Steel Authority of India Limited (SAIL) Earnings Call Transcript & Summary
July 28, 2026
Earnings Call Speaker Segments
Operator
operatorGood day, ladies and gentlemen, and welcome to the Q1 FY 2027 earnings conference call for Steel Authority of India, brought to you by Nuvama Wealth Management. Just a reminder that every participant line will stay in listen-only mode, and once the presentation wraps up, you'll have a chance to ask questions. If you need help at any point during this call, please signal an operator by pressing star then zero on your touchtone phone. Kindly be aware that this conference is being recorded. I'll now turn the conference over to Mr. Ashish Kejriwal of Nuvama Wealth Management. Thank you, and over to you, sir.
Ashish Kejriwal
analystThanks, Eric. Morning, everyone. Apologies that the conference call began late. To begin with, we at Nuvama Institutional Equities extend a welcome to Dr. Ashok Panda, Chairman and Managing Director, together with the Additional Director Finance charge of Steel Authority of India. I'd like to ask Dr. Ashok Panda for his opening remarks, after which we can open the floor for Q&A. The floor is yours, sir.
Ashok Panda
executiveMany thanks, Mr. Ashish Kejriwal. Good morning to all of you. I extend a warm welcome to every investor and analyst joining us for this results call — the concall covering SAIL's financial year, specifically the quarter one, 2026 to 2027 period. I'm sure most of you have likely already reviewed the results posted on the company's website and filed through the stock exchanges, but I'll take you through them briefly for everyone's benefit. Turning to the global economic picture, the Middle East geopolitical situation had an adverse impact on the period. It affected fuel supplies around the world, and it also disrupted the supply chain for inputs such as limestone, etc. To some degree, it even touched gas supplies — propane, etc. — for the steel industry. Meanwhile, rising fuel costs created inflationary pressures, pushing up various expenditure heads. Despite this, projections for India stay range bound between 6.4%-7.2% according to various agencies over the next two years. As for the Indian steel scenario, economic trends, trade policies, and technological advancements heavily shape the steel industry landscape. The Indian steel industry, however, continues to enjoy robust demand for steel, with consumption during quarter one, 2026 to 2027 having grown by more than 8% over CPLY.
Ashok Panda
executiveOn the production side, though, growth came in somewhat subdued—roughly 3% for the 2026 to 2027 first quarter. Imports rose more sharply than exports did, so both imports and exports went up. Net imports for quarter one of 2026 to 2027 came to somewhere around 0.4 million tonnes to 0.5 million tonnes, versus perhaps 0.3 million tonnes in the prior year's quarter one. Now let me take you quickly through how the company did in quarter one, 2026 to 2027. The performance of Steel Authority of India Limited. Before I walk through the company's results for quarter one, 2026 to 2027, I want to tell the House that because of the conditions prevailing and the widespread threat at the time, SAIL actually chose to bring forward certain of its big capital repairs into quarter one, so that afterward it would be clear of them and could produce better in subsequent quarters. We carried out major capital repairs at IISCO Steel Plant, Durgapur Steel Plant, and also Rourkela Steel Plant, Bokaro Steel Plant—all deliberately scheduled in quarter one. That explains this quarter one versus the same quarter last year. It affected production volumes as planned, and in the end it helped us in certain respects, which set us up for solid profitability ahead.
Ashok Panda
executiveNow turning to how the company performed in quarter one of 2026 to 2027, here are the key points. Crude steel output came in at 4.8 million tonnes for quarter one, 2026 to 2027, compared with 4.9 million tonnes CPLY. That decline stems from capital repairs, which by design were brought forward into this quarter one. Sales volume reached 4.2 million tonnes, a drop of roughly 7%-8% versus the prior year. Finished goods inventory rose by about 0.2 million tonnes. Even so, the company stays strongly focused on lifting its sales volume, including clearing out inventory over the remaining part of this year, just as we did last year too. Our efforts will also go toward bringing down working pool borrowings. Looking at our borrowing position as of June 30th, 2026, when this quarter ended, we sit at roughly the same level as at the start of this year. That holds true even though inventory has grown by 0.2 million tonnes. Helped by improved realizations, sales turnover rose by well over 1% versus the prior quarter one. Even with major imported inputs such as coking coal, fuel, and limestone rising sharply in price, the company managed to boost profitability by pursuing operational efficiencies, stronger financial management, and treasury management throughout this quarter one period.
Ashok Panda
executiveFor the first quarter of 2026 to 2027, EBITDA came in at INR 4,356 crore, which represents growth of more than 50% against the CPLY figure of INR 2,925 crore. At 16.7%, the EBITDA margin is among the best since 2021 to 2022, a period when the steel market was at its peak and coal prices were at their bottom in 2021 to 2022. EBITDA per tonne also went past the INR 10,000 per tonne benchmark, standing at INR 10,464 per tonne in quarter one, 2026 to 2027. Turning to PBT and PAT, those stood at INR 2,159 crore and INR 1,636 crore respectively in quarter one, compared with INR 890 crore and INR 685 crore respectively for the CPLY period, a growth of around 150%. As I mentioned earlier, cash outflows were managed smartly through better treasury management efforts, which helped keep borrowings under check, and these stood at INR 21,729 crore as on 30th June, almost the same level as on March 1st, 2026, which was INR 21,663 crore. The debt equity ratio was further brought down to 0.36x on actual basis at the end of quarter one, 2026 to 2027.
Ashok Panda
executiveLooking ahead, Q2 has historically been the hardest quarter for steel because of rain-related incidents and so on. We're making efforts to avoid any inventory build during quarter two, and after that, we'll work to bring inventory down in quarter three and quarter four, so that on a yearly basis there will be a reduction in inventory. We'll keep striving to raise our efficiency levels and push cost reduction efforts. Another positive development in this quarter, 2026 to 2027, is that our focus on mines has been foremost. Now we're trying to raise production from our captive mines as well as consume, and sell the remaining quantity in the market wherever possible. In quarter one, we could have had sales of around INR 400 crore more than last year's quarter one, and that has led to a profit of around INR 150 crore versus last year's quarter one. Those are the highlights. With that, I hand it back to Mr. Ashish for opening the Q&A session.
Operator
operatorWe appreciate that, sir. The question-and-answer portion starts now. To pose a question, you can hit star and one on your touchtone phone. Should you want to drop out of the queue, just press star and two. We ask that participants use their handsets when asking. Ladies and gentlemen, we'll pause briefly while the queue fills up. Our first question is from Alok Deora of Motilal Oswal Financial Services. The floor is yours.
Alok Deora
analystGood morning. Sir, I just have a couple of questions. First, could you tell me what the NSR was in 1Q compared with 4Q? Given how July looked and how prices are trending, what are you expecting for the second quarter?
Ashok Panda
executiveFor quarter one, average NSR came in at INR 57,100, versus INR 52,000 in quarter four. So that works out to roughly INR 5,000 more per tonne across those two periods. On Q2, as I mentioned earlier, we're in the monsoon season right now, and traditionally NSR always comes down during this time. Regarding what we expect for Q2, or if you look at July, flat product prices haven't dropped by much. Long product prices have been fluctuating. There were cuts, but lately a positive momentum is showing up, and because of that, long product prices could possibly rise. You could say that from June to July, long product prices fell by about INR 3,000 per tonne. Right now, they may go up by INR 500 to INR 1,000 in long products. For flat products, from June to July, there might be a decrease of roughly INR 1,000 per tonne. Something along those lines.
Alok Deora
analystUnderstood. And on coal cost, sir — what did coal cost come in at on a consumption basis during 1Q, and what guidance do you have for the second quarter?
Ashok Panda
executiveIn quarter one of 2026 to 2027, the price of imported coal was higher, at INR 21,300 versus INR 18,100 in quarter four — that's an increase of roughly INR 3,100. The imported coal index, which had peaked at around 235 a couple of days earlier, has now dropped to a level of 220 as of today. So there is some softening in the imported coal index — the Argus and Platts and Argus index. We are hopeful that, since during the rainy season there are monsoon conditions and so on, demand may decline, and because of that, prices might soften in quarter two.
Alok Deora
analystAlright. Is there anything you can share regarding coal cost? Yes.
Ashok Panda
executiveOur expectation is that starting in Q2, and perhaps from August onward, imported coal costs could come down by roughly INR 1,000 to INR 2,000, moving progressively month by month.
Alok Deora
analystUnderstood. One final question, sir: given how things have performed, do we still expect the volume guidance for the full year to hold?
Ashok Panda
executiveYes, we're keeping the volume for the full year, and by the time the year ends, we'll have grown compared with last year.
Alok Deora
analystUnderstood. Nothing further from me, sir. Thanks, and best of luck to you, sir.
Ashok Panda
executiveI appreciate that.
Operator
operatorOur following question is from Amit Murarka at Axis Capital. Amit, please go ahead.
Amit Murarka
analystMorning, everyone.
Ashok Panda
executiveMorning, everyone.
Amit Murarka
analystHi there, and good morning. My first question concerns cost inflation in West Asia — could you specify the figure?
Ashok Panda
executiveYour voice is breaking.
Operator
operatorAmit, we can’t hear you clearly. If you aren’t already on handset mode, please switch your phone to that. Hello, Amit, are you with us? Amit, if you’re able to hear me, kindly fix the phone problem, and then you can rejoin the queue. Thank you. We’ll go on to the following participant, Ritesh Shah from Investec India. Please proceed.
Ritesh Shah
analystYeah. Hello, sir. Appreciate the chance. Sir, first, a clarification on what you said earlier — you mentioned we're expecting coking coal prices to fall by INR 1,000, INR 2,000 going into Q2?
Ashok Panda
executiveIf we look at it month by month — not the average, I mean — in August there might be a drop of roughly INR 1,000. Then perhaps another INR 1,000 in September. That's what I expect.
Ritesh Shah
analystAll right, that's useful. Next question, sir: for the quarter, could you break out the volumes without RINL, or any other sales we've made — for instance, to NMDC Steel?
Ashok Panda
executiveIf you consider that specific number, NMDC Steel — as you're aware, we aren't doing the marketing this year, so it's nil, essentially nil, NSL. In CPLY, quarter one had INR 3.73 lakhs of sales. This time around it's zero. At RINL, we sold roughly 96,000 tonnes, and that wasn't there last year in quarter one. Overall, if you combine NSL and RINL, then last year CPLY — CPL means last year's quarter one — had a quantity of about 2.76 lakhs tonnes in that, compared with this year.
Ritesh Shah
analystThanks. Sir, I have just two brief questions. First, what is your view on the price difference between primary and secondary longs? You mentioned that we hope long product prices will rise by INR 500,000. Sir, how should we view the gap between primary and secondary? That is the first one. Sir, the second question: how are we interpreting the anti-dumping duty investigation that has just been initiated? Is there any likelihood that safeguards will essentially be brought back again?
Ashok Panda
executiveOkay, I'll take these one at a time. The first one concerns the spread between primary and secondary in TMT, within long products. Well, that spread has come down. At present it sits at roughly INR 5,000, and that's a healthy level. That likely explains the uptick in NSR for primary TMT product prices — that's my guesswork. Second, you asked about-
Ritesh Shah
analystRegarding anti-dumping.
Ashok Panda
executiveOn the safeguard duty and anti-dumping duty front — well, on safeguards, yes, a safeguard duty remains in effect, and it currently stands at 11.5%, since it was put in place for three years. We're presently in the second year of that period. It's still running, and it's providing relief — much-needed relief — to the domestic steel market. As for anti-dumping, that process is continuing, and depending on the investigation, some measures may arrive that would bring relief to the domestic steel sector.
Ritesh Shah
analystYes, please. Sure. Thanks a lot for those answers. Thank you.
Ashok Panda
executiveI appreciate that.
Operator
operatorOur next question is from Parthiv of Anand Rathi Group. You have the floor.
Parthiv Jhonsa
analystHello, and good morning, sir. Thanks for giving me this chance. Sir, my first question concerns the sub-grade ore of fines. I believe you mentioned that during the first quarter, you generated an additional INR 400 crore from ore sales. Actually, the question has two parts. First, regarding the sub-grade iron ore, what inventory do you hold? Second, if you look at recent auction data from Steel Authority, volumes have actually been declining, particularly since the June month at a couple of mines. Do you expect these third-party ore sales to keep going? I just wanted to hear your thinking on that.
Ashok Panda
executiveI'll take them one at a time. I didn't catch the last question. Let me handle the first and second. On the first, regarding SGF, sub-grade fines: we're carrying roughly 32 million tons of inventory on the balance sheet. About 3 million tons of it has been put up in the auction. The rates haven't come in yet. We're hopeful that this time we'll be able to click that particular thing. That will mark the beginning of our efforts toward selling 32 million tons going forward. Number two, on sales from the mines: those sales come primarily from the Odisha Group of Mines, from where we've been selling iron ore fines, fresh iron ore fines, and tailings. The quantities have more than doubled compared with last year. That's why turnover from there has risen by around INR 400 crore and profit from there is up by INR 150 crore. Our efforts are to raise production further and sell more and more in the market. We're also planning to sell from the Chhattisgarh Group of Mines. Two auctions have fructified recently, just a few days back, which falls in quarter two.
Ashok Panda
executiveThat will demonstrate our capacity to generate additional sales from the Chhattisgarh mines. We are also making attempts to sell from Jharkhand mines. Work is underway on that front.
Parthiv Jhonsa
analystAll right, thank you. Sir, I just want a quick clarification on one point. That 3 million tons — that's the target for 2027, correct?
Ashok Panda
executiveSorry, could you say that again?
Parthiv Jhonsa
analystRegarding the sub-grade, that auction target of 3 million tons of sub-grade ore—is it meant for the whole of 2027, or does it apply to 2028?
Ashok Panda
executiveActually, no — this is the first one. After it occurs and begins to progress, we'll see as well.
Parthiv Jhonsa
analystAlright.
Ashok Panda
executiveNaturally, that’s what we’re aiming for across 2026 to 2027.
Parthiv Jhonsa
analystAll right. And I think I just wanted to briefly get your take on the railway price revision — whatever you're able to share. What's your expectation there? How should we be looking at that as we move through the current year?
Ashok Panda
executiveYeah. All I can really tell you is that it relies on the provisional prices — the rail price. You mean the rail price, right?
Parthiv Jhonsa
analystCorrect.
Ashok Panda
executiveLooking at 2026 to 2027, imported coal prices are running on the higher side, and our provisional price sits pretty low at INR 74,000. We expect prices to come in better than that. Whenever it is declared, that should improve our profitability.
Parthiv Jhonsa
analystDo you think that’ll happen at any point in the near future?
Ashok Panda
executiveFor 2026 to 2027, that will land in 2027 to 2028, and the 2025 to 2026 prices will arrive in 2026 to 2027. We’ll see how it turns out at that point.
Parthiv Jhonsa
analystSir, do you have any initial sense of what pricing looked like last year?
Ashok Panda
executiveI mean, pricing for 2025 to 2026 is going to exceed what we saw from 2024 to 2025. It really hinges on how things play out. This could end up
Parthiv Jhonsa
analystAlright, if I could just quickly fit in one final question here. I believe the Government of India recently placed a definitive anti-dumping duty on met coke, for roughly 5 years, I think. Would that affect you in any way? Because I think—
Ashok Panda
executiveSAIL won't be affected by this, since our own capacity matches what we need — and it may even be in surplus.
Parthiv Jhonsa
analystAlright, that's great. Thanks a lot — I really appreciate it. That helps me quite a bit.
Operator
operatorOur following question is from Pinakin Parekh at HSBC Bank. Kindly proceed.
Pinakin Parekh
analystYes, sir. I have three quick questions. First, could you share your revised CapEx guidance for this year and the next couple of years, taking into account whatever the plans are?
Ashok Panda
executiveOn the CapEx side, for this year we're targeting INR 15,000 crore, and over the coming two to three years that figure will rise, since our expansions are underway. What that means is next year it could go beyond INR 20,000 crore, and then after that, perhaps INR 25,000, INR 26,000, something along those lines. It's set to keep climbing across the next four to five years. For this year the number stands at INR 15,000 crore, and we expect to complete it.
Pinakin Parekh
analystUnderstood, sir. For my second question: sir, you mentioned that NSRs were basically better in July than in June. If I average the NSR for the June quarter, the first quarter, and compare that against what has taken place with long product prices, should 2Q NSR be broadly lower by INR 2,000-INR 3,000 a ton, or flat? How should we view it?
Ashok Panda
executiveSo when we discuss NSR, I actually mentioned that in quarter one of this year, NSR is above quarter four. Come quarter two, which begins in July, NSR is going to be lower than quarter one's level, mainly on account of the monsoon, weak demand, and so on. What I meant is that across July, August, and September, the flat product price cuts might not be all that large, but the decline in TMT — that is, LP, long products — will actually be bigger. During June and July, we saw roughly INR 2,000 come off long product NSR, and lately there has been upward momentum in long product NSR. It could rise by another INR 1,000. If you compare quarter two NSR with quarter one, it may be down by roughly INR 1,000-INR 2,000, perhaps. That is only an estimate.
Pinakin Parekh
analystUnderstood, sir. Sir, my final question is this: could you provide revised guidance on employee costs for this year, and will you begin making provision for the wage provision in the January-March 2027 quarter?
Ashok Panda
executiveIn the first quarter of this year, salary raises came to INR 2,937 crore, versus INR 2,944 in the same period a year earlier — essentially flat. This first-quarter figure also includes VR, the differential VR amount and VRS, since our voluntary retirement scheme is running and many employees have opted for VRS. That element is reflected in employee remuneration as well. Headcount is declining and VRS remains in place. We expect employee cost to come down — that's point one. On your question about the possibility of wage revision: in quarter four, we'll examine the probability and possibility of setting aside some provision for wage revision. We will evaluate and review those aspects in quarter four, because that is when it will fall due. The material group will look into it.
Pinakin Parekh
analystUnderstood, sir. Thank you so much.
Operator
operatorThanks. We’ll take the next question from Pallav Agarwal at Antique Stock Broking. Please go ahead.
Pallav Agarwal
analystGood morning. I have a couple of questions. First, could you bring us up to date on the present product mix — how it breaks down across flats, longs, and semis?
Ashok Panda
executiveRight. Give me just a moment. It's roughly split down the middle, almost 50-50. One factor is that semis have declined. Semis dropped from, let's say, 14% in last quarter one to 11% in this quarter one. Long and flat sits at 52.7%, long comes in at 34.8%, and semis stand at 12.5% for quarter one.
Pallav Agarwal
analystYes, sir. On that slide covering sales performance, the share for semis appears as 6%. Is it the case that a portion of semis gets converted externally and then turned into finished products?
Ashok Panda
executiveSure, absolutely. Semis are being turned into finished goods. That’s why I mentioned to you that finished steel has risen from 86% to 89% this year. We’re working to convert the majority of semis into finished product and push that into the market.
Pallav Agarwal
analystAll right. The slide refers to 6%, I believe. Perhaps that figure comes after conversion — the final sales number lands at roughly 6%.
Ashok Panda
executiveThat's correct. You've got it right.
Pallav Agarwal
analystAll right. And on the coking coal side, how does that split out? The bulk of it comes in from overseas, but what sort of volume are we securing? Do our captive mines contribute at all, and what share is sourced from Coal India?
Ashok Panda
executiveSo yes, the captive mines are at Chasnala and Tasra. Those belong to the indigenous coal side, not the imported coal side. Imported coal sits at about 85%, while indigenous coal accounts for 15%. Within that 15%, roughly 5% comes from our own mines, and that share is likely to rise starting December, since production at the Tasra mines — currently under development — is expected to begin in the month of December. The fourth quarter should be a better one for us, as we expect to receive more indigenous coal from our captive mines. That should also help us on pricing.
Pallav Agarwal
analystSure. Could you give us a sense of the cost benefit when comparing domestic coal with imported coal?
Ashok Panda
executiveSo in quarter one, the domestic average price stands at INR 13,100, compared with INR 21,200 for the imported grade. That domestic figure is INR 13,100, but once we start sourcing from our own mines, it could come in at roughly INR 5,000 to INR 6,000 — around INR 6,000. Starting in December, that share is set to rise.
Pallav Agarwal
analystYes, sir. And on that final TV point, could you give us a sense of the blending in our coke ovens? You've covered the PCI, the coke rate, and PCI injection. Broadly speaking, what share of the coke mix is pure hard coking coal?
Ashok Panda
executiveHold on, just a moment. Soft coking coal accounts for roughly 25% to 27%. The remainder is hard. Also within that, taking the total picture, imports make up about 85% while domestic supply is roughly 15%. That's overall. If we break it down between soft and hard for backup purposes, soft is around — what share? 23% is soft, and hard coking coal is about 61.7%. So really domestic coking coal sits at 15%, imported hard comes to 62%, and imported soft is 23%. That's how you get to 100%.
Pallav Agarwal
analystAbsolutely, sir. Alright, and thanks very much.
Operator
operatorOur following question is from Sumangal Nevatia of Kotak Mahindra Bank. The line is yours.
Sumangal Nevatia
analystMorning, sir. I'd like some clarification on a couple of points. First, on the fourth quarter NSR, you mentioned INR 57,100 — is that correct? Could you break that down between flat and long?
Ashok Panda
executiveYeah. So for the fourth quarter, NSR came in at-
Sumangal Nevatia
analystApologies — first quarter. My mistake — I meant the first quarter.
Ashok Panda
executiveSo INR 57,100 is the average — and the long figure is basically the same at INR 57,100, while the flat one comes in at INR 57,200. To put it precisely, the average is INR 57,150.
Sumangal Nevatia
analystUnderstood. Sir, what would the July NSR be for long and flat?
Ashok Panda
executiveSo the July NSR average came in at INR 55,600. For the flat category it's INR 56,900, while long stands at INR 54,200.
Sumangal Nevatia
analystGot it, understood. Sir, regarding the captive mines, when we shared that sales came to INR 400 crore and profit was INR 150 crore, could you share what the volume is there? And for the full year, what are we expecting?
Ashok Panda
executiveFor this quarter, volumes came in at 1.1 million tons, while in the first quarter of last year they were 0.31 million tons. With 1.1 million tons this quarter, we sold roughly 3 point-something million tons last year. Even though our goal is set quite high at 8 million tons, we'll just have to see how far we can get.
Sumangal Nevatia
analystAlright. Over the course of last year, we moved 3 million tons.
Ashok Panda
executiveFor the full year, roughly 3.5 million tons, or thereabouts — something in that millions-of-tons range.
Sumangal Nevatia
analystHow much did iron ore volume bring in for revenue and EBITDA during the previous year?
Ashok Panda
executiveI need to verify that, actually, but I can share the details for quarter one. Let me give you the quarter one figures, actually. During quarter one, as I mentioned, turnover from iron ore sales came to INR 157 crore in the prior year's quarter one, while this year's quarter one stands at INR 574 crore.
Sumangal Nevatia
analystSo for this year, EBITDA stands at INR 150 crore — is that correct?
Ashok Panda
executiveRight.
Sumangal Nevatia
analystRegarding the first quarter.
Ashok Panda
executiveYou could describe that as approximately the EBITDA as well.
Sumangal Nevatia
analystPreviously, we couldn't hit our guidance owing to some logistical constraint, and I think even in the case of sub-grade mines, demand for that quality isn't present. Are those constraints now easing? What's the situation there?
Ashok Panda
executiveThe logistics bottleneck hasn’t gone away. We’re working to get in sync with it by improving how readily rates are available and by moving larger volumes via road. Those are the steps we’re taking so that the logistics constraints can be relieved to some degree. That work is underway. As for the quality of the iron ore sub-grade fines, demand is strong for both the sub-grade fines and the tailings, since these aren’t particularly low-quality sub-grades. They run 59%-60%, and the marketplace for them is good. Even with the tailings from Bolani — that is, from the Odisha Group of Mines — which are 57%, 58%, 56%, there’s solid market demand as well. The market for that is good. We can hit our sales volumes.
Sumangal Nevatia
analystAll right, one final question regarding the coking coal. You mentioned consumption came in at roughly INR 21,300. What consumption cost should we expect for 2Q? Are you anticipating that cost to come down or go up? I do realize purchase prices are trending lower.
Ashok Panda
executiveYes. It’s going to come down, since pricing is easing now, so the only direction is down. There may be a drop of roughly INR 1,200 or INR 1,500 in Q2 versus Q1.
Sumangal Nevatia
analystGot it. Sir, for 1Q, how much was spent on CapEx? That's my final question.
Ashok Panda
executiveINR 2,575 crore.
Sumangal Nevatia
analystUnderstood. Fine. Many thanks, and I wish you the very best, sir.
Ashok Panda
executiveThanks.
Operator
operatorOur next question is from Amit Murarka at Axis Capital. Please proceed.
Amit Murarka
analystYeah, hi there. Thanks for giving me the chance to ask again. My first question concerns the cost inflation that's been present. Broadly speaking, we've observed the effect of West Asia showing up in power costs as well as other raw material expenses. From your perspective, how much inflation would that have amounted to for you in Q1?
Ashok Panda
executiveThe rise comes mainly from two areas. First, on the coal side, since as you're aware, imported coal prices are up by roughly INR 3,500 versus the first quarter of last year, and that's easing at the moment. That's one factor. The second factor is that fuel cost has risen somewhat. Naturally, it hasn't affected sale purchase all that much, but the effect of limestone — the higher limestone cost — is also present in what it costs us to produce. Those are the main items that have hit the steel sector as a whole, though the effect on us is smaller than on others, since fuel doesn't weigh heavily in our case.
Amit Murarka
analystUnderstood. And just so I understand, you mentioned that you're processing some semis sourced from third parties. Which third party would that be, if you don't mind clarifying?
Ashok Panda
executiveThe conversion arrangements are in place—that falls under marketing’s remit—and we continue to handle it dynamically. As for lowering the availability of semis in the market, we’re working to keep raising our finished steel output more and more. That’s why I mentioned to you that finished steel’s percentage is up by roughly 3%-4% this year compared with quarter one of last year.
Amit Murarka
analystHas the NINL arrangement come to a halt, or is it still functioning at present?
Ashok Panda
executiveNo, that’s not a conversion arrangement involving NINL. What we’re doing is helping them with sales of their semis at whatever point they choose.
Amit Murarka
analystSir, during the first quarter, did NINL contribute any volume at all?
Ashok Panda
executiveWhen it comes to NINL, we moved 96,000 tons of semis via our own marketing setup.
Amit Murarka
analyst95,000 tons. All right.
Ashok Panda
executiveThat's actually not NINL — it's RINL. My apologies. It's RINL, Rashtriya.
Amit Murarka
analystApologies, that was my mistake. It's not NINL — sorry, my error. NMDC Steel is what I meant, sorry. NMDC Steel.
Ashok Panda
executiveAs I already mentioned, NMDC stands at zero.
Amit Murarka
analystAlright, my apologies, and thanks a lot. Yeah.
Operator
operatorOur following question is from Netra Deshpande of Mirae Asset Sharekhan. The line is yours.
Netra Deshpande
analystThanks for the chance to speak, and good morning, everyone, and good morning to the management team. For my first question, regarding what you mentioned last quarter about flux and the limestone costs going up because of the Strait of Hormuz in Dubai: is there any effect from that on sellable steel? As we saw a reduction of roughly INR 100-INR200 per ton. In the upcoming quarter as well, is there any-
Ashok Panda
executiveLet me elaborate on this question a bit further. Due to the Strait of Hormuz — actually, that's the Gulf war situation — there is an effect on fuel as well as on limestone and the steel sector. As far as fuel goes, for Steel Authority of India Limited, we don't see much impact, since we produce our own gases within the plant itself. Coke ovens are in good shape, blast furnaces are in good shape. We're able to produce the gases and use them, so not much impact. On fluxes, because of ocean freight and so on, prices have risen for everyone, and for us too. That increase in flux prices has been offset by cutting the specific usage of fluxes in quarter one this time versus the prior quarter one, and thanks to that reduction, we saved roughly INR 25 crore on that front. More or less, it has offset the price rise caused by ocean freight on the fluxes.
Netra Deshpande
analystUnderstood. Second, regarding the debt position: in the last quarter, finance costs came down, and that remained a major deleveraging support, while the overall debt and debt-equity ratio also held at a multi-year low of 0.55x. Will this deleveraging trend continue into Q1 FY 2027? What is the current position?
Ashok Panda
executiveSo, when you look at Q1 —
Netra Deshpande
analystThat's correct.
Ashok Panda
executiveDebt currently sits at INR 21,729 crore, roughly the same as the opening figure of INR 21,663 crore. The debt-to-equity ratio has declined to 0.36x, down from perhaps 0.38x or 0.39x at the start of this year. We continue with deleveraging efforts, and as of today's position, debt has fallen further to around INR 21,400 crore. We are working to lower working capital borrowings during this particular year by cutting inventory, as well as via other sources, to strengthen cash flows. Beyond that, thanks to focused efforts by treasury management — improved treasury management — our cost of debt has also decreased to 6.24%, versus roughly 6.8% in quarter one of last year. As a result, there is a saving of about INR 100 crore on finance cost this quarter relative to the prior quarter.
Netra Deshpande
analystUnderstood. Sir, the final point concerns only the blended gross spread. Could you provide some figures for Q1 on a term basis — similar to the blended realization you gave, but for the blended gross spreads?
Ashok Panda
executiveBlended what exactly? Your question isn't coming through to me.
Netra Deshpande
analystOn gross spread — when you look across the segment and the product mix, it comes down to that blended realization split you laid out.
Ashok Panda
executiveAlright.
Netra Deshpande
analystRegarding any adjustment, yeah.
Ashok Panda
executiveAre you asking about blended realization when we talk about NSR?
Netra Deshpande
analystNSR — yeah, sure, go ahead on that. On blended realization, you already brought up long and flat iron, the sellable steel — do you have anything specific, particularly?
Ashok Panda
executiveAs I mentioned, regarding blended realization in quarter one, our average NSR stands at INR 57,156, and looking at the breakdown within that, flats account for roughly 52% while long is about 38%, with semis at 12%. That's on the production side. As someone noted, on the sales side, semis are still lower by approximately 6%, since the remaining 6% has been converted into finished goods. Overall, our blend has improved in this quarter one relative to the prior year.
Netra Deshpande
analystUnderstood, sir. Noted, sir. Regarding the subgrade auction grade you mentioned in connection with FY 2027, that figure would be 3 million tons. As for sales from mines — from the Odisha mine and from the Jharkhand mine — could you elaborate or share some data?
Ashok Panda
executiveSo here's what we actually expect. During 2025 to 2026, our total sales came to roughly 3 point-odd million tons, and every bit of that was from the Odisha Group of Mines. Fresh fines are included in that figure, and so are tailings from the Odisha Group of Mines. For this year, we anticipate twice that tonnage out of the Odisha Group of Mines. There's also some volume coming from the Chhattisgarh Group of Mines — the auction for that concluded only a few days ago, with a modest quantity, yet it shows we can push higher, subject to what's available. On the Jharkhand side, we're in fact working to move our sub-grade fines, which we expect to be 3 million tons. How much will actually ship, we'll see. Second, we're likewise attempting to sell fresh fines out of Jharkhand. Specific figures I can't provide right now.
Netra Deshpande
analystAlright, sir, understood. Thanks, sir. I appreciate the response.
Operator
operatorBecause of time constraints and fairness to everyone else, participants should limit themselves to 2 questions. If you have additional questions, feel free to get back in the queue. Our next question is from Vikash Singh at ICICI Bank Securities. Please proceed.
Vikash Singh
analystGood morning, sir. Thanks for giving me the chance to ask. Sir, I just wanted to get some clarity on the downward revision when it comes to rail pricing. What benchmark were you using before, and what benchmark are you selling at now? And for FY 2026, given that costs have come down, what kind of additional downward revision might be possible?
Ashok Panda
executiveOkay, so let me walk you through that. There really isn’t a benchmark in this, to be honest. Efficiency and coal prices are what mainly drive it. It moves up and down based on input prices and the efficiency level at our rail mills. Right now, efficiency at our rail mills is very high — even exceeding global benchmarks. That’s the way it works for rail production at Bhilai Steel Plant, and Indian Railways appreciates it as well. As I mentioned, during 2024 to 2025, imported coal prices stayed low, and that’s why prices were low. In 2025 to 2026, imported coal prices have improved relative to 2024 to 2025. We expect better prices than in 2024 to 2025. In 2026 to 2027, imported coal prices are still higher — much higher than in 2025 to 2026. Naturally, costing will be greater, and the price will be greater, which will be decided in 2027 to 2028. That’s how it moves.
Vikash Singh
analystSo at this point, you aren't anticipating any additional downward revision when it comes to railway prices?
Ashok Panda
executiveWe don’t anticipate any additional P&L impact from that.
Vikash Singh
analystSir, my second question is basically about your DSP plant. That facility had the greatest share of semis. In that location, we were in fact installing some casters in order to raise the overall — Hello?
Ashok Panda
executiveWhich facility did you mention — the SP plant?
Vikash Singh
analystNope, the DSP plant.
Ashok Panda
executiveAll right, Durgapur.
Vikash Singh
analystTurning to Durgapur Steel Plant — that's where semis were highest. We were actually implementing some projects there to boost finished goods output. I believe it's the caster we're installing. Could you update us on what stage that's at? And how much in tolling charges are you paying third parties to convert semis into finished product?
Ashok Panda
executiveOkay, so let me address your question. At Durgapur, we're turning out semis, and that output exceeds 1 million ton per annum. That's the reason we're actually setting up a TMT bar mill at that location, and it will turn out roughly 0.8 million tons, 0.8 million tons-0.9 million tons of TMT from there. We expect that sometime in 2027, perhaps September-December 2027. That's what we're expecting. It's going to arrive during that window. Once it does, the semis available from Durgapur will drop drastically.
Operator
operatorThank you.
Ashok Panda
executiveAs you noted, those conversion charges are actually dynamic and depend on a certain formula and so on. They stay in line with the industry's best standards.
Operator
operatorOur following question is from Ritesh Shah at Investec India. Ritesh, you have the floor.
Ritesh Shah
analystSir, just one quick question on that. How much wage commissioning provisioning are we currently doing in total? Could you possibly provide a figure for employee cost for this year and next year, taking that variable into account?
Ashok Panda
executiveWhat did you say about commissioning?
Ritesh Shah
analystCommission payouts.
Ashok Panda
executiveWage?
Ritesh Shah
analystSir, regarding the pay commission. Yeah.
Ashok Panda
executiveSo the pay commission, as you're aware, is actually set to take effect from 1 January 2027. We don't have much certainty on it yet, and there aren't any calculations out there either. Like I said plainly, during quarter four we'll assess it, look into it, and determine what can be done regarding a provision.
Ritesh Shah
analystSure. Thanks. That covers everything.
Operator
operatorAkhilesh Kumar from Emkay Global Financial Services has the next question. Go ahead, Akhilesh — ask your question, and if your line is muted, please unmute it.
Akhilesh Kumar
analystYeah. Hello. Am I coming through?
Ashok Panda
executiveYeah.
Akhilesh Kumar
analystYeah. The big question is how we see the cost efficiency program shaping up, and what specific initiatives we're taking to get costs down. How much of the per-ton cost saving would come from those initiatives, say over FY 2028 and 2029?
Ashok Panda
executive2028 and 2029?
Akhilesh Kumar
analystYeah. In terms of rupees per ton, out of the total, how much are we looking at in cost savings?
Ashok Panda
executiveWe expect a cost reduction of roughly INR 2,000-INR 3,000 during this year itself. In quarter one, since a lot of our units are down owing to the advancement of the capital repairs, costs came in a bit on the higher side. Starting in quarter two, with all the means and facilities now in place, there will be cost reduction efforts, and that cost reduction is happening — that's number one. If we consider what costs might look like by 2028, 2029 — by 2028, 2029 — we'll have new facilities coming up at IISCO Steel Plant, and that will cut the variable cost drastically thanks to lower fuel rate, coke rate, and so on there. At that point, the cost reduction — the variable cost — could be on the order of INR 3,000-INR 4,000 per ton. But since the new units will come, naturally there will be a push when it comes to fixed cost at that time.
Akhilesh Kumar
analystTaking everything together, when we consider net cost per savings — since some costs will arise from the new plants that are coming up as well — is it fair for us to say that INR 1,500-INR 2,000 of cost savings per ton will flow straight into our EBITDA?
Ashok Panda
executiveThat's right, you're absolutely correct. In fact, once we begin to get output from the IISCO Steel Plant expansion units, around 2028 to 2029, variable cost should drop by roughly INR 4,000, while fixed cost might rise by about INR 1,500-INR 2,000. On a net basis, there could be a reduction in cost of INR 2,000 at that time. Even so, ahead of that, through our existing operations, we're attempting to bring down our production cost by approximately INR 2,000 via a range of efforts.
Operator
operatorAppreciate it. Our following question is from Rajesh Ravi at HDFC Securities. You have the floor.
Rajesh Ravi
analystYeah. Hello, sir. Can you hear me okay?
Ashok Panda
executiveYeah.
Rajesh Ravi
analystYeah. Hello, sir. I've got a couple of questions. First, with the volume drop and the low CapEx we had in Q1, can you give us a sense of what we're looking at to keep our full year volume and CapEx guidance? And the second one, the iron ore volume and revenue EBITDA you shared for Q1, could you share those same numbers for Q4 FY 2026 as well?
Ashok Panda
executiveOkay. Let me walk you through it — on the CapEx side, the Q1 target was INR 2,306 crore, and we actually hit INR 2,575 crore against that. For the full year, our target stands at INR 15,000 crore. We're moving ahead to reach those numbers. That's the first point. Second, on volumes, as I mentioned earlier, production is down by roughly 0.1 million tons. The reason is that we brought forward the capital repairs at IISCO, at Durgapur, and at Bokaro Hot Treatment. This was intentional. In Q2 and Q4, output will exceed what we saw last year. For the year as a whole, growth is expected compared with FY 2025 to 2026.
Operator
operatorThanks. Women and gentlemen, we'll treat that as today's final question. At this point, I'd like to pass the conference to management for some closing remarks.
Ashok Panda
executiveTo close things out from my side, many thanks for joining today's Q&A session. Various agencies have issued forecasts for the Indian economy that are quite encouraging, and government support is reinforcing confidence that the economy will keep performing well in the period ahead. Demand for steel is also continuing to thrive, and we hope prices will sustain the momentum gained after the monsoons. Beyond the better operational performance, the company stays dedicated to sustainable results, with focus on decarbonization, higher capacity utilization, value addition, and attaining cost competitiveness. My thanks go to all our investors for placing their faith in us, and I hope that same trust will carry forward into the future as well. Many thanks.
Operator
operatorAppreciate that, sir. Everyone, this wraps up today's conference call on behalf of Nuvama Wealth Management. Thanks for being with us — you're free to disconnect your lines now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Steel Authority of India Limited transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Steel Authority of India Limited earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Steel Authority of India Limited or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.