operatorGood day, everyone, and thanks for joining SSR Mining's conference call on the financial results for the third quarter of 2024. Please note that this call is being recorded. Right now, to give opening remarks and make introductions, I'll hand things over to Alex Hunchak of SSR Mining.
Alex Hunchak
executiveThanks, operator, and good day to everyone. We appreciate you being on today's conference call, where we'll give you an update on the Çöpler incident and also walk through our third quarter financial results. Our consolidated financial statements are presented in accordance with US GAAP. Those financial statements have been filed on EDGAR, SEDAR, and the ASX, and they're available on our website as well. There's an online webcast accompanying our call, and the details for accessing the webcast can be found in our news release relating to this call. Please note that unless otherwise indicated, all figures discussed during the call are in US dollars. Today's discussion will include forward-looking statements, so please read the disclosures and the relevant documents. In addition, we will refer to non-GAAP financial measures during our discussion and in the accompanying slides. For information about the comparable GAAP measures, please see our press release. Rod Antal, Executive Chairman, will be joined on today's call by Michael Sparks, CFO, and Bill MacNevin, EVP Operations and Sustainability. I'll now hand the line over to Rod.
Rod Antal
executiveThank you. Appreciate that, Alex, and I want to welcome everyone for being with us today. Today’s call will begin with an update on Çöpler, where I’ll recap the work done so far and outline the main areas we’re focused on moving ahead. After that, we’ll give you an update on the third quarter financial results along with operational highlights from Marigold, Seabee, and Puna. Since the incident at Çöpler, we have made solid progress on four key priorities. Those are: first, recovering our missing colleagues; two, containing and remediating the site; third, investigating what caused the heap leach failure; and fourth, getting ready to restart the Çöpler mine. On our missing colleagues, all nine individuals have now been recovered and returned to their families. We continue to support the families and community members affected by the Çöpler incident. Second, every piece of the planned containment infrastructure has been successfully installed and is proving effective. Statements made publicly by Turkish government officials keep reiterating that no recordable contamination has been found in local soil, water, or air at the sampling locations. Working alongside the Turkish authorities, we have kept advancing remediation at the site.
Rod Antal
executiveWe've made solid progress so far: more than 16 million tons of the displaced heap leach material has now been relocated into temporary storage areas, and that includes substantially all of the displaced material from the Sabırlı Valley. As part of the remediation effort, and consistent with what we previously disclosed, the heap leach pad is going to be permanently closed, and there will be no future heap leach processing at Çöpler. Discussions are ongoing with Turkish government officials regarding the final remediation plan, including approval and construction of the storage facility that will permanently hold all of this displaced material. The remediation and containment work at Çöpler is estimated to cost between $250-$300 million and to take a total of 24 to 36 months to complete. During the third quarter of 2024, $48 million was spent on remediation activities at Çöpler, which brings total remediation spend since April 1 to $103 million. Third, on the incident investigation: the initial design of the heap leach facility, prepared before production began in 2010, along with each subsequent expansion after that, was engineered, reviewed, and approved by independent third-party engineering firms. At the various stages of construction over the life of the heap leach facility, third-party reviews were also carried out to confirm conformance with the underlying engineering design parameters.
Rod Antal
executiveWork to determine what caused the Çöpler incident got underway soon after it happened. We brought in independent specialists to examine the design, the construction, and the operations of the heap leach facility. As of today, that review has not turned up any material non-conformance in how the heap leach facility was built or run when measured against the third-party engineered design parameters. On the last point, regarding a possible restart, we are continuing to cooperate closely with the relevant authorities to move forward the permits needed to restart the Çöpler mine. Once every regulatory approval, including the operating permits, has been reinstated, the expectation is that initial operations at Çöpler could begin again within 20 days from that moment. So let's now turn to slide four, where Michael will go over the third quarter results.
Michael Sparks
executiveThanks, Rod, and good afternoon, everyone. In the third quarter of 2024, output came to 97,000 gold-equivalent oz, with all-in sustaining cost of $2,065 per oz, a figure that includes cash care and maintenance costs incurred at both Çöpler and Seabee, amounting to roughly $252 an oz. Forest fires on August 21st led to Seabee being placed into temporary care and maintenance, and operations were restarted afterward on October 11th. Year to date, Marigold, Seabee, and Puna together have produced 249,000 gold-equivalent oz. Over the quarter, we kept advancing brownfield exploration programs at Marigold, Seabee, and Puna, which Bill will discuss later. In addition, site establishment and engineering activities at Hod Maden are continuing to progress. Moving to slide five for a brief look at the financial results. We recorded attributable net income of $0.05 per share in the third quarter, while adjusted net income per share was $0.03, largely reflecting the exclusion of minor tax and foreign exchange gains according to the quarter. As a reminder, we do not adjust for care and maintenance costs, and the full impact of these expenses at both Çöpler and Seabee are included in our adjusted net income. Including the remediation spend at Çöpler, third quarter cash generated by operating activities was negative $1 million, while free cash flow was negative $34 million.
Michael Sparks
executiveWe closed out the quarter holding $334 million in total cash, alongside a net cash position of $104 million and total liquidity of $834 million. Given the liquidity we already have on hand, plus expectations that production and free cash flow generation will improve in the fourth quarter, we continue to sit in a strong financial position and are well placed to handle the remediation costs at Çöpler while also meeting our ongoing reinvestment needs throughout the business. Moving to slide seven to talk about operations, where Bill will begin with Marigold.
Bill MacNevin
executiveThanks, Michael. At Marigold, output for the third quarter came to 48,000 oz, which matched what we had anticipated. Consistent with the 2024 mine plan, the fourth quarter carries the year's lightest production and its heaviest costs. We remain on course to achieve full-year production guidance of 155,000 to 175,000 oz. That said, we now anticipate higher full-year costs, driven mainly by greater royalty expenses and maintenance component costs that came in above what we expected. Roughly 60% of the upward revision to Marigold's AISC guidance stems from elevated royalty costs tied to the strong gold price in 2024. We anticipate that both of these cost pressures will carry over into 2025. Brownfield exploration and desktop studies at Buffalo Valley moved forward during the quarter, as we aim to keep replacing mine depletion and possibly extend Marigold's operating life further. Turning now to Seabee. At Seabee, third quarter production of 10,000 oz reflected the temporary suspension of operations on August 21st because of forest fires near the mine. Fortunately, no employees were hurt by these fires, and the processing plant at Santoy Mine was not materially affected. Although certain remote equipment—power poles, piping, and exploration equipment among it—sustained damage, operations were fully restarted on October 11th.
Bill MacNevin
executiveBecause of the suspension, Seabee's guidance for all of 2024 now stands at 65,000 to 70,000 oz, with AISC between $1,725 and $1,755 per oz. Seabee remains focused on assessing and drilling near-mine extensions of the existing underground mineralization, along with continuing to advance the Porky and Porky West targets. Those Porky targets offer a possible opportunity to extend mine life, and the team at Seabee is pushing technical studies forward aggressively so the opportunity can be better delineated. Although forest fires in the third quarter affected the surface drilling program, the vegetation the fires cleared has given our exploration team fresh opportunities to assess surface targets during upcoming field seasons. Turning now to Puna. Puna generated 2.9 million oz of silver in the third quarter, marking a second straight quarter of record throughputs at the Pirquitas processing facility. Given strong operating results across the last two quarters, Puna is now expected to produce 10 to 10.5 million oz of silver in 2024, which is an increase of more than one million oz of silver on a midpoint basis. Although Puna's full-year cost expectations remain unchanged, the AISC of 1,537 per oz in the third quarter showed the significant free cash flow margins Puna enjoys in the current silver price environment.
Bill MacNevin
executiveBeyond that, exploration and technical efforts are ongoing to assess chances for lengthening operations at Puna — through possible extensions at Chinchillas and by continuing to advance the Cortaderas target with near-mine drilling. At this point, we'll hand things back to Rod for his closing remarks.
Rod Antal
executiveThanks, Michael, and thank you, Bill. As I said, we laid out 4 commitments after the Çöpler incident. Those commitments represent significant milestones on the road toward a possible restart of the operation. And as I noted, we keep making solid headway on every front. We're expecting a strong finish to the year at Marigold, Seabee, and Puna, and we'll keep advancing chances to strengthen our business through operational excellence efforts and brownfields growth projects as we head into 2025. As Michael said, we have kept moving Hod Maden forward, and we expect to give an update on the capital spend we anticipate for 2025 at that project, alongside our usual guidance update early next year. So far, our work keeps showing an exceptionally high-quality asset that will be a key contributor to our portfolio going forward. With that, I'll hand the call over to the operator for any questions you may have. Thank you.
Operator
operatorLadies and gentlemen, we're going to start the question-and-answer portion at this point. If you'd like to pose a question, press star followed by one on a touch-tone phone. Should you wish to take your question back, press star and then two. For those of you on a speakerphone, we kindly ask that you lift your handset before hitting the keys so the sound quality is as good as possible. So, to repeat: to submit a question, press star and one. Our first questioner this afternoon is Ovais Habib with Scotiabank. You may now ask your question.
Ovais Habib
analystHello, Rod, and hello to the SSR team. I have just a couple of questions for you. To begin with, on the Çöpler remediation, you have obviously discussed this temporary storage facility that is in place at the moment, and then, obviously, at some point you will move to a storage facility that is more permanent. In terms of the fact that you are waiting for, I suppose, approvals, what kind of approvals do you actually need? Are permits required? Is there anything else you need in order to move forward with that? Any color at all on that would be appreciated.
Rod Antal
executiveOkay, thank you, Ovais. I think the main thing to highlight is that from a remediation standpoint, the situation is favorable right now—essentially all of the material has been removed from the Sabırlı Valley. That's genuinely positive news. Of course, at the time the incident occurred, we hadn't settled on a final design for what the permanent storage facility would look like, and we also hadn't anticipated needing to build one from scratch. So from that point onward, we've been consulting with the government, reviewing the different options available to us for siting the permanent storage facility, for defining it from an engineering standpoint, and for satisfying the obligations under Turkish regulations regarding what a full closure entails. All of that work has been underway, Ovais. A location was selected—which was a good step—and we refer to it as the storage facility. The engineering work has moved forward. Talks continue with the regulators to confirm we've satisfied every requirement, and keep in mind this will be the first closure of its kind in the country, so we're making certain we're following all the correct procedures. Once all of that is complete, the approvals should come through—we do expect them early next year—and from there we'll begin the construction work and then transfer the materials from the temporary locations to the permanent one.
Ovais Habib
analystThanks for that, Rod. On the EIA point — I believe you're now going back to the 2012 EIA, and it refers to 6,000 tons per day as opposed to the 9,000 tons per day in the 2021 EIA. If you secure every approval needed to restart, would a restart then be at that 6,000 tons per day rather than the 9,000? Just looking for some clarity there.
Rod Antal
executiveYes, that's right, Ovais. As we've disclosed, the cancellation was an administrative appeal in a court. Efforts are underway in country to appeal those cases together with the relevant government departments. So that work continues in the background. But the default position reverts to the 2014 EIA, which caps throughput rates at 6,000 tons per day. So assuming all things being equal, as we know it today, that would be the fallback position, and we'll plan on that basis accordingly. And then in the future, we have to do an EIA refresh in the future anyway, and that will simply accelerate those efforts as we move into next year.
Ovais Habib
analystAppreciate it, Rod. This will be my final question. Regarding any kind of restart on this side, given the talks you're holding with the regulators, must the restart wait until every bit of remediation is finished, or is it possible to restart while remediation is still underway?
Rod Antal
executiveThat doesn't hinge on every bit of the remediation or the other work surrounding it. As I mentioned earlier, the talks we've been having — I think all the efforts we've had going, the ones still in progress, with some finished and some continuing at Çöpler — really serve as a precursor to those conversations. And as you can imagine, those discussions keep evolving actively and continuously across many levels of government. So it isn't strictly conditional on us completing all of this work, but it does help while we're holding those conversations, because we're carrying out our commitments to make things right following the Çöpler incident, and we'll keep up the dialogue with the various government departments to ultimately reach a restart at Çöpler.
Ovais Habib
analystGreat, I appreciate it, Rod. Those were all the questions I had.
Rod Antal
executiveMuch appreciated. Thank you, Ovais.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete SSR Mining Inc. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →For developers and AI pipelines
Programmatic access to SSR Mining Inc. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in SSR Mining Inc. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.