VAALCO Energy (EGY) Earnings Call Transcript & Summary

December 2, 2025

NYSE US Energy Oil, Gas and Consumable Fuels Special Calls 36 min

Earnings Call Speaker Segments

Jeffrey Robertson

Analysts
#1

Thank you for joining us today for a fireside chat with chief Executive Officer, George Maxwell from VAALCO Energy. I am Jeff Robertson, Managing Director for Natural Resources at Water Tower Research. Before we begin, I would like to remind participants that our discussion today could include forward-looking statements as of today, December 2, 2025. VAALCO's disclosures regarding such statements can be found on the Investor Relations tab of its corporate homepage. VAALCO is an international oil and gas exploration company with assets located in Gabon, Egypt, Canada, The Ivory Coast, and Equatorial Guinea. VAALCO's asset portfolio combines a mix of short-cycle development projects and long-cycle development projects and exploration prospects that expose the company to future growth opportunities and support management's goal of building value and returning cash to shareholders. With that bit of introduction out of the way, George, thank you for taking the time to join us today.

George Maxwell

Executives
#2

Thank you, Jeff. Thanks for the introduction, and I'm looking forward to the chat.

Jeffrey Robertson

Analysts
#3

Before we get to the development or the drilling campaign that's getting underway in Gabon and some of the plans for Côte d'Ivoire for 2026, I just want to revisit some of the capital program for 2025. VAALCO's original CapEx outlook for the year, which was published back in March called for total CapEx in the range of $270 million to $330 million. The midpoint of total NRI production was estimated to be about 15,600 BOE per day. The latest full year estimates, which were updated on November 10 in conjunction with 3 quarter earnings payment to the CapEx midpoint at $243 million or 20% below the original midpoint impact NRI production midpoint at 16,500 BOE per day or a 6% increase from the original midpoint. George, can you walk us through where the CapEx savings have come from? And really what's driven the better than originally expected NRI production outlook?

George Maxwell

Executives
#4

Yes, I can. I mean we indicated some of these responses in our last earnings call. And predominantly, we've seen with a softening commodity price, we revisited our CapEx program for 2025, and we've removed around about $20 million of discretionary CapEx that was originally planned for this year. In addition, we've seen some increases in CapEx, primarily around the Ivory Coast project around the MV-10, where we pulled forward about $10 million of CapEx into 2025 to ensure that we can keep the MV-10 project on schedule. What we've also seen against the original budget is a delay in the drilling rig for the rig -- the drilling program in Gabon. That's been delayed probably between 2 to 3.5 months due to the availability of the rig. So we've seen some of that slippage for the capital program for Gabon slip into 2026. So those are the 3 key elements that have allowed us to have a lower CapEx guidance for 2025. When we look at the production and the performance, particularly in Gabon, we've seen continued improvement from our forecast position and our modeling position from the Etame field. Now part of the production increase has come from the continued flowing of 4H on Ebouri. We started that well up. It's been flowing very well for most of 2025. We started that well to allow us to test exactly how we were handling the H2S issues that we are all well aware of an Ebouri and whether those could be handled with the chemical scavenging that we have been planning for. I'm happy to say that well has performed well. It's getting us above -- well above our production forecast. When I look at how much of this increase on the NRI performance is related to reservoir performance and how much is related to the topsides activities that we undertook in 2022 and 2023, there's probably about at least 1,000 barrels a day contributing to those combined factors. And about 60% of that comes from the reduction in back pressure that we successfully completed with the reconfiguration of the field and about 40% of that is coming from enhanced field performance.

Jeffrey Robertson

Analysts
#5

With respect to the production performance, is it reasonable to expect that you may see some positive performance-related revisions when you go through the year-end 2025 reserve evaluation process?

George Maxwell

Executives
#6

There's 2 sides to that. One is definitely, yes, we are anticipating or we do expect to see significant revision movement within our reserves position. Now obviously, we can't quantify that yet until we go through the evaluation process with Netherland, Sewell. But given that we have not spun the drill bit in Gabon for 2 years and what we've seen in the production performance, the opportunity does give rise to significant revisions within the profile. So that's certainly what we are anticipating, but we won't be able to quantify that until we complete the exercise in early January.

Jeffrey Robertson

Analysts
#7

I think the original plan in Egypt that you laid out earlier in the year called for 8 to 13 new wells through the end of September. VAALCO has completed, I think, 14 new wells in the year. Can you talk about what's driving some of the efficiency gains that you're seeing in Egypt that allows you to do more projects with the same or even hopefully a little bit less capital?

George Maxwell

Executives
#8

Yes. There's 2 key elements there. The first element is, obviously, we've had this drilling rig working continuously for probably close to [Technical Difficulty] now. And that position allows the efficiencies on how we're executing the wells and with the experienced team on board and the performance of the rig. So we've gained efficiencies there and those efficiencies continue to accumulate for us in each well we drill. And secondly, we've established in Egypt from where we were when we first acquired that position back in 2022, we've continually improved the supply chain for providing the equipment inside Egypt for delivering these wells. So we've got limited to no downtime waiting equipment, limited to no downtime on rig performance. And that, combined with the types of wells we've started drilling now with more of the slant wells have contributed to us being able to drill more wells with the same level of CapEx. And you can see the -- although we're doing a little bit of a post-action review here, you can see how well it's held up in the Egyptian production performance.

Jeffrey Robertson

Analysts
#9

I know you -- VAALCO won't provide any detailed capital spend or operating update for 2026 until probably March of next year when you report your year-end financial results. But from a high level, George, how does the result -- how do the results in Egypt make you think about constructing a capital program for that asset base in next year?

George Maxwell

Executives
#10

We definitely are reviewing that right now. The first key element here is to understand the after-action review of the wells that we've drilled in 2025 and the ones we are just finishing off here in Q4. And then to review the performance of those wells and how they delivered and what have they delivered in respect of the reservoir performance that was anticipated. So before we move into a 2026 program, we have to do a review of where we can optimize the next drilling sequence in what is an aging asset. So where can we get the biggest bang for a buck and targeting both the workover positions and the new drill opportunities. What are we doing when we look at the opportunity in South Ghazalat? We're trying to evaluate that now between the gas and oil split, and we've -- that's still under evaluation. So I think when we look at Egypt's performance, it's been a strong performance in 2025, and we're going to have to do an evaluation of the subsurface position of -- to exactly where we want to position any 2026 drilling program.

Jeffrey Robertson

Analysts
#11

Turning to Gabon, you mentioned that the rig was a little bit late coming off its prior contract. Is the rig on site at Etame now? And can you talk about how that drilling program will unfold as we look into 2026?

George Maxwell

Executives
#12

Yes, I can. So the rig is on station. It arrived with us last week. It's -- we had a couple of days waiting on weather before we could pin it to the platform. But it is pinned to the platform now. And as of today, I think we're currently jacking up the rig. So we would expect to spud the first well in the next 72 to 96 hours. So that would be the first well in Etame. When we look at the program, and as you know, we've got 5 firm wells and 5 optional wells. So we start the program in Etame with definite 2 firm wells to drill there with an option of a third that we may consider during this program. And then the rig would then move to SEENT where we plan to drill a gas well for field fuel to reduce our diesel consumption. And then it would -- if we don't exercise options, we'll then move to Ebouri with the 2H workover -- sorry, the 4H workover and then a position on 5H drill. So it's quite an extensive program. We can be doing up to 10 wells. However, what we're trying to cycle in here is how the first wells are performing and trying to make a judgment call as to when we call off the options to minimize the amount of rig moves we have within the field.

Jeffrey Robertson

Analysts
#13

So the current -- or maybe it's a little bit revised from what you talked about in prior quarters, creates a more efficient drilling program with the rig. Is that what you're trying to explain?

George Maxwell

Executives
#14

Yes. I mean before -- because we initially were focused on moving, I guess, to Ebouri as the first location. But because we've seen strong performance on 2H, strong performance on 4H, and that has necessitated that, perhaps we go for -- fill up the Etame slots first. In addition to that, over the last 6 or 7 months, we've seen a depletion of the gas well in SEENT, and we've seen an increasing consumption of diesel in order to power the field. So that kind of brought forward that gas well in SEENT in order to alleviate the OpEx concerns that we have for increasing diesel. So it's just a basic resequencing. But what it does make us do is consider when we exercise options, the timing of those options to minimize the rig move because the options that exist, they exist in SEENT, they exist in Etame and they exist in Ebouri. So what we try to do is get our ducks in a row for exercising those if and when we want to minimize moving between the 3 main platforms in the field.

Jeffrey Robertson

Analysts
#15

Can you put a range on the -- dollar range on the amount of OpEx savings that you might be able to achieve with the new gas well that you plan by displacing diesel as fuel?

George Maxwell

Executives
#16

It's probably somewhere between $350,000 and $500,000 a month.

Jeffrey Robertson

Analysts
#17

You talked about Ebouri for the 4H well performing well to the crude sweetening chemical process that you all are testing in that well. How does the performance there impact the ability to monetize the reserves, which have been stranded since that field was partially curtailed back when the H2S concentrations increased?

George Maxwell

Executives
#18

Well, some of those reserves already came back when we put forward the plan in 2024, and we confirm the viability of that plan. So some of the reserves came back under the 2P scenario. Certainly, when we look at the issue on 4H and the performance of that well, given the age of the ESPs and the completions, that's certainly performing well. And there may be a narrowing of the opportunity to work over that well because it's performing so well, and there may not be enough reserves left in that well to justify a full workover. When we then look at 2H, 2H has considerable reserves still to produce. And the workover in 2H is really to facilitate our ability to inject the chemicals downhole will be much more efficient in the scavenging operation for the H2S. The key, in my view, is the opportunity to the sidetrack on 5H which I think holds a great opportunity for enhancement of our position in Ebouri and really monetize. To answer your question, I think the bigger prize is on the 5H drill than the other 2 potential workovers.

Jeffrey Robertson

Analysts
#19

At the Capital Markets Day in May of earlier this year, this -- I remind people the slide deck is available on VAALCO's website under the Investors tab. The Phase 3 development program in Gabon, which is beginning now was expected to test 2P reserve volumes in excess of 10 million BOEs and potential incremental initial production of about 16,000 BOE per day. Given the timing of the program and how you have it laid out now, George, should we expect those projects to be evaluated in time for later 2026 production and year-end '26 reserve bookings?

George Maxwell

Executives
#20

Almost definitely, I would say. I mean as I mentioned, the workovers, such as the workover in 2H doesn't really enhance any reserves. It's there to make it more efficient to produce with the scavenging opportunity on the downhole, the workover for downhole injection. But certainly, when we look at the Etame position and in particular, the Ebouri position, those are where the -- primarily the most of the reserves will come from. There is an opportunity for an optional well on SEENT, which is a little bit more complex, a little bit more difficult to drill, a little bit further outreach from the platform. But when we look at the main contributing opportunities, they reside within Etame and within Ebouri. So we're looking at potentially the drilling phase completing depending on how many options we exercise somewhere towards the end of Q3 in '26. So that does give us enough time to ensure that the results of that are fully within our 2026 reserve process.

Jeffrey Robertson

Analysts
#21

As I said earlier, the 2026 financial and CapEx guidance won't be released until March of next year. But with the 5 committed wells in the Gabon campaign, can you put a rough CapEx range around or an estimated range around those wells for us?

George Maxwell

Executives
#22

Yes. I mean it's -- we've had obviously slipped some of 2025 CapEx into 2026, and that value was somewhere around, I think I mentioned earlier, about $40 million of that in relation to the program slip. And we've -- on a gross spend basis, we were always budgeting around $250 million. So a net to VAALCO about $160 million on those wells, and we've quoted that previously in our Capital Markets Day. So you can work out probably somewhere in the region net to us of about $100 million, $120 million may slip into 2026 for the CapEx program from the previously disclosed information. Now when we come to do our CapEx guidance, we'll also have a lot more granularity to that as it folds out to the totality of our investment program across all our activities. But that's a rough rule of thumb for Gabon for the drilling side.

Jeffrey Robertson

Analysts
#23

Elsewhere in Gabon, a seismic program could commence on the Niosi and Guduma exploration licenses later in 2026. You talked about the performance of the reservoirs at Etame exceeding expectations. Should we expect that some of that outperformance at Etame and the upcoming development campaign to have an impact on the seismic interpretation and prospect development on those licenses? Or are they in some sort of a different petroleum system?

George Maxwell

Executives
#24

Well, they're all in a very similar petroleum system, but we're talking about connectivity of these systems. And I don't believe we've seen from the existing seismic within the Etame field block that level of connectivity. Now the seismic activity, yes, were due to commence in early -- late '25, early '26 for Niosi and Guduma, and what we do believe, and we've put this up on the map, and I think our partner, BWE believes also is that we have active hydrocarbon systems from Etame down south through Dussafu where BWE operate. So this seismic program is key to identifying those active -- potentially active hydrocarbon systems and where potential connectivity can be made, not just -- as I said, I don't think we've got connectivity in the hydrocarbon systems, but the connections back to production facilities is also key. And that's where we see potential life extensions both in Dussafu and in Etame, where near-field opportunities to tie back to existing infrastructure is where we see the prize on the seismic. So on the seismic taking place, acquisition, then interpretation is going to be all through 2026 is what I understand.

Jeffrey Robertson

Analysts
#25

If we shift gears to Côte d'Ivoire, the operator of the Baobab field expects the FPSO to return, I think, late in the first quarter of 2026. And I think you said on the call recently that the hookup should be completed during the second quarter. George, just from an operating perspective, how much time does it take -- generally take to restore the production to -- or restore production in the field to the levels that are approaching where it was when you took it offline?

George Maxwell

Executives
#26

Well, we've got -- in the program that we've seen to date from the operator, I think there's about a 70-day planned for the hookups. So that's picking up the flow lines and reconnection back to the FPSO. Also during that time, obviously, we've got systems commissioning, et cetera, will all run parallel to that. And that's really that 70-day period is where we see between the arrival of the FPSO coming into the field which is going to be sometime during March from a January 31 sailaway and the recommencement of production sometime during May. So those time lines are currently still within the project plan, and we're not seeing any movement on that. As we mentioned earlier, we're still seeing sailaway date for 31st of January, which is a key date where all the work on the vessel has been completed and the contracts laid for the recommissioning. So it's -- right now, what we still haven't seen yet is the complete start-up sequence for the wells, and that will really then dictate what levels of production will come on when. We've got some forecast for that. But until we see the full start-up sequence, it's difficult to comment on that. That's something we'll definitely be giving guidance to during Q1 when we give our 2026 guidance.

Jeffrey Robertson

Analysts
#27

Do you expect the FPSO upgrades to have an impact on operating costs and operating efficiency kind of like what you have -- what you saw when you reworked the infrastructure at the Etame field?

George Maxwell

Executives
#28

There's a couple of points there. One, this is slightly different from what we did in the Etame field. In the Etame field, we moved a lot of the processing equipment onto the platform. And therefore, we've just got a dump storage vessel, and we moved and modernized all the processing equipment through Etame. Here, what we're doing is -- or what the operator is doing is effectively reconditioning the existing processing plant. So we're not seeing significant upgrades in the processing plant from that standpoint. But we are seeing, obviously, renewals, renewals of steel, confirmation through the tank, the recoating of the tanks. We're seeing the class issue being renewed for the vessel through its tenure to end of field life or beyond. So we would expect to see some efficiencies through reduced downtime for maintenance. We've also got added engineering capacity on for some of the -- to accommodate Phase 5 drilling and to accommodate full lines for Kossipo. So there are efficiencies in there that will come with volume when the Phase 5 comes in on a per barrel basis. But dollar-for-dollar reduction, I think best way we'll see that is once it's back on stream and see where we are for maintenance downtime. That's a key that we'll be focused on.

Jeffrey Robertson

Analysts
#29

You mentioned Phase 5 development. So the development program in Baobab is expected to begin after the FPSO is put back in service. You talked about some of the upgrades. Do -- should you expect those to shorten the cycle time of connecting wells or new wells into production?

George Maxwell

Executives
#30

There's not a shortening of the cycle time. I mean the upgrades that have been done to the FPSO in order to accommodate Phase 5 on Kossipo facilitates that connection. So it means there's less -- there's not a requirement for engineering work that would have been required if we hadn't taken the vessel offline. So it's not -- I don't see any shortening of the connection time or the hookup time. It's just that now we have a topside position that can accommodate those additional production lines.

Jeffrey Robertson

Analysts
#31

Again, at Capital Markets Day, the Phase 5 development plan as it -- or program as it was laid out at that time, talked about targeting gross reserves of about 33 million BOEs with a peak gross production of about 27,000 BOE a day. How should we think about the reserve and production impact of Phase 5 in 2026? Or would that be more of a 2027 impact?

George Maxwell

Executives
#32

Yes. Right now, we see probably a late Q3 spud date for Phase 5. So that's definitely going to fall into 2027. I don't see us -- and again, we haven't had detailed discussions with the operator, but I don't see us getting enough wells down to make any significant reserve impact in 2026.

Jeffrey Robertson

Analysts
#33

You mentioned the Kossipo development project as a potential subsea tieback to the FPSO. Can you share any color on the timing of that project and what it could mean?

George Maxwell

Executives
#34

Yes, we still have time for those discussions with the operator. I think when we put that in our capital markets plan, we had it somewhere around late '27 into 2028 for that. But if you just think of that potential time line for the establishment of well locations and then equipment ordering for subsea trees, we're probably into the 2028 cycle time by the time we've got that ready fully planned, we've got an FDP planned and submitted to the government. And then we start to look for rig and equipment. So it's probably going to be a 2028 start-up position at the earliest.

Jeffrey Robertson

Analysts
#35

George, if we move to Equatorial Guinea, you talked recently about continuing to evaluate alternatives to develop the Venus discovery in the most economic fashion on Block P. You mentioned that a subsea tieback to a facility located in shallow water on the shelf could become the preferred scenario. Can you talk about how that type of a development, number one, impacts the decision line toward an FID and ultimately timing of when that could begin producing?

George Maxwell

Executives
#36

Yes. So the original plan of development was a MOPU on the shelf with a long reach drill from the shelf through down into the reservoir. And what we tried to do in the FEED study was look at how can we switch CapEx for OpEx in a field that has a relatively short life of about 60 months. It's high production short life. And when we did the FEED study, part of that was to look at can we look at leasing a MOPU and planting it on the shelf and how do the economics work? And going through all of that position, we did get to a point where the proof-of-concept was definitely there. We'd already established that. The proof-of-concept and the long reach drilling was there. But what it also highlighted was drilling extended reach and the angles of attack coming into the reservoir on a 3- to 4-kilometer basis. We're giving some high-risk factors, and it was possible, but it was a high-risk factor. So what we jumped to was how does that look if we did a vertical drill. And all of a sudden, all the risk factors on a vertical drill given how shallow the reservoir is from the seabed disappear. And it takes -- it gives us the opportunity to have much more accurate well placing especially for the water injector, which gives us a greater confidence in the sleep efficiency for the reservoir. And therefore, when we did remodel the reservoir simulation model, we came back and reconfirmed the potential of this field to produce 20,000 barrels a day. So taking that derisked position from a vertical drilling solution into account, we then said, okay, in order to be able to do that, we need to look at the efficiency of how do we do subsea tieback to topsides. And that's really where we've extended the FEED to look at the opportunity set where another FPSO coming in and that tieback opportunity for location of trees and timing, et cetera, how does that stack up against the surface MOPU that we would have on the shelf. And that's where we've kind of extended the study to, and we've looked at those opportunities. And when we look at the economics, now, of course, a vertical drill from a drillship on a day rate basis is much higher than a jack-up on the shelf. However, the time is about -- is less than 1/3 to drill those wells from vertical than it is to drill from the MOPU. So from a drilling perspective, it's almost a wash. And so therefore, we're looking at how efficient can we get on the top side. So that's really what's moved it from that extent to a simple MOPU and storage at the shelf. And it really was to try and derisk the 2 elements, the key elements for this study that came to -- came out of the study for me was, again, how resilient the reservoir will be if we get the water injection well in the right placing and the kind of benefits we can get from that in the order of the recovery factors. But certainly, it took away 90% of the risk factors and complexity on the drilling position, mainly because we can come into the reservoir from a much more efficient standpoint from the vertical versus the shelf drilling.

Jeffrey Robertson

Analysts
#37

Do you expect to be in a position with all the evaluation to consider an FID at some point in 2026 on that project?

George Maxwell

Executives
#38

I would certainly hope so. We -- I mean this project, we've demonstrated already, it has considerable value to the company, both in terms of production and economics. And it's just about balancing our capital spend with the commitments we have right now and making sure that if we were to enhance that capital spend, we're very firm on the execution plan in Equatorial Guinea to give us that return as quickly as possible. So there is a little bit of planning has to take place, so we don't overstress our capital position in the near term, but also make sure that we exploit as early as possible the value opportunities that can give us great returns to the company and to our shareholders.

Jeffrey Robertson

Analysts
#39

As I said at the outset, VAALCO has a project portfolio across multiple countries in Africa that expose it to significant reserve and production growth over the next -- over the coming years. Upcoming activity in both Gabon and Côte d'Ivoire could begin to crystallize some of that opportunity over the course of 2026 and 2027. George, just to wrap up on your -- the capital framework, can you talk about how you think about managing the program, which is essentially a multiyear-type program and opportunity set against the backdrop of $60 plus or so Brent oil as we look into -- at least today as we look into 2026 and how that impacts VAALCO's ability to maximize returns and continue your goals of returning cash to shareholders?

George Maxwell

Executives
#40

Yes. I mean clearly, we've got to focus on whenever we invest in the dollar, how quickly does that dollar come back to the company. So greenfield developments take some time and greenfield developments -- making the commitments on greenfield developments can tie up cash for extended periods of time. In order to commit to the greenfield developments such as EG or CI-705 that we're involved in as well, then we need to make sure that the near-term production and the operating cash flows coming from those near-term productions are coming back as quickly as possible. And that's where -- what we're investing in Gabon right now, enhancing that production and working closely with our partners there to ensure that we not just provide enhanced production, but we provide further longevity to that field. And it's worth remembering for Etame that when the company first entered that in 2002, it anticipated 5 million barrels to be recovered. We are currently not far off of 150 million barrels of production. So this is definitely an asset we want to invest in. It's definitely an asset we think we can continue with its longevity. We then couple that with the near-term production opportunities in CDI and where we are with the investments that we're making with our partners there and the investment in, again, enhancing the longevity of CI-40 right through to 2038 with the refurbishment of the FPSO and the commitment to at least Phase 5 and drilling programs to again enhance that recovery. Those are the -- for me, the cornerstones of where our investment profiles will be because those are the shortest time frame for those dollars to come back. Now when those dollars come back, we then have the choice. What do we do with those dollars? Do we go after our greenfield opportunities and also provide a return to our shareholders. And this is where we have the balance. We have a portfolio. That portfolio is there to ensure near-term monetization, but longer-term operations through into the 2040s. So the company has a visibility way beyond the next 2 to 3 years. And it's balancing those activities because we have to continue to invest. We can't just manage depletion because that is -- especially at lower oil prices, that's ever increasing circles. There's only one way that's going to happen and operating cash flow goes down. So we have to invest in order to enhance the production and manage our cash flows at these low commodity prices. And I think where we are right now, we've got lots of opportunities. I would love to have an endless source of liquidity to go after them all today, both human resources and monetary, but we can't. So we have to balance that with recognizing where the near-term opportunities deliver the near-term returns to both the company and the shareholders.

Jeffrey Robertson

Analysts
#41

Well, I think, we'll leave it there for today. I know with the portfolio you have, we'll have plenty of opportunities to host another fireside chat as some of the -- as we get closer to the start-up of production in CI and progress on the development campaign in Gabon. So I want to thank you for taking the time for joining us today.

George Maxwell

Executives
#42

Thanks, Jeff, I look forward to it. And certainly, as we know, we started the drilling program. So by March, we're going to have an awful lot to talk about between Gabon and CI-40.

Jeffrey Robertson

Analysts
#43

Good. For our participants, I want to thank you for joining us for today's fireside chat with George Maxwell from VAALCO Energy. Our research can be accessed from our website, www.watertowerresearch.com. The views expressed in this fireside chat may not necessarily reflect the views of Water Tower Research LLC and are provided for informational purposes only. This fireside chat may not be redistributed or reproduced without the written consent of Water Tower Research and should not be considered a research or recommendation. WTR is an Investor Relations firm and not a licensed broker, broker-dealer, market maker, investment bank, underwriter or investment adviser. Additional disclaimers can be found at watertowerresearch.com. George, once again, thank you for joining us today.

George Maxwell

Executives
#44

Thank you very much, Jeff. Look forward to talking to you soon.

Jeffrey Robertson

Analysts
#45

Thanks.

George Maxwell

Executives
#46

Bye-bye.

For developers and AI pipelines

Programmatic access to VAALCO Energy earnings transcripts and 32,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.