2026, and its commercial operation is expected to be achieved by the end of this month. Our Buxar power plant, when it will be commissioned fully, will generate about 9,828 million units annually, of which 85% shall be supplied to the state of Bihar, contributing substantially to meeting the region's growing power demand and strengthening SJVN's position in the thermal power sector. During the year, we also commissioned 1,000-megawatt Bikaner Solar Power Project on December 24, 2025, which significantly -- which has significantly enhanced SJVN's renewable energy portfolio. This project is located in Bikaner District of the Rajasthan and well under the CPSU scheme of the Ministry of New and Renewable Energy Government of India. During this year, we had commissioned another solar project in Dhubri, Assam, and it was commissioned on 5th of February 2026. This project was inaugurated by Honorable CM of the Assam. The project is expected to generate around 141 million units annually, and it will be supplied to Assam Power Distribution Company at a tariff of INR 3.92 per unit. With these additions in operating assets, SJVNL achieved a total capacity addition of 1,730 megawatts during '25-'26, comprising of 1,070 solar and 660 megawatt of thermal. With this, the total installed capacity of SJVNL stands at 4,196 megawatt. In addition to major capacity addition achieved during the year, SJVNL has also made significant progress in expansion initiatives, renewable energy development and project execution. During FY '25-'26, SJVNL awarded 850-megawatt solar projects in Gujarat on 16th of October 2025, further reinforcing the company's expanding footprint in the renewable energy sector. As a renewable energy implement agency, SJVNL has awarded 16 gigawatt renewable energy projects across solar, wind, hybrid and storage segments. During '25-'26 alone, SJVNL awarded 4 gigawatt capacity and signed power sale agreement of approximately 2,177 megawatt. SJVNL as a bid implementing agency for battery energy storage system has successfully awarded 2,000 megawatt hour [ best ] projects across Uttar Pradesh and Haryana. With regard to progress of SJVN hydro projects, significant advancement has been achieved in 69.5-megawatt Dhaulasidh hydro projects, which is targeted for commissioning by March 2027. Considerable progress has also been achieved in the execution of 900-megawatt Arun-3 hydro project in Nepal, including achievement of critical electromechanical equipment and transmission logistics milestones. To provide a brief overview of our current project portfolio, presently, SJVNL has 15 operational projects with a combined capacity of 4,196.5 megawatts, along with 2 transmission lines. We are currently constructing 4 hydro projects with a total capacity of 1,561.5; second unit of Buxar Thermal Power Plant, 660; and 10 solar projects totaling 1,705 megawatts. This brings our total under construction portfolio to 3,926.5 megawatts. I am pleased to share that SJVNL received the prestigious SCOPE Eminence Award in HR management from Honorable President, Shrivati Droupadi Murmu on 29th of August 2025 for its progressive employee-centric HR practices. Now I'm going to share with you the quarterly and yearly set of numbers along with detailed analysis. SJVNL Board has adopted the annual financial results for the year ending 31st March 2026 in its meeting held on 15th of May 2026, and same has already been communicated to the exchanges. As per these results, revenue from the operation in FY '26 increased by INR 648 crores from INR 2,897 crores to INR 3,545 crores, registering a growth of around 22% year-on-year. The increase was primarily driven by recognition of earlier year sales amounting to INR 679 crores pursuant to truing up tariff orders for the tariff period 2019 to 2024 in respect of Nathpa Jhakri and Rampur Hydro Power Station, along with provisional tariff order for the tariff period '24-'29 in respect of Rampur Hydro Power Station. Revenue from operation for the fourth quarter of FY '26 increased by INR 488 crores from INR 446 crores in FY '25 and to INR 2,934 crores in FY '26, registering a growth of around 109% year-on-year. During FY '26, other income is INR 325 crores as against INR 355 crores for FY '25, which is about 8% lower, mainly due to decrease in late payment surcharge due to better realization of trade receivables and interest from bank. During quarter 4 of FY '26, other income is INR 114 crores as against INR 127 crores, which is about 10% lower, mainly due to the decrease in interest from the bank. On the expenditure front, during FY '26, the employee benefit expenses have decreased marginally by INR 5 crores. Then during FY '26, there has been increase in finance cost by INR 184 crores, from INR 726 crores to INR 910 crores, which is mainly due to increase in exchange rate variation during the year by INR 206 crores. During FY '26, the depreciation, amortization and impairment expenses have gone up by INR 178 crores from INR 450 crores to INR 632 crores, which is mainly due to recognition of impairment losses amounting to INR 174 crores during the year as per AS 36. During quarter 4 FY '26, the depreciation and amortization expenses have gone up by INR 182 crores, from INR 108 crores to INR 290 crores, which is mainly due to recognition of impairment losses amounting to INR 174 crores during the quarter in AS 36. During FY '26, other expenses have increased marginally by INR 2 crores. During FY '26, tax expenses have gone up by INR 256 crores from INR 313 crores to INR 569 crores. This is mainly attributable to higher profit before tax and increased utilization of MAT credit consequent upon discontinuation of reduction under Section 81a of the Income Tax Act 1961 on completion of eligible block of 10 consecutive assessment years of Rampur Hydro Power Station and KWPP. During FY '26, our profit after tax is INR 1,008 crores as against INR 970 crores in FY '25, which is an increase of INR 38 crores, that is approximately 4% and the reasons in the lines as have been just discussed. We have earned PAT of INR 125 crores as against INR 31 crores of corresponding previous period, which is up by INR 944 crores for 308% approximately for the quarter FY '26. During FY '26, the incentive position are as under. Secondary energy, there is an increase of 20%. Then PAF, it's minus 23% and the division charges are minus 3%. During quarter 4 FY '26, the incentive positions are under. Secondary energy, there is an increase of 16%. The PAF-based incentive is minus 40% and deviation charges are 0%. The trade receivables, which is very important for us as a generating company as on 31st March '26 stands at INR 1,299 crores as against INR 262 crores on 31st March '25. This includes INR 906 crores as unbilled debtors as on 31st March '26 as against INR 136 crores as on 31st March '25. Unbilled revenue includes an amount of INR 776 crores on account of tariff order received in the last week of March 2026 in respect of Nathpa Jhakri and Rampur Hydro Power Station. Billing of the same has been done in the FY '26, '27. Unbilled revenue also includes INR 130 crores in respect of sales of power for the month of March, billing of the same has been done in April '26. The Board of Directors have recommended the payment of final dividend at the rate of 3.5%, that is INR 0.35 per equity share in addition to interim dividend at a rate of 11.5%, that is INR 1.15 per equity share, resulting into total dividend at the rate of 15%, INR 1.5 per equity share on the face value of paid equity share of INR 10 each for financial year '25, '26. So this is all from my side, and thank you for the patient listening. Now the forum is open for question and answers.

Operator

operator
#4

[Operator Instructions] We have the first question from Mr. Mohit Kumar from ICICI Securities.

Mohit Kumar

analyst
#5

My first question is on the losses at the consol level. Can you please explain what is -- why there's a loss on the consol level? Is it due to the fact that the -- you have started booking the revenue for the new power plant and -- which is at a much lower PAF and maybe much lower tariff because the final tariff order is still to come? Is that the right understanding?

Unknown Executive

executive
#6

The losses were in SGL, We had a loss of around INR 257 crores. And in Buxar Thermal, that is STPL, we had a loss of around INR 92 crores. Buxar, as you know, has been operational for around 3 months in the last year. And it was -- it has started operating at a PLF of around 60%. Once this PLF goes up to around 70% plus, this plant will start bringing in a profit. And as far as SGL is concerned, this -- as you know, solar is a cyclical industry. And this year, we have slightly lower CUF on some of our plants, commissioned plants plus Bikaner Solar, that is the flagship plant for this SGEL, that has also started operating in December 2025. So, that plant is yet to come up to its full capacity, which we will be seeing in our current '26, '27 financial year. But since these plants have already been commissioned, finance cost and depreciation are already being charged to the profit and loss account. So that's the major reason that these plants have shown a loss for this year. And this is going to be improved -- this will increase -- improve substantially in '26, '27.

Mohit Kumar

analyst
#7

Is it possible to share the plant availability factor for SGEL and Buxar for the quarter and the year?

Unknown Executive

executive
#8

Like I said, it is 60% PLF.

Mohit Kumar

analyst
#9

PAF, sir? Plant availability?

Unknown Executive

executive
#10

Plant availability was around 60 -- 30%.

Mohit Kumar

analyst
#11

20%.

Bhupender Gupta

executive
#12

All the details would be there in the investor presentation, which we are going to upload by Monday. So you'll have all the details regarding the operational aspects of our different plants, SJVNL as well as the subsidiary companies. And if you have any further queries, you can reach out to us.

Mohit Kumar

analyst
#13

Understood, sir. And sir, what about the SGEL revenues, EBITDA and PAT for the FY '26, if you can share that number for the full fiscal?

Unknown Executive

executive
#14

SGL P&L figure?

Mohit Kumar

analyst
#15

Revenue, EBITDA and PAT for the entire fiscal FY '26.

Unknown Executive

executive
#16

For this year, the revenue of SGEL was INR 510 crores against INR 232 crores in the last year and expenses were INR 802 crores against INR 415 crores in the last year. That translates to a loss of 258 in this year as compared to 151 in the last year.

Mohit Kumar

analyst
#17

And how do you see the new capacity addition in FY '27 and FY '28 for SGEL and the hydropower plant and especially Nepal, what is the progress?

Bhupender Gupta

executive
#18

If you see that capacity addition for '26, '27, there will be capacity addition of Buxar Thermal Power Plant, 660 megawatts thermal. Then we are going to commission 69.5 megawatts of Dhaulasidh Hydro Electric Project in March '27, all -- both the units. And there will be addition of around 1,555 megawatts of solar capacity by March '27. They are getting commissioned at various dates starting from May '26 to March '27.

Mohit Kumar

analyst
#19

And anything on FY '28, sir? Any guidance?

Bhupender Gupta

executive
#20

'28 also, we are -- we have a plan to add capacity around 650 megawatts. This is again mainly due to the solar projects only because our hydro projects are under construction. So we have a scheduled date of commissioning starting from FY '29 to FY '30. So 650 megawatt of solar will be added in FY '27 -- '28, in fact.

Mohit Kumar

analyst
#21

And sir, what is the progress on the Nepal hydropower project? Where it is right now? When are you expecting the commissioning?

Bhupender Gupta

executive
#22

Yes. Nepal hydro project is also in very advanced stage. We were having some issue with the dam. Some geological surprises were there on the dam right bank. So those have been tackled now, and there is a minimum time required to stabilize that area. So that is already in progress. And you know that there were a lot of uncertainty in the Nepal government side. So some of the approvals were pending on, but those are now okay. We are progressing well, and we have a plan to commission the entire plant, all the 4 units by December 28.

Mohit Kumar

analyst
#23

December 28, FY '29.

Operator

operator
#24

The next question is from Ragini Pande from Elara Capital.

Ragini Pande

analyst
#25

Yes. So I have a few questions on Buxar plant. So post commissioning of Buxar, what is the regulated equity for you right now?

Bhupender Gupta

executive
#26

Regulated equity as we have only capitalized the Unit-1. And as on date, the equity is around INR 4,000 crores to INR 2,000 crores is regulated equity for Unit-1. And once we commission both the units, the regulatory for Buxar would be around INR 4,000 crores.

Unknown Executive

executive
#27

The capitalized cost of Unit-1 is around INR 7,000 crores. So like my colleague said, that translates to a regulated equity of around INR 2,100 crores for Unit-1.

Ragini Pande

analyst
#28

And can you just repeat your generation from Unit-1 of Buxar and the revenue contribution and the profitability or losses which you mentioned for Buxar? If you can just repeat that.

Bhupender Gupta

executive
#29

STPL, that's Buxar Unit-1, that earned a revenue of around INR 522 crores in this year, in the last 3 months and the total expenses were around INR 644 crores. So post tax, that turns to a total comprehensive income of around minus INR 93 crores.

Ragini Pande

analyst
#30

And what is the design energy for Buxar?

Bhupender Gupta

executive
#31

Design energy is 9,800 million units.

Mohit Kumar

analyst
#32

For the full plant.

Bhupender Gupta

executive
#33

For the -- both the units. for the full plant, if you convert it to one, it's around 4,900.

Ragini Pande

analyst
#34

And there has been a significant increase in expenses. Is it -- this is because of commissioning of Unit-1 of Buxar...

Bhupender Gupta

executive
#35

Yes. As we told that because we were not running it on the full capacity due to various reasons. Number one, it was -- like when we commissioned it, there were not much demand and we were being -- the power was being curtailed down by the beneficiary. And there was a daytime there's a lot of solar power. So we were running at around 60% PLF only. So in thermal, what happens when you run the plant at minimum technical level, then there is always a loss to the project because there's a minimum expense that we need to incur. So beyond 70% PLF only, we start generating the profit, so -- but now this year, we will be commissioning the second unit also and everything have been stabilized in Unit-1 also. So we are very much sure that during this FY '27, we are going to have a profit from the Buxar Thermal Power Plant.

Ragini Pande

analyst
#36

And my next question on the renewable tendering. So do you see any slowdown in renewable tendering for this year and for next fiscal? And also, what is the status on the unsigned PPA of -- to the tune of around 40 gigawatts?

Bhupender Gupta

executive
#37

As far as SJVNL is concerned, we have our arm in the Renewable Energy Implementing Agency. We have awarded a contract of around like 16 gigawatts, 16,000 megawatts. And out of that, we have signed a PSA of around 6 gigawatt. The problem what's happening that there are a lot of tenders which came out simultaneously in the market. And the demand is not that much, frankly speaking, because ultimately, this power has to be purchased by the DISCOMs, distribution companies. And so they have their own plan to purchase the power from different sources, like they are looking for a combination of various things, solar, wind, hydro, then thermal because they need a baseload plant as well as the daytime plant and peaking power also. So as per their adequacy plan, so all the states have their different requirement. So that's why the present tenders, which were done by all the areas, in fact, not only SJVNL, NHAI, SECI and NTPC. So all have this issue, all have almost signed 25% of their -- 25% to 30% of their capacity, which has been tied up as of now. Balance is pending and there is a possibility that all the PPAs may not be done because there are 2 reasons. One is that requirement of that particular -- that configuration, which was there in the tender may not be required by the DISCOM. And secondly, there is a decrease in the -- like this bid, which they have like tariff -- decrease in the tariff with the subsequent bids which have come in the market. So these are 2 things. So there will be demand definitely. I don't see there will not be demand, but maybe with a different configuration like solar plus BESS, maybe every FDRE, which comprises of solar plus wind plus BESS. So this will come in the market. So demand will not decrease for the RE power as such.

Operator

operator
#38

The next question is from Rupesh Sankhe from Elara Securities.

Rupesh Sankhe

analyst
#39

Sir, a couple of questions. Firstly, sir, earlier, we had shared a vision for a rapid expansion to reach a target of close to 25,000 megawatt by 2030 and then 50,000 by 2040. So are we still maintaining the same target? And the second is, what is our CapEx guidance and how we are going to fund this huge CapEx?

Bhupender Gupta

executive
#40

This is good question. There were certain -- these projections were done based on certain market assessment and our growth, which was supposed to happen with RE as well as hydro projects. Unfortunately, due to one or the other reason, which is like unavoidable, but beyond the control of the SJVNL, the projects didn't come in time. And even the tenders for CPSU-like schemes and other like VGF schemes for the RE didn't come, which we were expecting in a similar manner, which came in '22, '23. So we found that due to some delays, number one, and due to some losses in the running -- ongoing our commissioned projects due to less CUF, for some other reasons. We have -- we are like -- now we are trying to consolidate ourselves with the ongoing projects. And we will be like -- we will be making this -- our future projections based on the realistic targets. And so that we will be sharing very soon what is our target. I told you our future plan that '27 FY, we will be commissioning around [ 2,284 ] then in FY '28, 650. Then in FY -- from FY '29 to '30, we will be around another 2,500 . But the target, which you were speaking about 25,000, 50,000. That is that we are reviewing it. We are making our new business plan, and we will be coming out with the new business plan very soon. Regarding CapEx, which you asked about our plan for CapEx. So this year, we have a CapEx plan of around INR 9,400 crores. And for FY '28 and FY '29, we have a plan of INR 7,800 crores and INR 7,500 crores, respectively.

Operator

operator
#41

We have next question from Mr. Mohit Kumar. This is a follow-up question from ICICI Securities.

Mohit Kumar

analyst
#42

My question is, for your operational assets of RE, are you seeing any curtailment of solar power projects? And how are you mitigating it?

Bhupender Gupta

executive
#43

We are facing curtailment in Bikaner. We have commissioned 1,000 megawatt, but there is a curtailment around 120 megawatt. So that is due to the SVR requirement. So that there is availability issue with the SVR. So that will be commissioning this year by October '26. We will be commissioning the SVR and then I think we will be running on the full capacity, 1,000 megawatts. So that is the one thing. There is a curtailment is there. Similarly, we will be commissioning some plants very soon in this Khawada, Gujarat. And there also, we are having some issue of connectivity. Though we were given the connectivity on some other dates, but now the connectivity dates have been postponed due to the delay in the transmission line. So there may also -- we may also have a curtailment in those plants also that may be around 300 megawatt. So the other places, there is no curtailment as such where we are operating the plants.

Mohit Kumar

analyst
#44

And what mean by SVR, sir? You said SVR?

Bhupender Gupta

executive
#45

Basically [ reactor ] for the compensation from...

Mohit Kumar

analyst
#46

So why is there a delay, sir? Any reason? Is it in your...

Bhupender Gupta

executive
#47

Actually, the requirements came from the authorities, Central Electricity Authority. Some regulation came and there is so much an influx of the solar power plant in the grid. So to balance the grid, this particular equipment is required. And there is an issue with the -- '23, in fact, this regulation came. By the time we have already awarded the Bikaner and the construction was going on. So when we ordered, so delivery of these equipment is not matching with our requirement. So now they are delivering us in October '26 only. because this equipment has a limited like manufacturer and it's like a transformer only, nothing else. It acts as a reactor only, nothing else. But there is a sort of -- yes.

Mohit Kumar

analyst
#48

This 1 gigawatt is under CPSU scheme, right, sir?

Bhupender Gupta

executive
#49

Yes, yes, yes.

Mohit Kumar

analyst
#50

My second question is, sir, what is the status of projects under REIA for you? How much of the PPA is still pending?

Bhupender Gupta

executive
#51

I told you, out of around 15 gigawatts, we have signed PPAs of around 6 gigawatt. So balance are pending because some of the PPAs are under progress. So 6 gigawatts are signed already.

Mohit Kumar

analyst
#52

How much you think you can convert out of 9 gigawatts?

Bhupender Gupta

executive
#53

Very, very difficult to say anything as of now. We are trying very hard because I told you it's a problem of the component of that -- sorry, power, which -- of the tender particularly because these PPA -- these all tenders are a mix of FDRE, then your solar standalone, then there is this hybrid solar plus wind. And so these are the major 3 type of tenders are there. So I told you because of the adequacy plan of the various DISCOMs and the states. So they are not finding some of them suitable to their requirement. Even the cost of...

Mohit Kumar

analyst
#54

How much is pure solar, sir? Pure solar in this?

Bhupender Gupta

executive
#55

Pure solar is -- just a minute to see. Just a minute.

Unknown Executive

executive
#56

3 gigawatt pure solar...

Bhupender Gupta

executive
#57

Solar, 1,200 plus 1,300. Plus solar -- around it, you can say 2,500 pure solar and around 900 is solar plus BESS.

Mohit Kumar

analyst
#58

So is it right to say the balance 6 gigawatts should easily find a buyer in due course of time? Or do you think also now may get canceled again?

Bhupender Gupta

executive
#59

Because actually some of the tariffs are attractive, in fact, some of the solar tariffs, there is a 2.53, 2.54 tariff is there. And now when the states are coming with a new tender, so they are getting a cost of around 2.8 to 2.9. So I am hopeful that the way we are following up with the respective DISCOM, there is a possibility that we may be able to sell even the pure solar also.

Operator

operator
#60

Thank you. Ladies and gentlemen, we can close the call. I now hand the conference over to Mr. Rupesh Sankhe. Over to you, sir.

Rupesh Sankhe

analyst
#61

Yes. We thank SJVN management for giving us an opportunity to host this call. We also thank all the investors and the analysts for joining this call.

Bhupender Gupta

executive
#62

Thank you. Thank you so much.

Operator

operator
#63

Thank you. On behalf of Elara Securities, that concludes this conference. Thank you for joining us, and you may now disconnect your lines. Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete SJVN Limited transcript — plus 246,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to SJVN Limited earnings transcripts and 246,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.