Hello, and thanks for being with us. You're listening to the Subsea 7 Q3 2025 Results Conference Call. <<operator_script>>. I'd like to let you know that this call is being recorded today. At this point, I'll turn things over to today's speaker, Katherine Tonks. Please continue.

Katherine Tonks

executive
#2

Hello, everyone, and thank you for being with us. Joining me today are our CEO, John Evans; Mark Foley, our CFO; and Stuart Fitzgerald, who is CEO of Seaway 7. You can download the results press release from our website, and the slides we'll be using during today's call are there as well. I'd like to note that certain information we discuss on the call today will contain forward-looking statements reflecting our current views. Such statements carry risks and uncertainties that could cause actual results or trends to differ materially from what we forecast. For additional information, please see the risk factors discussed in our annual report or in today's quarterly press release. I'll now hand things over to John.

John Evans

executive
#3

Thanks, Katherine, and good afternoon, all. I'll begin with a recap of the quarter, then hand things to Mark, who'll walk through the financial results in more detail. If we go to Slide 3. Subsea 7 posted third quarter adjusted EBITDA of $407 million, which is 27% growth year-on-year, with a margin of 22%. Our improved profitability comes from strong project execution and from the ongoing high-grading of our backlog. As Mark will explain, we now expect to beat our previous guidance for 2025 and to carry continued momentum into 2026. Order intake was high this quarter, at $3.8 billion, giving a book-to-bill of 2.1x for the quarter and 1.4x for the first 9 months of the year. Our backlog hit a record high, close to $14 billion. Slide 4 sets out the backlogs for both Subsea and Conventional and Renewables, which keep improving in quality as we finish work won before 2022 and shift our focus to contracts with more favorable terms. We have a combined backlog for execution in 2026 of $6 billion, giving us over 80% visibility on next year's revenue. And now I'll hand over to Mark to run through the financial results.

Mark Foley

executive
#4

Thanks, John, and good afternoon, everyone. I'll give you some selected comments on how the group, Subsea and Conventional, and Renewables performed financially in the third quarter, then I'll move on to cash flow and the financial guidance for 2025 and 2026. Slide 5 sums up the group's revenue and adjusted EBITDA results for the third quarter, shown against recent quarterly performance. Revenue in the third quarter came to $1.8 billion, in line with the high levels reported in the same quarter a year earlier. Adjusted EBITDA reached $407 million, up 27% versus the prior year period. Margin widened by 460 basis points, to 22%. Net income was $109 million, after depreciation and amortization of $175 million, net foreign exchange losses of $38 million, which came from noncash embedded derivatives, net finance costs of $12 million, and taxation of $73 million. I'll go through the key points on business unit performance over the next few slides. Slide 6 shows the key metrics for Subsea and Conventional. Third quarter revenue was $1.5 billion, a rise of 6% year-on-year, as high activity levels carried on in Brazil, Türkiye and Norway. Adjusted EBITDA was $368 million, which works out to a margin of 24%, up 680 basis points from the same quarter last year.

Mark Foley

executive
#5

That margin gain came from strong execution and high vessel utilization, plus the ongoing rebalancing of our portfolio toward projects with better risk and reward characteristics. Results in Subsea and Conventional include an $11 million net income contribution from OneSubsea, which is in line with our expectations. Net operating income came in at $228 million, almost 80% above the prior year period, which equates to a net operating income margin of 15.1%. Selected Renewables performance metrics appear on Slide 7. Third quarter revenue was $302 million, down 19% compared with the high levels reported in the prior year period, which were driven by elevated activity in Taiwan, while matching the second quarter of 2025. During the quarter, activity moved forward at Dogger Bank C and East Anglia THREE in the U.K and at Revolution in the U.S. after a delayed start. Adjusted EBITDA was $52 million, equating to a margin of 17%, up 70 basis points from the same quarter last year. Net operating income was $21 million, a margin of 7%. Slide 8 shows the cash bridge for the third quarter. Net cash generated from operating activities was $283 million, including an expected unfavorable working capital movement of $82 million.

Mark Foley

executive
#6

Capital spending came to $47 million, largely tied to upkeep of vessels and equipment. Financing activities used net cash of $123 million, including $79 million in lease payments. By quarter's end, cash and cash equivalents had risen $132 million, reaching $546 million. Net debt stood at $505 million, with lease liabilities of $421 million, which works out to a modest 0.4x ratio of net debt to last 12 months adjusted EBITDA. As of the 30th of September, the group's liquidity was $1.1 billion. On the 6th of November, the company made its second and final SEK 6.5 per share dividend payment to shareholders. Returns to shareholders this year, consisting purely of dividends, totaled roughly $376 million. To wrap up the financials, let's go to Slide 7 -- apologies, Slide 9. For 2025, we've refined some guidance metrics. I'll call out these favorable notable revisions. Revenue guidance's upper and lower bounds have each been tightened by $100 million, as full-year 2025 revenue is now expected to land between $6.9 billion and $7.1 billion. With strong results across the first 9 months of the year, plus high visibility and confidence in how we're executing, we've raised our 2025 adjusted EBITDA margin guidance to a range of 20% to 21%, up from 18% to 20%.

Mark Foley

executive
#7

We've likewise lowered our capex guidance to somewhere between $300 million and $320 million. That mirrors the ongoing emphasis we place on discipline around capital, plus a shift in timing that moves a portion of cash capital expenditure out of this year and into 2026. Today, following the usual practice for Subsea 7 in the third quarter, we rolled out preliminary guidance for the coming year. For 2026, we look for the group to keep posting revenue growth together with growth in adjusted EBITDA. Revenue, we anticipate, will land in a range of $7 billion to $7.4 billion, with an adjusted EBITDA margin of roughly 22%. Capex is projected at somewhere between $350 million and $380 million, and that figure takes in the rephasing of certain capital expenditure out of 2025, which I touched on a few moments ago. Underpinning our confidence in this guidance is the quality of our backlog, which provides more than 80% visibility on revenue, along with tendering activity that remains high and an attractive prospects pipeline. I'll now hand things back to John.

John Evans

executive
#8

Thanks, Mark. The following 2 slides show a few highlights from our technology-led solutions portfolio. Slide 10 covers 4insights, which our 4Subsea business in Norway developed. 4insight is software that merges real-time data from vessels with weather feeds and applies advanced algorithms to automate operating decisions on board. This extends the windows of operability for our vessels and boosts performance in project delivery by lowering the cost and schedule risks tied to waiting on weather. Automating the decision-making process also strengthens collaboration between marine and project crews and maximizes how efficiently we run our operations. The software has been rolled out across part of our fleet and has drawn excellent feedback from our offshore and onshore teams. In 2025 to date, it has added 35 days of operation to Seven Vega, an uplift of over 10% compared to our standard planning assumptions. The second highlight slide focuses on our unique bundle pipeline technology. Last quarter, we touched on this when we discussed our activity at Yggdrasil in Norway, which included the launch of a large bundle during the summer. By combining active heating, flow lines and the control systems into one towable bundle, we reduce the complexity of the Subsea architecture and offer a cost-effective alternative to traditional models.

John Evans

executive
#9

Bringing this to life calls for our proprietary lining, plus highly specialized welding done by the team based in Wick, Scotland. Among all contractors, Subsea 7 alone can point to a proven record of delivering production system bundles, with more than 90 installations to date. The repeat orders we receive from clients — Aker BP, BP, Chevron, Equinor and Shell among them — demonstrate how well this unique solution has worked, and more broadly they speak to the strength of the innovative solutions that come out of Subsea 7's advanced engineering and fabrication capabilities. Moving on, let's review our prospects, which you'll find on Slide 12 and 13. Within Subsea, tendering activity continues at high levels throughout our key regions, with a combined prospect value of roughly $21 billion. The majority of projects shown on this map are long-cycle deepwater developments whose economics are favorable. A good number of them hold strategic importance for the operators as well as for their host nations. Sanctioning will rest on how commodity prices are viewed beyond the next 5 years, which shields these projects from shifts in the spot price of oil and gas. Taking it all together, we have confidence in the long-term outlook for our Subsea business, since demand for our technology-led solutions is expected to stay at high levels. On the following slide, we provide a summary of the fixed offshore wind projects that could bid in the U.K.'s Allocation Round 7, AR7.

John Evans

executive
#10

While the cap of GBP 113 per megawatt hour on strike price got a favorable reception, the budget for AR7 that was announced recently fell short of what the industry had hoped for. As I mentioned last quarter, outside of China, the U.K. ranks as the biggest single market worldwide in offshore wind. And given that several other markets are growing more slowly than expected, how the AR7 process ultimately turns out will be a key factor driving medium-term momentum for the industry. Subsea 7 keeps helping a number of key clients optimize the AR7 developments, while staying selective about which contracts we take on so as to protect our future profitability. To wrap up, we'll move to our last slide, on Page 14. Subsea 7 closed the third quarter of 2025 with a record backlog of firm orders worth close to $14 billion. We've raised our guidance for 2025, and our guidance pointing to continued growth in 2026 shows our confidence in the outlook. Further out, we hold strong conviction about the resilience of the deepwater Subsea market, and together with a differentiated offering and a solid track record of delivery, this puts Subsea 7 in position to succeed. With that, we'll gladly take your questions.

Operator

operator
#11

<<operator_script>> Our first question now comes from Sebastian Erskine of Rothschild & Co Redburn.

Sebastian Erskine

analyst
#12

Thanks for the congratulations on today's results, and it's great to see the backlog sitting at a record level. I'd like to just follow up on the Renewables business. So I guess a seasonal uplift in Renewables margins is what we can expect in 4Q, which lines up with the new guide. But how should we think about that original kind of 14% to 16% EBITDA margin guidance into '26? And I guess tied to this — I mean, you brought it up in the prepared remarks — but could you give us an update on the time lines associated with Allocation Round 7, as there seems to be some stalling in progress? So yes, getting your thinking on that would be great.

John Evans

executive
#13

I’ll have Stuart address both of those questions, if he would.

Stuart Fitzgerald

executive
#14

Yes. So let me address the guidance question first. We are keeping that guidance as we move forward into 2026. It's also worth noting that our backlog position gives us especially strong visibility through '26 and on into '27. Then, turning to Allocation Round 7: developers have been submitting their various projects into the allocation round over the past week. As we understand it, that milestone is basically done, and the results are set to be announced around mid-January. So the next key milestone on the timeline is the mid-January announcement of outcomes. But to the best of our knowledge, the submissions have now been made.

Sebastian Erskine

analyst
#15

Thanks for that, Stuart. And if I could just ask one more question — I know it's a tough one, this merger topic. We've noticed that a number of interested third parties have come into the Brazilian antitrust review. Could you update us on where that process stands and when we might hear a ruling from CADE, if there's anything you can share on that? And any other news on the geographies where you're filing would be helpful too.

John Evans

executive
#16

Sure, I'll respond to those. As we've mentioned repeatedly during these calls, we're not going to provide a detailed step-by-step narrative here, but let's take a broader view. At the time we announced the merger, starting with the MoU signing at the end of February, our target was full completion in the second half of 2026. The CADE process is proceeding along the path we anticipated. We file our submissions. Interested parties then come forward and identify themselves as interested parties. A broader market consultation also takes place, involving suppliers, our peers and our clients, and that process is currently in progress. We'll then have a chance to talk with CADE about our responses to the various topics raised. After that, CADE will move into their review process next year. So our belief remains that the merger's time line and critical path, running through CADE and Brazil, should enable us to finish by the second half of 2026.

Operator

operator
#17

Our following question will be taken now. Victoria McCulloch from RBC is on the line with the next one.

Victoria McCulloch

analyst
#18

Also on Renewables, could you discuss what it will contribute in 2026? I understand you don't provide that figure specifically, but based on what Stuart said, should the growth driver then be seen as coming from the Subsea and Conventional business? And then, John, maybe a somewhat broader picture — your views. Could you give us some color on how you've seen the tendering pipeline and engagement with your customers over the last 3 months? The macro environment remains fairly unpredictable, but it would be interesting to hear about the conversations you're having and the engagement you have with customers.

John Evans

executive
#19

Yes. On Renewables, Stuart made it clear that a guidance range of 14% to 16% EBITDA for Renewables in 2026 is something we're comfortable with. And as he says, he already has a high coverage of work on the books. So again, Victoria, I don't think we'll provide any further information on that, but we're comfortable that we're in a good position in Renewables in '26, and as Stuart alluded to, also going into 2027. So for us, it's more about what it is in '28 and '29, and AR7 will be part of understanding that in the first quarter of next year. Coming to client interactions, I was down in Brazil at Rio OTC about 3 weeks ago. We've had a number of client discussions, which, as you'd expect, continue. We're seeing very little change in our clients' views. They are clear that they've got a number of large Subsea projects out there for bid or to be bid. The dialogue is all around timing of their bids, timing of their projects, what early commitments do they need to make, vessels availability. It's the traditional questions that we get in a busy market, Victoria. In Brazil, discussions with Petrobras.

John Evans

executive
#20

We anticipate that Petrobras' 5-year plan, coming out within roughly the next week, will keep Subsea projects as the primary engine and key driver for Petrobras. Their discussions on this are clear. Many other clients have some significant opportunities in view. We are bidding on work in Namibia. We are bidding on work in Mozambique. A couple of years ago, those nations were not on our radar screen. And down in Türkiye, during the first week of December. And once more, that relates to our vessels heading in for Phase 2. As you know, we secured Phase 3, yet additional phases of Sakarya are still to come. And we keep working with Equinor as planned on developing Wisting and Bay du Nord. Those 2 major developments, one located in northern Norway, the other in Canada. And they are quietly proceeding just as we had planned with Equinor — that we would be working alongside them, examining multiple different scenarios. So in short, we are not seeing a genuine change. And another point we mentioned last quarter was the pleasant surprise of seeing a number of new projects arriving in Norway.

John Evans

executive
#21

We anticipate that the ConocoPhillips project will be sanctioned by the end of the year. So there are quite innovative projects out there involving a number of clients, and our confidence remains strong. The sole geography where that does not hold true is the U.K., but I believe everyone understands that unless something shifts in next month's budget, the U.K. is likely somewhat out of step with the rest of the world.

Victoria McCulloch

analyst
#22

And perhaps only as a follow-up to that: it was interesting to hear — clearly, you have shown us quite a bit regarding the pipeline bundles you have completed for Yggdrasil, for Aker BP, and how that is optimizing CapEx and OpEx for your customer. I suppose, how many, I guess, new ideas in AI are customers seeking and sort of new wins from that? Since, I guess, AI is such a massive theme globally, but how much of that features in conversations in terms of them attempting to get economics better because of AI?

John Evans

executive
#23

Sure. Our customers are always keen. Yggdrasil is a good illustration — we're deploying every technology Subsea 7 possesses on that large greenfield development. There are bundles in the mix. Traditional relay is in there too. Heated pipelines are included. Cool pipelines feature in the system as well. Everything is in there. That's the reason clients come to us: we offer a complete toolkit, a full technology capability. Moving on to 4insight. 4insight is a type of AI technology that draws on real-time data, crunches massive data volumes to give our offshore crews clarity on what will happen over the next 24 hours and how they should consider whether we keep going into the good weather, or do we halt, do we begin, and similar questions. In the past, all of that was handled in a very static way. Before heading offshore, we plan various scenarios. We carry those scenarios out there. We have a book that tells us what we can and cannot do. If we're within the parameters, we can work; if we're outside the parameters — what 4insight has done is say, let's take the actual parameters we have here and the actual forecast parameters and what you've experienced over the last 24 hours and precisely which direction the weather is striking the ship and so on, and can we keep laying pipeline.

John Evans

executive
#24

And once more, like I mentioned during my prepared remarks, we're seeing some meaningful gains. So it comes down to the mix of technologies we have, genuine productivity, and also simply questioning the way things have always been done. We're additionally putting in a fair amount of effort alongside certain regulators and certifying bodies regarding how our DP vessels are operated. The dynamic positioning rules date back to the 1980s, a time when fuel cost nothing. Emissions weren't on anyone's mind. So today we're discovering alternative methods for operating these ships, yet the codes need to be updated for us to do so. That lets us boost our fuel efficiency — which our clients cover the cost of — and it also cuts our emissions, but the codes must be revised to reflect the fact that what worked in the '80s doesn't have to carry over into the 2025 we're living in now. So plenty of excellent developments are underway, Victoria, a lot of strong engagement with our clients and, along with that, with each and every client on those kinds of technologies. So the industry is in a good spot. And as we're aware, deepwater subsea carries one of the lowest costs per barrel lifted among any form of oil or gas available.

John Evans

executive
#25

So my sense is that we're positioned well and the timing is favorable.

Operator

operator
#26

Our next question comes from Kevin Roger of Kepler Cheuvreux, and we'll take that now.

Kévin Roger

analyst
#27

The first question is really kind of two parts, because if I look at backlog execution for 2026, you're saying our visibility there is roughly 13% higher, yet the top-line guidance only points to 3% growth in '26 compared with '25. So could you shed a little light on why execution backlog is up 13% while the top line is guided up 3%? Does it have to do with the fleet utilization rate being essentially fully booked at the end? I just want to grasp the reasoning behind the top line. And the second thing, John, you touched on it briefly — the big Equinor project for 2026. There's been some chatter, particularly this morning, that Equinor is out in the market right now for fabrication tools. So I just want to understand from your perspective whether this would be full scope, or whether it will come phase by phase — meaning that for '26, it would be more than $1 billion, as you've flagged the projects in the pipeline, or a smaller phase, since it's going to be carried out in different phases?

John Evans

executive
#28

Yes. Regarding the backlog for 2026, I suppose that simply shows we're operating in a really active market, and clients have made commitments to us sooner. Our capacity is limited, and that's the reason revenue isn't growing as much. Naturally, we'd expect to be at 100% backlog by the close of next year. So it's really a matter of timing, Kevin. Many of our clients have come to us early, and that's been happening for a number of years now — they make commitments to guarantee capacity is available for them as they head into '26 and '27. So it's essentially a timing mismatch rather than anything more, not a fundamental problem. In this quarter, utilization stands at 87%. We're approaching the top end of what's achievable, and we've talked about that several times during this call. What matters most to us after the merger is cutting down the number of transits between projects and similar things. That's one of the genuine draws for many of our clients — more days become available when you don't relocate these assets. But right now, we have the fleet we have. We know precisely where those assets will be positioned next year.

John Evans

executive
#29

I don't really view that as a disconnect. Revenue is going to be revenue within the range we provided. The backlog is simply higher than what we'd typically anticipate. That said, from what I remember, whenever the market heats up, customers lock in their assets sooner. On your second question, Bay du Nord is a project we execute seasonally across several seasons, and we won't be offshore until later in this decade — that has always been the situation. Given the weather conditions there, roughly 100 days per year is what we can manage. So it's a multiyear project. Next year, we'll keep operating in the same work mode we're in now, which means working with Equinor on the field layouts and letting them pass through the various decision gates, DG2 and DG3, that they need to clear. So from our side, Bay du Nord has meant continuing to work with them in the mode we've been in for a couple of years. And so they'll make their key decisions, I suspect, in '27, once they have all their information regarding their fabrication, their local content, as well as the SURF packages. What I'd say is, I think there's been solid work between the SIA and Equinor over a couple of years, and some very interesting thinking has gone into how to phase the project and how it all comes together.

John Evans

executive
#30

To return to the question you raised at the start, Kevin, this was a phased project from the beginning, since the weather out there and how remote that area of the Atlantic offshore Canada is mean that you can only work 100-day slots each year. And the key to probably unlocking the economics in that field is simply how you sequence it and how you develop the wells along with the reservoir that goes with it.

Operator

operator
#31

Guilherme Levy from Morgan Stanley has the next question.

Guilherme Levy

analyst
#32

Starting with the first one, and keeping your guidance in mind, how much of the lower figure this year would you attribute to activity that may have — that might have slipped into 2026? And could you perhaps tell us what kind of activity that is? Then, looking at 2026, is that a reasonable level for us to consider for your capital needs over the long term? Or are there any nonrecurring factors within the 2026 figures? And then the second one, turning to Brazil. Earlier this year, a headline said that Petrobras was keen to do a long-term lease of a vessel for installing rigid pipes in the Pre-Salt itself. Do you feel this is a live discussion? Are they actively looking to do that? Or do you feel it was just a headline that didn't really evolve over the course of the year?

John Evans

executive
#33

So, regarding that first question about the sort of revenue guidance between this year and next year and so on — you know our projects well. They're recognized on a percentage-of-completion basis at the close of each year. It swings around on big projects; a couple of percentage points can move dollars quite a lot. There's no reason for concern. It's simply a matter of how the different sequences across our projects are lining up. As for 2026, like I said earlier in response to Kevin, we have a reasonably clear picture of how it all fits together. We've provided a revenue range that we feel comfortable putting out to the market here, with a high level of visibility into how that comes together, and even for the work that isn't yet in backlog, we have a pretty clear sense in our minds of how it will come together. And naturally, as we've always done, should things change, we'll update the market each quarter as we see those changes. Finally, Petrobras is speaking with the market about possibly taking a long-term lease on a rigid pipelay vessel. Interestingly, we held a contract several years back, from 2012 to 2017, covering precisely that same kind of work, known as hybrid steel, which was an agreement Subsea 7 had with Petrobras.

John Evans

executive
#34

I'm old enough to recognize what those look like, and we have done this before. Once more, when Petrobras brings something to market, we'll respond, and that would interest us. But keep in mind the timeline probably involves 4 or 5 major projects, each needing a pipelay. So again, if they take that route — and I do understand. We've been talking with them. It comes down to when the FPSOs arrive, and the difficulties of running different projects on different schedules with FPSOs arriving at different times. So perhaps the riser hangoffs would use a vessel closer to a PLSV, which is more of a day rate contract, giving them control that way. So I fully understand the logic. It makes a lot of sense, and we would certainly be interested in the opportunity set if that reaches the market next year.

Guilherme Levy

analyst
#35

Sorry, the first one — I was actually just referring to your new CapEx guidance. So yes, just thinking about your 2026 CapEx guidance, is there any reason why 2027 should be materially different from that?

Mark Foley

executive
#36

Honestly, this comes down to the ships that need to complete their mandatory dry docking. So, as you're aware, our CapEx rises and falls based on where those vessels sit in the cycle. Most of what we spend on CapEx goes toward vessels and equipment. So I believe we gave updated guidance for this year, a bit lower, and that's really because of tight capital discipline across the organization, plus a late phasing — some cash capital expenditure shifting into 2026 — and then an amount we've guided to for next year. So again, it's going to differ year-on-year based on what the vessels require and the opportunities we see for growth, capital expenditure on minor modifications, supplementary equipment additions, et cetera. So hopefully, that gives you some additional color.

Operator

operator
#37

Alejandra Magana from JPMorgan has the next question in the queue.

Alejandra Magana

analyst
#38

Regarding the strength in your SURF and Conventional margins, could you help us understand what portion of that improvement comes from execution outperformance as opposed to older, lower-margin projects rolling off? And how much of it stems from structurally better commercial terms or pricing power on more recent awards? Also, as the 2026 backlog converts, in what commercial ways do these contracts differ from those you've executed this year?

John Evans

executive
#39

I won't break down the margin mix. As I mentioned during my prepared remarks, it's a combination of several factors. This year we're bringing fewer projects that were taken before 2022 into the portfolio, and by the time we move into next year, none of those will remain. As we've been quite open about in this market, every project gets bid on its own, so each of the different projects carries a blend of margins. At times, certain projects fit us well because of equipment availability, timing, and clients' decision-making, along with possible delays on other projects. So once more, that mix is fairly complex. And finally, as we've talked about, execution has been very strong all year, and I'm quite happy with what we've achieved on that front. When you put all of these together, we end up with a very good margin in the business. But we're not going to get into how those items break out. Looking ahead to 2026, once again it comes down to the stack of projects we have in there. Nothing from before '22 is in the mix. So it's the packages of work secured over the last 3 years, at their various stages, that deliver the margin we expect to see next year.

John Evans

executive
#40

We've therefore provided clarity via the guidance regarding the revenue range, and we expect to land at roughly 22% EBITDA next year on the portfolio we hold. And to wrap up on that point, we're fairly confident about it, since more than 80% of that margin is already booked. And as I mentioned earlier, I'm fairly sure I understand how the remaining 20% will come together. That remaining 20% portion consists of things like call-off agreements with a number of clients where we're already under contract. We know the margin, but we haven't yet received the call offers. So the confidence level here is quite high. And we'll move into '26 and let it run and see how things go from there.

Alejandra Magana

analyst
#41

That's very clear. Turning to the new PLSV contracts in Brazil, could you help us understand how the rates under these stack up against earlier agreements? And should we anticipate an increase in PLSV earnings across the coming few years?

John Evans

executive
#42

Yes. So those were awarded a year back. That’s information that, if you look through the press releases we have put out and those our competitors have put out, is all publicly available. You can — you know that every contract runs about 1,000 days. So they were better than what we had, for sure, and all 4 PLSVs are now under the new contracts. Just last week, the fourth of our PLSVs moved onto its new agreements. So next year, part of the margin uplift comes from the fact that the mix of work we have next year, as we talked about earlier, is a better mix. So the PLSVs are public domain information. So if you go back and dig through those, you can work the figures out from where we were and where we are now.

Operator

operator
#43

<<operator_script>>. Our following question is from Erik Aspen Fossa of SB1 Markets.

Erik Aspen Fosså

analyst
#44

I've got at least 2 questions. The first one's for you, John. As I understand it so far, the expectation has been that we'd see a modest pickup in activity from '25 to '26. And I'm wondering how we ought to think about that on a stand-alone basis for Subsea 7 as we go into 2027. Is there still room for additional gains — say, via fleet optimization and similar measures? Or have we more or less plateaued at this point in terms of what's achievable with the fleet you currently have?

John Evans

executive
#45

Eric, I think the interesting thing for us is that the backlog we have for '27 is quite strong. Looking at the numbers alone, we hold $3.8 billion in backlog for 2027, and that puts us in a very good position this far out. We're making some changes next year. It also comes down to how we lift margins on our projects. We've had certain efforts underway — on some Jones Act work, for instance, that we won't carry into next year. Those chartered vessels will go back to their owners, since the margins we expect aren't achievable. The Champion has been returned in the Middle East. So for us, it's also a matter of being extremely selective regarding which assets we deploy, the way we deploy them, the returns we earn, and the risks we accept to earn those returns. So improvement is possible. There's always room. But at this point it's about taking the asset base we have, as Mark said, and being fairly brutal about what it's doing, where it's working, and what it's returning for us. So you'll see some changes in the fleet next year — in fact, reductions in our fleet size next year while revenue is going up.

John Evans

executive
#46

Right now, Eric, that’s the job we’ve got: get the most out of what we have during the cycles we operate in.

Erik Aspen Fosså

analyst
#47

I believe you've kind of begun addressing my second question as well, which concerned the lease costs, and those came down a bit this quarter. So I'm just wondering how we ought to think about that going into 2026 — should it decline for the reason you just laid out, John?

Mark Foley

executive
#48

Right, Eric. In 2026, we'll see the cash impact from lease liabilities trend downward directionally, and that comes from returning a portion of the leased vessels currently in our portfolio. As you're aware, of the 41 vessels, 11 are leased, and several of those will revert to their owners once the charter period ends.

Erik Aspen Fosså

analyst
#49

Did that involve only the Jones Act vessels, or were other vessels included as well?

Mark Foley

executive
#50

Every vessel in the fleet, Eric.

John Evans

executive
#51

Yes. So I went through the Champion — it was leased, and it was located in the Middle East. That one has come back already. A couple of Jones Act vessels are going to go back, and at least one more — an additional one — will go back too, though we aren't ready to include that one right now. But as Mark is saying, that's the direction we're heading; we're working through it, making sure that if we bring in extra tonnage, the first question is whether it adds value to the portfolio and whether we can — what we're trying to accomplish here is growing revenue while also making sure we hold the margin. So that's what this fine-tuning is all about. But it also brings our lease obligation line down, which, again, I know gets a lot of attention in the market as well.

Erik Aspen Fosså

analyst
#52

And finally, can you give us some idea of the kind of level we should be thinking about for next year when it comes to the lease payments?

Mark Foley

executive
#53

For this year, Eric, it's going to be noticeably lower than what we've incurred up to now. I believe we've discussed this each quarter. Cash out for the year — principal plus interest — will likely come in just under $300 million, and we've provided some color on the vessels that, with everything else held equal, we'll take out of the fleet. I'll leave it to you to apply your own assumptions about what that translates to in terms of the impact — the favorable impact on cash.

Operator

operator
#54

That wraps up the Q&A portion for today. At this point, I'll turn things over to John Evans, who has some closing remarks.

John Evans

executive
#55

Thank you so much for being with us. There's an interesting story we want to share, and we value your ongoing backing, the questions you raise, and the papers you write concerning Subsea 7. As I see it, 2026 is set to be a very good year for us. We've attempted to lay that out for you and to provide information that helps you model it and plan ahead. And we remain engaged in a number of quite constructive conversations. Stuart has likewise been quite candid regarding the opportunity sets in Renewables for '28 and '29, and those will become clearer in Q1 next year. So with luck, when we come together for our Q4 results around the end of February or early March, we'll be in a position to share further updates on how we view AR7 and what it means for Seaway 7. So, as always, many thanks for your support and your questions, and we'll see you again before long. Thank you. Goodbye.

Operator

operator
#56

That brings us to the end of today's conference call. Thanks for joining us. You can disconnect now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Subsea 7 S.A. transcript — plus 131,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Subsea 7 S.A. earnings transcripts and 131,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Subsea 7 S.A. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.