Solaria Energía y Medio Ambiente, S.A. (SLR) Earnings Call Transcript & Summary

November 18, 2024

Bolsa de Madrid ES Utilities Independent Power and Renewable Electricity Producers earnings 51 min

Earnings Call Speaker Segments

David Guengant

executive
#1

Good afternoon, everyone, and welcome to the webcast on Solaria's results for the first nine months of 2024. I'm David Ganguins, Head of IR at Solaria. With me today is Arturo Diaz Tejeiro Larranaga, our Chief Executive Officer. On this call, we will talk about how our business is shaping up and make forward-looking statements. What he says reflects our predictions and expectations as of today. In this presentation, we will start with a look at the results and the key developments in the period, presented by our CEO, Arturo Diaz Tejeiro Larranaga. After that, we will go to the Q&A session. I'd also like to point out that all of your questions need to be submitted through the web. Many thanks again, and I'll now pass the word to Arturo.

Arturo Díaz-Tejeiro Larrañaga

executive
#2

Thank you. David, thanks — and thanks to all of you for being on this conference call. As I always do, I'll go very quickly through the presentation, and then we'll move on to the Q&A session. And of course, the key highlights we want to present in this nine-month presentation. Data centers. Data centers remain — they're at the heart of one of the key elements of our strategy across Europe. In our view, the data center business is set to expand substantially, particularly in Spain, though not solely there — globally throughout Europe, similar to what we're seeing in the United States, in line with the readings coming out of the United States. And, as you're aware, data centers are going to rank among the main customers for the electricity markets going forward. They will consume electricity heavily and, in theory, they ought to get renewable power, and for us that makes them a crucial customer down the road. We're bidding aggressively for this business unit, and we're expanding, adding consumption points across every country in Europe, with a particular focus on Spain — though not only Spain: Italy, Portugal, Germany. Now even the United Kingdom, but with Spain as the main focus. Today we have solutions, a power line solution, for 1.7 gigawatts, allocated mainly in the Iberia region for data centers.

Arturo Díaz-Tejeiro Larrañaga

executive
#3

So today we're in negotiations with a different player from Europe and the United States — companies active in the data center business — and what they want is to reserve connection points, consumption points for electricity, power, and land. Land, as we say, plus options, and at the same time renewable PPA electricity for the future. As you know, in our data center business we've decided to enter through two distinct routes. The first is selling connection points and land, which is one of the options we're developing, and we're working with several groups. We'll explain that during this presentation. The other route is setting up joint ventures with key players — tier 1 players — with a long track record who want to build long-term business in Europe, especially Spain, but with a focus on all of Europe, with strong experience in the data center business, and who want to establish long-term joint ventures with renewable energy players, infrastructure players like Solaria. And during this presentation we'll try to explain our business model for joint ventures in the data center business. Of course, something new: we're entering the United Kingdom. We've opened a branch, a new office in Birmingham in the United Kingdom.

Arturo Díaz-Tejeiro Larrañaga

executive
#4

As we've said, this doesn't come as a surprise, since we entered that market earlier. The new government in the United Kingdom is very bullish about expanding renewable energy. We believe it's a good market to be in, particularly with a focus on wind technology and onshore technologies. We think growth in the data center business will be positive, and at the same time, renewable expansion will be positive over the coming years, since the government intends to grow wind capacity and also solar capacity in the country. Given our experience, our team can expand our activities there, and we've decided to enter with all of our business. And we will report quarterly on our progress in the United Kingdom, in the country. Company situation, and where we stand today. As you know, this year we've been through two-year (ph) from a price standpoint. In the second quarter, particularly the price of electricity, we had a very low electricity price. The good news today is that the electricity price is recovering, the price, and it's in a better position than before. You know that today, for instance, in Spain, the electricity price is EUR120 per megawatt hour, which is more than we had previously estimated.

Arturo Díaz-Tejeiro Larrañaga

executive
#5

The gas price situation will likely persist through November, December, January, and February. As you know, we're currently exerting significant upward pressure on gas prices, and this is seriously impacting electricity prices here in Spain and across Europe generally. Our results, however, are affected by these low electricity prices, particularly during the first half. We're still maintaining really solid levels of revenues and EBITDA, associated especially with strong production that's growing by more than 15%. But we have reduced our EBITDA by 14%. Hopefully, we'll close this year with an EBITDA better than the previous year, better than 2023, with an estimated EUR205 million to EUR215 million of EBITDA — and we maintain that estimate for the end of this year. Of course, we'll briefly discuss the various important points of our business strategy for this year and the years ahead. Right? I've explained the data center concept and where we stand in that business. Ultimately, Solaria is a Powerland partner. We provide the data center players with power, electricity, connection points, infrastructure, substation and grid, and land. Obviously, around our substation and grid, we're contracting land because it's necessary.

Arturo Díaz-Tejeiro Larrañaga

executive
#6

We’re talking with data center operators. And under their assumptions, we’re signing contracts and leasing land that’s going to be essential for building future data centers throughout Europe. Today, our business model—I’ve laid it out in two different ways: sale and joint venture. And sale is opportunistic business, cash generation, PPA, under good conditions; joint venture is a long-term vision. We believe it makes sense to bring the company into the data center business so we can get EBITDA and cash from that business over the long term. We won’t be using CapEx, because ultimately, in these joint ventures, we’ll provide the power and land, and we’ll assign a valuation to the power and land that we supply to the joint venture. We’ve included several estimates, and we’ll tie them to the joint ventures we’re negotiating today, but roughly we estimate revenues of EUR30 million to EUR45 million per year for 100 megawatts. That depends on the final stake we keep within the joint venture, but it’s an estimate based on a share of between 30% and 50%.

Arturo Díaz-Tejeiro Larrañaga

executive
#7

Naturally, at this point we have multiple negotiations underway, and there are some new things we're explaining as we speak — today we're in talks with the tire 1 players that they have. As I mentioned when this presentation began, that means tire 1 players from Europe and the United States in particular. And I believe we're in a good position today to say that likely, by the annual results presentation, we will close a number of these joint ventures. With one European player, we've made genuinely good progress. The negotiations are at a really good stage. And likely, in December or January, we could make an announcement with these guys. With the United States players, I think we need to take more time, but we'll try to make an effort — to put in that effort, to make an effort — and to try to sign before the 2024 results presentation. We're continuing with our sales, or with our opportunity sales, of connection points, and we're moving forward on these other deals. On the UK, as I've said, I won't take a lot of time, because in the UK we're at the beginning. For us it's a promising country for the renewable energy concept.

Arturo Díaz-Tejeiro Larrañaga

executive
#8

So I'd say wind particularly, though solar too. We're talking with the UK government. In our view, it's an attractive market for renewables with real opportunity. We'll remain there — that's a commitment on our part. As we've laid out over recent years, Europe is where our strategy is centered. Our plan is to expand across Europe, in solid countries that offer strong legal security — serious nations, as we put it. And to us, the United Kingdom is definitely a serious country, in a good position and favorable for renewables. Right now is the time to move in. This is the moment to be present, and stay we will. In our thinking, it makes good sense to keep a presence in various European countries carrying differing risk levels, the UK among them. Wind technology, of course. No — Solaria today is a mature participant in the solar sector. Without question. One could say — we can say we're likely among the leading platforms in solar, no doubt, with extensive experience across all those countries. Yet wind is central to our future. As you're aware, when you already have solar development, building out a wind pipeline is straightforward, and that's what we're doing and executing right now.

Arturo Díaz-Tejeiro Larrañaga

executive
#9

And hopefully over the next two to three years, we're going to build a massive amount of wind parts. Especially, as always, we'll start in Spain, the Iberia region. We have really good visibility on more than 1 gigawatt of wind pipeline across different locations. But those locations, because it's Caronia, in Trio (ph), in places where we've established or are constructing solar plants, and we're going to combine that with wind, a hybridization process that we'll complete over the next two to three years. It's exciting for us because the concept, for us, is a clear strategy for the future: to combine solar, wind, batteries, and data center consumption. It's a great idea in our view for the long-term vision of Solaria — wind, solar, batteries, and, obviously, data center consumption, and traditional PPAs. But it's a global infrastructure strategy. And I love it. And our projection for the future, but — estimated is to achieve more than 3 gigawatts of wind in Europe, including Italy, Germany. In Italy, we are not extremely bullish about wind. We think that it's better for solar and wind. We think that Italy is not the place for different reasons, especially for political reasons.

Arturo Díaz-Tejeiro Larrañaga

executive
#10

Germany looks fine, and the UK is obviously fine too. Naturally, as a pure infrastructure player with more than 20 gigawatts, we're extremely diversified. As for Europe, we won't be leaving Europe, neither in the short-term nor the medium-term. We believe Europe delivers high-level project IRR to us, a high level of profitability, cash generation, security, and CapEx under control. That's critical for us. We believe we're probably the most powerful renewables platform in Europe. Generia. Generia mind (ph), it's a good combination. It's something we put together a long time ago because, as you know, land is critical. You're seeing it now, even with the data center business — land is one of the key parts of the strategy of an interest (ph) to put player. Right? And Generia was a good idea made a few years ago that is growing. Today it's attracting interest from some partners, but at the end of the day, the people looking for fixed interest long-term, 20, 25 years, and Generia offers this great opportunity to these guys. It's like they're going to warranty a good interest rate close to 8% during the next 30 years. And a lot of interest from the market.

Arturo Díaz-Tejeiro Larrañaga

executive
#11

As you're aware, we have contact banks (ph). We're in discussions with various players — funds in particular, insurance companies, but really all sorts of infra funds and pension funds — that are looking to put money into a long-term business offering solid profitability with limited risk, and Generia fits that business idea. Hopefully, at the full year's presentation 2024, we'll provide the name of the final partner we'll be with in Generia, and the combination will probably be Solaria 51, this partner 49%, and he'll remain with us with cash as a financial investor, and hopefully in three, four years this business will grow and we'll see what we're going to do. And it's probable that we could sign an option to sell the company to this guy or other options, but it's still too early to talk. Probably at the full year presentation we'll give all the visibility. Of course, CapEx continues, it's incredible, but not a surprise. CapEx falls all quarters. Module price is suffering an awful evolution for module manufacturing companies, because the reduction is crazy per quarter and continues. Not only module, inverters, all the components of the installation. And in my mind it's going to continue, it's not something opportunistic, it's a continuous line that we're going to see during the next 10 years.

Arturo Díaz-Tejeiro Larrañaga

executive
#12

The technology's evolution has been remarkable. From a CapEx standpoint, we lead in Europe—and clearly in Spain as well. And our CapEx keeps coming down. Naturally, at this stage on the construction side, 1.7 gigawatts are already operating, with nearly 1.5 gigawatts under construction. Hopefully, over the coming year we'll progressively hook up a great many installations, and we'll end 2025 above 3 gigawatts, as the leader in the Iberia region and likely one of the leading platforms in Europe. And hopefully we'll add some construction tied to Italy, where we have a solid state of development, and we'll probably begin building in Italy. We haven't included this here, but I think that on an optimistic view, probably during 2025, we'll add a good volume under construction in Italy. But we keep building—not complicating construction. I think that progressively we will connect. Naturally, PPA—where we stand is something we always get questions about, regarding the PPA market. Over the last month, the price of electricity suffered a lot. Solar price, but not only solar—the global price of electricity, speaking about Spain especially, suffered a lot; today the price is recovering.

Arturo Díaz-Tejeiro Larrañaga

executive
#13

Our position has improved, and I believe the PPA price situation has improved as well. As of today, we have signed three term-seat agreements. Three term-seat agreements have been signed with Tier 1 players. Oil and utilities, as usual, new partners. A few of them are new, and that will be a positive new. We had considered including this even in the presentation, but it will likely be announced over the coming weeks. Attractive prices and, above all, the schedule, since they are planning to begin the contract after 2026. That affords us plenty of time, is comfortable for us, and mid-30s. That represents a good price, good conditions, and a good long-term view for us. At present we are negotiating 0.6 gigawatts, though we could probably raise that if we choose to. But we are reserving some power for our data center business. Why? Because we believe the data center customer will be better. Better is not the right word to use. Every customer is great. But in our view, the data center business could pay more. Why? Because they are going, because they use connection points, they demand connection points, it's a self-consumption concept. They are going to save some regulated cost, they are going to save taxes and retail margins.

Arturo Díaz-Tejeiro Larrañaga

executive
#14

When all is said and done, they'll save roughly EUR20 for each megawatt that the utility or oil company ought to pay. Clearly, when everything is factored in, they can afford higher PPA prices. That's a huge edge for these folks. Meanwhile, they want electricity as fast as possible, and that gives them certain leverage. My view is the PPA price we might secure is considerably better than the conventional prices we're quoting to the market. Still, time will tell. Time will tell — particularly regarding the joint venture, since it will likely be some combination. We'll receive shares within the joint venture on the basis of power — land and power plus PPA combined. We'll report the details. Naturally, as I said, results show we raise output and cut sales in line with the electricity price. This quarter is going well since the power price is climbing sharply, above all in November. December, in all likelihood, will head the same direction, because I've discussed (ph) the gas situation and gas prices — for gas in Europe, which in my view won't shift, particularly given Russia and how the war unfolds, though I believe that is not favorable where gas prices are concerned.

Arturo Díaz-Tejeiro Larrañaga

executive
#15

And as you’re aware, Gazprom has reduced its gas deliveries. That isn’t a shock for Austria, yet it does push inflation up through prices. Still, we’ll have to see. Naturally, we’re carrying on with our EBITDA. Tax is hitting it hard. Spain’s government gave the green light to the Spanish 7% generation tax, which was approved at the start of this year. Hopefully — and I’m optimistic on this point — I believe we’ll be done at the close of this year. In my opinion, following a great deal of conversation with the Spanish government, in my mind and in my view that tax will be cancelled at the end of this year, though we’ll see whether that proves true or not, but it matters a lot to us since it’s something seriously affecting our EBITDA. Naturally, cash recovery — we made progress on that in the prior results presentation. We’re operating cash — and we’re getting payments from project finance players, suppliers and banks. I believe our construction reading carries on, we’re putting an enormous amount of money into investment, and we keep holding our cash. We’re enhancing our pipeline. We’re enhancing, across countries, the quality of our pipeline — more wind, more solar, more countries’ data centers.

Arturo Díaz-Tejeiro Larrañaga

executive
#16

And meanwhile, we keep our cash position and the discipline within the company to hold costs in check. Right? That's good. As you're aware, every bit of our debt is project (ph) debt, and the average cost of that debt isn't bad at 3.7%; likely with a cut in interest rates, we'll bring that average cost of debt down, which we'll see over the coming quarters. Naturally, as I said at the outset, we reaffirm our EBITDA targets, and nothing special tied to Generia has been included here. Nothing particularly tied to data centers has been included here either; it's like the standard business, we'll watch how it evolves, but we believe it will probably come in better than we've estimated, particularly in connection with the price of electricity.

David Guengant

executive
#17

Thanks, Arturo. At this point I'll begin the Q&A session. And thanks again for spending time with us. So our first question comes from Fernando Garcia at RBC. First, when does revenue begin in our JV DC deals? Second, could you give us some timing on signing the agreement with data section? And third, can you explain why the capacity under construction slipped from summer 2025 to mostly the second half of 2025?

Arturo Díaz-Tejeiro Larrañaga

executive
#18

On the timing for data center revenue, that's a fair question — probably toward the end of 2026, though before that it's hard to say. Why? Because we'll likely announce joint ventures ahead of the February presentation, the results presentation — at least one, possibly two, but definitely one — and we'll set out all the JV terms in full detail, including precisely Solaria's share participation, the power, and the land we'll be supplying. The main thing is that we'll begin the physical construction of the data center. That isn't simple, and it will likely take time — 1.5 years of time, which is at minimum a reasonable figure. We aren't heavily focused on revenue and EBITDA from this business. That isn't the central point for us. It's the overall valuation, because we're moving into a new business alongside key players, with partnerships involving key Tier 1 players who will bring us significant knowledge of this business. Solaria will be the energy partner working in technology, and I love that, because it's — sort of — we are globally shifting our strategy with ease — well, not with ease.

Arturo Díaz-Tejeiro Larrañaga

executive
#19

It sounds simple, yet it isn't simple—but it comes easily. It's as if we're bringing a company into a new world with new, enormous customers—exciting customers with enormous capacity. This is a new business that requires many things: not just power and land, but services too. And we'll go in through partnerships with the key players worldwide. I'm tremendously excited. On valuation, in my mind it's a limit valuation. I feel extremely comfortable today, because in my mind—what does that mean? I can't say. I believe it's a new business. It's a new company. We're going to change our face entirely, and the valuation is—I grasp the concept of revenues and EBITDA. And after 20 years, trust me, I understand the concept of EBITDA and revenues perfectly. But it's a new company, and it will transform Solaria entirely. It's the energy partner of the technology world, and I'm excited about this. In Europe it is something new—not in the United States. You know that in the United States, it isn't new, because there are plenty of energy players supporting the growth of these key guys—enormous guys—country guys, because they are larger than countries.

Arturo Díaz-Tejeiro Larrañaga

executive
#20

Yet over in Europe, there’s a fresh development. We still — we remain — we haven’t gotten our heads around it. The reason we don’t grasp it, in my view, is that we aren’t tracking the market. Even so, we’ll be a central participant. We’ll be among the partners working with these people. And this makes me hugely enthusiastic. Still, to address what you asked, likely during the latter half of 2026, with 2027 being reasonable. The same data segment that you brought up remains unchanged. We’re actively addressing it, and I — these are tough transactions requiring due diligence. They must fully grasp where the connection points stand, whether those connection points in Spain are regulatory or otherwise. As I said earlier, at the February results presentation, we’ll disclose completed deals along with every detail. Under construction in summer 2025’s second half — that’s where we’ve slipped. It isn’t — people sometimes ask me why you push back your construction timeline. The answer isn’t that Solaria is causing delays for some reason. Tomorrow we could build the entire capacity. We hold permits for the site. Everything on site is in place, and the financing terms are secured.

Arturo Díaz-Tejeiro Larrañaga

executive
#21

The funding is in place. The module is in place, and that's why there are sometimes delays. Regrettably, Spain is in an odd situation right now — not odd, actually. We ourselves foresaw it quite a while back. Many small players share infrastructure with us. And regrettably, they find themselves in an extremely tough spot. They aren't responding to the ministry or regarding the installations they ought to build and ought to begin building. A number of them share positions with us and — regrettably, they have at times held up Solaria projects, not a significant delay, but a few months. Some are being pushed out by the market since they lack money. They lack project finance capacity. They aren't serious in the Spanish market, and globally in the renewable energy market there are plenty of speculators but serious companies are only a few, not many significant serious players. That's our life, the power (ph) effect of renewable energy, but that's something we knew previously. And they are delaying some of our projects. The good point is that it isn't significant, a few months, but it is something that has happened.

David Guengant

executive
#22

Fernando Garcia from RBC has the next question. At present, how many megawatts of DC with grid connection do you have, and how many megawatts are pending answer? As we updated during the last quarters, at this moment we had 270 megawatts secured and 730-megawatt pending answer. As you can see, pending answer, we have much more than this 730-megawatt. But today, we won't update the market. Next question is coming from Philippe Ourpatian from ODDO. Good morning. May we have the amount of capital gain included in the EBITDA? Is there any change versus H1 '24? No change. As you say, Philippe, we have included EUR11.5 million of capital gain in the first half in our EBITDA. And in the third quarter, we don't have any capital gain. Next questions are coming from Enrico Bartoli from Mediobanca. Can we provide more color on the cash flow generation of the data center business? Then as this revenue recurring every year? Then next question is coming from Generia. And can we provide any update on discussion with potential investor in Generia? And maybe your last one from Enrico. What is the amount of capacity currently under constructions that Solaria plans to secure through PPA contract?

Arturo Díaz-Tejeiro Larrañaga

executive
#23

Sure — regarding revenue in the data center business, cash flow is still premature to discuss. So I think that — let me address all of that in the results — the annual results presentation, together with the joint venture signing and with the team, our partners agreed, and with every detail of the joint venture, covering the contract and the long-term contract and all particulars. I think it remains too soon to discuss cash flows. It will be recurring, obviously. If we come in as a joint venture participant, we will generate recurring cash flow throughout every year across 30 years. That's the joint venture concept, and our intention is to enter this business, with a solid business opportunity. I don't know whether we will be there long-term or stay a few years and then sell, we will see. Initially, our vision is that we will secure recurring cash flow. Investors in Generia, we are speaking with several investors. As I have explained, we haven't discussed the amount of money. It's something that obviously is significant because we are not going to increase Generia capital just to get a small amount of money.

Arturo Díaz-Tejeiro Larrañaga

executive
#24

Talks with them are still ongoing. The base — and the way Generia is being valued at close to EUR300 million — but it's still too early, or I think we have to move ahead with our partners, our future partners, with our investors, and we need to watch how this deal finally evolves. And the PPA contracts and the concept remain the same as always. We believe it makes sense to keep roughly 70%, 30% — approximately 70% PPA, 30% merchant — a concept that could rise to 80%, or staying somewhere between 70% to 80% is reasonable. Ultimately, we're an infrastructure player. We want secure cash flows, and locking in PPAs is smart. But today — and not today, since we announced this before — the key point is that PPA isn't only about oil or utilities and the traditional retail distribution company. We're opening the door to new players such as data centers that might pay more, and signing contracts with them is probably more interesting for us.

David Guengant

executive
#25

The following question comes from Fernando Lafuente at Alantra. He has three questions. First, what is behind the 60% decline in prices in Portugal and Greece? I'll take that one. As you're aware, Portugal is merchant today. It was merchant — pardon me — and now it's PPA. Keep in mind that we also had merchant revenue from Portugal at income during the last year. But starting in summer, all those plants — the 63-megawatt plant — will move to the PPA. Recall that the Portugal PPA stood at roughly EUR22, EUR23. So that's why revenue in Portugal declines as we shift from merchant to that EUR22, EUR23 PPA. Second question, the 2024 EBITDA target — what does infra contribute to the improvement? As we said, we estimated roughly EUR24 million, EUR25 million from infra without asset rotation for 2024. And then the next questions come from Manuel Palomo at BNP Paribas. More questions about the DC business. Have we already closed a deal, and can we share our plan for growing in the UK wind field, or through acquisition? And could you please help build the revenue bridge from total revenue of EUR157 million to energy sales? Perhaps I'll answer that last one. Energy sales over nine months are EUR104 million, which bridges to sales of EUR157 million.

David Guengant

executive
#26

First, you need to account for the EUR11.5 million of asset rotation that occurred in the first half. Then, on top of that, roughly EUR21 million must be added in infra revenue. During the first half, we recognized EUR14 million of infra revenue, and in the third quarter only EUR7 million. As a result, the third quarter had no asset rotation and just EUR7 million of infra revenue.

Arturo Díaz-Tejeiro Larrañaga

executive
#27

Regarding the UK and the growth we've been considering, it will clearly be greenfield rather than through acquisitions. What we intend to do is build out sizable developments along the lines of hub-style projects involving a substantial megawatt capacity, able to pair solar with wind at particular sites within the United Kingdom—not spread extensively across the whole country, but concentrated in selected spots, where we'll pursue big schemes combining solar and wind. That's our plan, above all in two locations.

David Guengant

executive
#28

Our next question comes from Arthur Sitbon at Morgan Stanley. Since we're now looking at two different business models for data centers, are we still committed to producing EUR670 million in cash from the data center business across 2024 to 2028, as we laid out in the first half results?

Arturo Díaz-Tejeiro Larrañaga

executive
#29

From where we sit, if these parties settle in shares, that's equivalent to paying with cash. To me, getting cash makes sense. It matters a great deal, but should these parties value our cash against equity in an enterprise that will produce recurring cash flow, then ultimately for me that is even more attractive. As I've laid out, I believe we'll blend the two approaches. Tier 1 companies — serious participants with a long-term vision — could transform the whole profile of the company and the profile of Solaria's joint ventures, global agreements, and our intention is to remain alongside them over the long term. Consistent with our strategy, solid customers, solid profiles, a long-term perspective — that's how we read this business. And from my standpoint, if they contribute the joint venture's equity and fund the full CapEx to build it while bringing their expertise, that's a superb arrangement for Solaria. Conversely, as I've described in another presentation, there's the opportunistic route of securing cash.

David Guengant

executive
#30

Our next question comes from Daniel Rodriguez at Bestinver. He has two: first, what capacity is currently under construction? Second, on the share buyback — has any decision been made about the possibility of a buyback that was already mentioned in the first half?

Arturo Díaz-Tejeiro Larrañaga

executive
#31

Executing a sharp buyback and acquiring shares is always on my mind. But life at Solaria is extremely complicated. A lot of things happen at the same time. And honestly, it's complicated to explain all of it. But share buyback is always on my mind. And who knows — it's complicated because share buyback is on my mind.

David Guengant

executive
#32

To respond to the first question, the capacity we have under construction right now is 1.4 gigawatts, and we anticipate that this capacity will be under construction and fully operational by the end of 2025. The next question comes from Henry Tarr at Berenberg. Regarding our 2024 EBITDA guidance, what are we assuming about capital gains, or data center revenue compared with the energy business? Consistent with what Arturo said and what we have said previously, we do not expect any further asset rotation this year. We have already included EUR11.5 million of asset rotation in the first half. And we may include some data center revenue, for 2024. The next question comes from Nashik Ho at Barclays. If we maintain our 2024 guidance, does that imply the Japanese data center deal will go through? That is the first question. And the second question is whether we can provide any timeline for the UK.

Arturo Díaz-Tejeiro Larrañaga

executive
#33

Naturally, the cash deal execution remains on schedule, and as we've explained, our aim is to complete it during this year. Negotiations are ongoing, and we keep working through the closing details. Hopefully, within this year, we'll be able to report the cash deal you're referring to. And of course, regarding the UK, when the first operational project might be expected — it's still too early to say at this point, though we will move quickly. That said, I believe during 2026 and 2027, we could report projects under construction as well as operational projects for 2027.

David Guengant

executive
#34

There are two more questions coming, and they're from Daniel Rodriguez at Bestinver. The first one: will we sign a PPA for the 1.4 gigawatt of capacity that's under construction? And the second: are we supplying power behind the meter to data centers?

Arturo Díaz-Tejeiro Larrañaga

executive
#35

Sure, on the PPA — yes, we will sign it. As I’ve said, we currently have a signed term sheet for just under 600 megawatts, and we had considered including that in this presentation too — the names of the parties and the term sheet, along with all the specifics of the term sheet agreements — but we’ll probably put all of that information into the full year report. That said, honestly, I don’t think signing the term sheet today and signing the contract is a big deal. I think it was done. And today, I could say that 600 megawatts is contracted under PPA, and the data center is the same. Obviously, with the joint venture — with a cash operation, as we’ve explained. Obviously, we’ll proceed with PPAs contracted and signed. And sorry, behind —.

David Guengant

executive
#36

Yes. Daniel's second question had to do with the — behind the meter. I think this matters a great deal for us, and not just for us, but for the choices the end customer makes. What our Powerland solution offers is behind the meter solutions. That is very important. Why? Because, as Arturo mentioned earlier, there is a cost saving — huge cost savings for the end customer of more than EUR20 per megawatt hour. This works as self-construction — as a self-construction solution it lets the data center avoid paying all the regulated cost — toll cost, transport cost, and also all the taxes plus the retail margin. So the saving is enormous. And thanks to that saving, the PPA price would be higher than in the normal PPA. The next questions come from Tomás Reis of CaixaBank. First question: in the case where we provide the land to the DC joint venture project, will you have to invest in acquiring or renting the land? Second question asks for more detail on the battery pipeline. When should we expect ready to build with geography?

Arturo Díaz-Tejeiro Larrañaga

executive
#37

It varies by project. Some projects call for leasing, while others involve buying the land outright. Ultimately, what we do is secure and allocate the land, then transfer it into the joint venture along with a fee. That's Solaria's role. Solaria is not going to purchase land using its own capital. We hand it over to the joint venture, and that includes a fee covering our development work — development that Solaria itself doesn't carry out. As for the battery pipeline, to be honest about batteries, I'm aware the market is intensely focused on them. My view is that it's a sound idea, though it hinges on regulation from the Spanish government. As you know, they intend to pass new regulation, theoretically in December. Whether they actually approve it, and what exactly they approve, remains to be seen. We would install batteries across all our PV assets and power plants. We've obtained licensing for batteries. That part is straightforward, not complex, and it could deliver a price premium. Still, we must wait for the new regulation, since at present in Spain — and not just Spain, but other European countries too — incorporating batteries isn't simple; in Spain especially, as things stand, it doesn't make sense.

Arturo Díaz-Tejeiro Larrañaga

executive
#38

I think if the Spanish government changes the law at the end of this year or in the first quarter of next year, we'll see. And with the new law, obviously, we could begin installing batteries on a massive scale across our installations.

David Guengant

executive
#39

Philippe Ourpatian from ODDO has the next question. Could we break down what makes up the "other" portion of revenue compared with electricity sales? I'll take that. Philippe, consistent with prior quarters and years, our other revenue has two primary parts: chiefly cost activation plus certain penalties—it varies by year and by quarter—but cost activation and penalties. Henry Tarr from Berenberg asks the next question. Which projects have mostly been affected by the infrastructure delays? How is the Garona project progressing?

Arturo Díaz-Tejeiro Larrañaga

executive
#40

Garona was among those projects. The Garona products ought to remain tied to the grid, likely during the summer of 2025, starting around the second half of 2025. In theory, the earlier plan had it in the first half of 2025. But this is a complicated piece of infrastructure. We ran into some issues with some of our colleagues. In the end, we are on our own at this connection point. And naturally, we are building out all the interest, but they have pushed things back a few months. And with luck, by the summer, we will begin connecting Garona. That covers three separate phases, three separate stages, and this progress runs live through the second half, when we are going to connect.

David Guengant

executive
#41

I’ll take the final question. Apologies for not responding to the question. The last one may be from Naish at Barclays. Is there any power assumption for Q4 in our guidance?

Arturo Díaz-Tejeiro Larrañaga

executive
#42

It's like a casino, honestly. The power price in Spain right now is just like a casino. There are plenty of analysts and folks out there offering clear, wise takes on electricity prices — they likely know more than I do, even after 20 years. Still, in my view, you'll probably see electricity prices in December looking similar to November, since gas prices and the Trump victory, Russia — you know, the situation is affecting gas prices, particularly in Europe. And obviously, that's going to have an impact on electricity prices. Short term, 100%. Medium and long term, I don't know. We'll see how the conflict — that war of Ukrania with Russia — evolves, and how the Trump government moves. That is something that's going to seriously affect euro prices of electricity.

David Guengant

executive
#43

Thanks, Arturo. And thanks to all of you for being on today's call.

Arturo Díaz-Tejeiro Larrañaga

executive
#44

I appreciate everyone joining this conference call. We'll be around to provide any further details. In my view, this is an exciting team, and the timing is exciting as well, since we're set to expand into new business and new activities. Europe is well positioned to draw data center investors who wish to grow — and who are required to grow — within Europe, and those investors will consume large amounts of power, specifically renewable power. They require infrastructure, and they require electricity — solar and wind power. And I believe Solaria will be among the leading players providing solutions to these parties, with a particular focus, as I noted, on Europe. In our thinking, this is the place to be; at times people assume the business lies outside old Europe. Yet from our perspective today, if you're after solid profits, solid project IRRs and security, Europe is the place — above all given this new growth tied to the data center business. Many thanks, and enjoy a great afternoon.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Solaria Energía y Medio Ambiente, S.A. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Solaria Energía y Medio Ambiente, S.A. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Solaria Energía y Medio Ambiente, S.A. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.