SSR Mining Inc. (SSRM) Earnings Call Transcript & Summary
November 8, 2022
Earnings Call Speaker Segments
Operator
operatorWe appreciate everyone being on the line. I'm the conference operator. Good day, and welcome to SSR Mining's conference call covering the third quarter 2022 results. Please note that everyone is in listen-only mode at this time, and this call is being recorded. Following the presentation, we will open things up for questions. If you'd like to enter the question queue, press star followed by one on your phone's keypad. If you require help at any point during this call, you can reach an operator by pressing star then zero. At this time, I'll hand the conference over to Alex Hunchak of SSR Mining. You may proceed.
Alex Hunchak
executiveThanks, operator. Good morning, everyone, and thanks for being with us on SSR Mining's third quarter 2022 conference call, where we'll give you an update on the business and walk through how we performed financially. Our consolidated financial statements for the third quarter of 2022 are presented under U.S. GAAP. Those statements have been filed on EDGAR, SEDAR, and the ASX, and you can also find them on our website. There's an online webcast that goes along with this call, and the details for accessing it are in our news release about the call. Please keep in mind that unless we say otherwise, every figure we discuss today is in U.S. dollars. This discussion will contain forward-looking statements, so please read the disclosures in the relevant document. With us on the call today are Rod Antal, our President and CEO; Alison White, our CFO; and Stewart Beckman, our COO. I'll now hand things over to Rod for his opening remarks.
Rod Antal
executiveOkay, thank you, Alex. Hello, everyone, and I appreciate you being with us. During the third quarter, the suspension at the Çöpler mine clearly had an effect on our business. I'm happy to say that operations began again at the end of September and increased steadily without issues. Even with that setback at Çöpler, our company is still in an extremely strong position, supported by a solid balance sheet that has given us a capital returns yield above 5% across two years in a row. As we look ahead, we are in great shape, with each of our four assets set up for a strong fourth quarter, in which we anticipate getting back to meaningful free cash flow generation. A few important highlights from the quarter. Taking into account the minimal contribution from Çöpler and the ounces that were delayed from Marigold, we generated 107,000 gold equivalent ounces. Production for the year to date now stands at 441,000 gold equivalent ounces. Our all-in sustaining costs for the third quarter came to $1,901 per gold equivalent ounce, after we absorbed over $30 million in cash costs that were incurred at Çöpler during that quarter. For the year to date, our all-in sustaining cost is $1,331 per gold equivalent ounce. I'll discuss guidance in a bit more detail later in the presentation. On the financial side, our balance sheet and free cash flow outlook have supported the buyback of $100 million in shares under our NCIB so far this year.
Rod Antal
executiveWe’ve been moving quickly on the NCIB—it was announced only in June—and that puts us on pace to return almost $160 million of capital in 2022, which works out to a +5% capital return yield. Turning to growth, during the quarter we obtained the EIA for stage 1 of the Çakmaktepe extension project at Çöpler. Infrastructure construction is now underway, and that keeps us on schedule for first production in 2023. As a reminder, this project will contribute more than 1.2 million ounces to the Çöpler life of mine plan, with incremental CapEx of roughly $70 million. We expect the C2 PFS results next year in an updated technical report for Çöpler, and we intend to publish a new technical report for Marigold that will reflect exploration success and potential production growth. Near the end of the year, we plan to issue exploration updates for Marigold, Seabee, and Copper Hill. That comes on top of the positive drill results we just released for the Çakmaktepe extension. Finally, we keep advancing our strategy of reinvesting proceeds from non-core asset sales in our core jurisdictions, as shown by the Kartaltepe transaction announced in October. Let’s move on to the next slide on ESG.
Rod Antal
executiveNow, I'd like to emphasize our core values as they connect to a few of the initiatives we have in place. During 2022, we kept delivering on the targets set out in our annual sustainability report. For instance, we're continuing the rollout of our integrated management systems, with full implementation anticipated by year-end. In addition, we're making headway on developing a water stewardship strategy, since we aim to keep shrinking our environmental footprint as we move forward. You'll hear more in our update early next year. Turning to slide number five. As we move into 2023, it's worth pointing out our long-term, stable platform of 700,000 ounces of annual gold production. With every operation back at steady state in the fourth quarter, we're confident we can sustain and grow from this production baseline through 2030 and perhaps beyond. A strong foundation, combined with the many growth targets being advanced across the portfolio, means this production graph is simply the baseline we'll keep building on. Moving to slide six. As a company, we've built a proven track record of discipline and accretive M&A, along with project development. That includes the sale of Pitarrilla, which closed in the third quarter and was another element of our non-core asset sales that have brought in $245 million in sale value since early 2021, over 2 times the Street consensus attributed to those assets.
Rod Antal
executiveLike I mentioned, we've successfully put those proceeds back to work in our core jurisdictions. First, through the Taiga acquisition, which expanded our Seabee land package earlier this year, and most recently through the Kartaltepe transaction, which raises our ownership across the entire Çöpler district to 80%. That latest deal delivers meaningful operational, financial, and exploration synergies, including removing future ore purchases and payments tied to the ownership differential that existed before. Çöpler is our cornerstone asset, and we're glad to be increasing our exposure to the district's longer-term growth and its excellent exploration potential. With our strong track records in operations and project execution, along with a robust balance sheet, we keep thoughtfully assessing strategic opportunities throughout the sector, while staying disciplined in how we approach them. Moving to slide seven. Over the past two years, we have returned our strong free cash flow generation, which shows up in our capital returns programs. Along those lines, so far this year we've returned $144 million to shareholders via the base dividend and share buyback program. Even more impressive, since the start of 2021, we have returned more than 90% of our free cash flow generation to shareholders, which delivers on one of the key promises made after the merger.
Rod Antal
executiveI'd like to turn to slide eight now and talk about the quarter. These are the main points worth considering as we close out the third quarter. As I said, Çöpler restarted at the end of the quarter, and the ramp-up of the sulfide plant has progressed very well — a major accomplishment for our team. Year-to-date production came in at 441,000 ounces, with all-in sustaining costs of $1,331, which mirrors the suspension at Çöpler and the delays in recovering gold at Marigold. Now that our operations are back to steady state, we anticipate a return to robust free cash flow in quarter four and beyond. We're certainly excited about our portfolio of low capital intensity growth opportunities and keep moving each of them forward, with several updates anticipated before year-end. Turning to slide nine. I'd like to offer a few remarks on guidance. We remain on track for a strong quarter four, though we haven't been able to make up the lost production, so we are now revising full-year production guidance to 620,000 to 655,000 ounces. That reflects slower-than-expected leaching of the stacked higher-grade ounces at Marigold, which Stu will go into further, along with the shutdown at Çöpler.
Rod Antal
executiveOver at Puna, the team has performed really well against the guidance we originally set, though weak metal prices have shifted the gold-to-silver ratio, which means fewer GEOs when converted than what we initially guided to. And Seabee is still tracking toward the higher production guidance we shared last quarter — a terrific outcome for that crew. Our all-in sustaining cost guidance now sits at $1,315-$1,345 per gold equivalent ounce to account for that updated production guidance. That works out to roughly 200,000 ounces in quarter four, and so far in quarter four we're tracking right to that target. As I noted, several exploration updates are coming before year-end. Looking ahead to next year, we intend to publish the PFS for C2 along with a new technical report for Marigold. Inside the company, we're excited about what lies ahead for every one of these assets, and this year's exploration results keep reinforcing that confidence. With that, I'll hand the call to Alison, who will take you through our financial performance beginning on slide number 10.
Alison White
executiveThanks, Rod, and good afternoon—or good day—to everyone joining the call. During this quarter, we generated just about 107,000 gold equivalent ounces, which lifted production for the year to date to 444,000 gold equivalent ounces. Sales of 97,000 gold equivalent ounces in the quarter generated $167 million in revenue. The attributable net loss for the quarter came to $26 million, or a loss of $0.12 per diluted share. Adjusted attributable net loss was negative $14 million, or a loss of $0.07 per diluted share. Worth pointing out is that both the attributable and adjusted attributable losses take in over $40 million of care and maintenance costs incurred at Çöpler while operations were suspended for nearly the whole quarter. Over on the right-hand side of the slide, I'll address the reported $0.07 loss per diluted share, which is computed using the company's own definition of adjusted attributable net income or loss per share. The attributable net loss of $0.12 per share was adjusted for transaction costs tied to the Pitarrilla sale, tax adjustments, and minor adjustments for foreign exchange fluctuations during the quarter. Moving to slide 11, we can discuss SSR's financial position. As the quarter closed, the company held a cash and cash equivalent balance of almost $800 million, with net cash exceeding $450 million.
Alison White
executiveThat solid cash position comes from $100 million spent buying back shares, $44 million paid out as dividends to shareholders, $53 million used to repay debt, and $35 million distributed as dividends to joint venture partners so far in 2022. Given the net cash we already hold and our expectation of a strong fourth quarter for free cash flow, I want to restate the three priorities guiding how we allocate capital in the business. Above all, we will keep reinvesting in growth across the business, including our C2 and Çakmaktepe extension projects, which deliver exceptionally high returns and together will represent roughly $300 million of growth capital through 2025. Next, we are dedicated to keeping a robust balance sheet so we can ride out volatility in commodity prices and make certain that every capital commitment, debt servicing obligation, and base dividend payment is fully funded even if the gold price cycle turns down. Our base dividend of $0.07 a share is likewise resilient to gold price downturns, since it remains payable down to a gold reserve price of $1,350 per ounce. We anticipate that the $88 million left on the term loan will be fully repaid by the end of 2023. All told, we have produced $371 million of free cash flow, equal to $300 for each gold equivalent ounce produced, since the beginning of 2021.
Alison White
executiveCapital returns to shareholders remain a priority for us—they’re the third pillar of how we allocate capital. So far this year, we’ve bought back $100 million of stock. Add in the 40% dividend increase we announced earlier this year, and we’ve given back almost $150 million to shareholders—the second year in a row our capital returns yield has come in above 5%. From the beginning of 2021 through now, we’ve returned roughly $335 million to shareholders while producing 1.2 million ounces over that stretch, which works out to $270 returned per gold equivalent ounce produced during the period. Taken together, we have a clear capital allocation framework that we execute on regularly, and we’ll stay disciplined in how we approach capital returns well into the future. With that, I’ll hand it over to Stu for an operational update.
Stewart Beckman
executiveThank you, Alison. I'll begin, as I always do, with the HSMS. We felt good about getting operations going again at Çöpler near the close of the quarter, after the improvement initiatives the Turkish authorities required had been finished. The suspension was a letdown, yet it gave us a chance to go back over several of our processes and systems and make them better for performance. That start-up went smoothly, which speaks to the effort the team put in. On a separate and encouraging note, we secured a number of outstanding permits in Türkiye over the quarter. We'll keep working hard to preserve and strengthen these relationships, making sure we deliver positive contributions to our stakeholders and host communities. The safety and care of our teams, communities, and the environment are core values that we believe are also fundamental to business performance. Turning to slide 13, I'll discuss Çöpler. At Çöpler, the operation ramped up without a hitch in the third quarter — an impressive feat for our team considering how long the suspension lasted. As we mentioned on the Q2 call, during the suspension we managed to speed up maintenance on autoclave one, which included completing partial relining of the face bricks. Because of that, no major planned maintenance is scheduled in the sulfide plant for the rest of the year, so we can run the autoclaves without significant interruption through the fourth quarter.
Stewart Beckman
executiveBecause operating hours and output were quite constrained during the third quarter, per-ounce costs don't carry much real significance. Across the whole year, our expectation is to generate 180,000 to 190,000 ounces, with an all-in sustaining cost between $1,345 and $1,375 per ounce. That lower production guidance mirrors how cautiously and deliberately we are bringing the operations back up, along with oxide ounces becoming accessible later than we had anticipated. Turning to the growth initiatives, the EIA has come through for phase one at the Çakmaktepe extension, infrastructure construction is moving along nicely, and we still expect to achieve first production during 2023. In addition, we are advancing the C2 project via a PFS and anticipate sharing results from this more optimized project with the market in the coming year. Both of these growth projects, which offer high returns with low capital intensity, have us genuinely enthusiastic. The Kartaltepe transaction we spoke about earlier should likewise assist us in achieving long-term cost and operational synergies, while letting the exploration team dig into a variety of highly prospective exploration targets throughout the district, free from the added complication of blended ownership percentages. At the Çakmaktepe extension, for instance, half the holes in the October exploration release sat on Kartaltepe ground, expanding the deposit beyond the lease boundary and further strengthening our case for the transaction.
Stewart Beckman
executiveNow turning to slide 14, we'll give an update on Marigold. Once again, Marigold showed sequential quarterly gains, although the timing of production is still being affected by the stacking of finer material coming out of the north pits. Output of 52,000 ounces, with an all-in sustaining cost of $1,444 per ounce, fell short of what we had expected, but we're beginning to observe a favorable trend when it comes to leaching in the fourth quarter. A couple of the factors behind the leach rate being slower than we had forecast were that we wound up with a larger number of tons of fine material showing up in the north pits than had been scheduled. That's actually a positive, and it happened at the same time as less durable material was coming from the Mackay Pit, which pushed the proportional fines in the heap leach higher. In addition, following advice from certain subject matter experts, drawing on experience at other sites, we have begun to slow down the application of the leach solution at the outset of leaching, with the goal of enhancing the overall performance of the heap leach. Consequently, taking into account the leach cycle delays experienced so far this year caused by the stacking of finer ore, along with the ongoing difficulties with shovel availability, we now anticipate full-year production of 195 to 205 ounces at an all-in sustaining cost of $1,410 to $1,440 per ounce.
Stewart Beckman
executiveThe really weak results from the Komatsu PC7000 shovels have been offset by keeping older digging units in service longer than planned, and by year-end we anticipate stacking roughly the budgeted ounces. During the quarter we kept stacking higher-grade material, with over 135,000 recoverable ounces placed at a grade of 0.63 grams per ton — extremely high for Marigold — across Q2 and Q3. On top of that, October was an outstanding month, with 48,000 recoverable ounces stacked to the pad in a single month. Consequently, we project robust output late in Q4, continuing into the first half of 2023. As one further remark, we've conducted numerous internal and external evaluations of heap leach performance over the course of the year and feel confident the gold will be recovered and that this is purely a timing issue. Permitting at Valmy kept moving forward, and the EA for the expanded Valmy pit is still expected on schedule for 2024. An exploration release is due in the coming weeks, intended to add more mineralization and ultimately reserves within the Valmy EA areas. We'll incorporate as much of that as we can into the updated Marigold technical report, which we expect to publish to the market in 2023.
Stewart Beckman
executiveLet's turn to slide 15. At CC&V, the third quarter came in broadly as planned. After record output in the first half, the mine kept lifting its underlying performance, though grades were weaker. Because of Q3, we now anticipate reaching the bottom of the full-year guidance range we raised earlier — 150,000 to 160,000 ounces — which is a truly remarkable result for this operation. All-in sustaining costs of $715-$745 per ounce also match what we expected previously. We're running a touch ahead of schedule on mining a very high-grade reserve area later in Q4. Exploration is moving forward on the extension of that exceptionally high-grade zone, the one that produced the spectacular first-half output beyond reserve estimates. This zone narrowed to nothing just beneath the last slope, yet it looks like it reopens a couple of levels lower, and we expect to be able to mine there in 2023. We simply need a little more drilling to confirm the zone before we can add it to the mine plan. The plant has been running at record throughput, and a decent-sized run-of-mine stockpile sits ahead of it. As a reminder, the CC&V plant generally has more capacity than the mine does and typically runs with little or no ROM stockpile.
Stewart Beckman
executiveFor CC&V's future development, we see plenty of targets with strong potential. At the Porky West target, we've kept advancing both drilling and modeling — it could be an open pit option for CC&V. Should it pan out, Porky, together with extensions to the resource we're currently exploiting, might offer an exciting route to reframe CC&V. Above all, we keep working hard to broaden what we know about the resources and reserves surrounding the active mining areas, including the testing of that very high-grade zone I brought up earlier. To back the longer-term vision for CC&V, we're also prudently exploring the numerous targets across the very large tenement at CC&V and the recently acquired Taiga tenement, with the goal of feeding more into our medium and long-term resource pipeline. Turning to slide 16, I'll give a brief update on Puna. Puna kept up its steady production and stays well on track toward guidance of 8.25 to 8.75 million ounces of silver, with improved all-in sustaining cost guidance of $1,550 an ounce. For the asset, Q4 has so far been another strong quarter, and we're genuinely pleased with the team and what they've achieved in Argentina despite a number of local headwinds. Let's move to slide 17.
Stewart Beckman
executiveTo spotlight a few of the exploration efforts we moved forward during the quarter. During the third quarter, we advanced exploration programs throughout the company, and we're getting ready to publish the results from that work over the next few months. As you observed, resource development and extension drilling produced several exciting outcomes at Çakmaktepe extension, as we look toward further growth of the ore body to supplement the production profile already set out in the last technical report back in Q1. In Türkiye, we've been enjoying some strong success with drilling at the Copper Hill target, our copper prospect — surprisingly, located in the Black Sea region. We expect an update on that project by the end of the year. I've already covered Seabee exploration. In Nevada, exploration advanced both near the mine and across the region. Drilling is ongoing at Trenton Canyon and Buffalo Valley, and near-pit drilling at New Millennium is delivering encouraging results. Six rigs are on site, and we're carrying out geophysical studies to deepen our understanding of the opportunities. An update on these exploration wins is expected imminently, and a portion of the New Millennium drilling ought to be part of our next reserves and resources update. Finally, at Puna, we began drilling for the first time since 2018.
Stewart Beckman
executiveAt the moment, our attention is on targets within the pit and close to the mine, and the team has been genuinely energized by a number of the intercepts and grades we have encountered to date. The goal, clearly, is to expand the mine reserve and prolong the currently known life of the Chinchillas mine and Puna. Right now, we are exploring the distal and regional targets that look promising, which would deliver a considerably longer life at Puna. Drilling at some of the more regional targets in the vicinity of Chinchillas and Pirquitas is set to start over the next few months. To sum up, we intend to publish exploration updates for Copper Hill, Seabee, and Marigold within the next few months, and for Puna next year. All of these exploration programs share the objective of delivering a high-return build-out of our medium- and longer-term production profiles. Before I hand things over to Q&A, a farewell. Being part of the team that built up and transformed Alacer and then subsequently SSR has been very gratifying. I leave the business in great hands with a fantastic management team, strengthened by my role being split into an EVP Growth role, which John Ebbett is leading, and the new EVP Operations and ESG role. We have a fantastic business with huge potential. Both John and the new EVP Ops are very accomplished and capable, and I'm sure they will leverage off our successes so far and lead the business to bigger and brighter achievements in the future.
Stewart Beckman
executiveMuch appreciated. Over to you now, Rod.
Rod Antal
executiveThank you. Stewart, Alison — my thanks to you both. I'd also like to use this moment to acknowledge how much Stewart has contributed to this business; he's leaving all four operations in great shape and well set up for a solid fourth quarter and beyond. We wish him every success going forward, and I'd note that an announcement about Stewart's successor will be coming very soon. Our business stands in a very strong position, and we're advancing at full pace into the final quarter. With every asset now back to steady state, we anticipate a return to robust free cash flow, and we have several potentially positive catalysts ahead. We're eager to share these developments through a steady stream of news releases in the months to come and to report a much stronger result when we next speak in early next year. With that, I'll hand the call to the operator for questions. Thank you very much.
Operator
operatorThanks, Mr. Antal. We'll move on now to the Q&A portion. If you'd like to join the question queue, just press star followed by one on your phone's keypad. A tone will confirm your request. Should you be on a speakerphone, lift your handset first before hitting any keys. If you need to pull your question, press star then two. Our first question comes from Ovais Habib at Scotiabank. Please go ahead.
Ovais Habib
analystThanks, operator. Hi, Rod, and hello to the SSR team. I've just got a couple of questions. Regarding Marigold, Stewart brought up the fines there. My understanding is that these relate to the north pits. So the question is whether you've finished sufficient met test work around and within the north pits to feel comfortable moving forward in handling those fines. And is the high grade also largely situated around the north pits?
Stewart Beckman
executiveAffirmative on every one of those. Yes, that high grade was recovered from the north pits. The test work has been completed, and, as I mentioned during my talk, several different people have reviewed those results, and we see no issue with the heap leach. Drawing on their experience at other sites, we anticipate that we will ultimately recover this, the gold. As you can see, we have sacked a considerable amount of gold. We also sacked it fairly late. We expect this wave of gold to reach us over the course of this quarter and on into the next one. We have essentially completed mining the fine material as well.
Ovais Habib
analystSo the mining of fine material wrapped up during Q4? Or did that actually finish at the close of Q3 — which was it?
Stewart Beckman
executiveIt's wrapping up very soon now. We're nearly there.
Ovais Habib
analystUnderstood. Are there additional high-grade zones inside these pits that you plan to focus on as you move into 2023?
Stewart Beckman
executiveThe northern pits are done — we've wrapped up work on all of them.
Ovais Habib
analystAlright.
Stewart Beckman
executiveThose were never anything more than small pits. That's exactly what the mine schedule calls for.
Ovais Habib
analystGreat, thank you Stu. On Çöpler — regarding Çöpler, are you at nameplate capacity at the sulfide plant now? Or should we expect some wrap-up in Q4?
Stewart Beckman
executiveNo, the sulfide plant performed really well and got up and running quite fast. Honestly, I was very happy with it, and considering what I've seen from starting up these kinds of operations following an extended shutdown, I believe it showed the effort we put in. You have to keep in mind that we halted everything, so sadly, mining of the oxide operations and exploration had to stop, and we even stopped the infrastructure work across the district. When we brought things back, the sulfide plant ramped up nicely and very fast. It's extremely steady and operating beautifully. I couldn't have asked for more. Mine operations also needed restarting, and that required more time since we had to get the team back together. For clear reasons, we didn't retain a very big idle mining crew onsite. Bringing them back and getting the mine going again took a little while, and that hurt the grade going into the plant and also held us up somewhat in gaining access up to Çakmaktepe to recover some ounces we had intended to bring down from there. Toward the end of the year, we also restored higher-grade gold feed at the back end.
Stewart Beckman
executiveBecause of that delay we had during that stretch, the timeline has shifted out too. Mining is happening in the pits right now. We're pulling material from the Çakmaktepe area and trucking it down. Another step we took: when the sulfide plant was brought back online — since that's exactly where the problem had occurred — we proceeded very cautiously. First we began recirculating and stacking the material, and after we felt confident with that, we reintroduced the cyanide, purely to ensure there were no small disruptions while we did so. That has consequently held up some of the leaching from the oxide plant too. To put it in perspective, we still have not observed the cyanide and gold emerging since leaching began there. Restarting that leaching cycle simply requires a bit of time. Once again, we have strong confidence that we're in a very solid position and the operation is running really well. It will simply take a little time for us to get the oxide fully coming out and to bring the grades in the sulfide back up.
Ovais Habib
analystStu, thanks for that update too. Regarding Çakmaktepe, when it comes to getting to the oxide material, do we see you starting to process that material in Q1 of next year? This is sort of heading toward—
Stewart Beckman
executiveAlright.
Ovais Habib
analystAs you bring things to a close and move toward the latter half of the year?
Stewart Beckman
executiveI think it's just worth keeping in mind — and you cover this in detail when you discuss it — that Çakmaktepe has two components. There's the old residual mine up there, where we produced gold a couple of years ago, and it still holds some residual ounces that we had expected to bring into this quarter. Then there's the new Çakmaktepe extension. I just don't want people to get confused, because I think those are two different things. One is a new project, which is earmarked for next year. The other is the residual ounces that we're going up there to mine as the last piece of this quarter.
Ovais Habib
analystAppreciate the clarification there, Rod. Yeah, my question concerns the new Çakmaktepe. Could you share a bit more detail about how progress is going at that site?
Stewart Beckman
executiveThings are moving along nicely. The infrastructure prep has been underway — some public roads need to be rerouted. We've put up overpasses to keep our mine haul trucks apart from the rest of our vehicles and away from public traffic. A few dedicated roads are also being built. Right now we're handling the upfront steps for the relocation. One telecommunications tower has to come down. Power lines and water lines also need shifting. That work is actively in progress at the moment, and it's going quite smoothly. We've consistently anticipated a late 2023 kickoff for it.
Ovais Habib
analystGreat, that covers everything on my end. Appreciate you answering my questions.
Stewart Beckman
executiveAppreciate it, everyone.
Operator
operatorWe’ll take questions once more—just hit star one if you’d like to ask one. Cosmos Chiu from CIBC is up next. Go ahead, Mr. Chiu—your line is open.
Cosmos Chiu
analystApologies—I had myself on mute. Hello, Rod. Thank you, Alison, and best wishes, Stu. I'd like to begin with a question about Marigold. What I wanted to ask is whether the elevated grade—stacked at 0.63 gram per ton compared with your reserve grade of 0.48 gram per ton—can be sustained. It appears the grade is positively correlated with the fines and with the North Pit. Stu, as you noted, once mining of the North Pit wraps up, should we expect the grade to return to the mean relatively soon?
Stewart Beckman
executiveCosmos, you've hit the nail on the head. Reverting to the mean is precisely what we'll do. That's the very reason it's called the mean.
Cosmos Chiu
analystAlright.
Stewart Beckman
executiveWe'll return to that point. In the oxide — sorry, in those North Pits — we actually got a windfall. They reconciled high. More material ended up coming out of those pits than the reserves had contained. We were quite pleased about that. Those areas are now finished, and we had anticipated higher grades during this period while we were processing them.
Cosmos Chiu
analystThanks. Stu, I may have missed it — did you say how much additional time these fines need before the gold comes out, in terms of the leach cycle? I understand you expect it to come out in Q4 into 2023, so how much longer is that?
Stewart Beckman
executiveI don’t believe we’ve really put a number on it in months, because it doesn’t necessarily show up in one discrete step—it tends to draw out with a fairly long tail. I also mentioned one of the directives we received—I think it came from John Marsh—and what other sites have seen when they have fine material: when you first begin leaching, you start at a much lower rate and saturate the pile first, so it doesn’t mobilize the finer material inside it and then create stratification, which then makes leaching take even longer. We have two impacts this quarter. We have the effect of stacking more fine material, and we’ve also begun the leach cycles more slowly, so we’re applying less leach liquor to it for the first couple of weeks and then increasing it. It’s somewhat difficult to express it in exact weeks. As you know, it depends—since we’re approaching the end of the year, we try to stack in the narrowest parts of the heap leach so that we can get it out by year end. It’s also a function of where on the pile it is stacked.
Stewart Beckman
executiveThat is a rather tough one to answer. We've also been collaborating with Forte Dynamics, and that effort has stretched across the entire year, aimed at building three-dimensional leach plans along with a far more precise picture of exactly what went where on the heaps, so we can forecast more accurately what will come off the heap.
Rod Antal
executiveYeah. And the other point I'd make, Cos, is that what Stu described leaves us feeling very confident as we head into the next phase. It's a strong position to have those ounces stacked up. When you've got plans weighted toward the back end and something like this occurs, you really get no room to recover. I'd say we're partly a consequence of that too. I simply wanted to calm any worries people out there might have that the gold won't arrive. We committed ourselves through to the end of the year. We've got the gold sitting on the pads. The leach cycle has come in slower than our models anticipated, and there's no time left to make that up — that's really all that has happened.
Cosmos Chiu
analystUnderstood. Perhaps we can turn to Çöpler now. You may have already addressed this as well, but as I work through the math, it's great to hear that you did 18,000 ounces in the month of October, and from my math it sounds like you still need to increase that on average by about 16% in November and December. Is that a function of tonnage and grade? From Stu and Rod, your comments, it sounds like it is both, but I just want to confirm.
Stewart Beckman
executiveI'm sorry, could you say that again? We didn't really follow what you were asking.
Cosmos Chiu
analystYou hit 18,000 ounces. To meet your full-year guidance for Çöpler, I believe you need 60,000 ounces in October — 60,000 ounces in Q4. Running the numbers, that means roughly a 16% gain over the 18,000 ounces from October. I'm just curious whether that November and December improvement, on average, comes from tonnage, grade, or both. Stu, I think you sort of said it could be both — I just want to confirm.
Stewart Beckman
executiveSure.
Cosmos Chiu
analystSimply Çöpler.
Stewart Beckman
executiveYes. Over at Çöpler, the oxide is arriving somewhat later than expected, and consequently we're seeing slightly lower grades — that's due to the mine ramping up along with certain efforts we've had to undertake in order to rearrange the mine plan. Tonnage won't be the driver. What drives it will be timing plus a bit of grade.
Rod Antal
executiveYeah, Kos, I'm not sure — I believe you joined slightly after that point.
Cosmos Chiu
analystYou're right about that.
Rod Antal
executiveDuring discussion — that's fine. Just to clarify once more: in the Stewart discussion, we mentioned that bringing the mining contractor back to site and getting mining underway took somewhat longer than we had expected, and also getting that ramp-up in place to reach the higher grade, which we anticipate will now begin to arrive for the sulfides I'm referring to. We're heading in that direction. Everything suggests we will hit that restarted guidance.
Cosmos Chiu
analystUnderstood. Thanks, Rod. I joined a little behind schedule. Signing on took me 10 minutes. Possibly something related to the financial side. I hope I'm not making the same mistake again. I saw a note in the MD&A. It doesn't seem significant to me — you did say that because of what occurred at Çöpler, there's non-compliance with the term loan covenants. There isn't much outstanding on that, so I just want to confirm: should we be worried?
Alison White
executiveNot at all, Cosmos, that wouldn't worry me. The reality is that this was our position when the quarter wrapped up, and we believed it mattered, from a disclosure standpoint, to let everyone know. Even while the closure was going on, we kept making the payments on the loan whenever they came due. And as I said in my remarks — apologies if you missed that part too — we actually expect to be in a position to pay off that loan in full by the close of next year.
Cosmos Chiu
analystThanks. Alison, while you're on the line, I wanted to ask about the cash cost and the unsustaining cost this quarter, which took a hit from roughly $31.1 million in costs tied to the Çöpler suspension. I just want to confirm whether there are any costs we ought to know about that are carrying over into Q4. My assumption is that these are one-time in nature. I simply want to verify that none of those one-time costs are spilling into Q4. Given that operations have already restarted, that doesn't seem to be the case, but I'd like to confirm.
Alison White
executiveYou've got that right. Not a single one of those expenses will carry over into Q4, Cosmos. Every one of them was a one-time expense tied specifically to the closure, along with standby-type costs for labor and other items, so that we could ramp up as fast as possible once we received the go-ahead to reopen.
Cosmos Chiu
analystAll right, perhaps one final question here. This one may be tough, but I’ll go ahead and ask it anyway. Rod, after the restart—once you received the permits again on September 22nd and brought Çöpler back online—did you at that moment think about revising guidance? And if so, what has shifted from that point to the present?
Rod Antal
executiveNo, that's a fair question, Cosmos. Look, I think back when we held the quarter 2 results call, remember, we stated that we would do everything possible to recover the time we'd lost, along with the lost production. We had a plan in place, just as we always do. There were several levers within the business that we could use to help, to try to pursue that as an objective. As things turned out, given the clarity around slower leaching at Marigold, the effects of the gold to silver ratio at Puna, and some of the other initiatives we had aimed at chasing those residual answers at Chalcocite, we simply don't have the time available to pull it off. Unfortunately, we did a great many things in an effort to capture it, but in chasing the high grade at Seabee that Stu mentioned, we just haven't been able to catch it. No, that wasn't taken into consideration. At that point we wanted to see how the operations were performing so that we could have a more accurate representation. If we're going to recut guidance, obviously we want to be in a position to hit it. It wasn't the appropriate timing. Look, we did everything we could. It's disappointing to all of us that we couldn't capture it.
Rod Antal
executiveIf Marigold had not come up short on gold output during the quarter just ended, we would likely be sitting pretty right now — but that isn't the case. That's the situation we're in. Honestly, the underlying business is quite robust, in my view. As we exit into Q4, with a consolidated outlook of roughly 200,000 ounces for the business, we're heading into what should be a genuinely strong 2023. With all the positives that go along with that — free cash flow and the rest — we're positioned well. We hit a rough patch, and at this point we're focused on what's ahead.
Cosmos Chiu
analystThanks, Rod — that’s completely clear. And again, I appreciate you taking my questions, and best wishes to you, Stu.
Rod Antal
executiveAppreciate it.
Stewart Beckman
executiveCosmos, nicely done — thanks.
Operator
operatorThat brings the question-and-answer portion to an end. Mr. Antal, I'll hand the conference back to you for any closing remarks.
Rod Antal
executiveThank you very much. Appreciate all of you being here today. As we said, we anticipate reporting a considerably improved set of full-year results early next year, and we're finishing this year in a really robust position that will prepare us for what promises to be an excellent 2023. On that note, have a good day, everyone, and thank you for attending.
Operator
operatorThat brings us to the end of today's conference call. You can go ahead and disconnect your lines now. Thanks for joining us, and have a pleasant day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete SSR Mining Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to SSR Mining Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in SSR Mining Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.