Good morning. I’m the conference operator for Chorus Call. Welcome, and thank you for being with us on the TREVI First Half 2025 Results Conference Call. <<operator_script>> This call is being hosted today by Mr. Giuseppe Caselli, CEO, and Mr. Vincenzo Auciello, CFO. At this point, I’ll hand the conference over to Mr. Caselli. Sir, please go ahead.

Giuseppe Caselli

executive
#2

Good morning, ladies and gentlemen. Joining me as well is the 2 General Manager of the construction company, TREVI and Soilmec, <<inaudible>>. I'll give just a brief highlights, and then I will hand the floor to our CFO to illustrate our financial and economical results. Just in terms of economic performance, the first half closed at EUR 312 million with a 19% growth year-to-year, and this is mainly driven by the Italian activities as well as the Middle East activities. The group recurring EBITDA stands at EUR 44.3 million in the first semester that has a strong increase compared to the previous year that was at -- that is 64% -- 65% increase with a 14.2% margin, thanks to a more selective commercial bidding approach. It's important to remark and I keep on repeating myself, and I'm sorry for that, that our jobs, our projects are extremely on a fast track basis and they last between 3 to 6 to 9 months. Very rarely, we go beyond the year. So the comparison on the semester has to be taken into account the amounts of works that we perform in that specific period. In terms of order intake, the first semester, we were able to get EUR 350 million on the first semester with again an increase with the previous year.

Giuseppe Caselli

executive
#3

At the close of June 2025, the backlog is EUR 652 million, and that figure really needs some explanation relative to the prior backlog at the end of December. Later in our presentation this will be covered, since the number appears to show a slight decline versus the previous year. That said, when you examine it on a constant perimeter basis, the backlog is more or less at the same level. What that tells us is that contract acquisition has been steady across the period on a year-to-year basis. Turning to the financial position, CapEx came in at almost EUR 9 million. Net debt has fallen to EUR 190 million versus December, a reduction of EUR 8.5 million, and with that meaningful deleveraging the leverage ratio sits at 1.9x. On outlook — which I consider the most important section of the presentation — based on the information available to us as of today, we believe second half 2025 performance will land more or less in line with the business evolution we laid out at the start of the year. Recurring EBITDA, as will be explained later as well, is expected to stay within the guidance we gave at the beginning of the year, between EUR 80 million and EUR 90 million.

Giuseppe Caselli

executive
#4

Regarding the PFN, we'll keep the guidance we issued at the start of the year. So, in short, the first half saw a very strong performance from us. And unless things change dramatically, and provided there's no worsening of the current situation that all of us are aware of — meaning the dollar's valuation and crises in various parts of the world — we think we'll be able to hold to the guidance we gave at the beginning of the year. On to the numbers. For revenue, we have EUR 280 million — sorry, EUR 312 million, which is plus 19% versus the prior year. For recurring EBITDA, EUR 44.3 million, up almost 65% against the previous year, which stood at EUR 27 million. For total adjusted net profit, we're at EUR 11.3 million versus the EUR 5.4 million of 2024. Free cash flow from operations was plus EUR 32 million compared with the EUR 7.9 million of 2024. On net debt, EUR 190 million against the EUR 207 million of the previous semester.

Giuseppe Caselli

executive
#5

The leverage ratio stands at 1.9x compared with 3.0x. What drove that change? Essentially, there are quite a few projects we're executing across the globe. We've just -- we're wrapping up the North-East Link Tunnels in Australia. Work is moving forward at Rogun Dam in Tajikistan. We've -- activities got underway in Spain. The Metro Manila Subway is progressing. We finished the final work order secured at NEOM. And after that, work continues on the Malta activity. Over in the States, a new contract has just been awarded to us. Simultaneously, the earlier activity there is still moving ahead. In Dubai, in the Emirates, multiple projects are underway right now. Things are really booming across the Emirates. A station on the Metro in Algeria was awarded to us. In Nigeria, construction of 2 berths is moving forward. In Italy — a significant piece of what we're doing at present in the first semester — the High-Speed Rail Link in Florence is progressing. Building work began in Rome. We're starting -- activities got underway on securing the Garisenda Tower, and then Venezia and Metro C in Rome, followed by the railway doubling in Messina-Catania.

Giuseppe Caselli

executive
#6

As I mentioned at the start, order intake for the first half is EUR 350 million. For those of you watching the webcast, you can basically see that we're on the higher end compared with last year's order intake. That means our company continues to secure contracts, and we only secure contracts when we judge them to be profitable and beneficial to our results. So we've become increasingly selective about what we pursue and what we take on. Another factor to keep in mind is that we operate across a fairly broad geographic footprint, which helps us reduce the risk of concentration in a single region — and of facing a serious risk of no activity if something happens there. So we aim to balance our workforce and our activities around the world. Backlog stands at EUR 652 million. One thing I'd like to point out is that Soilmec's backlog has grown since 2023. That said, this backlog was affected by the cancellation of a project in the United States totaling roughly EUR 60 million.

Giuseppe Caselli

executive
#7

That contract got canceled because certain conditions weren't satisfied between the local government and the federal government. So while the discussion between the 2 government parties kept dragging on, the federal government chose to pull the financing for the project. So the project was canceled. We were paid for the work we completed on this project early on, and at this point those activities are fully out of our backlog. So on the right side of the slide, as you can see, there's a breakdown of the backlog. That aligns with our policy, which comes from the fact that we aim to spread our risk across the world rather than concentrating it in just one region. This naturally means we must take an extremely quick approach to moving around the world, staying extremely flexible to demand, also because we target projects that make sense in terms of profitability. We don't take on everything that comes along, but we are extremely — and I stress extremely — selective about what we pursue. And that's demonstrated by the fact that our group EBITDA ranks among the highest compared with our peers.

Giuseppe Caselli

executive
#8

Maximizing revenue isn't our focus. What matters to us is maximizing profit along with cash generation. At this point I'll hand things over to Vincenzo Auciello, our CFO, who will walk through all our economic and financial results in detail.

Vincenzo Auciello

executive
#9

Alright. Thank you, Gigi, and good morning, everyone. We'll begin on Slide #10, where you'll find a summary of our financial results for the first half of 2025 versus the same period in 2024. Group revenue rose 19% year-on-year, while recurring EBITDA grew by a notable 64.9%, reaching EUR 44.3 million. That remarkable growth has come mainly from our TREVI Division. During the first half, we also saw a significant improvement in EBITDA margin versus last year, with the margin reaching 14.2%. This higher margin reflects the disciplined approach we take, awarding and executing projects that deliver healthy marginality. Let me also point out that reported and recurring EBITDA are almost aligned, since our extraordinary cost amounts to only EUR 850,000. Moving on to the adjusted net result. The adjusted net result came in at EUR 11.3 million, compared with EUR 5.4 million in the first half of 2024. We refer to adjusted net profit because both the 2024 and 2025 net results were impacted by the reversal of nonmonetary financial costs resulting from our successful financial restructuring, which was completed in 2023. The impact on P&L figures is mainly related to IFRS 9 on debt, which is reversing pro quota through the end of 2026.

Vincenzo Auciello

executive
#10

The gap versus the adjusted net profit figure of EUR 5.2 million is precisely the IFRS 9 amount that was absorbed during the first part of the year. It goes without saying that our reported net result of EUR 6.1 million is solid and well above the first half of 2024. Free cash flow came in positive at EUR 32 million, which is 4x what we delivered in the first half of 2024. That demonstrates the headway we have made on cash flow conversion. In our view this is a notable outcome, showing how margin growth gets converted into cash generation. Turning to Slide 11, we look at our revenue footprint. The Middle East makes a significant contribution. That said, because our revenue mix is well diversified across geographies, we are well placed in numerous markets and can seize additional commercial opportunities. Let's move now to the results for our 2 divisions, beginning with TREVI. This division recorded EUR 260.5 million of revenue in the first half of this year, an increase of 26.4% from last year, driven by performance in Italy and the Middle East. Recurring EBITDA reached EUR 42.9 million, up by 92.2% compared to 2024, with an EBITDA margin of 16.5%, which rose by more than 560 basis points from the first half of last year.

Vincenzo Auciello

executive
#11

Sure — the increase in EBITDA comes from both higher revenue and a better geographic mix, as projects move forward or are underway in Saudi Arabia, the Emirates, Tajikistan, and other locations. As you might expect, these improving metrics have lifted the group’s overall results, in terms of both economics and cash flow generation. For this year’s second half, we anticipate the division will post somewhat lower revenues and EBITDA than in the first half, reflecting project schedules across the Middle East, Europe, and North America. Even so, we expect a result that remains significant and robust. Turning to the Soilmec Division on Slide 13, revenues fell 6.4% year-on-year, with recurring EBITDA lower both in absolute terms and as a percentage of revenues. That decline stemmed mainly from reduced contributions from business activities in North America and the U.K. Regarding North America, uncertainty over how the U.S. government will implement tariffs significantly affected sales that were expected to be finalized in the U.S. market. To better grasp the economic trend of the Soilmec division, though, we should also factor in something Gigi mentioned on one of the earlier slides.

Vincenzo Auciello

executive
#12

Regarding Soilmec's backlog as of the close of June 2025, it stood higher by EUR 10 million versus the corresponding period a year earlier. This points toward second-half revenues and margin helping to close the first-semester shortfall and aligning performance with 2024. Now let's turn to the overall P&L, which is on Slide 14. Revenue and EBITDA have already been covered in detail. Therefore, I'd like to highlight a few lines beneath EBITDA. Depreciation came in at EUR 14.7 million, down against the prior-year period, thanks to reduced depreciation on leasing contracts under IFRS 16. Financial expenses rose to EUR 14 million from EUR 13.3 million, largely because of greater nonmonetary financial charges tied to IFRS 9, which totaled EUR 5.2 million in the first half of 2025, a bit above EUR 4.8 million in the first half of 2024. For the whole of 2025, we have budgeted financial expenses at roughly EUR 27 million to EUR 28 million. Accordingly, approximately EUR 13 million to EUR 14 million is anticipated for the second half of 2025. Income tax was EUR 8.5 million, in line with taxable income recorded in certain geographies where no tax losses carryforward exists to offset the tax burden.

Vincenzo Auciello

executive
#13

Then, last of all, net profit comes to EUR 6.1 million. The share attributable to minorities matters in practice, since it amounts to only roughly EUR 400,000. That means the profit booked is almost entirely the group's. Now let's turn to the slide covering cash generation. I should note that the company stayed highly focused on producing cash flow, with the aim of cutting our debt. As Slide 15 shows, by the end of June 2025 we posted a positive result on operating cash flow, which came in at nearly EUR 41.2 million, with EBITDA cash conversion of 93%. Free cash flow for us was EUR 31.1 million (sic) EUR 32.1 million. And when we refer to free cash flow here, we mean free cash flow to farm, so it is before interest is paid on that. This outstanding outcome stemmed from robust operational results combined with a favorable working capital trend, and it let us release cash to cover close to EUR 9.1 million of CapEx and, as the following slide will show, to meet our debt obligations.

Vincenzo Auciello

executive
#14

Looking at the back half of this year, we anticipate generating positive cash flow, though it will come in below what we saw in the first half — that is, the earlier portion of this year — and the main reason is the reversal we expect in the positive working capital dynamic that showed up in H1. If you turn to Slide 16, you can see how our net debt structure has evolved. The cash flow generated during the first half of this year strengthened our net financial position by EUR 14 million on a pre-IFRS 9 basis. That took us from a net debt of EUR 221 million down to EUR 207 million, and on a post-IFRS 9 basis the improvement was EUR 8.5 million. So we went from a net debt post IFRS 9 of EUR 199 million to a net debt of EUR 190 million. These results came from generating EUR 32.1 million in free cash flow, and that cash generation allowed us to cover the debt interest payment along with the dividends to minority, for a total of EUR 9.3 million, despite a negative ForEx impact of roughly EUR 9 million, which reflects the depreciation of the dollar against the euro beginning in March this year. Let's now take a look at liquidity and the debt structure as of the end of June 2025.

Vincenzo Auciello

executive
#15

We're now at Page 17 of the presentation. As you can see, we maintain a comfortable liquidity level on the balance sheet, which stood at EUR 97.4 million at the end of June, so pretty much in line with December 2024. In addition, we hold other current assets of EUR 12.8 million, of which EUR 10 million will turn into cash during the second half of 2025. Our gross debt was EUR 300.7 million, an improvement of around EUR 11 million compared with December 2024. Let me also emphasize the concept that bringing gross debt down remains a key priority for TREVI as we keep derisking the company. A more detailed overview of the gross debt -- of how the gross debt moved -- is provided on the right-hand side of the slide. The increase in gross debt determined by IFRS 9, so a nonmonetary effect, of EUR 5.2 million plus the interest peak. So all in all, EUR 7.6 million was more than offset by the debt repaid during the first half of the year, for EUR 18.8 million. And the EUR 18.8 million we repaid in the first half has 2 components. One is related to the amortized plan of our long-term debt as provided by the financial restructuring agreement.

Vincenzo Auciello

executive
#16

The remaining item relates to the short-term facility that was repaid during the first half of 2025. Now, returning to the analysis of net debt: when cash, liquidity, and other current financial assets are subtracted from gross debt, net debt as of June 2025 came to EUR 190.4 million. Our leverage ratio, defined as net debt over recurring EBITDA, stood at 1.88x, which reflects the continued work we are doing to deleverage the balance sheet. And for the audience's information, the covenant threshold established under the financial restructuring agreement with the banks for June 2025 was 3x (sic) 3.00x. Since our ratio is 1.88x, we are comfortably below that limit. I'll now turn things back to Gigi for our closing remarks.

Giuseppe Caselli

executive
#17

Thank you so much, Vincenzo. I really appreciate the clear and thorough walkthrough of our economic and financial results. Well, let's begin with revenue, which is a key element, though it isn't the company's most important one. We think we can land within a range of EUR 630 million to EUR 650 million by year-end. And of course, that has to be read alongside a couple of factors that have driven this result. One is the cancellation of the projects in the U.S. where we were supposed to have carried out certain activities, a number of activities on this project. So we need to find suitable replacement and try to cover with some additional activities around the world. A second element that needs to be considered is the valuation of the dollar compared to the euro. Everybody knows that, more or less, we are above 10% in terms of the valuation of the dollar compared to the euro since the year -- almost the beginning of the year. The second and, in my opinion, one of the most important, the most important element is the recurring EBITDA. We will maintain what we have foreseen at the beginning of the year.

Giuseppe Caselli

executive
#18

So through various measures—and, again, with a highly flexible approach to what we do—we'll be able to beat the guidance we issued at the start of the year, which sits in the range of between EUR 80 million and EUR 90 million. For net debt, we're looking at a range of between EUR 182 million and EUR 194 million. And as for the leverage ratio, it will come in between 2x and 2.4x. So we're simply proud, very proud to report that over the past number of years we've been working to restore this company to the position it deserves as a leader in what we do. Despite all the troubles occurring around the globe that are clearly beyond our control, we have so far always delivered on what we predicted. What we can say is that the first half results are positive. And I keep repeating that comparing half year with half year, trimester with trimester, in a company like us, ours, where the activities essentially last the span of 1 night, since they run between 3, 6, maximum 9 months, is of course an indicator of how the company is performing, but it isn't the only indicator—you always have to consider the company in what we believe is its outlook at the year-end.

Giuseppe Caselli

executive
#19

As I said earlier, regarding our outlook for the year-end, we're keeping what we anticipated at the start of the year. Why are we confident we'll get to that kind of level? We're more confident than previously, since we have a positive 6-month result — the results for the first part of the year. Naturally, that means we'll keep deleveraging the company, as we've been doing over recent years since the restructuring projects began. We have to keep delivering and generating free cash flow. And last but not least — I don't want to bother anyone — we will reaffirm what we foresaw at the beginning of the year regarding EBITDA and net debt. Thank you for paying attention to what we've just said; we're now ready to take any questions you might have. Thank you very much.

Operator

operator
#20

<<operator_script>> Our first question comes from Emanuele Gallazzi at Equita.

Emanuele Gallazzi

analyst
#21

Three questions come to my mind. If that works for you, I could take them one at a time — that might make things a bit simpler. So, all right.

Giuseppe Caselli

executive
#22

Yes, go right ahead. Thanks.

Emanuele Gallazzi

analyst
#23

Yeah. So, first thing is about the Messina Bridge — that's a possible opportunity worth looking at. You obviously bring the expertise and the know-how. I realize it may be too early, but I'd like to hear your initial thoughts, so to speak, on this opportunity and this project.

Giuseppe Caselli

executive
#24

Alright. On the Messina Bridge — for us, it's certainly a fantastic project. From our standpoint, it will be a major target for participation. Naturally, as you're aware, activity is expected to kick off sometime during this year. We've been putting together a plan for taking part in those activities. Our hope is to begin getting bid documents by the end of next year. That's really all I can say on that. The volume of work involved is enormous. I firmly believe there's no way around it — the consortium that's been given responsibility for building the bridge will split the scope among various contractors. We'll be prepared to take part, and we'll assess the opportunities just as we assess every opportunity worldwide.

Emanuele Gallazzi

analyst
#25

Got it, thanks. Moving to Saudi Arabia: could you give us an update on NEOM and the Line project, since the press has been reporting that the client is rethinking it? And more broadly, looking at the Middle East — which accounted for roughly 50% of TREVI revenues — how do you expect the region to develop?

Giuseppe Caselli

executive
#26

Okay, so let's begin with Saudi Arabia — the Line. Just recently, on the web, it's been reaffirmed and reconfirmed yet again that this line is going to be formed through construction of the 3 modules, 45, 46 and 47. Right now, we've been working on 46. At this moment, as I mentioned at the start of the presentation, we've finished the last work order that was awarded to us some time ago. Our performance was not only good economically, but technically and operationally we did extremely well. In fact, we received the prize for the best contractor — piling contractor — on the Line. At present, the client, as far as we understand, is reevaluating a certain part of the engineering so as to cope with additional technical requirements. We hope the new bidding rounds will come by end of the year for the activities relevant to module 46 and 47. If you consider that so far we've mainly just been working on module 46, in the event we are successful in winning the new contract for the 2 additional models, this will give us a positive horizon in terms of activities for next year and even half of the year after.

Giuseppe Caselli

executive
#27

At this point, with the last work order finished, our backlog stands at 0 when it comes to potential revenue. So our backlog covers only all activities apart from NEOM. Regarding the Middle East, leaving Saudi Arabia to one side, I think it's fairly well known that we read every bit of press, information and news out there — sometimes it's accurate, sometimes less so — and right now, given the incredible volume of things done recently, there is a moment of — I don't want to call it a pause, but investment pace is easing slightly. As for other Middle Eastern countries, we're seeing booming activity in the Emirates. In fact, our entire work fleet in the Middle East that was based in the UAE is operating at a 100% pace. We're mobilizing extra equipment in the Emirates, since continuous activities keep arriving on the horizon in — on our pipeline. In Oman, we've seen some activity going on, and it's fairly steady as a country. You don't expect sparks either. Most often, you don't expect them. So business as usual, I'd say.

Giuseppe Caselli

executive
#28

And activity in Kuwait has been picking up lately, just to give you a sense of which Middle Eastern nations we're active in.

Emanuele Gallazzi

analyst
#29

Got it. Soilmec is the final item, and it's a quick one. Could you remind us how much exposure Soilmec has to the U.S. market, and what strategy you're considering putting in place to offset the tariff impact?

Giuseppe Caselli

executive
#30

Yes. Okay. As everyone can readily see, Soilmec's revenues in the first semester fell short of what was expected relative to the prior year, and that is because of the American market. With the tariff — with the uncertainty surrounding the tariff — the market was essentially almost frozen. There was some activity, and we hope that now, with the current tariff set at 15%, the market will respond favorably and certain opportunities will become credible. To be sure, we do anticipate an impact on Soilmec in the U.S. market, because whatever was not fulfilled in the first half cannot be made up in the second half. Our hope is that starting now, the dealers and the companies will go ahead with investing and purchasing our equipment. We see that something is already moving following the announcement of the 15% tariff. We hope this movement will generate the relevant purchase order, the Level 1 contract. What we plan to do in case we don't — in case the tariff level should hinder our market share in the U.S.: well, we brought back something that had been on a shelf, a project we had in the past to manufacture a couple of types of equipment — not equipment, but types of equipment, the one with the most appeal on the market — and to use a certain type of machine, a base machine from the States, and the relevant part, the precious part, to bring in and assemble in the States.

Giuseppe Caselli

executive
#31

We're looking at this right now, since you can't simply decide that for a relatively brief stretch of time you're going to put a substantial amount of energy, effort and money into creating a new — into forming a new production line in the State. But when it comes to engineering, to strategy, to realization, we'll reach a point where all we have to do is push the button and carry out what we began previously. As for time to market, if we're able to — if we decide to move in this direction as well, to recover the portion of the market that the tariff will hinder, we figure we'd need around 6 months. So we want to be ready like a Formula 1 starting grid. And the moment we decide the traffic light will be green in 6 months, we'll be ready to produce in the States. Right now, though, we're carrying out all the preparatory work, and we're making use of what we've done before. We put a substantial amount of effort, engineering man-hours, money and people into studying and adapting this kind of solution.

Giuseppe Caselli

executive
#32

And because of that work done previously, in a little while we'll be set to stand at the starting line. At that point we'll look at whether to give the go-ahead or not. That call will rest on what unfolds over the next month and the following few months.

Operator

operator
#33

Our next question comes from Gian Marco Gadini at Kepler Cheuvreux.

Gian Marco Gadini

analyst
#34

I also have 3 questions, and I'll take them one at a time. The first one is about -- again, about the opportunities. It's great to see the backlog rebalancing from a geographical standpoint. I was wondering if your pipeline shows a similar distribution of projects, and whether you can tell us how big this potential pipeline is in the following -- for the following semesters? And specifically, do you see any opportunities in Germany tied to the infrastructure plans that are being approved and funded at the national level? And are there any projects -- any other projects in your backlog that carry a risk of cancellation?

Giuseppe Caselli

executive
#35

Alright, let me take the last question first. As things stand right now, no project cancellations are on our radar. Losing a single project — and I believe this is the first such case in 6 years, in fact beyond 6 years since I took this chair — is a highly unusual event. It does happen. What I want to emphasize once more is how well we are able to withstand that kind of situation and still deliver the result we have just shown. That, again, stands as proven evidence that our approach to bidding, to carefully examining the market, and to building real intelligence about it ranks among the key ingredients of our success. Now, on the pipeline and how the backlog has evolved: once more, we hold a strong conviction — I personally hold an extremely, extremely, extremely firm conviction — that we must stay extraordinarily, extraordinarily, extraordinarily responsive to demand. We do not invent a market. We do not manufacture a market. Our task is to be exceptionally shrewd, capable, and prudent in grasping where the market is heading and to move in ahead of others, and that is precisely what took place with NEOM. With NEOM, no one was discussing NEOM at the time. We had ears and contacts in Saudi, and we got ourselves mobilized on NEOM even before there was the remotest possibility of seeing a contractual document — working purely off an idea.

Giuseppe Caselli

executive
#36

So that's the approach we're taking. Because, again, as things stand right now, if I were to predict what will occur over the next — within 2 years in some country, or attempt to set up a country presence because we believe projects will materialize there in 2 years, in my view that's money wasted. You've got to be extremely quick and extremely adaptable. And as you can see, for example in Nigeria, we secured a contract and we're mobilizing the equipment, but we won't be staying there, keeping equipment for its whole lifetime or building an establishment that drains money indefinitely. We watch what's coming with the short runway. We act quickly. At the same time, we return quickly to wherever the equipment is required. On the projects side, well, there are quite a few projects stretching from New Zealand to South America and Central America. What I can say is that we're putting in extremely hard work on business intelligence across the globe so that, as I tried to explain earlier, we're the first to hear and the first to move and to accept a certain risk by going there even before we get the bid to quote.

Giuseppe Caselli

executive
#37

Up to now, this strategy has proven highly effective, in our view. What we avoid is depending on what I’d describe as the market segment offering an extremely thin margin. Revenue generation is not our goal. Our goal is to pursue projects involving a particular degree of complexity—high complexity—since that is precisely where our expertise can be leveraged to the fullest. With Soilmec, we can also build equipment capable of carrying out those kinds of activities. And we aim to take on what is genuinely difficult, because in ordinary day-to-day business, profitability levels are extremely, extremely, extremely thin relative to the risk you must bear and the payment delays you encounter.

Gian Marco Gadini

analyst
#38

Understood.

Giuseppe Caselli

executive
#39

I’m not sure whether I covered everything you asked. If I didn’t, please just ask me again. On Germany — Germany, Germany, Germany, Germany.

Gian Marco Gadini

analyst
#40

Right, yeah, yeah, that's right — it's basically Germany.

Giuseppe Caselli

executive
#41

Alright. Germany is a very unique market. One key factor that many people lacking deep familiarity with the German market may not be aware of is a hurdle facing anyone who wants to come into that market. In Germany, most contracts require the posting of a bond that is essentially perpetual. This obstacle exists specifically to keep other contractors from entering Germany. In fact, if you look at who is operating in Germany, do you see any international contractor that isn't German? It's very hard, particularly in our line of business. And as you know, when you approach a bank and request an open-ended bond — so essentially a perpetual one — you simply cannot obtain such facilities. So in essence, it's an intimate barrier to the market. There are — we have been active in Germany, but on a private basis, where the investor is a private entity willing to accept what is regarded as the standard approach to providing bonds. That means a set number of years, rather than, for instance, an excessive number of years. And that is the other factor. So we are keeping a close eye on the market.

Giuseppe Caselli

executive
#42

We’re aware of this barrier that’s been put in place in Germany to favor the German contractor and to prevent additional contractors from entering the market, but really it’s on a case-by-case basis.

Gian Marco Gadini

analyst
#43

Okay, that's clear. My second question concerns the favorable result of the litigation you referenced in the press release about the sale of the Oil & Gas division. As we understand it, roughly EUR 10 million to EUR 11 million will be received in cash during the second half. Do you plan to put that toward speeding up your deleveraging plan further? Or do you see other productive uses for this cash?

Vincenzo Auciello

executive
#44

Thanks, Gian Marco. This is Vincenzo. Yes, as you remember, what we've classified in our debt structure — those other financial current assets of EUR 12.3 million — includes EUR 10 million that relates to the litigation you just mentioned. So we expect that EUR 10 million to convert into cash during the second part of the year. In terms of net financial position, I'd say it doesn't change, since it's already embedded there. So essentially there will be a swap from other current assets — other financial current assets — into liquidity. I'd also say that at this moment we view this liquidity — this additional liquidity — as ready for our operations or for a further reduction, not of the long-term debt, because that follows the plan, the amortized plan set by the structuring agreement, but it may be used to further reduce the short-term facility. So operational or financial, including the conversion of those financial current assets into liquidity. So it may also help with debt reduction, but that isn't written down at the same right now.

Gian Marco Gadini

analyst
#45

And on that final point about the recurring CapEx level — we saw it was significantly lower in H1 than the prior year, though last year you were upgrading the fleet. So can we treat this level as the ordinary, recurring CapEx level, also measured against revenue? So roughly the 3% we see in H1? Or should we expect any meaningful additions in the near future?

Vincenzo Auciello

executive
#46

So let's say that over the past years, our CapEx level ran at roughly EUR 30 million each year. And that CapEx level was a really high peak. That same CapEx level also made it possible to rejuvenate the asset fleet. So because of that, in the first half of this year, we have CapEx of about EUR 9 million in cash flow terms, and we expect an equal amount in the second part of the year. So overall, there will be -- we see a reduction in CapEx in the year 2025 versus the past. We see a range for the year of about EUR 20 million, EUR 22 million. That's because previously, we have already pushed -- in past years, we have already pushed on our CapEx, capital expenditure, and rejuvenated the fleet. And what also matters is, let me say, our assets are movable as well. So we can shift our assets from one country to another, so as to satisfy the different project schedules. So this also helps keep the CapEx expenditure under control. What we spent more in past years, we will benefit from this year, and we see a lower CapEx level versus past years.

Giuseppe Caselli

executive
#47

Sure, I just want to add a few basic points. This is under normal circumstances. Since we're trying to improve where future revenue levels are concerned, CapEx could change if we're awarded some key projects that require extra equipment. So if things stay as they are, what Vincenzo said a moment ago is what will happen. If we succeed with a couple of acquisitions in terms of the projects we're targeting, then the quantity of assets we'll need to purchase will certainly go up.

Gian Marco Gadini

analyst
#48

Okay. But I believe this will also involve extra down payments to address the financial employment side of things, I think.

Giuseppe Caselli

executive
#49

Yes, that's right. Yes, that's correct. Yes, indeed. It hinges — once more, it hinges on the situation. That will be the deciding factor. Take, for example, as you're aware, within the United States there's no down payment — the down payment mechanism that exists in other regions of the world doesn't apply here. In other regions of the world, a down payment will be required. That will hinge on what kind of project it is, what profitability this project is expected to deliver, and how complex this project is. And if every one of those elements is met, that means a very visible project with high profitability, cash flow positive while the project is being executed. But you need to invest. We will evaluate and we will invest.

Gian Marco Gadini

analyst
#50

Got it.

Giuseppe Caselli

executive
#51

We need to stay very adaptable. In this business, being inflexible with your assumptions and refusing to revise them marks the beginning of the end. At our company, whatever we settle on this evening might have to be altered by tomorrow, since circumstances we don't control shift — that is, if we intend to continue along this path of getting better, of ongoing enhancement of the company's capabilities and its results.

Operator

operator
#52

Luca Arena from Alantra has the next question.

Luca Arena

analyst
#53

Okay, most of what I wanted to ask has been covered already. And I appreciate the slide deck — it was quite thorough. But on that U.S. project that got canceled, once we understood it should have represented roughly EUR 60 million of backlog, what would its revenue impact have been for 2025?

Vincenzo Auciello

executive
#54

Luca, Vincenzo here. This is a very direct question, and it gets a very direct answer. We included it in the budget. When we put the budget together at the start of the year, we counted approximately EUR 20 million of revenue — EUR 20 million, within the EUR 20 million to EUR 25 million range — from projects that were canceled. So naturally, in the new revenue estimate we've provided, revenue from those is 0 debt. That means a deviation of EUR 20 million to EUR 25 million versus what we presented in that budget at the beginning of the year and what we disclosed to you yesterday and today.

Luca Arena

analyst
#55

All right. Now turning to the TREVI Division, recurring EBITDA climbed to 16.5%. How much of that gain would you call structural versus temporary, driven by a favorable country mix, let's say?

Vincenzo Auciello

executive
#56

Alright. I'd say this also ties into our commercial strategy and that selective bidding approach. Of course, 16.5% is a really strong outcome. I wouldn't treat that figure as representing what our average will be. Still, over the last 3, 4 years, we've consistently stayed in double digits — nearly at the low end of double digits, roughly 15% — 14%, 15%. So that 16.5% reflects the highly selective approach plus the geographic mix. It could come in a few basis points lower, but we remain in a solid, robust range of 14.5%, 15%. So let's say somewhere between 14.5% and 15.5%. That's robust, meaningful, and, as our CEO mentioned earlier, one of the best — among the highest margins when you look at our industry and our peers.

Giuseppe Caselli

executive
#57

Okay, let me just add a few points here. Like I said earlier, we aren't the ones creating the market. What we have to do is anticipate it and try to see what's out there, then decide which project to go after — which kinds of activities you want to pursue. The high level seen in the first semester also comes from a mix of projects that are very complicated and very risky. When I say risky, it shouldn't be viewed negatively — it should be viewed positively. Why are we able to take on that kind of risk activity? Because our know-how, our expertise, our capability, and the caliber of our people are such that we can mitigate those risks that other companies can't take on. So this year, this semester, in a number of situations, it happened that we consolidated this count of highly complicated projects. Naturally, we'd like to have only complicated projects in our backlog, but unfortunately that isn't the case. And we have to live on what's available to bid, of course, while trying to select what isn't at a profitability level that won't meet our minimum demands.

Giuseppe Caselli

executive
#58

That EBITDA figure we showed is absolutely at the very, very, very top end — it's not normal for it to sit at that level. We wish. Of course, if we succeed on a couple of the projects we're bidding on, which, I'll say again, are extremely difficult in a very difficult area, with difficult conditions and a difficult environment, then most likely we'll be able to keep up that kind of level going forward — but that's not something you can count on as routine EBITDA.

Luca Arena

analyst
#59

All right, turning to the final question — given that strong figure you posted for the first half, your guidance looks pretty easy to hit. Are you being overly cautious, being realistic, or are you actually seeing some tangible risks in the back half of the year?

Giuseppe Caselli

executive
#60

Alright, everyone, I think it's been 6 years now that I've had fairly ongoing contact with the financial community. My principle isn't to lean conservative or optimistic. We need to be realistic. So whatever we give is what we expect to achieve. That's the driver behind all our decisions — mine first, and my colleagues' as well. We don't like to hand over a conservative figure and then at year-end show an improvement — a dramatic improvement — because if you deliver a dramatic improvement 1 year, the following year you can deliver a dramatic loss. So to me, what matters is stability. Whatever we state at the start of the year, we have to hold to. And that's what we've done throughout this year. You can check and verify every piece of guidance we've given since the year began, and we keep it exactly as we gave it. We want to be a reliable company that holds to what it says.

Luca Arena

analyst
#61

Absolutely — nice work, everyone.

Giuseppe Caselli

executive
#62

Thanks a lot — I really do appreciate that.

Operator

operator
#63

<<operator_script>> Mr. Caselli, gentlemen, at this point no further questions have been submitted.

Vincenzo Auciello

executive
#64

Much appreciated.

Giuseppe Caselli

executive
#65

Thanks a lot. Thanks to all of you.

Operator

operator
#66

Thank you for being with us, everyone. That brings the conference to a close. You're welcome to hang up your phones now. We appreciate your participation.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete TREVI - Finanziaria Industriale S.p.A. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to TREVI - Finanziaria Industriale S.p.A. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in TREVI - Finanziaria Industriale S.p.A. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.