SSR Mining Inc. (SSRM) Earnings Call Transcript & Summary

February 23, 2022

Toronto Stock Exchange CA Materials Metals and Mining earnings 64 min

Earnings Call Speaker Segments

Operator

operator
#1

Good day, everyone, and thank you for joining SSR Mining's conference call for the fourth quarter of 2021. Please note that this call is being recorded. Right now, to give opening remarks and introductions, I'll hand things over to Alex Hunchak of SSR Mining.

Alex Hunchak

executive
#2

Thank you, operator, and good day, everyone. We appreciate you being with us for SSR Mining's conference call covering the fourth quarter of 2021. On this call, we'll share a business update and go over how our financial performance looks. Starting with the Q4 and full-year 2021 financial results, note that our consolidated financial statements follow U.S. GAAP. Those statements, together with the comparative restated financial statements covering the prior 2 years, are now filed on EDGAR, SEDAR, and the ASX, and you can also find them on our website. Alongside this call, an online webcast is available, and details on how to access that webcast appear in our news release for this call. Keep in mind that every figure we discuss today is denominated in U.S. dollars unless we say otherwise. This discussion will contain forward-looking statements. So please review the disclosures in the relevant documents. With us today are Rod Antal, President and CEO; Alison White, CFO; and Stu Beckman, COO. At this point, I'd like to hand the call to Rod for his opening remarks.

Rodney Antal

executive
#3

Thanks, Alex, and hello everyone—thank you for being with us today. We plan to take our time here, since there's plenty of encouraging news we're eager to share with all of you today. The main points are as follows: first, record production for the full year, reduced costs, and substantial generation of free cash flow. Second, the considerable organic growth opportunities across our portfolio have now produced a 14% boost to our reserves, which is a tremendous achievement. Third, the release of our new technical reports, which set out a remarkably strong 700,000 ounce per year baseline for our company. And lastly, our forthcoming execution plans for near-term growth opportunities, which rank among the highest-returning projects in our sector. So, to begin with our results. 2021—our first year after the merger—gave us the chance to demonstrate the quality and resilience of our asset base, which is diversified globally. We produced nearly 800,000 ounces, landing at the top end of our guidance range, while our all-in sustaining costs of $955 an ounce came in below the all-in sustaining cost guidance we had previously reduced, defying inflationary pressures. These outcomes reflected our outstanding operational performance and proactive management of the supply chain, and that performance delivered peer-leading free cash flow generation of $444 million for 2021, equal to a 12% yield.

Rodney Antal

executive
#4

Like we promised our shareholders, that free cash flow has gone straight into capital returns, and we returned almost $200 million to shareholders in the last year, which works out to roughly a 5% yield. With such a strong outlook for free cash flow generation over the years ahead, we'll keep delivering on our capital allocation strategy, and the 40% base dividend increase we announced recently shows that commitment. Second, alongside our full year results, we put out our updated resource and reserve statements. Those included impressive reserve growth of 14%, or 1.1 million ounces year-over-year. That came directly from our successful resource to reserve conversion at both Ardich and Seabee Gap Hanging Walls. This achievement is even more remarkable given that the cutoff — for our technical reports did not give us the opportunity to incorporate much of the drilling that occurred last year. We now stand with over 10 million ounces in reserves, with a weighted average mine life in excess of 17 years, anchored of course by Copler's 22-plus year mine life. Third, as part of our transition to becoming an SEC issuer, we are obligated to issue the SK-1300 technical report summaries at all 4 of our operating assets.

Rodney Antal

executive
#5

Like I said, the timing wasn’t perfect, since a lot of the good drilling results from 2021 hadn’t yet been included in the update, but we’re pleased with how the new production base line for SSR turned out. Taken together, the new technical reports have added over 2.5 million ounces of gold production beyond what the earlier versions showed. What that means is our goal of maintaining a production base above 700,000 ounces of gold for at least the coming decade has now become a reality. And on that note, we’re also excited about the possibility of improving this further through the drill bit. The fourth highlight concerns our upcoming growth projects. Within the Copler technical report update, we present both the maiden reserves and development plan for Cakmaktepe Extension, or Ardich, along with an initial resource and development plan for the Copler Copper Gold Project, or C2. That report showed how the many growth opportunities at Copler can add substantial value and deliver high-return, low-capital-intensity projects. Ardich and C2 together will each contribute at least 1 million ounces of production for modest capital outlays. C2, for instance, gives us 1 million ounces of production in its initial iteration for roughly $220 million of capital and an impressive IRR of 60%, whereas Ardich will deliver 1.2 million ounces for approximately $70 million of capital.

Rodney Antal

executive
#6

All in all, 2021 delivered outstanding results right across the business. If we turn to slide 4, the ESG slide, I'd like to restate how dedicated we are to our ESG priorities and initiatives. That said, I want to pause for a moment first and remember a tragic loss that hit our team in Argentina. Melina Estrada died on January 26 when the vehicle carrying her was swept off a river crossing on Highway 70 as she headed home from the mine site. The other 3 people in the vehicle were rescued, but tragically Melina was not. Steps were taken both to keep such an incident from happening again and to help her family and everyone affected. Her family, friends and work colleagues remain in our thoughts, as they always will. For SSR Mining, ESG has been a central focus and value for a long time, since it is a firm foundation for the success of our business. We are dedicated to the communities and to the environment, and we keep delivering on the priorities set out in our 2020 sustainability report. As we enter 2022, we will go back over and update those priorities, and we are putting the finishing touches on a refreshed sustainability report for release in the months ahead.

Rodney Antal

executive
#7

Crucially, our pledge to an action plan aimed at reaching net zero greenhouse gas emissions by 2050 remains something we keep working toward. That pledge is taken seriously by us and has been carried forward, and we are embedding it within the cycle of project development, which safeguards both the longevity and quality of our assets. In addition, we have begun already to strengthen climate and water disclosures, and we reported for the first time to the carbon disclosure project. Our efforts to sharpen our ESG approach make us proud, and we will keep evolving as a sustainable business going forward. Now, turning to the following slide and our performance highlights, I want to call out just a few items worth considering for the quarter. On operations, we posted another strong quarter, with production exceeding 210,000 ounces and all-in sustaining costs of $961 per ounce. On the financial side, adjusted EPS for the quarter came in at $0.46. Robust margins combined with low-cost production converted into $149 million of free cash flow, and $444 million across the full year. Following $191 million in capital returns and ongoing debt repayments, we held a net cash position of $681 million, which gives us the flexibility needed to move our large organic pipeline forward while continuing to deliver capital returns in the future.

Rodney Antal

executive
#8

We pointed to our growth portfolio, which had several encouraging exploration updates throughout the company, and our strong history of accretive, strategic M&A deals continues. We expanded our footprint in key jurisdictions — that includes announcing the Taiga Gold acquisition in Saskatchewan and raising our stake in the Copper Hill prospect in Turkey. On top of that, portfolio rationalization carried on, and we brought in more than $235 million in total consideration by selling non-core assets, among them our royalty portfolio and the recently announced divestiture of the Pitarrilla project in Mexico. Turning to the next slide: looking ahead to 2022, it's worth calling attention to our strong record on growth and execution. Back in January, we put out our first 3-year guidance, which demonstrates a solid production platform — we anticipate output of more than 700,000 gold equivalent ounces per year through 2024. That's a level we think we can sustain over a longer horizon, thanks to the abundance of exploration and growth opportunities that Stu will go into in more detail, and it is backed by the suite and the new technical reports we issued today. Now on to our 2022 outlook; I'd like to call out several of the priorities for the business this year.

Rodney Antal

executive
#9

We believe that our steady production foundation and cost structure are going to let us produce substantial free cash flow, and at the same time keep returning capital to shareholders via our higher base dividend and share buybacks. As we announced last month, our portfolio rationalization moved forward with the sale of Pitarrilla, and we are still assessing other opportunities to surface value inside the portfolio. We have now finished the SEC transition, including the new technical reports that highlight our baseline production platform, and we have budgeted a 45% increase in year-over-year exploration spend to further speed up some of the growth opportunities. And when it comes to cost, we will keep up our continuous improvement efforts in supply chain management initiatives so as to limit the escalating impact of inflation. At the asset level, we keep investing across the business in several high-growth opportunities, including breaking ground at Ardich later this year and advancing the C2 project toward prefeasibility study and ultimately targeting first production in 2025. Overall, we are in a fortunate position, with a plethora of exciting growth opportunities underway and on the horizon. As we look to improve even further the new baseline production profile contained in today's technical reports. A couple of highlights on the SK-1300s, and we recognize there's a lot of information in the technical reports to digest.

Rodney Antal

executive
#10

Alright, I'll go over a few of the top-level points, and Stu will go into more depth shortly. First off, we're pleased to highlight a 14% rise in gold mineral reserves compared with a year earlier, thanks to the maiden mineral reserve at Ardich Seabee's Gap Hanging Wall conversion. Total gold reserves now stand above 9 million ounces, and gold equivalent reserves climb to 10 million ounces. Regarding the technical reports, it's worth pointing out that these documents are an SEC requirement — for every SEC issuer under the new SK-1300 regulations. Although we had anticipated putting out the new master plan for Copler around this timeframe, much of the exploration and study work at Seabee and Marigold in particular had not yet progressed enough to be included in these tech reports. At Copler, we've published production scenarios covering both the reserve case mine plan and an initial assessment case for the C2 project, which resembles the PEA case for anyone familiar with that terminology. The reserve case includes maiden reserves from Ardich, giving a 21-year mine life with total production of 4.4 million ounces of gold.

Rodney Antal

executive
#11

That works out to a 37% lift in life-of-mine output versus the CD MP20 reserve scenario, and Ardich is what drives it — contributing 1.2 million ounces of total production beginning in 2023 for development CapEx of just $69 million. Beyond the reserve case, the initial assessment case sets out the possible development of the C2 project. The SGN resource gives us a chance to grow and lengthen the production profile even more by adding a copper concentrator to the existing flow sheets, which unlocks extra gold output from sulfide material. The initial assessment case demonstrates a total gold production profile of 5.4 million ounces, with average output above 300,000 ounces annually across the first 10 years. With total CapEx of roughly $220 million, this production scenario generates a robust overall after-tax NPV of $2 billion along with an internal rate of return near 60%, which I'm sure you'll agree are stunning returns. At Marigold, life-of-mine planning encompasses 2.5 million ounces of total gold production across an 11-year mine life. We see chances to optimize the production profile in the near term from targets such as new Millennium, plus potential further upside from incorporating exploration success at Buffalo Valley and Trenton Canyon.

Rodney Antal

executive
#12

Over at Seabee, the mineral reserve production profile gives us a 6-year mine life. During 2021, mineral reserves rose 18% year-over-year, which came from converting the Gap Hanging Wall, and alongside the current mine development we see additional chances to add reserves that would complement and extend future production profiles. At Puna, the tech report captures the mine's recent outperformance, including throughputs of almost 4,500 tonnes per day more. Exploration work is ramping up, with opportunities to complement the existing production profile through in-pit drilling and by targeting other brownfield opportunities. And last, the main takeaway is that the combined technical reports set a baseline production platform, and we see a clear opportunity there to deliver more than 700,000 ounces of gold equivalent production each year through 2020. But we're not finished, and with abundant growth targets moving forward across all 4 operations, we're excited about what we can build on top of this incredible result today. So with that, I'll hand the call to Alison, who will go into the financial performance in more detail on slide #9.

Alison White

executive
#13

Thanks, Rod, and hello, everyone. It's really exciting to be able to talk about yet another strong financial quarter for the business, as you can see on slide 9. Before I get into this slide, I want to note that this marks the first occasion on which SSR has reported results under U.S. GAAP, and that framework provides the accounting basis for the figures presented here. I'd also like to spend a moment thanking our team members for what was a major undertaking over the last month. It was an incredible effort across the business, and it involves nearly every function in the company to get us to where we are today, having filed for the first time as an SEC large accelerated filer. As we take our first look at the U.S. GAAP results, Q4 was another solid quarter operationally for the company. We produced more than 211,000 gold equivalent ounces and had gold equivalent sales of more than 218,000 ounces, for a total of $408 million in revenue for Q4, bringing total 2021 revenues to more than $1.4 billion. Attributable net income for the quarter was $127 million or $0.60 per basic share and adjusted attributable net income was $98 million or $0.46 per basic share. For the full year, attributable net income was $368 million or $1.70 per share and adjusted attributable net income was $402 million or $1.86 per share.

Alison White

executive
#14

Like Rod pointed out, we keep delivering across every part of our business, and we're proud of the cash flow and returns this produces — among them $609 million in operating cash flow and $444 million in free cash flow for 2021, which works out to a peer-leading 12% free cash flow yield. Over on the right-hand side of the slide, I want to give you some commentary on the $0.46 in adjusted earnings per share we reported, which is calculated using the company's own definition of adjusted attributable net income per share. We begin with attributable net income of $0.60 per share, then make adjustments to strip out the after-tax effect of certain items that don't reflect the company's ongoing operations. Every one of those items appears in the waterfall chart at the right of the slide, and the biggest adjustment, at $0.28, mainly involves removing the FX impact on non-monetary assets for the purchase price adjustment that was recorded as a result of the Alacer transaction. We'll go into more detail on this on the next slide, since it's a new adjustment stemming from the U.S. GAAP conversion. The other material adjustment is one you've seen before, at $0.14, owing to the fair value adjustment for inventory assets at Copler.

Alison White

executive
#15

That adjustment won’t carry into 2022. The smaller adjustments relate to COVID costs, other tax impacts, and transaction or integration expenses. Moving to Slide 10, we can discuss SSR’s SEC transition. Effective January 1st, 2022, SSR Mining moved to U.S. GAAP reporting as a large accelerated filer under the SEC. Consequently, our full year 2021 financial results came out under U.S. GAAP and were reported together with restated 2019 and 2020 financial results. On this slide, we’ve highlighted some of the more material changes to our financial reporting stemming from the U.S. GAAP transition. As we’ve mentioned before, our underlying business remains unchanged. Our basis of accounting has changed, and overall, even though we carried out a very thorough analysis of the details underlying the business that form our financial position and assessed the accounting positions needed to complete the transition, we have only a few material adjustments to highlight. A few key points to consider, which are also listed on this slide. First, the equity component of convertible debt is reclassified from equity to debt and is amortized under U.S. GAAP. Under U.S. GAAP, changes in the fair value of marketable securities are reclassified from other comprehensive income to net income.

Alison White

executive
#16

This figure is derived from adjusted attributable net income. We've updated both our reclamation and closure cost assets and liabilities so they reflect the company's specific discount rate as applied under U.S. GAAP, along with the tranche layering concept that the discounting analysis requires. The result is a lower liability and reduced depreciation on the asset retirement assets, offset by higher accretion expense. For the income statement, the combined effect of greater accretion and lesser depreciation isn't anticipated to be material. Under U.S. GAAP, writing up assets that have been impaired isn't permitted. Before 2019, IFRS rules allowed the Pirquitas mill at Puna — which had been impaired earlier — to be written up once the Chinchillas mine offered a chance to lengthen that mill's operating life. That subsequent write-up has now been reversed under U.S. GAAP so the original impairment is reflected. U.S. GAAP likewise eliminates the foreign exchange impact on deferred taxes. That said, under U.S. GAAP, when the functional currency — say the U.S. dollar — isn't the local currency, or the Lira in Turkey, remeasurement of nonmonetary assets and liabilities becomes necessary. Take, for instance, purchase price accounting for mineral properties and equipment of roughly $1.2 billion, the adjustment created when Alacer was acquired: it's treated as a nonmonetary asset subject to remeasurement, which produces a book basis deferred tax liability that will never be deducted for tax purposes.

Alison White

executive
#17

This item gets adjusted out of adjusted attributable net income since it's merely a book entry tied to foreign exchange on nonmonetary assets. Deferred stripping is no longer capitalized; instead it runs through production costs as an expense, which pushes cash costs higher and keeps AASC fairly steady, depending on gold prices and the total value of inventory. Last, reflecting the U.S. GAAP conversion, we've stripped out the GAAP-related effect attributable to the 20% noncontrolling interest in Turkey. Taken together, the U.S. GAAP regulation changes don't affect our underlying business and, apart from deferred stripping, are largely immaterial when it comes to analysts' estimates and forecasts. Moving to Slide 11, we can discuss SSR's continued balance sheet strength. At the close of 2021, the company held a cash and cash equivalent balance of over $1 billion, after returning over $191 million to shareholders and making $70 million in debt repayments during 2021. 96% of that cash balance sits in U.S. dollars. We stay well positioned to carry on our capital allocation policy going forward, fully funding our portfolio and focusing on additional explorations and growth opportunities that align with our business. We continue to hold a peer-leading net cash to EBITDA ratio of 1.1, along with the scale of our capital returns illustrated on slide 12.

Alison White

executive
#18

Through the first-ever share repurchase program in 2021 plus our base dividend payment that year, we've given back over $190 million to shareholders, which works out to capital returns above 5%. As we've mentioned, stronger operational results throughout 2021 fed into healthy cash flows, and we plainly matched that free cash flow achievement with our capital return efforts. When we issued our first 3-year guidance in January, we laid out a solid production outlook. Our Board declared a dividend that lifted our base dividend 40% to $0.28 per share annually, building on our pledge of substantial capital returns to shareholders. As 2022 proceeds and we look further ahead, our capital allocation priorities stay the same: putting money into growth, keeping the balance sheet strong and sending cash back to shareholders. We'll remain disciplined in carrying out our priorities, financially and operationally alike, as 2022 unfolds. And with that, I'll hand things over to Stu for an operational update.

Stewart Beckman

executive
#19

Thank you so much, Alison. Before I get into the specifics, I want to say a few words about the composite production profile shown in the technical reports on Slide 13. This represents simply the following stage and a solid base that we can build on. Keep in mind that C2 is captured in this slide, yet no production upside at all from our broad near-mine and in-mine exploration portfolio is reflected here. This year, we have committed considerably to raising our organic growth spending, so that we can define and demonstrate what we believe will be a far longer and stronger future production profile. I will pass my optimism along to you as we go through the slides for each property. Let's begin the discussion with Copler on Slide 14. We began putting together the Copler District masterplan several years back, to help steer and concentrate this strategic mine development. We released CDNP 20 in November 2020, setting out Ardich as the PEA case, with the intention of converting it to a feasibility level reserve in the technical report for the following year. As promised, Ardich added 1.6 million ounces of reserves and 1.2 million ounces to our production profile in this year's CDMP21 report, which was even better than the case we had laid out in the PEA.

Stewart Beckman

executive
#20

The production and development group along with the Copler team have stayed occupied with permitting and getting things ready, and later this year we intend to begin work on the ground. Project costs are quite modest, confined to infrastructure and enlarging the Copler heap leach. Material from Ardich will be hauled by truck to Copler for processing. Exploration continues at Ardich, which remains open. Given the drilling now underway, we anticipate continued growth in both resource and reserve. We likewise have certain concepts and studies in progress regarding ways to draw additional value out of the deposit through better recoveries, so further value should still emerge from Ardich. Beyond the success at Ardich, we have presented an initial assessment, or PA case, offering a first look at the next development of the Copler deposit, the C2 projects. Let me spend a minute describing the C2 project. Copler holds a substantial quantity of copper in the deposit, within as well as around the resource and reserve. Historically, that copper carried little or no economic value. Following successful drilling and metallurgical test work, we shifted the paradigm and took a fresh look at the mine, presuming we could capture value from the copper.

Stewart Beckman

executive
#21

The result of this study was the extremely accretive food project that we laid out in the initial assessment case. In that initial assessment case, a small 1.8 million tonne per annum copper concentrate was added to Copler. That will produce both a gold-rich copper concentrate for selling to smelters and a gold-rich pyrite concentrate, which we'll use as supplemental fuel and gold fee into the autoclaves. We're also adding a copper recovery circuit inside the sulfide plant that will produce the copper concentrate for sale. The addition of the copper concentrator and the sulfide copper recovery circuit has 2 big impacts. The first, and really the obvious one, is that it adds direct value from the copper and gold recovered from a -- from the copper gold ore, as copper concentrates. And second, the extra value from the copper lets us make a much bigger pit. As we dig that bigger pit, we uncover far more sulfide and oxide gold ore to feed the existing oxide and sulfide gold plants, which gives a longer life and higher production from these plants. The C2 project is being accelerated into feasibility study. We expect to leverage more value out of the project as we optimize the metallurgy and the mine scheduling.

Stewart Beckman

executive
#22

Copler is an outstanding asset, and beyond the Ardich and C2 upside laid out in the technical report, there are quite a few exciting, active exploration targets at Copler and across the Copler District. Moving to Marigold on Slide 15: because the technical report was filed on an accelerated basis, the exploration results at Marigold that we announced recently weren't ready to be included. Even so, Marigold still put out a solid base technical report, with a couple of notable features. As we deplete the existing high-grade areas, production dips, particularly around 2026 and '27, and then Red Dot comes online, bringing a big increase in output in 2028. A lot of the exploration from our December release, both recent and ongoing, is designed to drill the production date 2024 through 2027 — in particular the near mine exploration inside the existing plan of operation and the current application to extend Valmy, including much of the new Millennium exploration. Over the longer term, we have extensive targets at Marigold, among them Trenton Canyon and Buffalo Valley, where we do hold some historic permitting, which may help make them quicker to advance. The bulk of our exploration centers on delivering high-grade oxide ores, since those offer the lowest cost and easier development pathways.

Stewart Beckman

executive
#23

That said, we've encountered some quite intriguing sulfide intercepts at Marigold — most recently at Trenton Canyon, for instance — and we have a hypothesis about the potential for meaningful sulfide deposits. In light of that potential, along with the company's expertise in constructing plants and processing refractory sulfidic ores, we are keeping some exploration work focused on the sulfide ore targets. Funding for exploration and resource work at Marigold will rise substantially this year, by roughly 20%. If you'll turn to Slide 16, we'll talk about Seabee. A few important points from the technical report: it extends Seabee's mine life by more than twofold. We achieved record output of 119,000 ounces at Seabee in 2021, and our budget assumes '22 and '23 will be back-to-back record years. Each of those years will exceed 120,000 kilo ounces — 120,000 ounces — which is the new normal at Seabee. Although the technical report has production declining in '24 and beyond, we anticipate adding higher-grade ore from Santoy 8 and 9 — today's source of high-grade material — into the production profile during those later years. Santoy 9, for instance, produced some terrific upside surprises in 2021 and that has carried into this year, a strong reminder of what in-mine exploration can deliver.

Stewart Beckman

executive
#24

We're boosting exploration and resource development drilling at Seabee by over 20%, so that we can be sure to hold the current production profile at this new normal. On top of that, we've managed to secure solid gains in production performance at Seabee, and we're factoring those into the plan. Even with those gains, we still have spare capacity at the mill, which we're able to capitalize on by growing production rates in the mine. So the operation sits in a strong position to ramp up production on the strength of exploration success in the mine, and at very little cost. Beyond the active mining area, the Seabee district holds a spectacular endowment of exploration targets at various stages of evaluation. We have a multiyear exploration strategy that brings in the Tiger Holdings. Our focus is mainly on near-mine low-cost development, with a modest spend still directed to generative work and target evaluation. One area that's bubbling to the top of our list at the moment is the Shane target, which sits just off the Haulage Road close to the Seabee plant. You'll hear more about Shane through the year. Please turn to Slide 17, and I'll give a brief update on Puna. Puna delivered a solid base technical report, which assumes the recently demonstrated improved mill performance of 4,500 tonnes per day.

Stewart Beckman

executive
#25

During 2021, we were quite active at Puna, going back through the exploration database, doing a substantial amount of field geochemical sampling, plus relogging and reassaying portions of the historic drill core. We've identified some very solid targets, and drill testing will get underway imminently. First, inside and around the Chinchillas pit, we believe there's a strong opportunity to expand the resource, and drilling will begin soon. Having reassayed some of the Cortaderas drill core, we've formed some hypotheses regarding a possible extension of the deposit and its value. Similar to the depleted San Miguel pit, we're beginning to see gold emerge at depth alongside the silver and zinc. The geology team is busy putting together a drill program to test the potential extension and value proposition. We also have regional targets that emerged from last year's work, and we'll devote some effort to advancing those too. Kindly turn to Slide 18 for the close; SSR holds a very high-quality and extensive exploration portfolio, and our aim is to leverage value from it in a structured manner. Just as we did with the Copler district masterplan, we're strengthening strategic mine planning and mapping out pathways toward a growing, long-term production profile. To close, 2021 was an excellent year for the operations and development teams at SSR.

Stewart Beckman

executive
#26

We supported our communities and our teammates through yet another difficult year of the pandemic. Our ESG performance improved — we more than halved the total recordable injury frequency rate — and our ESG reporting got better, something reflected in higher ESG ratings. As always, those results stem from stronger ESG and operational discipline, which brings better production performance — better production performance — and in 2021 we delivered the top end of guidance in a merger year, thanks to a lot of work, went against the industry trend and managed to keep costs down below guidance, grew our resources and reserves, and delivered a number of highly accretive projects for the business, which you can see showcased in our technical reports. We have a great team, a great exploration portfolio — you can see it on this slide — and a solid base, and we'll keep developing that and leveraging value from it. With that, I'll turn the call back to Rod for his closing remarks.

Rodney Antal

executive
#27

Okay, thank you Stu and Alison. There's certainly plenty on the agenda today. In summary, 2021 proved to be a year in which SSR outperformed on operating results, on generating free cash flow, on capital returns and, naturally, on the exceptional growth outcomes. Through the technical reports released today, we've now established a solid baseline production profile, along with a clear opportunity to carry our 700,000-ounce production profile forward into the coming decade. We'll keep building on that foundation over the near and medium term. 2022 will be another strong year for the business, including continued robust capital returns and free cash flow generation. Given a solid portfolio of organic growth opportunities, we anticipate that our expanded exploration budget will help us further pinpoint and define an even brighter future, which we've laid out today. So with that, I'll hand the call back to Eileen so she can take any questions you might have.

Operator

operator
#28

<<operator_script>> The initial question comes from Tyler Langton at JPMorgan.

Tyler Langton

analyst
#29

Yeah. Rod, Alison, and Stu, I appreciate you taking my question. So Stu, to begin, I suppose, with Copler — for Ardich, I believe you're mentioning production beginning in 2023. Could you give us a bit more detail on whether certain permits or other items are needed in order to reach that production date? And then regarding C2, I think you mentioned the next step might be a PFS, and I'm curious about the timing you anticipate for that?

Stewart Beckman

executive
#30

Alright, Stewart here — I'll take that one. So permitting for Ardich has been underway for a while now. And as some of you on these calls may recall, roughly 50% of Ardich fell within the Cakmaktepe EIA, which is the reason that in quite a bit of the documentation you'll find it referred to as the Cakmaktepe extension. So the application covering the extension at Cakmaktepe — the first stage of Cakmak for the start of pits — is currently in process, and we expect it to come through within the next 2 months. Following that, we'll have a number of local earnings coming on the back of it. At this point, we see a path to having those permitted so that we can begin work in Q4 of this year and then advance in line with what the technical report shows. And as is always the case with permitting, a series of subsequent permits follow. We're currently writing the scope of work for the C2 feasibility study. Obviously, we do have work ongoing that came out of the order of magnitude scoping study work we were carrying out through last year — that continues. And we're now at the stage where — we did engage Senko for the capital cost estimates, and then we factor those using the numbers we had from the recent construction of both the Float plant and the CEC treat plant.

Stewart Beckman

executive
#31

We believe those figures are quite robust. And at this point we're ready for far more granular scheduling and engineering effort, which we anticipate getting approved at the start of April, with serious work beginning right after that.

Tyler Langton

analyst
#32

Thanks, that's useful. Then I suppose, turning to capital returns, Rod — I’m aware of the recent dividend hike. Any views on buybacks? And clearly, during last year you completed quite a few sales of noncore assets. Are there further ones you might consider, or have you largely sold off what you intended to?

Rodney Antal

executive
#33

Tyler, I'll take the second part, and Alison can handle the first question. Regarding the portfolio review, that process remains underway, and we're looking internally to be sure we've covered the obvious candidates you might raise, such as San Luis and others. But we're applying that same discipline throughout the exploration portfolio too. We're land rich — we hold considerable acreage around our asset bases — and we keep working through it, turning over and replacing ground where the hypothesis may not <<inaudible>> for our exploration efforts. That churn is going to continue; it's ordinary business for us as 2022 moves along. Still, we did a heavy lift in '21, so I'd say the larger-scale opportunities have largely been addressed by now.

Alison White

executive
#34

And Tyler, on the share buyback plan, I'll take the first part of that. So as you may remember, earlier in 2021 we announced a plan allowing us to repurchase 10 million shares, and roughly 1.2 million shares remain outstanding under that plan. Our intention is to execute against it, provided doing so would be accretive for us. So we'll take a look at what that valuation amounts to and act accordingly.

Operator

operator
#35

Cosmos Chiu from CIBC has the next question.

Cosmos Chiu

analyst
#36

Perhaps I'll start with a question about Copler and what kind of growth we might see there. As you mentioned, the ore that's rich in copper is going to let you expand the pit. How much of that possible extra sulfide and oxide material have you factored into the technical report you have today?

Stewart Beckman

executive
#37

So with Cosmos, everything mined that meets the cutoff grade for plant feed—once we've built the larger pit—gets included in what goes to the plant. So the value of C2: even though copper is what enabled us to make the bigger pit, the bulk of the value comes from gold. And as a matter of fact, the concentrates we produce from the concentrator run about 2 ounces. So as far as our read is concerned, it's mostly a gold concentrate.

Cosmos Chiu

analyst
#38

Alright, and after that...

Rodney Antal

executive
#39

I believe… Cosmos, go right ahead.

Cosmos Chiu

analyst
#40

Alright, yes. I’d like to ask a follow-up about capital expenditures, specifically the $218 million at C2. Your record for staying on budget and on schedule is quite strong. Still, I’m curious about how much inflation you’ve built into your CapEx estimates. Stu, you mentioned this briefly, but I’d like a little more detail on how you’ve incorporated it. The Turkish lira has also been volatile, so how have you accounted for that possible risk when you put these CapEx figures together?

Stewart Beckman

executive
#41

Yes. So keep in mind, this is a case at the initial assessment stage. So the estimate is, roughly speaking, one with a plus or minus 50% range. That said, I'd tell you that we have a fairly solid grasp of what the costs look like. We've just completed construction of the flotation plant. So when it comes to concrete and steel costs, especially the ones we're able to source locally within Turkey, it's a very cost efficient location in which to build things. As I mentioned, Senko did support us with the engineering work, and then we factored that using good factoring numbers. So as estimates go, it's a good one, a really solid estimate for a project at this point in time. But there is a lot of work still ahead of us. I think there's actually quite a lot of opportunity in what we ultimately end up with at the plant, and in how we might be able to leverage value from the plant as we go forward. We've been examining whether or not we would be — get a significant advantage by bringing Ardich and some of the high-grade Ardich ores, the oxide ores, and treating those through the sulfide plant, either simply grinding them or augmenting them with sulfide to boost the recoveries, and leveraging quite a lot of value out of that.

Stewart Beckman

executive
#42

That said, it's a fairly big undertaking, along with the scheduling, and that will take place after this particular piece of work. So I'd say there's considerably more still to come from it, Cosmos.

Cosmos Chiu

analyst
#43

No, I'm glad you raised that, since it ties in nicely with what I was going to ask next about making use of the infrastructure and the copper concentrate. And as you said, you've raised your stake at Copper Hill. Was that sort of thing factored in too? Might you be able to take advantage of it further down the line with some of these other, richer copper areas?

Stewart Beckman

executive
#44

No. Of course, there will be difficult synergies from the business. But the gap between the operations is going to prevent us from sort of shifting any of the material around. And regarding Copper Hill, what we observe there is a very clean chalcopyrite ore, which is really just chalcopyrite. And it's near the coast, and it's actually very close to the smelter. So we'll move a little bit there. Copler is also blessed with sort of amazing infrastructure as well. So you might recall when you were there, we have a railway directly beneath the mine, which sits right next to the hydroelectric power stations on the other side of the highway. So as far as the infrastructure for building a copper concentrate, it could be in a better place. A little bit more flat ground would have been handy.

Cosmos Chiu

analyst
#45

Absolutely. Let's turn to Marigold next. As you noted, the technical report released today was essentially a base case, built solely around reserves. Could you remind us — as your map showed, there are quite a few targets in play, including New Millennium, Buffalo Valley, Trenton Canyon and Valmy, just to name a few. Which of those made it into this base case? And what should we expect regarding what gets included in what I believe is another technical report possibly coming later this year?

Stewart Beckman

executive
#46

Basically, the reserves are as they were — everything stayed at Marigold, so just the deposits that already exist. What we're aiming to take advantage of moving forward are the zones surrounding the current pits. And keep in mind, we also have an application in for a Valmy extension, and that Valmy extension was submitted using a considerably bigger pit shell. So it captures essentially all of New Millennium, and that will more or less end up inside that new pit. So we're concentrating on drilling out that region, so that within roughly the next year, we can bring it into the reserve and then demonstrate that value and close that gap — the one I mentioned — in the production profile before we reach Seabee — sorry, not Seabee, Red Dot.

Cosmos Chiu

analyst
#47

Possibly just one final question — a quick follow-up on that. In the MD&A, I saw mention of a possible standalone infrastructure setup for Buffalo Valley and Trenton Canyon. Could you say a bit more about that? Is it simply a matter of scaling it up, or are you hinting at something for the sulfides? Would you mind expanding on that a little?

Stewart Beckman

executive
#48

One opportunity that's emerged which could genuinely boost efficiency — and maybe lead to a fair amount of rescheduling at Marigold — involves putting in a heap leach at the property's southern end, right where the pits sit today, cutting down the haul, and then being able to apply that to Buffalo Valley as well, plus the southern pits at the Marigold deposits that already exist. And from there we'd move the carbon up to the desorption circuit that's already in place. So we're working through that right now, and we figure it might let us extract some genuine value from Marigold by going that route. Still, we haven't done sufficient work at this point to fully get our arms around what that could be worth.

Operator

operator
#49

Moving on, we have a question coming from Ovais Habib at Scotiabank.

Ovais Habib

analyst
#50

Rod and the SSR team, congratulations on a strong quarter. Most of my questions have already been answered, but maybe a bit of a follow-up to the last question Cosmos asked. Regarding the tech reports released today, you noted that all of these are base case scenarios and don't include drilling that took place in 2021. So based on the endpoint and what your exploration team expects, which operating asset do you see with the most potential upside in the near term?

Stewart Beckman

executive
#51

That is a tough one to answer. Some of it did get included. For us, the drilling cutoff, for instance, came around late May into early June. And I believe we had roughly 104 holes after that point. So my sense is Ardich will keep expanding. We are confident growth will show up around the pits that already exist at Marigold. So over time we will build on that. What is happening at Seabee has us genuinely enthusiastic. And I think if you look at Seabee's figures — Seabee's output rate being higher, a step off — we feel quite certain we can fill that gap, just as we managed with the extensions at Santoy 8 and Santoy 9, pushing those sideways from where the mine sits today. And since we have so much unused capacity in the mill, we can add the somewhat lower grade — 5 or 6 grams lower grade — at Seabee. We will deploy that as top-up material wherever we have spare room in the mine. Down the road, and there is a great deal of work before we get there, we would eventually like to see perhaps another decline at Seabee, an all-weather road, and a meaningful increase — that is entirely conceivable at Seabee.

Stewart Beckman

executive
#52

Even so, there's plenty left for us to accomplish, along with some exploration that needs to accompany it. Still, the signs look favorable.

Rodney Antal

executive
#53

Yes. I think you can take — when you look at it, it's across the portfolio, they're different, but they're all just as exciting as each other, as we work through. I think what Stu's outlined here and what the team have done, during 2021 has just been terrific in terms of prioritizing and being very methodical and thoughtful in the way we've approached it. That's going to continue into this year, and if we have time and obviously success, you can see what we can do — if we have the focus on the right areas, and we do expect that to come from the rest of the portfolio as Copler did, so.

Stewart Beckman

executive
#54

I think at some point you should also start getting excited about Copper Hill. If you look at the drilling assets that we have there and the fact that it's open around, it's a nice high-grade copper deposit, relatively easy, and it looks like it will be easy to treat at daylights. So relatively easy access. So we're hoping we can develop that site pretty quickly as well. But that will rely on getting access to drill.

Ovais Habib

analyst
#55

Great, and let me ask one more thing on that front. I realize we've discussed all of this away from these calls, and it shows in the portfolio you hold today. Do you have any views on M&A? What about projects you might be considering, extensions of the assets you already own, or anything else available in the market?

Rodney Antal

executive
#56

Ovais, this is really the same question, and I think our position has consistently been this — we'll be thoughtful about it. We'll examine opportunities. We won't cease evaluating possibilities outside our current portfolio that would remain consistent with our strategy, so that they complement both the strong asset base we hold and the solid fundamentals of the business we've built, and we'll move them forward. And the less we say about them, and obviously they're not of interest to us, and we're not discussing a lot. So at this point there's genuinely nothing further to discuss. But we will look into it.

Operator

operator
#57

Moving on to Mike Parkin from National Bank Financial, who has our next question.

Mike Parkin

analyst
#58

Folks, honestly, most of it has already been covered, but regarding the exploration activity you have underway at Trenton Canyon and Buffalo Valley, could you give us a bit of a walkthrough — you have shared some fairly solid detail on your thinking. That said, how should we think about things past the exploration updates — for instance, where would you expect to begin seeing resources come together there, assuming the drill programs keep delivering success?

Stewart Beckman

executive
#59

My guess is that this will get clearer as we move through this year and likely into next year. At Buffalo Valley, we actually carried out quite a bit of geochemical work to confirm we hadn't overlooked anything. We wanted to be sure we were targeting the right locations and applying some alternative methods. We've been drilling with the aim of expanding the resource already identified there. At Trenton Canyon, we're also encountering some intriguing results — we're seeing somewhat more of that narrow-vein, high-grade material, in contrast to the broader, lower-grade zones found elsewhere. That actually lines up with how it was mined historically, when the workings were comparatively narrower than our current mining approach. So there's still a fair amount of work ahead of us before we can present a clear development pathway there...

Mike Parkin

analyst
#60

All right. Also, is the historical drill core available to you — the one the legacy pits were based on?

Stewart Beckman

executive
#61

Yeah. So every bit of that data got passed along. When situations like this come up, that's just how it goes, and many of those records are pretty dated. So I wouldn't call it flawless. Still, we've got the full delta.

Mike Parkin

analyst
#62

As I understand it, that work was carried out at a rather small scale, using smaller benches, which means the cut-off grade is likely higher. So do you see potential for some of those results to serve as fairly easy wins for you — perhaps, just because of how old the data is, you would want to verify it with some holes — but is that part of your thinking, that it may be low grade yet actually quite strong relative to what you currently mine at Marigold and generate plenty of cash from at a larger scale?

Stewart Beckman

executive
#63

Yes. Well, if that's what you have in mind, our focus would likely be more on outflow value. In that region, we do encounter certain anomalies related to drilling, because when the work was carried out — at Trenton Canyon in particular, we see this from some time ago — the grade fell below the cutoff, and in some of the data sets those grades weren't reported; they were simply recorded as no report. So we've been going back and redoing the analysis on a number of those samples. And that is partly what drives the drill plans we are putting together for those projects.

Mike Parkin

analyst
#64

All right, and this will be my final question. We are noticing a bit of a squeeze when it comes to the availability of drill crews, mainly in Canada. Are you encountering that same sort of limitation in Turkey or in Nevada?

Stewart Beckman

executive
#65

Things are going fine on our end. In Turkey, we have everything we were after. The labs are definitely having a hard time, no question. Jim, who runs things in Nevada, did manage to lock down the drills he requires for this year, though it was not easy on health. So yes, we have observed a bit of tightness in that area.

Mike Parkin

analyst
#66

That covers everything from my side, everyone. Many thanks, and I look forward to the years ahead of us.

Operator

operator
#67

The last question comes from Michael Siperco at RBC Capital Markets.

Michael Siperco

analyst
#68

Let me just focus on the 3-year guidance for a moment. You clearly had a strong 2021, coming in almost at that $800,000 mark, but over the next couple of years the outlook is lower — understandably so, given the sequencing items you've talked about. How worried are you about that lower headline production figure? And are there any levers you could pull in '23 or '24, perhaps? From the base you've built, is 800,000 ounces a year achievable, or does that not concern you much?

Stewart Beckman

executive
#69

Honestly, Michael, I’d say this mostly comes down to how we’ve sequenced the mine. Especially at Copler, when you take the combined view across all our operations. In the recent technical reports, we had already signaled the Life of Mine production profiles, and output does decline for a period as Cakmaktepe is brought online. So this is exactly what we expected, and no, it isn’t something that concerns us. What we’ve really concentrated on is building a longer-dated future and laying out that next decade so we can hold at least 700,000 ounces and give ourselves a very stable platform. If it moves up to 750,000, then to 800,000, and later back down to 750,000, that works for us too, and our priority has really been to target a production profile of 10-year plus 700,000 ounces. As of today, with the technical reports that have been published, you’ve probably heard us mention around 4 times on this call that we feel very confident we will get there. So that has really been a priority for us.

Michael Siperco

analyst
#70

All right, great. And just very briefly on capital allocation — sorry if I already missed this earlier in the call — but you're at or near a 52-week high right now. Could you refresh any guidance on how you're thinking about repurchasing shares, where you'll be active, and perhaps whether there's a point where you'd prefer a special dividend over a buyback?

Alison White

executive
#71

Yes, and thanks for asking. Our plan is definitely to keep going with the buyback program we launched back in 2021. That program still has a few months remaining for repurchasing shares, and we've also got some shares still available to buy under it. Roughly 1.2 million shares remain. Beyond that, we'll factor in where the market prices sit right now, along with the company's valuation, and reassess whether launching another buyback program makes sense. Or we might consider other alternatives, such as a special dividend or perhaps something different altogether. So we will certainly be examining that, and we just need a bit of time to sort through it all, given everything that's been disclosed today and all the information we currently have.

Operator

operator
#72

That brings the Q&A portion to a close. Mr. Antal, I'll now hand the call back to you.

Rodney Antal

executive
#73

Well, thank you all. Clearly there’s plenty to cover today, so I appreciate your patience while we went through things a bit. Obviously, a huge amount — really interesting, exciting news, building on a fantastic ’21. So we look forward to keeping you updated during the year and talking more as ’22 unfolds. Thanks, everyone.

Operator

operator
#74

That brings us to the end of today's conference call. Your lines can be disconnected now. Thanks for joining us, and enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete SSR Mining Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to SSR Mining Inc. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in SSR Mining Inc. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.