TC Energy Corporation (TRP) Earnings Call Transcript & Summary
February 14, 2025
Earnings Call Speaker Segments
Operator
operatorAppreciation for holding. I'm the conference operator, and I'd like to welcome everyone to the TC Energy Fourth Quarter 2024 Results Conference Call. Please note that today all participants are in listen-only mode and this conference is being recorded. Following the presentation, we'll open things up for questions. If you'd like to join the question queue, simply press star then one on your telephone keypad. And if you require assistance at any point during the call, you can signal an operator by pressing star then zero. At this time, I'll hand the conference over to Gavin Wylie, Vice President, Investor Relations. Please go ahead.
Gavin Wylie
executiveThank you so much, and good morning everyone. It's my pleasure to welcome all of you to the 2024 Fourth Quarter Conference Call for TC Energy. With me today are François Poirier, our President and Chief Executive Officer, and Sean O'Donnell, Executive Vice President and Chief Financial Officer, as well as other members of our senior leadership team. François and Sean will kick things off today with some comments regarding our financial results and operational highlights. You can find a copy of the slide presentation that will accompany their remarks on our website in the Investor section. After they speak, we'll be taking questions from the investment community. We ask that you limit yourself to two questions, and if you're a member of the media, please reach out to our media team. I'll remind you today that remarks will include forward-looking statements that are subject to important risks and uncertainties. For more information, please see the reports filed by TC Energy with the Canadian Securities Regulator and with the U.S. Securities Exchange Commission. Finally, during the presentation, we will refer to non-GAAP measures that provide additional information on TC Energy's operational and financial performance. However, these measures may not be comparable to similar measures presented by other entities. A reconciliation of various GAAP and non-GAAP measures is contained in the appendix of this presentation.
Gavin Wylie
executiveHaving said that, I'll now hand things over to François.
François Poirier
executiveThanks, Gavin, and good morning, everyone. For TC Energy, 2024 has been a year marked by major achievements and milestones, and we continue to deliver on our strategic priorities. First, we're proud to report the strongest safety performance our company has seen in the past five years. As I've said before, we firmly believe that outstanding safety practices lead to superior operational performance, which, of course, drives strong financial results. So in 2024, we increased comparable EBITDA from continuing operations by 6% compared to 2023. We successfully completed the spinoff of our liquids business and the declaration of commercial in-service for Coastal GasLink. We successfully placed $7 billion of assets into service while reducing our net capital expenditures by 10% and have identified an additional $1.3 billion of capital reductions to be realized in 2026 and 2027. With strong EBITDA performance, lower capital expenditures, and completed asset sales, we have significantly strengthened our balance sheet, which Sean will address further. Finally, we're making substantial progress on our major projects, including Bruce Power's Unit 3 MCR and, of course, Southeast Gateway that remain on cost and schedule. Our public-private partnership with CFE on Southeast Gateway has been a huge success, delivering the project 13% below our original budget by leveraging the strengths of both the CFE and TC Energy.
François Poirier
executiveWe wrapped up the last golden welds on January 20th and hit mechanical completion — a huge milestone for Mexico and for TC. Back in mid-January, we sat down with the Secretary of Energy and the CFE, and everyone stayed on the same page about wrapping up the outstanding work needed so Southeast Gateway can reach commercial end service on May 1. Zooming out, President Sheinbaum just introduced her Plan Mexico 2030. That plan sets a goal of lifting Mexico's economy from 12th largest overall into 10th place within six years, and it seeks to draw more than $270 billion in investment, partly via public-private partnerships like the one we have. We see a strong fit between what the government and CFE are prioritizing and the natural gas deliveries that TC Energy makes possible. Our partnership with the CFE will keep playing a key part in hitting the targets laid out in Plan Mexico. I'd like to thank our committed teams for their unflagging work on this project, and to repeat that this represents a significant inflection point for TC Energy. With broad electrification as the foundation, natural gas and electricity are expected to account for 75% of the growth in final energy consumption from now through 2035. That growth takes in a threefold rise in LNG exports, robust growth in power generation fueled by coal retirements and data center demand, LDC reliability requirements, and a substantial boost in Ontario's need for added nuclear generation capacity — all of which lines up with our North American footprint.
François Poirier
executiveLooking at this opportunity, we announced five new growth projects not long ago, with build multiples ranging from five to seven times. On our Columbia Gulf system, the Pulaski and Maysville projects together represent an investment of more than $700 million, and they will help enable coal-to-gas conversions at two power plants that already exist. The Southeast Virginia Energy Storage Project, at $300 million, is an LNG peaking facility that will serve an LDC's rising winter peak day load. At Bruce Power, we're moving ahead with Stage 3A of Project 2030, which provides 90 megawatts of incremental capacity. Once finished, Project 2030 will add roughly 700 megawatts of incremental capacity. We expect total Bruce output to exceed 7,000 megawatts after MCR and Project 2030. Also, on January 31, we submitted the final basis of estimate to the Ontario ISO for Bruce Power's newest nuclear project, the Unit 5 Major Component Replacement. That refurbishment should extend Unit 5's operational life by more than 35 years. Let's look more closely at Bruce Power and our power and energy solutions business in Ontario. The Ontario ISO forecasts a shortfall of approximately 69,000 megawatts in total installed capacity by 2050, driven by industrial expansion, data center developments, and population growth. Nuclear power and storage will be essential pieces in meeting Ontario's demand.
François Poirier
executiveWe're deeply engaged in a number of important initiatives — Bruce Power's MCR program, of course, plus possible future expansion at Bruce C and the Ontario Pumped Storage Project. Back in January, we said TC Energy and the Saugeen Ojibway Nation would kick off pre-development work on the Ontario Pumped Storage Project, backed by up to CAD 285 million from the Ontario government so a detailed cost estimate and environmental assessments can be developed to better gauge feasibility. Moving to the next slide, this chart shows how visible our growth is through the end of the decade, and we'll keep building that backlog. The room we have to sanction additional projects through the end of the decade appears as the white space separating our net CapEx limit of CAD 6 billion-CAD 7 billion from the colored bars. All together, that comes to roughly CAD 8 billion across 2026 and 2030. With the pipeline of development projects we're chasing, we expect to fill most of that leftover project capacity by the end of 2026 using lower-risk projects capable of delivering appealing build multiples of five to seven times. Turning to 2026 in particular, our goal is to fill that spare capacity by combining small projects with a short cycle to cash flow, and we're looking at pulling capital expenditures forward from 2027 and 2028 so we can free up additional capacity for new growth projects in those years.
François Poirier
executiveWe will keep evaluating the projects sitting in our pending approval bucket—those are the ones shown by the gray bars—so that we retain the flexibility to direct capital toward projects with better returns. Our aim is to generate meaningful value by widening the gap between the returns we earn and our cost of capital. Now, a few comments on tariffs. We are still monitoring the trade talks that are underway among the U.S., Canada, and Mexico. Energy flows among the three countries are substantial, which makes our energy markets deeply interconnected. In our view, the 30-day pause on possible tariffs will help foster more engagement with North America's leaders so that an agreement can be reached benefiting consumers throughout the continent. Since 97% of our comparable EBITDA sits under regulated cost-of-service frameworks or take-or-pay contracts, we expect no material effect on our financial performance. Our regulated Canadian natural gas pipelines business, which carries gas that our shippers export to the U.S., is shielded from higher costs or volume losses, and our Mexico natural gas pipelines business mainly takes receipt of gas from the southern U.S. for delivery in Mexico, with contracts denominated in U.S. dollars and grounded in long-term take-or-pay agreements. Within our power and energy solutions business, Bruce Power is the largest contributor, and more than 90% of its supply chain is located in Canada.
François Poirier
executiveOf course, we realize that if tariffs drag on, that may affect how we decide where capital goes. That said, since our portfolio is spread across three jurisdictions, we can keep directing capital toward markets where energy demand holds up. We will keep collaborating with customers in all 3 jurisdictions to make sure service stays safe, dependable, and competitively priced. With that, I'll hand things over to Sean.
Sean O'Donnell
executiveThank you, Francois. Morning, everyone. I want to begin today by acknowledging something important: the exceptional safety and operational results our team delivers are essential to the strong financial performance TC keeps posting. The table on the left shows a number of operational and financial highlights for the quarter. The standout item is that our natural gas assets in every country established new delivery records between last November and February of this year. At Bruce Power, performance was outstanding, with 99% availability, and that helped push a 28% rise in quarterly EBITDA growth for our power and energy solutions business unit. As you may remember, Unit 6 finished its MCR in 2023 and ran at over 99% availability across calendar year 2024. We hope to see that same availability trend as each unit wraps up its MCR program over the remainder of the decade. All in all, it's a remarkable accomplishment for TC that every one of our business units delivered exceptional safety performance while at the same time setting new operational and annual EBITDA records from continuing operations. Turning to the EBITDA bridge on the right, let me take a moment on a few of the more notable items. Canada Gas showed the largest variance, driven by the $200 million incentive payment to Coastal GasLink at mechanical completion in the fourth quarter of 2023, which did not recur in 2024.
Sean O'Donnell
executiveMexico saw improvements largely tied to the peso's decline, since our revenues there come in U.S. dollars, and lastly, the power and energy solutions group turned in quite strong numbers, driven mainly by a 14% year-over-year availability gain at Bruce Power. Moving to page 13, we lay out the pieces behind comparable earnings of $1.1 billion, down 8% versus the fourth quarter of 2023. Interest expense rose this quarter, chiefly because of reduced capitalized interest as assets entered service, more short-term borrowing, one-time charges tied to the spin, and the timing of our liability management program. The rise in AFUDC stemmed from our Southeast Gateway project, slated to enter service this May, partly offset by larger NCI deductions. On currency, the EBITDA improvements in Mexico are partly offset by losses in our corporate risk management program, through which we hedge Mexican net income against peso swings. So, wrapping up the 2024 financial summary, TC posted solid fourth-quarter results that came in modestly above our overall plan and helped deliver yet another record year of comparable EBITDA from continuing operations, up 6% for the year.
Sean O'Donnell
executiveThis chart shows how the record EBITDA we posted from continuing operations — more than $10 billion in 2024 — stacks up against the EBITDA outlook we gave at Investor Day in November. Under our base case, we expect to deliver 2025 comparable EBITDA of $10.7-$10.9 billion, a 7%-9% increase year over year. Looking ahead to 2027, we're projecting a target of $11.7-$11.9 billion, which implies a 5%-7% growth rate across the three years. One thing worth flagging is that our base case outlook assumes an average U.S. to Canadian dollar exchange rate of 1.35, below the rates we're seeing today. To help investors grasp the potential upside to EBITDA from exchange rates, the rule of thumb we give on the bottom right is that each penny increase in USD/CAD translates into roughly $45 million of incremental EBITDA. As an example, if we chose an exchange rate of 1.43, that's 8 cents above plan and would leave 2025 EBITDA approximately $350 million higher than our base case outlook. It's important to reiterate that we systematically hedge our US dollar net income to insulate our comparable earnings from FX volatility. Given our hedge strategy, we do not expect a material impact related to FX on our 2025 comparable earnings.
Sean O'Donnell
executiveOver the longer term, and assuming no hedging, each one-cent move in the USD/CAD exchange rate translates into approximately a one-cent swing in comparable EPS. Now, looking at the right-hand side of the page, we've summarized a number of other items that could affect our EBITDA outlook. When it comes to base case planning, we generally incorporate cautious assumptions regarding rate case settlements as well as other revenue enhancement and cost optimization initiatives, which have the potential to generate further upside. In addition, we're aiming for availability across our operational portfolio that beats historical levels, especially at Bruce, where Unit 3 is set to come back into service next year. And lastly, one of our key strategic priorities continues to be bringing our growth capital projects into service ahead of budget and schedule wherever we can. If you turn to page 15, we've achieved considerable progress on our deleveraging efforts. Since 2022, we have delivered a reduction of 0.6 times in debt to EBITDA through asset divestitures, cost optimizations, revenue enhancements, and reductions in actual capital expenditures. Company-wide efforts are underway in every one of these areas to advance our organic deleveraging program. One point worth noting regarding the year-end 2024 leverage metric: the fourth quarter was unusual in terms of how rapidly FX rates shifted. We closed out the year on December 31 with a spot rate of 1.44 USD CAD, which was applied to our balance sheet calculations, compared with an average rate of 1.37 in 2024, which we used for income statement purposes.
Sean O'Donnell
executiveThat CAD 0.07 FX timing differential gave us a year-end debt to EBITDA ratio of 4.8 times, which was largely in line with the 4.75 times target we set. If we had instead used the same average FX rate of 1.37 for converting both our debt and EBITDA, the resulting debt to EBITDA ratio would have come out at approximately 4.65 times. Setting aside the FX calculations, we made significant progress toward strengthening the balance sheet, and I want to reiterate François' comment that we all remain steadfast in our deleveraging efforts and in maintaining our long-term upper limit of 4.75 times debt to EBITDA. To conclude, TC had an exceptional year in 2024, and I am pleased to share that our board of directors has declared a first quarter 2025 dividend of CAD 0.85 per common share, which is equivalent to CAD 3.40 per share on an annualized basis. That works out to a 3.3% increase compared to TC Energy's fourth quarter dividend, which now reflects TC's proportionate dividend following the spinoff of South Bow. This marks our 25th consecutive year of dividend growth to our shareholders, a commitment we're proud to meet year after year as part of our shareholder value proposition, which is underpinned by our solid growth, low risk, and repeatable performance.
Sean O'Donnell
executiveHaving said that, I'll now hand things back over to François.
François Poirier
executiveThanks, Sean. As I mentioned earlier, our attention will stay fixed on the things that brought us to this point: getting the most value from our assets by prioritizing safety and operational excellence, delivering on our carefully chosen set of growth projects — which includes placing $8.5 billion of assets into service during 2025 — and third, making sure we have financial strength and flexibility. Keeping our focus on these clear priorities will let us produce that solid growth, low risk, and repeatable performance year after year. I'd like to take a moment to recognize Stan Chapman's retirement following an exceptional career at TC Energy. Although we'll keep benefiting from Stan's experience as a member of Bruce Power's board, I want to express my gratitude for his leadership, dedication, and contribution over the years. Thank you, Stan. I'm also pleased to announce two recent appointments to our executive leadership team with Tina Faraca and Greg Grant. These changes form part of our deliberate and planful long-term succession plan, reflecting the strength and talent of our internal leadership. We've appointed Tina to Executive Vice President and Chief Operating Officer of our natural gas pipelines business. Tina has been a member of our executive leadership team since 2023. Bringing her onto the executive leadership team at that time was a very intentional move to support the eventual transition of the chief operating officer role.
François Poirier
executiveTina brings deep experience in project development, engineering, and operations, along with know-how in commercial operations and corporate strategy. She has spent more than 30 years in this industry and has built a solid record in both leadership and performance. We're also delighted to share that Greg Grant will serve as Executive Vice President, Power and Energy Solutions. For the past three years, Greg has led our Canadian natural gas pipelines portfolio successfully, and he carries wide-ranging experience in strategy, power, corporate development, and commercial operations into this new position. I have every confidence that Tina and Greg will keep producing outstanding results. With that, Operator, we're happy to take questions.
Operator
operatorWe’re moving into the Q&A portion now. If you’d like to ask a question, press star and one on your phone’s keypad. A tone will confirm your request. Please keep it to two questions, and if you have more, just re-enter the queue. On a speakerphone? Pick up your handset first, then press any keys. To pull your question, press star then two. Our first question is from Praneeth Satish at Wells Fargo. Go ahead.
Praneeth Satish
analystThank you, and good morning. To begin, I want to congratulate Stan. You will certainly be missed, though I'm confident you're happy to be free of those pesky sell-side analyst questions. Let me begin with Southeast Gateway. I have two things to ask. The first concerns the in-service date of May 1st. Is that somewhat ahead of what had been indicated previously? My understanding was that startup had been expected on June 1st. Second, could you help us grasp the way your commercial contracts are set up to safeguard returns in the event of a delay affecting any of the interconnecting pipelines, such as the Mayakan pipeline? Also, are you able to provide any further information about your discussions with CFE regarding aligning the different parts of the network, and whether all parties agree on that?
Stan Chapman
executiveYes. Morning, Praneeth. Stan here — thanks for those remarks, and it's always a pleasure to speak with you and your colleagues on this call. Regarding May 1, I'd simply note that it aligns very closely with the guidance we provided on the earnings tied to SGP. On your wider point about where the plants stand and when CFE will pay, here's what I can tell you. As we understand it, the Mérida and Valladolid facilities — the two most relevant to SGP — have both now reached mechanical completion and will enter service once gas supply is available. CFE is examining a rebalancing of its overall supply portfolio so that gas reaches the Mérida plant by Q4 2025, at which point the first phase of the Mayakan expansion wraps up. That initial phase is an expansion involving compression only. For the other facility, Valladolid, gas is expected to begin flowing around Q3 2027, when phase two of the Mayakan pipeline expansion is finished — and it is that second phase which will incorporate the physical connection to SGP. In the interim, CFE keeps engaging with us as well as other third parties regarding the possibility of constructing short laterals off SGP that might, among other benefits, move gas into the CENAGAS system — for instance, to supply the plants somewhat sooner.
Stan Chapman
executiveI realize there are a lot of questions about our May 1 in-service date and whether CFE will pay us, so let me offer a few points for you to consider. To start, our contracts with CFE run 30 years, and the infrastructure we're constructing will last more than twice that long. Our partnership with CFE is strong and mutually beneficial, and they recognize that a May 1 in-service date gives them the lowest overall cost; backing that up, as we understand it, CFE has secured budgetary approvals adequate to fund SGP starting May 1. Second, under the contract, declaring SGP in service is not contingent on downstream third-party capacity being available, and our project aligns with President Sheinbaum's plan for Mexico to draw investment, construct new infrastructure, and cut emissions. Third, because storage capacity is limited throughout Mexico, and so that we can offer some level of utility at in-service, we've been talking with CFE about possibly using the finished SGP pipeline for park and loan or storage service until the downstream laterals and interconnects are ready. Fourth, pending additional COFECE approvals, the process for CFE's extra 2% equity stake to begin is likewise triggered at in-service, so from that standpoint CFE has an incentive.
Stan Chapman
executiveThe key takeaway I'd like to emphasize, though, is what François mentioned before. In January, François, our team, and I traveled to Mexico. We had meetings with the Energy Secretary. We also sat down with CFE's leadership, and everyone is in agreement on a May 1 in-service date for this project.
Praneeth Satish
analystThanks — that covers a lot. I'd like to change direction and ask, more conceptually, how you view some of these behind-the-meter gas projects that a few of your competitors are going after. Would you consider an integrated gas-to-power development in which you supply the pipeline infrastructure and possibly also construct the generation assets? I'm aware that you hold attractive positions in the order book for simple cycle gas turbines, which gives a speed-to-market advantage should you choose to pursue such projects, but I'm just interested in your perspective on it.
François Poirier
executivePraneeth, this is François. I'll begin with that particular strategy, and then I'll turn it over to Tina so she can give you the broader picture of just how bullish we are about growth in data center demand, drawing on the dozens of conversations we're having. When it comes to what I'd describe as a fully bundled or complementary solution — one where we're constructing a lateral alongside a power plant for generation — that's expertise the company has built up for more than 30 years. Today we own and operate gas-fired power plants in Alberta and in New Brunswick. In fact, we're a sizable buyer of gas turbines, though I'd note those are mainly for compression purposes. They're generally smaller units. We hold no preferential position in the queue for the larger turbines that power generation would require, but we are absolutely talking with a number of parties about direct connections where we'd offer the two combined. Growing an independent IPP company inside TC is not really something we're interested in anymore, and we would only really consider new power generation as part of a complementary, fully bundled kind of product offering.
François Poirier
executiveThat said, our outlook on data center demand remains very bullish, and I'll turn it over to Tina to go into more detail on that.
Tina Faraca
executiveThanks, François. And Praneeth, I'll try to give you a full picture of how we think about data centers. Data centers represent one piece of the power demand opportunities we're pursuing, alongside coal-to-gas conversions and other electrification growth. But speaking specifically about the data center sector, our extensive footprint puts us within 15 miles of 60% of the more than 350 data centers currently under development. On top of that, we connect to eight of the top 10 utilities and more than 100 power plants, which gives us another competitive edge when serving data center demand. Right now we have roughly 10 gigawatts of requests with our business development team. We've ramped up commercial engagement with more than 20 parties throughout the data center value chain, representing about $2 billion of potential opportunities in that sector across several of our systems: Wisconsin, Ohio, Virginia, Kansas, Indiana, Louisiana, Nevada. Interestingly, what customers need differs, and it varies from developer to developer. Our focused strategy is to partner with our established, high-quality utilities on the larger data center loads and supply the gas infrastructure required to support their portfolio build-out. In addition, we'll pursue direct-connect behind-the-meter solutions where it makes sense and aligns with our risk preferences.
Tina Faraca
executiveI'll walk you through several important proof points and pieces of data. Last year we announced and sanctioned our ANR Heartland Project — roughly a $900 million investment with a five- to seven-times multiple — and it will now serve data center demand in Wisconsin as well as broader economic development needs there. We plan to file that project with FERC in the weeks ahead, with a targeted in-service date of November 2027. We had been on track to sanction another project driven by data centers, anchored by some of our utility customers, during the first half of 2024. As it happens, we are currently talking with those counterparties about possibly enlarging that project, which could push our schedule out by a couple of months but would represent a more substantial expansion tied to meeting data center demand. In Loudoun County, Virginia, we created a behind-the-meter solution for a data center that went into service last year, and we are actively negotiating several comparable direct connect opportunities. We also just wrapped up an open season on Columbia Gas that ended with 60,000 dekatherms a day contracted to a customer for supplying gas to behind-the-meter data center load in the New Albany area of Ohio. Beyond that, we are moving forward on new power plant interconnect projects amounting to approximately 4.7 gigawatts of generation, which will serve rising electricity demand, data centers included.
Tina Faraca
executiveSo as we move these projects forward, the way we proceed is going to line up with our strategy: low risk, performance we can repeat, take-or-pay commitments over the long term, and build multiples that are attractive, in that five-to-seven-times range.
Praneeth Satish
analystThat's great. Thanks. I appreciate it.
Operator
operatorOur next question is from Barclays, with Theresa Chen on the line. You have the floor.
Theresa Chen
analystGood morning. First off, I'd like to add my congratulations to Stan on his retirement. We wish you the best, and congratulations too to Tina and Greg on your new roles. Maybe turning to the nuclear part of your portfolio, regarding Bruce C, while it's early, what are the next steps toward FID? Do you have a timeline in mind, and could it be eligible for accelerated cost recovery like MCR?
François Poirier
executiveThanks, Teresa and François. With Ontario's fundamentals—including a projected 69-gigawatt capacity shortfall by 2050—we're quite bullish about the part nuclear will play. As Ontario pursues reshoring of manufacturing, nuclear is how the province will meet data center demand along with other industrial demand. Under the MCR program, we carry the cost and schedule risk on those projects. The successful return to service of unit six, along with unit three coming in on time and on budget, has shown that we manage that risk very effectively. On Bruce C, it's still early days. Plenty of development and assessment work lies ahead to evaluate that project's potential, including which technologies we'd use, supply chain impact, labor, and so on. What I'd say there is that you're unlikely to see us take on a significant share of cost and schedule risk on new build. That simply doesn't fit our low-risk value proposition, and for Bruce C we would look to adopt a more traditional cost-of-service rate-making model. Maybe one way to think about this from a timing standpoint is that nuclear sites hold a huge competitive advantage when it comes to nuclear growth.
François Poirier
executiveTo start, an operating license is in place. Next, there's a community nearby that feels at ease with nuclear operations in the vicinity. Third, for Bruce Power specifically, we possess the land footprint needed to add Bruce C and Bruce D at that site moving forward. And fourth, I'd say we have a management team that ranks among the most capable in the nuclear industry — arguably the most capable. Both existing units currently run at extremely high efficiency levels, holding INPO 1 ratings. That made Bruce a highly strategic move. They put money into training, building trades, and labor for the refurbishment effort. A logical timeline would see us transition from the MCR projects — finishing in 2031 or 2032 — into new build around then. So plenty of planning remains to be done, but as you noted, we're quite enthusiastic about nuclear's long-term potential. Over the long haul, it will serve as a meaningful growth wedge for this company.
Theresa Chen
analystThanks. Turning to your leverage and overall balance sheet picture, where do things stand with S&P now, after it reaffirmed your BBB plus negative outlook rating late last month? What do you believe would be needed to get that outlook improved?
Sean O'Donnell
executiveHi Teresa, this is Sean — good morning. Look, absent a direct conversation with S&P, we prefer not to speculate about what any single rating agency might do. I'll say this much. We stay in touch with all the agencies on a regular basis. They've had a preview of the investor day materials, and every one of them has completed its annual review. And as you pointed out, S&P wrapped theirs up recently, within the past two or three weeks. And look, in our dialogue with each agency, a major point of emphasis is SGP arriving on time and on budget, and you heard from Stan today. That's likely the topic we discuss most often with each of the agencies. And then when it comes to the rest of the year, it's more or less about delivering on the plan and that CAD 6-CAD 7 billion capital range, right — executing on time and on budget within that CAD 6-CAD 7 billion range. I really believe that's the formula for our organic deleveraging and for continued success with each of the agencies.
Theresa Chen
analystI really appreciate it.
François Poirier
executiveHappy to have you with us.
Operator
operatorOur following question is from Maurice Choy at RBC. You may proceed.
Maurice Choy
analystThanks, and good morning to all of you. I'd like to shift our focus toward Canada, and what I'm asking about specifically is mainline. Just how much mothballed capacity exists across the system, and what would be required to restore it, covering both expense and schedule? Alongside that, quite a few Canadian energy projects are clearly under discussion at the moment, with potential tariffs on the horizon. A number of those costs are rather enormous. Where the company has a role to play, how firmly are you holding to that CAD 6 to 7 billion goal?
Stan Chapman
executiveHey, Maurice. I can handle the first part of that. This is Stan, and François can address the second piece. Regarding spare capacity on the mainline, I'd simply note that with the strong demand we've observed for natural gas, the amount of spare capacity we have today is quite different from what it was 10 years ago, back in 2015. For instance, the restoration work we performed on the western mainline was finished in 2023 and 2024, and since then our contracts have grown from roughly three BCF a day to five BCF a day, which means all the available mainline capacity is now fully contracted. There is one line, which we call line two, that is currently unavailable for service. As market demand for this capacity keeps maturing, we will reassess things such as the timing, the cost, and the potential capacity that could be optimized and perhaps restored, subject to any upstream and downstream constraints. Just bear with us and allow us time to complete that work as the market needs materialize.
François Poirier
executiveAnd Maurice, regarding what I’d describe as an energy corridor running coast to coast to coast, we’re seeing a lot of inquiries on the liquid side. Those I’d point toward our friends and former colleagues at South Bow. When it comes to natural gas, there is definitely demand for additional LNG exports, and there’s market opportunity for us to pursue. We’re quite bullish on the prospects for CGL phase two going ahead. That, of course, is just one input into the FID decision our customer, LNG Canada, will make in due course. And when we look at other infrastructure in Canada, it will have to compete for capital within our company, as it has over the last few years, with projects in other jurisdictions. At present, we see the highest risk-adjusted returns in the United States. The vast majority of our discretionary capital is going there, and we expect it will keep going into the United States. That said, there’s an interesting data center opportunity in Alberta. We’ve been working closely with a number of stakeholders to understand where there may be spare capacity in our system in Alberta, and we see some very exciting opportunities there. There are 10,000 gigawatts—pardon me, 10 gigawatts of interconnection requests within Alberta.
François Poirier
executiveThe market for data center development is really quite natural right now, and we believe we're going to be positioned very well for it. That wouldn't necessarily happen inside our NGTL entity. It could sit in separate unregulated entities, where the risk-return profile differs from what NGTL offers.
Maurice Choy
analystGot it. And perhaps to wrap up on capital allocation, as you referenced here, you noted in the press release that extended tariffs might affect how capital is allocated. I'm wondering whether you could expand on that a bit further, acknowledging, as you put it, that the U.S. already ranks as your biggest geography for near-term CapEx, with only limited investment in Canada up to now. So I'm just curious what other adjustments to capital allocation you could make?
François Poirier
executiveAll right, I'll kick things off and turn it over to Tina to say a few words about where our supply chains stand at the moment and how we're positioned regarding the effects on capital costs. Put simply, Maurice, that simply mirrored the reality that any shifts in the prices of key raw materials and inputs will get reflected in whatever capital allocation choices we make going forward, with the overwhelming bulk of future discretionary capital headed into the U.S. for projects that would move molecules from U.S. production to U.S. demand centers. Tariffs would have no effect there. We believe there's ample domestic capacity for steel production and pipe fabrication within the United States to serve our projects, though naturally we'd benefit from seeing how things play out and would factor that into our projects. Tina, perhaps you could elaborate on where our supply chain situation currently stands.
Tina Faraca
executiveOkay, thank you, François. For our projects in Canada and the U.S., we anticipate only quite limited effects when it comes to materials — mainly fittings and flanges. Projects in Mexico see no impact at all. Across the whole portfolio, we routinely take steps to tackle and reduce any risk of cost escalation. Turning to the U.S., pipe for every one of our sanctioned projects has already been purchased, and it came from mills in the U.S. Those pipe orders carry firm pricing, so any volatility in the market is a risk the vendors bear. On top of that, we use a highly diversified supplier base for all materials, and we mostly buy large-scale materials ahead of time, concentrating on a select group of proven suppliers in return for commercial benefits that work for both sides.
François Poirier
executiveTo circle back on that point, Maurice, here's what I'd say: when we look toward the end of the decade, as I noted in my prepared remarks, we anticipate using up the rest of our incremental capital capacity by the close of next year, and for the projects we plan to sanction between now and then, we continue to see build multiples in the five to seven times EBITDA range.
Maurice Choy
analystThat's clear. And I appreciate the question. Thanks for the answers. And of course, congratulations to Stan on your upcoming retirement, and to Evan and Greg on your new roles. Thank you.
Operator
operatorJeremy Tonet from J.P. Morgan has the next question. You're up.
Jeremy Tonet
analystHello, and good morning to everyone.
François Poirier
executiveGood morning, everyone.
Jeremy Tonet
analystI simply want to second that, Stan. Congratulations on a wonderful career. You will definitely be missed, and I also want to wish everyone a happy Valentine's Day. Perhaps just the first question here, if you could quantify, I suppose, maybe the upside to the plan, at least from our perspective. It appears that business operations are going well regarding nuclear operating rates and possibly what you get in some of these rate settlements here. It just seems as though there is some upward pressure on the guide, but I was wondering whether you could sort of offer more thoughts there.
Sean O'Donnell
executiveMorning, Jeremy. Sean here. So, in the part I covered, we listed a few items we track that could shift the outlook in either direction. On your specific point, though, Bruce keeps delivering extremely strongly — in the fourth quarter at least, at levels above what we build into the plan for conservatism. We tend to think of it as the low 90s. You've raised FX rates with me before, and we offered some added clarity on that. Just for context, we run a rolling hedge program spanning three years with high, medium, and low bands, and we're monitoring that curve closely to consider what we might adjust over the medium to longer term to capture some of the impact. Some of the proven formula for upside that you witnessed in 2024 carries on — rate case strategy, EBITDA, and cost reduction overall. That plan has many facets, and we're a full year into making it work. Thanks for the question.
Jeremy Tonet
analystUnderstood — that's useful, thank you. And glancing through the deck a bit, at slides seven and nine, it feels as though plenty is in the works at the moment. So when you consider what's possible for new projects, with leverage really dropping off at Southeast Gateway, how do you view the pace at which these projects might come together across roughly the 2026 to 2030 window? I'm just trying to get a sense of what's achievable.
François Poirier
executiveAs Jeremy mentioned in our prepared remarks, near term, we're addressing that white space in 2026. We're pursuing multiple proposals to put fairly modest amounts of capital to work in short-cycle projects that generate cash flow. We're also examining ways to pull forward certain capital spending from 2027 and 2028, which would help create extra capacity in those years too. To sanction roughly $8 billion in aggregate of remaining capital through year-end — by the close of 2026 — you'll see a steady cadence over the coming quarters. We filed the Basis of Estimate on Unit 5 on January 31st, and it landed inside the range contemplated in the contract. The IESO, naturally, holds assurance and verification rights regarding the validity of those estimates. Yet since the estimate fell within the contract's contemplated range, we're highly confident that we'll reach an FID on another unit at Bruce Power in the very near future. So opportunities are showing up not just in our gas business — coal-to-gas conversion and data centers — but also on the nuclear side, given the shortfall and the signals we're receiving from the Ontario government about a supply shortfall.
François Poirier
executiveThat is partly why they were willing to give us CAD 285 million in additional capital so we can move the Ontario Pumped Storage development forward. So we feel quite bullish about where our footprint stands and about the growth prospects tied to the fundamentals in each of those markets. And so, again, what we're aiming for is a big count of smaller projects, low risk, within our corridors. And so you'll see a steady cadence over the coming seven or eight quarters. And that is how we'll fill the rest of our backlog. And I'd say our emphasis, which is on lengthening the duration of our capital program, is somewhat distinctive relative to our peers. We believe it matters a great deal in the near term to manage and preserve capital discipline and remain at or below that $6-$7 billion range. We aren't missing out on any opportunities at present, yet we can also sanction projects in service all the way through the end of the decade.
Jeremy Tonet
analystUnderstood — that answers my question. I won't push any further on this. Thank you.
François Poirier
executiveAppreciate that, Jeremy.
Operator
operatorOur following question is from Manav Gupta at UBS. You have the floor.
Manav Gupta
analystMorning. Two things I want to ask, and I'll get right to them. First, at your anniversary you announced 4 new projects, and today we received further updates. Could you give us additional detail on how those 4 projects you announced are coming along? Second, you went into depth on the data center opportunities. Could you also say a bit about the coal-to-gas switching opportunities you're seeing out there?
Tina Faraca
executiveI'll address the first question regarding the projects we've announced and then fold in your second one as well. In the U.S., we've announced three projects. Two of them are coal-to-gas conversion efforts situated off our Columbia Gulf system, plus a Virginia project meant to serve our local distribution company's reliability requirements through LNG peaking supply. Those are coming along well. We're at early stages in developing our FERC applications. Landowner notifications are moving along nicely too, and they'll be delivered on the timelines laid out in our disclosure. So those are going really well. On the coal-to-gas side, we keep seeing a lot of opportunities throughout our footprint. Within 15 miles of our assets, we have 42 coal plants in operation. By 2031, nine of those plants are slated to retire. Their combined capacity comes to roughly 9 gigawatts, and about 19 gigawatts sit within 50 miles of our pipelines and are expected to retire through 2033. We're seeing many of those materialize. In the Midwest, for instance, we have a couple of projects — our Wisconsin Reliability and our Heartland Project — that are backing coal-to-gas conversions. We're also in active talks concerning roughly 7.5 gigawatts of generation from further conversion opportunities, and we'll keep chasing all of those that fit within our $6-$7 billion capital plan and hit the 5 to 7-time build multiple.
Manav Gupta
analystMuch appreciated.
Operator
operatorJohn Mackay from Goldman Sachs has the next question. Go ahead, please.
John Mackay
analystMorning, and thanks for making room for me. I’d like to return to Mexico, given all we’ve discussed today and amid the tariff chatter and so on. Could you update us on the possible separation or sell-down — or whatever way you’d like to describe it — of the Mexico business as of today?
François Poirier
executiveThanks, John. This is François. As we said during our Investor Day, the aim is to have every pipe carrying gas, and after that have every pipe carrying cash, so to speak. Naturally, we anticipate accomplishing that with Southeast Gateway by May 1. For Tula-Villa de Reyes, we also expect completion by the end of the year. So we want that finished and behind us, with all our projects done and in service, and after that we will shift our focus to that opportunity. As we noted, we will be looking at both capital market options — an IPO of sorts — and a sale of a minority interest to a buyer, using a transaction style similar to the GIP deal on Columbia. On timing, regard it as the first half of 2026. We believe that is how we will maximize value for our shareholders and set a positive mark for the rest of the portfolio, and we also see so much growth outside Mexico that selling down our interest is not the sole tool for reducing our exposure. Growing our businesses in Canada and the U.S. will be the other tool.
François Poirier
executiveAnd another approach we’re considering for handling and reducing risk in Mexico is that, once SGP is in service, you should expect us to begin exploring financing at the Mexico level or possibly even at the asset level, which would help lower the equity capital we have at risk in Mexico—so stay tuned for that.
John Mackay
analystOkay, that's useful, thanks. Now for the second item—this should be quick—but looking at how you've laid out the forward growth projects on slide nine, that layout seems quite different from what we saw at the Analyst Day. Are these new projects entering the mix, or is it simply existing ones being reclassified into different buckets? Could you just take us through that?
François Poirier
executiveWas there a specific year you had in mind? The color scheme might look a bit different than what you're used to, but that pipeline is largely the same. Just a handful of small additions, really.
John Mackay
analystSo I suppose I'm seeing power gen at 56% at this point, compared with 32% in the investor deck. That could just be rebucketing, though I'd say those are new projects coming in.
François Poirier
executiveMy guess is that it comes down to the color coding. Your slides may just be rendering it slightly differently. I can clear that up once the call is over.
John Mackay
analystAbsolutely. We can circle back on that. Appreciate it.
François Poirier
executiveAppreciate it, John.
Operator
operatorBen Pham of BMO has the next question. Go right ahead.
Ben Pham
analystHey, thanks. Can I begin with the Columbia rate case? Could you bring us up to date on any recent feedback from customers and on the timing you expect?
Tina Faraca
executiveSure, we’re glad to provide a quick update. As you know, we filed a rate case for our Columbia Gas system in the prior year. Those rates take effect in April of this year. At the moment, we’re awaiting what we refer to as top sheets from FERC, and those will lay out where the agency stands on our rate case. Usually, once those top sheets arrive, talks with our customers intensify significantly toward settlement discussions. So we still intend to resolve that rate case in a way that benefits both our customers and our company, probably during the third or fourth quarter of this year.
Ben Pham
analystAll right, thank you for that. And moving on to my second question, perhaps, about the data centers — more specifically those in Alberta — you brought up François, and maybe looking at the non-regulated side of things. Is that pointing to the gas plants that you have there, or were you referring to something different?
François Poirier
executiveNo — those would be oil pipelines outside NGTL's oversight, under the Alberta Energy Regulator instead, I should clarify. So nothing in that reference relates to power generation.
Ben Pham
analystAll right, I understand. Fine. Thanks.
François Poirier
executiveAppreciate it, Ben.
Operator
operatorI believe we have room for a single final question. That one will be from Jessica Hoyle at Scotiabank. Go right ahead.
Jessica Hoyle
analystThanks. Good morning, and I appreciate you taking my questions. To begin with the power segment, could you elaborate a bit on what lies ahead for the Ontario Pumped Storage Project, particularly in light of the government's recent backing?
François Poirier
executiveAppreciate that, Jessica. The money coming from the Ontario government is meant to push that project forward, covering the environmental assessments that are needed, so we can get to the stage where a final investment decision becomes possible. That date is 2028. There's a lot of work still ahead on the contracting side, geotechnical items, and so on. We wouldn't move ahead on a project of this kind absent a really solid Class 3 estimate, and naturally the environmental effort will run a couple of years once you factor in what the federal and provincial rules demand, and after that you'd be looking at a construction window of four or five years, so plenty of activity carries on. It's 1,000 megawatts, effectively a 12-hour battery. The Ontario government only just brought in a prohibition on Chinese components. Naturally, that makes this project more appealing to them as a firming resource next to battery options, where a big share of the supply chain depends on China. We're quite keen on this project. Our plan at the end of the day is not to sanction it unless it comes with cost of service regulation. We won't accept cost and schedule risk on a project like this.
François Poirier
executiveThat said, it will still need to compete for a capital allocation against the rest of the opportunities we have to invest across the capital stack.
Jessica Hoyle
analystThanks for that, Corey. Could you expand a bit on what your thinking is regarding the upcoming wave of LNG, and on how pipelines owned by TC Energy might serve and support it?
Tina Faraca
executiveSure. I'll begin with the U.S. We have a strong presence in Louisiana especially, thanks to Columbia Gulf and our ANR assets, and we already have a fair amount of connectivity with multiple LNG export terminals there. A project we're advancing now, East Lateral XPress, is set to enter service later this year, providing capacity to one of Louisiana's LNG export terminals. There's also an intra-state project, Gillis, that we'll be extending to serve added load in Louisiana and along the Gulf Coast with LNG exports, and I'll hand things to Stan for any Canadian and Mexico updates.
François Poirier
executiveLooking at the broader picture, everyone knows the CGL pipeline is already operating in Canada, and at this point we're waiting for the terminal to enter service. We keep moving forward on scope and the other work products tied to phase two. And once again, that FID decision is up to LNGC as well.
Jessica Hoyle
analystMuch appreciated.
Operator
operatorThat brings us to the end of the Q&A portion, everyone. Should anything else come up, you can reach out to Investor Relations at TC Energy. At this point, I'll hand things over to Gavin Wylie, who has some closing remarks.
Gavin Wylie
executiveThanks, everyone, for being here. I realize all of you today have a very full schedule, since a number of our peers are also reporting. We appreciate your time and your participation on this call. And thank you for your interest in TC Energy. As Drew said, should any further questions come up, please don't hesitate to reach out to the Investor Relations team whenever you like. We're always glad to assist. We look forward to our next update after the first quarter. We'll speak with you then.
Operator
operatorThat wraps up today's conference call. You can go ahead and disconnect your lines now. Thanks for joining us, and enjoy the rest of your day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete TC Energy Corporation transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to TC Energy Corporation earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in TC Energy Corporation or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.