Thanks for joining TC Energy's conference call on our financial results for the first quarter of 2023. <<operator_script>> This call is being recorded. <<operator_script>> At this point, I'll hand things over to Gavin Wylie, Vice President, Investor Relations. Go ahead, please.

Gavin Wylie

executive
#2

Absolutely — thank you, and good morning to all of you. It's my pleasure to welcome everyone to the 2023 First Quarter Conference Call for TC Energy. With me today are Francois Poirier, our President and Chief Executive Officer, and Joel Hunter, our Chief Financial Officer, as well as other members of our senior leadership team. Francois and Joel will open today's session with some remarks on our financial and operational results. The slide presentation that accompanies their results is posted on our website in the Investors section. After those remarks, we'll open the line for questions from the investment community. We do ask that you keep yourself to 2 questions. If you're a member of the media, please reach out to our media team. Before Francois begins, I'll remind you that today's remarks will include forward-looking statements that are subject to important risks and uncertainties. For more information, please see the reports filed by TC Energy with the Canadian securities regulators and with the U.S. Securities Exchange Commission. Finally, during the presentation, we'll refer to certain non-GAAP measures that may not be comparable to similar measures presented by other entities. These measures are used to provide additional information on TC Energy's operating performance, liquidity and its ability to generate funds to finance its operations.

Gavin Wylie

executive
#3

You'll find a reconciliation of the various GAAP and non-GAAP measures in the appendix of the presentation. So with that, I'll hand things over to Francois.

François Poirier

executive
#4

Good morning, everyone. I'm happy to say that the strong financial results we delivered in 2022 have carried over into the first quarter of 2023. Exceptional first-quarter results were made possible by high utilization and availability throughout our system. That reflects the efforts of our people, sustained robust demand for our critical energy assets, and the resilience of our low-risk business. Our priorities for the rest of 2023 are clear. First, executing on our major projects and our industry-leading, high-quality secured capital program; second, accelerating our deleveraging targets by advancing our $5-plus billion asset divestiture program, which we expect to complete throughout the year; and third, operating our assets safely and reliably to provide essential energy services across North America. We firmly believe that achieving these priorities will unlock value and maximize shareholder returns. And given our strong start to 2023, we reaffirm our 2023 comparable EBITDA outlook of 5% to 7% higher than in 2022. Driven by our focus on strong operational performance, first quarter results had comparable EBITDA up 16% from the same period last year, while comparable earnings per share rose by 8% year-over-year. During the quarter, we placed a total of $1.4 billion of projects in service, and we remain on track to place $6 billion of assets in service during 2023.

François Poirier

executive
#5

In Canada Gas, we placed $1.1 billion worth of projects into service, which adds further incremental market access for customers in the basin. Also in March, we brought the Port Neches Link pipeline into service, and it came in under budget, extending our Keystone system so it now includes last-mile connectivity to the largest refinery in North America. In our U.S. natural gas business, 2022 stood out as a record year for compressor reliability across the fleet. And in 2023 so far, we are on track to match or even surpass that performance. This year we have set a number of all-time records for deliveries to LNG export facilities, which reinforces how critical our assets are. And in Power and Energy Solutions, Bruce Power achieved exceptional availability of 95%, and we expect 2023 to average in the low 90s. Unit 6 MCR is moving ahead on schedule and on budget and now sits in the final stages of the installation phase. Executing our major project is our central priority for 2023. I'm pleased to share that Coastal GasLink continues along our revised cost and schedule and moved through the winter on plan. We hit several major milestones, with the overall project now 87% complete, and roughly 570 of the 670 kilometers of pipeline has been backfilled, with restoration activities underway in many areas.

François Poirier

executive
#6

Work has started on commissioning the Wilde Lake compressor Station, and natural gas has been brought in as the facility moves toward operations. Over 85% of all classified water crossings are finished at this point, and we completed excavation at Cable Crane Hill safely and ahead of schedule; final pipe installation is now underway through that critical path section. Mechanical completion by the end of the year remains our target. The Southeast Gateway pipeline, our second offshore project in Mexico, is likewise moving forward on cost and schedule. First milestones have been reached, with land acquired for compressor stations and offshore landfalls. Key federal environmental authorizations and local permits for the project have been obtained. Critical long-lead items, the offshore vessel among them, are secured, and materials have started arriving. We expect to begin onshore construction of our compressor stations this summer. Civil work, in fact, is already underway. Offshore pipe installation will get started toward the end of 2023. As a reminder, roughly 70% of total project costs sit under fixed price contracts, which gives greater certainty on cost and schedule, and completion by mid-2025 remains our target. After the Milepost 14 incident on the Keystone system in December, we have been working diligently to restore the area to its original state.

François Poirier

executive
#7

We're happy to say we've brought back more than 98% of the release volume. We want to give a big thank-you to the Washington County community for their continued support, and we're dedicated to making sure the effective area is fully restored. We've gotten the independent third-party root cause analysis. And with what those findings show, we're committed to putting in place a comprehensive plan to strengthen our pipeline integrity program and our overall safety performance. Now, as we look to the future, our North American footprint gives us access to a diverse set of high-quality growth opportunities. That's a high-grade problem to have. But when we evaluate incremental projects, we have to consider both financial and human capacity. We recognize we're in a period of increased development spend. However, after 2024, we're committing to capping annual sanctioned capital expenditures at $7 billion or less. In fact, we'll strive to manage annual capital spending at approximately $6 billion, which gives us the flexibility to further reduce leverage or buy back common shares. When we sanction new projects, a key consideration will be the timing of the capital spend, and it has to fit within our annual capital expenditure parameters and deleveraging targets. We've also strengthened our governance practices and set higher standards around sanctioning large or complex projects, which includes requiring a Class III estimate as well as an independent third-party assessment, as was the case with the Southeast Gateway.

François Poirier

executive
#8

We will keep sticking, as we always have, to the risk/return preferences we established long ago. Let me point out that long-term take-or-pay contracts or rate regulation back 98% of our secured capital program, and in those areas we bear no commodity price risk and no volumetric risk. A long-term perspective on energy fundamentals is what underpins the resiliency of our business and of our capital allocation strategy. In North America's energy future, natural gas will keep playing a pivotal role, and that fits well both with the portfolio we hold today and with the projects we have sanctioned. Lower carbon energy solutions will steadily gain market share, and we will deliberately shift the makeup of our portfolio, though gradually as time goes on. And we'll place emphasis on building firm capacity in areas such as nuclear, pump storage, hydrogen and carbon transportation and sequestration. In decarbonizing our own assets, renewable energy will serve a complementary function, and we can extend that product and service to our customers as well. Still, affordability, reliability and sustainability will in the end dictate how quickly we put capital into these areas. Thank you — and now I'll hand the time to Joel.

Joel Hunter

executive
#9

Thanks, Francois. On top of the record results we delivered in 2022, we hit a new quarterly record in first quarter 2023, and that speaks to strong utilization, availability and sustained operational performance throughout our asset base. Comparable EBITDA for first quarter 2023 rose 16% year-over-year, comparable earnings grew 12%, and comparable earnings per share increased 8% year-over-year. Once again we're showing how certain and stable our cash flow growth is, which reflects the fact that more than 95% of our assets are rate regulated or backed by long-term contracts. The quarter's strong performance came from a combination of strength in our North American natural gas pipelines plus larger contributions from our Power and Energy Solutions business. Net income at our rate-regulated Canadian natural gas pipelines climbed 11% year-over-year, mainly on growth in the NGTL system average investment base. Average NGTL system deliveries increased year-over-year, hitting 14.5 billion cubic feet per day. The 14% growth in comparable EBITDA at our U.S. Natural Gas Pipelines came largely from higher earnings at ANR after the FERC approved rate case settlement, along with contributions from growth projects that were placed in service. Throughput averaged 28.5 billion cubic feet per day for the quarter, and several of our assets ran at near record levels when demand peaked.

Joel Hunter

executive
#10

For Mexico, comparable EBITDA rose 16% compared with a year earlier, which mirrors the north section of the Villa de Reyes pipeline and the east section of the Tula pipeline both entering commercial service during the prior year. So far this year, the Keystone system's operational reliability has exceeded 95%, which supports delivering all contracted volumes safely and dependably for our customers. Power and Energy Solutions delivered excellent results, with comparable EBITDA up 79% versus the same period last year. In February, our Alberta cogeneration power fleet hit 100% peak price availability for the first time ever in the company's history, while pricing stayed strong and averaged $142 per megawatt hour. Bruce Power posted 95% availability for the quarter, with fewer planned outage days and higher contract pricing than in the first quarter of 2022. We are reaffirming our expectation for 2023 comparable EBITDA growth of 5% to 7% versus 2022. We also anticipate comparable earnings per common share will be modestly higher. Our confidence in this outlook holds even with rising interest rates and inflation. And as a reminder, fluctuations in these variables and other factors could affect our 2023 outlook, and we will look to revise it throughout the year if necessary. Global markets have seen high volatility, and I want to take a moment to talk about how confident I am in our outlook and in our ability to meet our financing requirements.

Joel Hunter

executive
#11

The chart on the left shows how quickly rates rose during 2022, and those increases were fairly uniform along the curve, which pushed interest expense higher year over year. That said, 10-year government bond yields are starting to come down from their recent peaks. We keep showing that we can access capital markets at competitive cost, and Q1 demonstrated this when we completed more than $6.5 billion of new issuance spanning various maturities and geographies. The fixed rate debt tranches from those issuances carry a weighted average cost of 5.6%. Our debt maturity profile is manageable, with a weighted average maturity of roughly 18 years and an average pretax coupon of about 5%. About 15% of our debt portfolio carries exposure to floating interest rates, and we have programs in place to actively manage those exposures. Now let me turn to our funding program. Capital discipline is a key priority for us. Without compromising operational safety or reliability, beyond 2024 we will hold our annual sanctioned capital spending to $7 billion or less, including maintenance capital. As Francois mentioned, we will aim to manage annual capital spending at approximately $6 billion. This strengthens our financial position while giving us optionality to deleverage further or repurchase shares.

Joel Hunter

executive
#12

I should point out that the sources and uses shown on this chart don't factor in the effect of possible asset sales that we anticipate completing through 2023. As our divestiture program moves forward, you can expect our incremental funding needs to come down, which will let us speed up our deleveraging target even more. Regarding the dividends declared on February 13, 2023, participation in our dividend reinvestment plan came in at 38%, which meant roughly $360 million was reinvested into common equity through the program. The discounted dividend reinvestment plan is expected to remain available through dividends declared for the quarter ending June 30, 2023. Lastly, I'd like to draw your attention to two charts that really demonstrate how resilient our value proposition is: First, TC's Energy Board of Directors has declared a second quarter 2023 dividend of $0.93 per common share, which works out to $3.72 per share on an annual basis. Second, we've posted strong results. That reflects the strength of our utility-like business model, our unwavering focus on safety and operational excellence, and growing demand across North America for our essential services. We've generated meaningful shareholder value despite market volatility and macroeconomic challenges, and I'm confident we'll keep doing so.

Joel Hunter

executive
#13

Thanks. At this point, I'll hand things back over to Francois.

François Poirier

executive
#14

Thanks, Joel. To sum up, what we need to accomplish this year is straightforward. First, we keep delivering on our big projects, including CGL and Southeast Gateway. Second, we speed up our deleveraging goals by controlling capital spending and pushing our asset divestiture program forward. And third, we pursue safe, reliable and sustainable operations, with operational excellence as our focus so we can generate higher returns. To show how committed we are to these priorities and to align better with our shareholders, we've put in place new performance measures that directly link executive compensation to cash flow per share, deleveraging and greenhouse gas emission reduction targets. I'm confident that the opportunity set ahead, together with our capabilities and reflecting capital discipline, will unlock additional value and deliver superior shareholder returns well into the future. Thanks. And now I'll hand the call back to the operator for questions.

Operator

operator
#15

<<operator_script>> Our initial question is from Rob Hope at Scotiabank.

Robert Hope

analyst
#16

The first question is about capital allocation. In the prepared remarks, it was mentioned that approving new capital has to align with the organization's financial capacity. How does the Wind acquisition fit with that? Why not take a more capital-light approach for your renewables here, given that you are selling some assets?

Corey Hessen

executive
#17

Rob, it's Corey Hessen here. These opportunities came out of a process we started back in 2022 that wraps up during 2023, and they were already baked into our capital plan. They're top-quality operating assets featuring best-in-class equipment that will throw off EBITDA for the enterprise right away. For both sites, we hold a long-term service agreement running more than 15 years with the original equipment manufacturers, and those agreements carry availability guarantees covering both facilities. We're deep into talks with creditworthy counterparties regarding the power generation as well as the environmental attributes coming from these facilities. To sum up, the Texas wind farms sit inside our capital plan and represent a modest capital investment that helps TC Energy deliver on our decarbonization goals.

Robert Hope

analyst
#18

Okay, thank you. Turning now to Coastal GasLink: now that winter is over, it appears you achieved certain successes in maintaining that project’s schedule and budget. Still, when we consider the summer construction period and also the in-service date at the close of 2023, which risk factors do you regard as most important for preserving both cost and timeline? And what progress are you making in addressing them?

Bevin Wirzba

executive
#19

Bevin here, Rob — I’ll handle that one. You’re correct that we achieved really strong progress over the past season. Our attention is firmly fixed on bringing this project to completion safely. As we said in the remarks, that confirms again our cost and schedule targets for the year. What you should be watching for during the balance is essentially the same thing we’ve been addressing up to now: on a project of this size, there are an enormous number of work fronts, as you can imagine. We’re shifting mainly away from what you might call mainline construction toward a real emphasis on smaller, discrete work scopes — whether that’s Creek installations or Rock Bluffs. So we have been putting together mitigation plans for every possible eventuality across those smaller, discrete work scopes. And although we’re making excellent progress across the whole project, we’ve needed to become truly proactive about having backup plans for our backup plans. So when we give updates, our main focus will be on how we’ve advanced through these critical final areas of the project and how we’re implementing some of those backups as necessary. Just to offer a few proof points there: we pre-positioned some equipment so we could keep working through certain spring breakup periods, which lets us add a little more float to the schedule.

Bevin Wirzba

executive
#20

As Francois mentioned earlier, the trenching work at Cable Crane Hill is now finished. We're 3 months ahead of schedule on that. So wherever possible, we're looking to build in a meaningful buffer, since we're aware that any one of these critical work scopes could force us into Plan B or Plan C. That's really where our attention is. But gas was successfully introduced at Wilde Lake. That was carried out according to plan. More than 1 million man hours were completed safely there. So we're quite encouraged, though we remain extremely focused on managing those remaining critical scopes during the balance of the year.

Operator

operator
#21

Our following question is from Theresa Chen at Barclays.

Theresa Chen

analyst
#22

To start, I'd really like to hear more specifics about where things stand right now with the asset sale process. Given that it's now been several months in the works, do you have any clearer picture of which kinds of assets you intend to divest? And how should we approach thinking about the valuation?

François Poirier

executive
#23

I understand there's a lot of curiosity about the asset sale processes and the deleveraging plan. As I said, that's 1 of our 3 main priorities for this year. Let me just remind everybody that discussions are at a very commercially sensitive stage right now. We currently have multiple processes in progress. So we'll hold off on offering any specific remarks about any individual asset or about where valuations are heading. I'll say again, though, that our goal is to preserve the quality of our portfolio. So we'll be monetizing assets in -- or interests in assets in different parts of the portfolio to keep our cash flow composition, which we regard as very high quality.

Theresa Chen

analyst
#24

And if I could ask Stan about where things stand right now with Southeast Gateway. What share of the work is finished? Of that $4.5 billion, how much capital has gone out the door? And what milestones ought we to watch for next?

Stanley Chapman

executive
#25

Hey Theresa, it's Stan. As Francois <<inaudible>> said at the start, our Southeast Gateway pipeline is still on track for a mid-summer 2025 in-service date, with $4.5 billion of CapEx — both unchanged from when we took FID on the project this summer. I'd note that we're really happy with our partnership with CFE. They have played, and will keep playing, a very key role for us in helping secure both land and permits. On the activities that have been ongoing: steel plate is being delivered, pipe is being rolled, and preparations for its concrete coating are underway, so that the subsea pipeline work can begin at the end of this year. Specifically to your questions, there are 3 key milestones we're focused on this summer — diligently focused on, I should add. First is starting construction on our two compressor stations. Second is securing the right of way for our onshore pipeline, which, as you recall, is relatively small at about 21 kilometers. And lastly is beginning preparations for the onshore construction work associated with the micro tunnel, so that the microtunneling itself can take place in early 2024. So overall, we continue to incorporate the lessons learned from prior projects, such as <<inaudible>>, but we're really pleased with how our projects are progressing as of now, and we'll keep updating you as the project develops over the coming months.

Operator

operator
#26

Our following question is from Linda Ezergailis at TD Securities.

Linda Ezergailis

analyst
#27

Could you give us an idea of what you expect capital expenditure for 2024 specifically to look like? And roughly what scale of further wind or solar power purchases might be included in your budget for this year or next year, or possibly even added on top of what you've already factored in?

François Poirier

executive
#28

Francois here — I’ll handle that question. As we’ve discussed previously, when a project reaches construction and we break ground, we’ve likely already spent a couple of years on permitting, project planning, and ordering long lead items. And one reason we’ll aim to build in some optionality below our $7 billion capital run rate going forward is that we want to be sure we preserve some capacity for additional debt reduction or share buybacks down the road. Getting down to that $7 billion — or really $6 billion — run rate is going to take us the balance of this year and 2024. So you should expect us to be well under the $11.5 billion to $12 billion of capital in the plan for 2023, trending toward that $7 billion run rate, though not quite there yet — because of the dynamic we’ve identified. Regarding plans for additional renewables or other assets in our program going forward: remember, these involve very small capital dollars — tens of millions to low hundreds of millions over time. Wherever possible, we’ll use project financing and tax equity to bring our equity checks down to very modest levels.

François Poirier

executive
#29

So as we've gone through the capital plan and really tested whether we can keep the balance sheet steady, increase cash flow per share, raise the dividend, and maintain solid payout ratios, we've gotten to a point of comfort where we can say $6 billion to $7 billion is our run rate. Within our capital program, we've built in some added renewables, along with some extra investment in our other businesses.

Linda Ezergailis

analyst
#30

As a quick follow-up, just to complete my picture on Coastal GasLink, could you let me know whether any of the contingency in your budget has been drawn on this year — either to enlarge your schedule buffer or for any other purpose? And at this stage, do you consider it highly likely that you will tap into that contingency to fund some of the buffers and the Plan B contingencies you are putting in place to make sure you remain on schedule?

Bevin Wirzba

executive
#31

Bevin here. So at this point, we're following our cost and schedule targets quite closely. Of course, when we preposition certain work scopes, we do spend some of those dollars somewhat ahead of plan or otherwise, but we actually built that into our thinking back when the CSRA was done. And so we look at this probabilistically. And so under certain scenarios, we will certainly draw down on some of the contingency. But at this point, we're tracking where we've been or where our plan was to be at this time. So a lot of -- when we're making the trade-off decisions to pre-spend on different activities, those sit well within the plan. We've kept access to the head wall and other critical path scope, removing a ton of snow. We put that in the plan. So we were very thoughtful when we came forward with our revised budget last quarter to make sure that we had a variety of scenarios, not just a single scenario in mind in terms of the finishing or the executing of the project.

Operator

operator
#32

Our following question is from Jeremy Tonet at JPMorgan.

Jeremy Tonet

analyst
#33

I'd like to return to CGL construction, looking at it from a somewhat different angle. There may have been some competition for labor between CGL and TMX. I was wondering if you could speak to that — I suppose, how do you see TMX coming along right now, and if it's nearing the point of winding down, does that mean less strain and less demand on the labor pool? And what effect would that have on CTO?

Bevin Wirzba

executive
#34

Jeremy, I won’t comment on TMX. Their exact plans aren’t something I know. On our project, what we’re seeing is really strong retention among contractor labor. Quality has improved, and actual productivity has risen this year. As I said earlier, we’re moving toward a very different scope of work, and what I can tell you is that scope looks quite unlike what TMX is concentrating on in this year’s construction. So we’re very, very aware that competition exists for labor. Our focus will be on how our workforce comes back after the breakup. But after the Christmas breakup, when the same kind of competition from TMX was present, we actually returned stronger. We had nearly 6,500 people on the right of way during the first quarter of this year at a time when TMX increased their labor force significantly more than they had last year. So right now we’re holding a pretty strong position with our labor force, which we’re grateful for, and we’re collaborating very closely with our contractors to stay laser-focused on keeping the right people so this gets finished by the end of the year.

Jeremy Tonet

analyst
#35

Understood — that helps. I’d like to shift focus briefly to Columbia. There’s reporting out there about what I believe was a lightning strike that may have hit the <<inaudible>> compressor station and resulted in a force majeure, and I recognize this is all very much real time, but I wasn’t sure whether you could give us any color on how we should think about that.

Tina Faraca

executive
#36

Speaking is Tina Faraca from the U.S. Gas Pipeline business. A lightning strike hit us this morning — very early today — and it started a fire inside our fence line at the <<inaudible>> compressor station. That fire has been put out since then, with very minimal impact on facilities. We've worked our way through it and expect to bring the station back online later this afternoon.

Jeremy Tonet

analyst
#37

So basically, the effect here is only going to last a single day, is that right?

Tina Faraca

executive
#38

Absolutely.

Operator

operator
#39

Moving on, our following question is from Robert Kwan at RBC Capital Markets.

Robert Kwan

analyst
#40

Let me return to that $7 billion figure, if I may, and ask a few things. First off, are acquisitions counted in it? Second, a good chunk of this stretch of elevated CapEX has come from cost overruns, so I'm curious how you plan to handle cost risk in a different way from here on. And third, to be specific, what are the implications for Meaford? Or is project-level financing left out of that $7 billion number?

François Poirier

executive
#41

Robert, this is Francois, and I'll handle that question. Regarding how we handle cost overruns, sound project management means we hold a sensible contingency for every single project in our capital program. So we're working toward a $6 billion run-rate program as we move forward, and that provides us with flexibility and optionality for additional debt repayment and share buybacks. It also gives us extra flexibility should unforeseen circumstances arise around any one individual project. Our sanctioned capital stands at $6 billion or $7 billion. If we have partners, that amount would come on top of or outside that figure. As for the particular characteristics of any given project, project financing may or may not be taken into account depending on the project. Something like Ontario Pump storage is a major undertaking. So this isn't purely a financial calculation — it's also a question of human capacity. When we consider running a very large capital program, our ability to manage a smaller one lowers execution risk and lets us keep growing the dividend at the stated rate, grow cash flows at or above that rate, keep a stable balance sheet, and maintain stable and very conservative payout ratios.

François Poirier

executive
#42

So the capital program won’t be way ahead of our sanctioned capital because of human capacity reasons. And as we go ahead with various projects, we’ll contract for them in a different way, reducing risk by using full wrap EPCs where that makes sense, and also seeking commercial mitigations to manage those outcomes. So taking all of the above into account, you should think about that $7 billion, aiming for $6 billion as our sanctioned capital going forward.

Robert Kwan

analyst
#43

Understood. And regarding acquisitions—are those counted in or left out?

François Poirier

executive
#44

I appreciate you bringing that up. We don’t make a distinction there. M&A isn’t part of our plan. Given the opportunities we have to grow distributable cash flow per share faster than dividend growth while keeping payout ratios steady and the balance sheet stable, we don’t believe M&A is necessary for us. Right now, it simply isn’t something we’re focused on. And if it were, Robert, it would be covered within that cap.

Robert Kwan

analyst
#45

That's great. If I could just wrap up on capital allocation and ask a question framed around the wind acquisitions. You mentioned that while they're part of the 2023 capital program, you'd previously spoken about the general ability to defer capital, and this seems like something that could have been cut. So while they're operating, I assume you bought them at more than 5x EBITDA and below a 15% FFO yield — meaning the acquisition should be accretive to the credit metric. So was there anything that bound you to take these deals? Or could you just discuss the strategic nature of the two assets and the synergies they bring to the existing asset base?

Corey Hessen

executive
#46

Robert, this is Corey. I'd say yes, that was part of our plan. And what I'd stress is that we have decarbonization goals for the enterprise. Meeting those decarbonization goals is critical for us — they're long-term commitments to our shareholders and to constituents across our jurisdictions.

Operator

operator
#47

Our following question is from Robert Catellier at CIBC Capital Markets.

Robert Catellier

analyst
#48

I realize you don't want to talk about any specific asset, but could you address merchant power as an asset class? Power prices in Alberta have been pretty robust over the past year or so. How does that shape your thinking about this asset class as a candidate for portfolio management? Put another way, does the market justify a higher valuation, or would you rather hold on to them for the strong cash flow they're generating right now?

François Poirier

executive
#49

Robert, this is Francois. What I'd say is that divestitures—our divestiture program exists in order to deleverage. So we refer to that as raising internal equity, and internal equity comes from valuation above 5x debt to EBITDA. Consequently, when we pick which assets to monetize, we look at what the EBITDA multiple is beyond that 5x level, since we must maximize that spread above 5x EBITDA so as to maximize our deleveraging. Thus, if our Alberta assets were able to achieve multiples substantially higher than 5x debt to EBITDA, we would be willing to move ahead, and that's all I'll say on it.

Robert Catellier

analyst
#50

Okay. And perhaps one thing for Stan here. Deliveries into LNG facilities once again seem to have shown pretty solid volumes. I'm curious whether you could give us an update on how things are progressing with any further positioning you have in the U.S. gas portfolio and on development projects aimed at addressing additional LNG opportunities.

Stanley Chapman

executive
#51

Robert, it's Stan here. As I've mentioned previously, our top-tier pipeline footprint keeps delivering far more than sufficient growth prospects at appealing build multiples. What we're up against now, as you've heard, is chiefly a matter of originating new projects and making certain we have the means to finance them. So with that in mind, our origination work is extremely selective and centered on strategic opportunities where we can draw on our existing footprint — in particular, in areas where projects can secure permits and be built at appealing build multiples. Such opportunities currently lie in added LNG exports, especially in Louisiana, as you pointed out, and in strengthening the connections we have with our LDC customers, which are supported by long-term 20-year contracts. So in certain cases, where it makes sense, we might also look at bringing in a strategic joint venture partner. But just as important, I want to emphasize that we are sharply focused on guaranteeing operational excellence and bringing our costs down — and doing that without compromising the safety or integrity of our assets, and making sure we bring our projects into service on time and on budget.

François Poirier

executive
#52

And Robert, this is Francois. I want to build on what Stan said. When we consider approving capital moving forward, the schedule of that spending is going to be a key element in how we evaluate it. We are intensely focused on remaining under that $7 billion mark — and in fact under a $6 billion yearly pace of capital expenditure. So when you think about greenlighting projects down the road, and given how large our capital program has been up to now, really, as we approve projects going forward, the substantial capital outlay will land in later years. That's acceptable. Permitting a project and securing the long lead items typically takes a couple of years. So the projects we are currently looking to develop and competing for have spending in that '25, '26, '27 window, when we do have extra room to sanction projects while staying inside that $6 billion annual cap.

Operator

operator
#53

Our following question is from Ben Pham at BMO.

Ben Pham

analyst
#54

I’d like to circle back to renewables and what you’re doing strategically in that area. For a while, I believe what kept you somewhat constrained on growing that business was the higher valuations placed on renewable power assets, and you also brought in the aggregation approach last year. Could you discuss the trends you’re observing at this point? Is acquiring preferable to building? How does that stack up against aggregating power? Perhaps you could give an update on your strategy in that area?

François Poirier

executive
#55

Ben, this is Francois, and I’ll handle this question. As we’ve discussed previously, our long-term capital sanctioning is anchored in affordability, reliability, and sustainability. Renewables will serve as a complementary asset class within our portfolio, supporting our own decarbonization objectives while also helping customers lower the carbon intensity of their energy use. Wherever feasible, we’ll pursue a capital-light model. We discussed the aggregation activities last year, and those continue to move forward. In certain cases, where we identify value and it aligns with our capital plan — and I want to stress that it must align with the capital plan and the $6 billion per year limit — we’ll consider taking ownership stakes in projects. But as Stan noted, in the context of our U.S. gas business and across the entire portfolio, one area we’ll be examining is joint ventures and partnerships with financial firms and other strategics, to ensure we can push forward on our decarbonization goals and our market share ambitions in the U.S. LNG market, while remaining within our annual sanctioned capital constraints going forward.

Ben Pham

analyst
#56

All right. Moving on, perhaps, to flexibility regarding share repurchases. Could you say a bit more about that? How do you <<inaudible>>? What leverage level would you need to reach before considering it?

François Poirier

executive
#57

Yes. Look, that isn't something we can do over the next couple of years. For 2023 and 2024, deleveraging is our priority. Our aim is to reach 5x debt-to-EBITDA or lower as fast as possible without hurting shareholder value, and then stay at that level. What I was trying to get across in my comments is that once you've committed to a project, halting it is very hard. Simply because your stock price sits at a level you find attractive for share buybacks, by the time you break ground, you can't just inform your customer that the transportation service they've been planning on and waiting on for many years won't be delivered. So by building in flexibility, and that flexibility would come from the gap between 7 and 6 in our program on an annual basis, we will have the option every single year with that incremental capital to live within our means by either paying back debt or buying back shares. But to be clear, we don't view that as an option until we get at or below our 5x debt-to-EBITDA, and we're confident that we're going to remain below.

Operator

operator
#58

Our following question is from Andrew Kuske at Credit Suisse.

Andrew Kuske

analyst
#59

This is really a question for Francois, and it centers on the push to cap CapEx after 2024 at $7 billion and then bring that figure down to $6 billion. Does that, in effect, let you upgrade your capital allocation process toward projects with higher returns?

François Poirier

executive
#60

Absolutely, Andrew. It isn't solely a matter of unlevered after-tax IRRs. We do intend to shift the portfolio. A high-quality, diverse portfolio with low volatility is something we consider part of our value proposition. But without a doubt, as I've mentioned before, the opportunity we see for deploying capital far exceeds the financial and human capital we have available to execute. And that actually is going to let us high-grade projects. In fact, looking at what we sanctioned in 2022, the unlevered after-tax IRR sits in the 10% range, and that is above the weighted average IRR for what we sanctioned in 2021, which I believe was in that 8.5% to 9% range. So we are seeing returns trend upward on the projects sanctioned over the last couple of years. And clearly, by limiting our capital spend to living within our means, it will give us the chance to high grade toward our higher returns, but we are also going to consider maintaining proper diversity and migrating the portfolio to an appropriate supply mix.

Andrew Kuske

analyst
#61

Thanks for that. And perhaps this is pushing my luck, but looking at how high-grading returns have been trending, plus what you said earlier about bringing partners in — financial, strategic, or of another kind — does that open the door to some sort of asset management approach, where you'd earn a promote on a project? How do you frame that and think it through?

François Poirier

executive
#62

Andrew, first off, that's a really good question — the main thing is that we're going to concentrate on our people capacity. There's a certain scale of capital program that we're able to handle, and we'll make sure we always possess both the capacity and the capability to properly manage whatever capital program we currently have going. Under an asset management model, you'd be developing and building projects on behalf of others. And we're going to stay very mindful about keeping the capital program at a size that falls within our team's capacity.

Operator

operator
#63

Our following question is from Patrick Kenny at National Bank Financial.

Patrick Kenny

analyst
#64

Regarding Keystone, as you move ahead with rolling out the enhanced integrity program, could you share a bit more detail on the cadence — those extra in-line inspections and the excavation work that has to be finished across the system? I suppose also what the program's total cost might mean for your earlier maintenance CapEx guidance, and how the process would work for recovering those costs through your total structure or by other means?

Richard Prior

executive
#65

Yes, absolutely. Richard Prior here, and I'll handle that question. As we noted in the release, there is further remediation work ahead of us. We need to address our remedial work items related to Milepost 14, along with the FINSA corrective action order, which will involve more excavations, as you pointed out, plus in-line inspection runs. That work is already underway. To date, we have completed 300 miles of tool runs on the pipeline near the incident location, and we have not identified evidence of similar features. Beyond that, we will also be finishing an engineering assessment. This time around, we received the recast failure analysis just last week, as did FINSA. So additional effort will be required to keep studying that and to flesh out the specifics of this program. I cannot give you a time line for working through these remedial work plans and closing out the corrective action order. What I can say is that we are fully committed to moving this work forward as quickly as possible. I also do not have a cost estimate for this integrity scope.

Richard Prior

executive
#66

I’m able to share this now. That said, this effort would sit within the scope of operating maintenance and integrity for the system, and it would be recoverable by means of our variable tools.

Patrick Kenny

analyst
#67

All right, thanks. Now, turning to how things look for egress from Western Canada — could you give us an update there? And given where natural gas prices stand right now, what are you seeing on the customer side when it comes to demand for added market access — California, the Gulf Coast, the East Coast? And what might that imply for debottlenecking work over the near to medium term across GTN, mainline, A&R and the like?

Greg Grant

executive
#68

Absolutely, Patrick. This is Greg Grant with the Canadian Gas Business, and I'll kick things off before passing it back to the U.S. Gas business. To begin, it's been terrific to witness on both the operational front and with our capital programs. We keep getting assets in the ground, and in fact we're running a few weeks ahead of schedule in exiting our '21 program and with some of our NCE build this spring. So a year ago, you'd typically have placed roughly 1.3 Bcf of intra-basin and egress. In this quarter, we added more than 700 Mcf, with another 500 soon to follow. So that's been excellent for the team and for the performance there. That hasn't absorbed the demand, I'd say. We still have considerable demand arriving across all parts of -- all points of egress, I'd say, and intra-basin. You'd have noticed we're around a Bcf once more on the supply side. So that's year-over-year, across 2 years, we've exceeded Bcf added into the system. So even though we've brought on that capacity, we remain at high utilization levels. So you'll likely see, probably within the next couple of weeks, months, we did announce that some open seasons are on the way.

Greg Grant

executive
#69

The team is therefore exploring how the system can be optimized on an ongoing basis and how we might create additional capacity wherever possible. That covers both current and some new opportunities, and we'll discuss those during the next quarter.

Stanley Chapman

executive
#70

On the U.S. side, you can basically view us as the major capture point, and we aim to grab that volume. As you know, we currently have an expansion underway on the GTN system — our GTN Xpress — which is now pending at FERC. We're eagerly waiting on our certificates so we can build that capacity and place it into service either later in 2024 or early 2024. We're also able to draw volumes onto our Great Lakes system, again collaborating closely with Greg's team as they file open seasons on their side of the border to bring added capacity down into the U.S. Another point I'd note recently is that there appears to be some interest from the Louisiana LNG market in gaining more exposure to Canadian volumes too. So we're chasing opportunities to expand our ANR systems where it makes sense, to move more Canadian gas down to the LNG terminals.

Operator

operator
#71

Brian Reynolds from UBS has the next question.

Brian Reynolds

analyst
#72

To piggyback on the earlier questions about labor, perhaps. You said the job currently sits at 6,500. So I'm wondering what peak labor assumption you're using across the projects for Coastal GasLink this summer, so that mechanical completion targets can be hit as workers begin rolling off TMX this summer?

Bevin Wirzba

executive
#73

Right, thank you, Brian. We've essentially hit the peak and are now going to wind things down. So when we come back fresh in the spring, we won't be bringing back crews at that same level, though a substantial number of people will return. As I said, we're at some discrete scopes at this point. We're basically wrapping up any of the traditional main lining activities where we've got a significant number of crews. So I'd say that by the fall, we'll see a much more substantial ramp down of folks in the field. But how well we can keep successfully managing and mitigating all our risks through the summer and fall construction will be the key determinant of whether we can meet our cost and schedule goals. So our focus is more on managing those risks. And that includes the labor front, but we believe we're in a good position there.

Gavin Wylie

executive
#74

All right, I believe there's room for only a single final question, if that's okay with you.

Brian Reynolds

analyst
#75

Yes. Great. And just briefly on the credit rating — S&P has moved TransCanada to a negative outlook. So the first part of my question is whether TransCanada is committed to defending that credit rating at any cost, maybe in the context of M&A sales. And second, how does TransCanada approach asset sales versus potentially affecting its earnings mix?

Joel Hunter

executive
#76

Thanks, Brian. Joel here. This will be the final question for today, and at last I have a chance to answer. On the subject of credit ratings, those ratings matter a great deal to us. As you pointed out, at present we carry a negative outlook with 3 agencies — S&P, Moody's and DBRS. Fitch downgraded us after the announcement concerning the CGL cost overruns. We place considerable importance on that rating. We think that, through our plan to sell more than $5 billion of assets, we can bring leverage down to the target Francois referenced — reaching 5x in the near term and, eventually, getting to 4.75x. That is what we are aiming for. So, with the plan in place today — over $5 billion of asset sales plus our growing EBITDA — and you just saw us note today a 60% year-over-year increase in EBITDA — combining those two, we believe we can reach 5x and, in the end, have the negative outlook lifted by the agencies and our ratings reaffirmed going forward. As for your question about asset sales, and I believe you said with <<inaudible>> if I heard you correctly, we balance both.

Joel Hunter

executive
#77

So as we mentioned, there are over $5 billion in asset sales here. And in our plan, we've always factored in that roughly 15% of our capital structure consists of hybrid securities and preferred shares, and going forward that isn't going to change.

Operator

operator
#78

That brings the Q&A portion to a close, everyone. Should anything else come up, you can reach out to Investor Relations at TC Energy. At this point I'll hand things over to Gavin Wylie. The floor is yours, Mr. Wylie.

Gavin Wylie

executive
#79

Yes. I appreciate everyone joining us this morning. For any questions we weren’t able to get to, please contact Investor Relations, and the team will be glad to talk with you later this morning. Many thanks for your interest in TC Energy, and we look forward to our next update. Have a great day.

Operator

operator
#80

That brings us to the end of today's conference call. You can now disconnect your lines. Thanks for joining us, and enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete TC Energy Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to TC Energy Corporation earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in TC Energy Corporation or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.