Vestas Wind Systems A/S (VWS) Earnings Call Transcript & Summary

May 5, 2020

Nasdaq Copenhagen DK Industrials Electrical Equipment earnings 72 min

Earnings Call Speaker Segments

Henrik Andersen

executive
#1

Good morning, everyone, and welcome to Vestas' Q1 presentation. First of all, I will say we didn't choose the music ourselves, so would you just leave that out to another atmosphere on another day. I will also say, on behalf of Marika and myself, we've been looking forward to this investor call. First of all, it comes on the back of very intensive communication with a lot of our other stakeholders, namely customers and colleagues. And therefore, let's go through our first quarter and also how we have performed, but not least also how we are addressing the current lockdown due to COVID-19. Disclaimer, you know all about. So the key highlights of Q1. First of all, safety first in this very challenging environment. I will comment on it much further in the coming slides on how we are doing in the COVID-19 crisis and what we have put in place and how we're dealing with it. The increased order intake, you knew from the 7th of April when we said we had an order intake of 3.3 gigawatt, up 10% compared to Q1 2019. That leads us to an all-time high order backlog of EUR 34 billion. And in the quarter, we had revenue and profitability broadly in line with our expectations.

Henrik Andersen

executive
#2

Revenue rose 29% to EUR 2.2 billion. Profitability took a hit from some low growth margin during the quarter, and we'll return to that point later. Once again, Service delivered a stellar performance in the quarter. Organic growth came in at 12% versus Q1 2019, with an EBIT margin of 26%. But before diving into the financials, let me give you a quick overview of how COVID-19 is affecting us in the first place, how we're responding to it, and say a bit more about how we keep performing through this crisis. So I'll point you to the left chart, over here in the corner, where over the last couple of decades we've seen renewable clearly striving to become critical infrastructure on the energy side. And that has indeed happened. So I think in all of our plus-70 countries where we operate, we're regarded as critical both for energy production and for infrastructure, country by country. That also means that with all our employees out working diligently on site, in factories and elsewhere, the health and safety measures for all our employees are, of course, absolutely top priority for us.

Henrik Andersen

executive
#3

We'll say a few words about that. But like I mentioned here, during this whole crisis, 25,500 people have been working hard on COVID-19. And all in all, as of last night, we had 30 cases, with 21 people recovered. So our protocols actually work very well. Very early on, when we had that discussion in China in February, we insisted firmly that we would run Vestas under business continuity across all our Vestas operations globally. I think that also here has meant there's been a clear ambition and an insistence from both ourselves and all our partners across the supply chain that continuity be one of the prime drivers throughout. What we see now, as countries begin talking about reopening again, is that, I'd say, our mobility and access to site is of course very important. We can also see that access and mobility to site has in a number of cases been questioned or challenged. But I'd also say here that thanks to many internal colleagues and many external stakeholders, namely customers, we've had enormous support in getting access to all the sites where we're required to perform work, either as a service or as a construction, and also in our factories, which has been really, really strong.

Henrik Andersen

executive
#4

Now, if we look at the worldwide picture and the business climate surrounding it, as I mentioned, it's plainly regarded as critical infrastructure at this point, and that's something we've witnessed. To illustrate, across most of the countries where we operate, the maximum stretch any of our plants has been shut is 2 weeks. That was how long it took before we were partially permitted to resume operations in China. We've experienced comparable stop-and-go situations in certain European nations too. In the U.S., though, we've had almost no downtime in terms of our performance and keeping the factories running. We're based in Denmark, so I also want to express gratitude to our colleagues at the Danish factories. You hear that Denmark was shut down entirely. In practice, from 13th of March, when Denmark closed its borders, we've maintained a very tight relationship and very tight collaboration with DSV. So at every moment since then, we've succeeded in bringing all our components and required raw materials into the factories, and we've also succeeded in getting our finished products back out again.

Henrik Andersen

executive
#5

And it does in fact work. We should also note here that, given the global situation, it matters to recognize we moved from a pandemic into what everyone is now clearly discussing, the economic crisis. We won't speculate on how severe it might become. But it's clear we are now urging everyone to genuinely factor the green agenda into recovery programs as we begin rebuilding and reopening societies. As for Vestas and how Vestas is run, I believe we have -- we found we'd had some time rehearsing that back in February with the China days, but we assembled a cross-functional crisis management team. Those colleagues have labored utterly tirelessly through this entire crisis, and I cannot thank them enough for holding Vestas together so tightly as an entity. You'll all understand that most countries have adopted their own individual measures, whether to close, partially close, or take some action of their own. So because of that, I think operating a global company with that many countries active genuinely demands something special where the crisis management team is concerned, along with the entire discipline of following the protocols. So once more, a heartfelt thank you for how this has gone, but I think it also offers everyone some proof that even large companies and operations can be run safely while society stays open.

Henrik Andersen

executive
#6

I'd also like to thank a few of our partners once more, since they've collaborated closely alongside us. They adhered to those same protocols. And because of that, they too were granted an exceptional opening in the majority of nations where our operations are located. So having said that, I'll note that yes, we will have taken certain actions as well. There are probably areas where we could have improved. Still, if I were to attach a percentage, we are — on 9 out of 10 decisions, we're absolutely pleased with our performance in COVID-19 up to now, and we currently possess genuinely extensive experience to carry forward should this prove to be an ongoing or recurring situation for us. Yet we're firmly convinced that we can continue running Vestas even amid such harsh, challenging circumstances. Let me briefly walk you through market share. I won't devote much time to this, only to mention that once the final figures were released spanning '18 and '19, when China is factored in, as you'll notice at the left of '19, we land at an 18.1% market share within a total onshore installation market of 53 gigawatt.

Henrik Andersen

executive
#7

Now, if you look to the right side, which is also the picture when China is excluded, installations were more or less flat from '18 to '19, and we're running in the 36% to 35% range on that. I think another point this slide makes is simply that '19 also showed this is increasingly a game among the 3 top global companies, which now hold a combined consolidated market share above 75% — the 3 global OEMs. Let me then get into more of the quarter's details. As you already saw on the 7th of April, order intake came in at 3.3 gigawatt. Those orders came from 21 countries, and China, Sweden, Poland, and Brazil were among the biggest contributors in Q1 2020. Turning to ASP, ASP came out at EUR 0.72 million, but you'll also note that with a somewhat lower scope in China, once we adjust ASP for China, the underlying ASP stands at EUR 0.77 million, adjusted for China. So once again, pricing stayed stable in Q1 as well. That brings us to a consolidated order backlog of just under EUR 16 billion on the turbine side, and EUR 18 billion on the service side, when we look at it.

Henrik Andersen

executive
#8

That works out to EUR 6 billion of year-on-year growth, which is almost 20% versus the same quarter a year ago. A brief update on the Power solution: we now have 115 gigawatts of turbines installed around the world. That also means we have displaced 154 million tonnes of CO2 emissions annually, and it leaves us with a 17% cumulative global market share across all installed turbines. Turning to the Q1 '20 highlights, I would say our very strong worldwide push to keep the business running has been very evident throughout this quarter. We can see that a number of the auctions scheduled in and around 2020 have either been postponed or delayed by, at least as far as we can tell, 1 to 2 months. And I think that is exactly as expected, since some auctions call for physical presence as well as, to some degree, knowledge of the land and of land allocation. Looking then at the order increase and order taking in Q1, you will really see that we have had higher order intake, and particularly when we look across EMEA, where we had a very, very good Q1.

Henrik Andersen

executive
#9

Order intake in the Americas has come in lower. I think we already pointed out by the end of last year that we believe it will take a bit more time to see how 2021 will pan out for the U.S., because we are still in a very, very busy year executing on the existing order pipeline in the U.S. Brazil partly offset that and therefore also contributed positively to order intake in Q1. So just below, you can see order intake across the Americas was 612 megawatt, down 63%. We had 1.9 gigawatt in EMEA, which was 166% higher. And we had 0.8 gigawatt in APAC, 27% up. So with that, go to the Service business. As mentioned here or can see here, we are closing in on celebrating our Service business passing 100 gigawatt of onshore turbines under service. Clearly, it's something we expect to happen in the coming quarters. In the quarter, we also saw that 18 years was the average duration on new contracts signed, which is up from the 17 years we had by end of last year. And we are now active in 70 countries in total. When we look across Q1, I think encouraging for our long-term strategy in China.

Henrik Andersen

executive
#10

We have seen a 20-year full-scope services order in China, and that aligns very closely with the ambitions we hold for China, both regarding the orders and the way our operations there are set up. You have also seen, on the multi-brand side, that we secured a Senvion turbine order in Australia totaling 126 megawatts, and our focus will remain on both our own capture and the multi-brand approach. As for the breakdown of the service fleet below, I will leave that to you. Turning to offshore and MHI Vestas Offshore, this was again a busier quarter where order intake is concerned. So we have 5 gigawatts of orders installed. We have 3.4 gigawatts under installation as unconditional orders. And then, overall, we have 2.1 gigawatts of unconditional orders plus preferred supplier agreements. For the Q1 highlights, I will actually begin in reverse order by simply noting that MHI showed exactly the same dedication to keeping operations going. It was genuinely good to be there last week and meet some of the colleagues, since they too have been working diligently on operations and service throughout this entire COVID-19 period. As a result, they also experienced very limited interruption, for example with the Northwester 2 project.

Henrik Andersen

executive
#11

So that's almost finished right now. Then when we look at order intake, we recorded 589 megawatts of firm orders in Taiwan. And we also had firm orders in Japan — 2 wind parks, Akita and Noshiro offshore wind parks, which now consist of 33 V111 -- V117 turbines in Japan. So with that, I'll pass it over to Marika for the financials.

Marika Fredriksson

executive
#12

Thank you, Henrik. Now, looking at the income statement, I want to begin by noting that it matches what we had anticipated. You'll also notice revenue rose by 29% versus the same period a year ago. So clearly, we're doing our utmost to sustain that level of activity given the current conditions. Gross margin declined by 6.5 percentage points, and the main cause is the logistics difficulties we've discussed many times, along with supply chain bottlenecks. Unfortunately, the COVID-19 situation has made that even worse. Two other factors weighing heavily on this quarter are COVID-19 on a standalone basis, plus a smaller service share and greater provisions, all of which hurt the gross margin. EBIT has clearly fallen, mainly because gross profit is lower. I'll come back to SG&A performance a bit later. Special items came to EUR 58 million this quarter, resulting from a write-down of a platform aimed at further optimizing our technology and simplifying that platform even more.

Marika Fredriksson

executive
#13

Looking at SG&A cost, I'd say it remains well under control. And obviously, as you can see, that's driven by volume. Keep in mind, this is a 12-month rolling figure. We're down to 6.1%. So I'd call it well under control and, obviously, a very important factor for us given the circumstances everyone finds themselves in right now. Our Service business continues to be very strong — not just in terms of growth but also high profitability here in the quarter. So it's a very stable business, also in more difficult times like now. And obviously, the Service business is also very dependent on access to sites. So there, we've done a good job trying to keep things as normal as possible. MHI Vestas — I think Henrik mentioned the overall performance. Activity level is, to no surprise, down here in the quarter and in this year, but EBIT margin has improved year-over-year. And consequently, there's a EUR 6 million net profit here in the quarter in total. So let's have a look at the change in net working capital. We continue to build inventories. So obviously, we are expecting and we also see a continuous high activity level.

Marika Fredriksson

executive
#14

Naturally, the closer you get to a quarter, the clearer things become, and as you're aware, we're already in Q as we speak. We also have down payments and milestone payments that partially offset the liabilities sitting here in the quarter where inventory is concerned. And during this quarter, we've paid out a bonus to employees globally. Looking at cash flow for the quarter, it's clearly been hit negatively by operating activities. Other than that, the largest effect is, once again — no surprise, and it was planned for — the movement in net working capital. Our net interest-bearing position remains strong. And clearly, we maintain an ongoing emphasis on cash discipline throughout the company. Here you can see total investments are somewhat lower than a year ago, and we're also referring to CapEx below EUR 700 million for this year. And clearly, that stems from the optimized product platform I mentioned earlier in connection with the P&L. Warranty provision and lost production factor. Here, as you can see, warranty provision has gone up versus last year, and the lost production factor is up slightly.

Marika Fredriksson

executive
#15

Keep in mind that we’ve rolled out plenty of new products. We also have a very large volume that we’re working through right now, and that affects the lost production factor in this quarter. Our capital structure is still solid and sits well under the target, and liquidity stays strong, with EUR 2 billion in cash on hand. On top of that, we have credit facilities totaling EUR 1.55 billion, plus a new loan facility of EUR 1 billion that we signed on May 1, 2020. With that, I’ll hand things over to Henrik.

Henrik Andersen

executive
#16

Thank you, Marika. I really want to say thank you as well to the executive team, and to Marika here too, since you've been with us from 2013 onward. And like I mentioned, you've witnessed shifts in the cyclical side of the global economy as well as other parts, and I truly appreciate the prudent and conservative approach to the classic disciplines that we see here. We have the facilities ready should this also disrupt the world economy on a broader scale. But cash, EBIT and growth are clearly on our priority list. Moving to the outlook, I'll just briefly note here that you clearly saw on the 7th of April, when we suspended the guidance. It's also fair — and this is how we run Vestas and how we will keep running Vestas as we see it, we're absolutely still running Vestas in line with the initial plan. We still have the same targets, how we work through diligently, both the projects region by region and also the manufacturing. And I think we're assured from our daily discussions with operations that we're actually doing that pretty well, and we're positively assured about how that is running.

Henrik Andersen

executive
#17

That's also the reason we're stating that hitting our guidance remains a realistic goal, and it's the way we operate internally. We don't treat COVID-19 as a justification for failing to do the right things. But it's also evident that we, along with most societies worldwide, are only now beginning to open up again. So it's likewise fair to say that until we have complete visibility, we won't reinstate any guidance for the year. What we can at least state here today is, of course, that the Service business continues to perform very well. For the year, we expect it to grow approximately 7%, with an EBIT margin of around 25%. And then, as Marika rightly alluded to regarding the changes we made in our late April press release, the total investment with the optimized product portfolio will still come in below EUR 700 million. With that, I'll say thank you and also hand things over to the operator.

Operator

operator
#18

<<operator_script>> Kristian Johansen of Danske Bank has our first question.

Kristian Johansen

analyst
#19

Yes. So to start, you said a number of times, I believe, that the Q1 results matched what you had originally anticipated. But clearly, when you look at where consensus had the gross margin, it isn't really in line with what we were expecting. So — particularly since you brought up logistic challenges and supply chain bottlenecks, along with commissioning of projects delayed from 2019, could you go into a bit more detail on that impact, and especially on how much the logistical challenges and supply chain bottlenecks have accelerated relative to Q4? And for both of those factors, what do you anticipate over the coming quarters? Will this level off? Or what are you seeing at the moment?

Marika Fredriksson

executive
#20

Right, yes. And obviously, in this quarter we have a few projects that got delayed. And as — I believe we've mentioned this on many occasions — any adjustments to our planning, or any rerouting, or anything along those lines, will carry a higher cost. And that's clearly visible here in Q1. That said, Q1 is roughly in line with what we ourselves expected. From a profitability standpoint, we anticipated a more modest quarter. On top of that, we also raised the warranty during the quarter, so that's a gap of EUR 34 million. And we've also got what you might call the isolated corona impact — approximately EUR 10 million in the quarter. We also see a lower percentage coming from the Service business, purely because volume, or revenue, is higher here in Q1 of this year than it was last year. But it's the logistical challenges and transportation that are costing us the most in this quarter. And the visibility we have looking ahead tells us we won't face the same headwinds on that front. But then, obviously, going forward — we have visibility over Q2, though we don't fully have a crystal ball for what happens beyond that, but there's no indication it will be bad for us.

Marika Fredriksson

executive
#21

But I mean, the logistical hurdles and the expense for them — my expectation is that this will keep going to some degree. And just to give a really straightforward example, Kristian: I mean, we get a lot of inbound. And when supplier delays hit, or we can't even move things and need to make it up to customers, we use air freight. And at the moment, there aren't even flights to book. So the logistics side is incredibly cumbersome when it comes to securing supply, and it's also expensive when we do find someone who can actually haul it for us. So what we're attempting to do is, obviously, live up to the customer agreements. Because if we don't, that ends up being even more expensive for us on its own, and also down the road when it comes to customer trust.

Kristian Johansen

analyst
#22

All right, so I want to be sure I've got this right — you're anticipating that the headwinds tied to the logistical challenge will be smaller, yet they'll still be present. Is that what you mean?

Marika Fredriksson

executive
#23

Yes.

Kristian Johansen

analyst
#24

Great. For my second question, you also said on auctions that delays of a few months have been observed. When you consider the order pipeline and the discussions with customers about possible new orders, what amount of delays or cancellations are you seeing at this point?

Henrik Andersen

executive
#25

Generally speaking, I don’t believe we’re seeing many delays. There are certain physical delays — which is likely what we’re discussing at this moment — involving simply moving papers and other materials from one place to another, and that slows things down. Then, when it comes to finalizing it, delays can occur since not every region of the world operates as electronically as one might expect. So, Kristian, some of those projects will experience certain delays. But thus far, as we already mentioned in Q1, we’re actually positive about how effectively that portion continues to function. And we aren’t seeing any impact, really, for the near-term quarters ahead.

Marika Fredriksson

executive
#26

And to verify your question, on the cancellation side as well, we haven’t observed anything like that. And I believe it’s also favorable with regard to the order intake we have in this quarter. You can plainly see a solid level of activity on a continuous basis.

Operator

operator
#27

And our next question comes from Vivek Midha at Deutsche Bank.

Henrik Andersen

executive
#28

I didn’t…

Vivek Midha

analyst
#29

My apologies for that. First, may I ask about the U.S.? You mentioned it, and it's hard to get a clear signal there. Could you perhaps share some sense of your discussions with customers and whether they might be altering their plans for '21 and over the midterm? Second, you brought up the 20-year service contract in China. I'm curious what your view is on how that market will evolve after the auctions, both from a service perspective and regarding market share development?

Henrik Andersen

executive
#30

Alright, I'll begin with the U.S. And I think we've consistently stated that from an orders standpoint in '21 and '22, a great deal of planning is still underway. But I also believe that, at this point, customers are, naturally, about 99% focused on what's happening in 2020. So here, we're diligently collaborating on the existing pipeline. We're collaborating on the scheduling side. And naturally, as you might expect at this moment, certain reschedulings are occurring, which likely shifts a number of the weeks. And I think it's also reasonable to say that we'll now begin to see a portion of the projects slipping some weeks into Q4. I think everybody attempted to steer clear of Q4 when we talked a quarter or 2 back, but I think it's reasonable to state at present that the delivery focus is 100% on what's happening in 2020. That's what you can also observe we're getting well prepared for. And so, I'm also quite pleased that our manufacturing and supply chain are functioning to the degree they are at present, since that provides us with confidence toward it. So I think, as we've consistently stated, it likely requires until midyear before we begin to see some traction.

Henrik Andersen

executive
#31

There's clearly plenty of discussion out there, though I think part of it is also about where the PTC lands at year-end and how that might impact '21. And I'll come — I don't have more than what you've probably seen as of yesterday, so there's no news to report on those discussions. On China, we've consistently spoken about profitable growth there, and that means growth that's profitable and tied to conversations with customers. Broadly speaking, we don't accept orders that fall below our global profitability threshold. And naturally, it's genuinely good for us to see — we believe that once the feed-in tariff is scheduled to finish at the end of December, China will likely move more toward the free market, and as a result maintenance and service suddenly also become part of the value proposition, as well as part of how you seek to boost the efficiency of your renewable investments in China. We believe we'll have a role to play there. We haven't set any percentages or market share targets for that. We want to remain, and we will remain, a leading global player in China, but the market share we hold will be a profitable one.

Operator

operator
#32

The next question comes from Akash Gupta at JPMorgan.

Akash Gupta

analyst
#33

I've got 2 questions, if I may. The first one concerns the Service business. So you're restating your guidance from the full year results. The question is, what portion of that 7% revenue growth is already covered by your Service backlog of more than EUR 18 billion? And what kind of new or additional sales input would you need in order to hit this 7% growth target?

Henrik Andersen

executive
#34

I don't believe we have anything definite — well, we do have the orders. As you can see, there's the order backlog, and that doesn't really drive when different things get activated — it goes live when it goes live. And we've begun the services contracts, so that means more planes in operation. Then you'd understand that when you look quarter-on-quarter, it isn't evenly distributed in a Service business as we see the quarters. So because of that, we expect this is the visibility we have for the quarters ahead in the Service business, which indicates that a few of those quarters will come in slightly below the first quarter's 12% when compared with the quarter — the first quarter of 2019.

Akash Gupta

analyst
#35

And as a follow-up, a couple of years back, you—or Vestas—announced a strategy of putting money into projects to drive growth, and over the past couple of years we haven't really seen much investment happening in co-development. So my question is this: in the current environment, where there may be some headwinds in the credit market that could leave some projects struggling otherwise, will you be more open to co-development?

Marika Fredriksson

executive
#36

I don't believe we hold a particular position on providing compensation. From the start, we've stated that whenever customers would like us to take part in co-developing or developing projects, we're ready to do so. Our stance, then, remains unchanged. And we'll carry out — we'll apply the same valuation to a co-development project that we'd apply to any other project. The terms and conditions must be right before we commit to it. And clearly, wind conditions, along with how adequately they're assessed, matter just as much as they do for our ordinary business. So from that standpoint, our methodology hasn't shifted, Akash.

Henrik Andersen

executive
#37

And it's a small thing. So because of that, it won't...

Akash Gupta

analyst
#38

So we shouldn’t — we shouldn’t be looking for any increase in co-development during the remainder of the year,

Marika Fredriksson

executive
#39

No, like I mentioned, we proceed only when the right project is in front of us—and that's exactly what we're delivering on. Obviously, we already have Lake Turkana, where we hold a stake. We also have the Sweden project together with PKA and Vattenfall—we hold a 40% stake there, and that one is coming to fruition next year.

Operator

operator
#40

Our next question comes from Lars Heindorff at SEB.

Lars Heindorff

analyst
#41

I’ve got two questions as well, if I may. The first is about order intake and what your capacity looks like for this year. In the first quarter, there was what I’d call perhaps an unusually high proportion of orders from China, all of them for deliveries during this year. And in fact, we saw another one of those the other day. For quite some time now, you’ve said that the backlog is completely full for 2020, and still we’re seeing these orders to China. So the real question is, I suppose: do you have room for additional orders of that type—meaning, can you actually handle more? And do you have the capacity to deliver them this year? That’s the first one.

Henrik Andersen

executive
#42

I can assure you that we wouldn’t have signed those agreements if we weren’t able to deliver on them. So we had — and when that situation exists, naturally, you’ve got some supply chain capability in China with an open window for it, and so we’ve set aside some capacity in that area. So it’s fair to say that when a situation like the one in China arises, where both we ourselves and some of the partners we work closely with have capacity, then we’ll take advantage of that. And naturally, you can appreciate that if something is manufactured and produced in China, the transport and supply chain challenge in today’s environment is considerably smaller. So that’s how we’ve gone about planning it.

Lars Heindorff

analyst
#43

Okay. And that's not — because I gathered a bit that it might have to do with cancellations somewhere else, which let you take care of those orders for China.

Henrik Andersen

executive
#44

Nope.

Marika Fredriksson

executive
#45

No. We haven't run any calculations.

Lars Heindorff

analyst
#46

Alright, the second point concerns the write-down you’ve been taking on the EnVentus platform. I’d just like to get some sense of whether that’s actually being driven by weak demand or whether it’s more of a cost exercise.

Marika Fredriksson

executive
#47

Demand isn't the problem. The order intake we've got makes that obvious. And second, we were optimizing — asking how we can simplify. From a cost standpoint, with the extra cost we carried this quarter, we're working to be as diligent as possible. But this isn't some random look at the platform, since we plan on a 5-year horizon for it. So we've clearly examined other opportunities that appear more fruitful to us, and that's the reason for the write-down.

Lars Heindorff

analyst
#48

So would I be right to assume the chance of another write-down of that kind is extremely, extremely small?

Henrik Andersen

executive
#49

And, Lars, when you begin developing a product — specifically this one — that means a halt. And the employees and colleagues connected to it are then let go as a result. And that's simply because we hold the broadest and deepest product portfolio for onshore in the industry. And what that means here is simply this: if 1 or 2 of those products we had planned to develop won't bring us anything new and can be covered by some of the existing ones, then the only right thing to do is that, if it doesn't yield the right return on those investments.

Operator

operator
#50

And the next question comes from Supriya Subramanian at UBS.

Supriya Subramanian

analyst
#51

My first question is about profitability, both for the quarter and for the full year. As you said, there's still a plan to aim for the original guidance, particularly on margins of 7% to 9%. Given that the cost headwinds would at least persist to some degree through maybe not all of the remainder of the year, but perhaps into 2Q and into 3Q as well. What's your plan to offset this so that you still meet the guidance? Or, put another way, what would need to go right for the 7% to 9% to still be achieved?

Marika Fredriksson

executive
#52

Yeah, to be very clear about Q1, we expected it to be more or less in line with what we presented. Obviously, we didn't anticipate the COVID-19 situation, to be clear on that. But all the indications we have for the full year—and obviously we're assessing that monthly—are that there's still a possibility for us to reach the guidance we provided to the market. The obvious thing is the best visibility we have right now is Q2, since we're in the middle of it as well, and that's what our comments are based on. Then we don't have a crystal ball, and no one else does, obviously, but the low-margin project we're alluding to here that has a big impact in the quarter, we don't expect in the coming quarters.

Supriya Subramanian

analyst
#53

Okay. Okay. And I just have one question regarding — in terms of — you also said that certain projects have experienced delays. Is there any exposure to liquidated damages tied to those contracts? And in that context, more specifically for the U.S. market, since this is a critical year when it comes to the deadline — there's a hard cutoff of December 2020 — so what happens if a U.S. project slips into 2021, both from the customer's side and what happens with PTC? Is there any possibility for them to still recover and essentially claim 100% PTC even if it slips into 2021? And then what would Vestas be liable for as well?

Henrik Andersen

executive
#54

Yeah, I'd prefer to stack by. And I think the current environment and legislation is that there's a hard stop on 31st of December, after which it can be sort of deemed and commissioned, and that will then be decided under the legislation. But I think that'll be a longer conversation, Supriya. But if we then look at ourselves, we generally don't have any LDs towards the PTC end of December, but we will have LDs for delays as normal in our industry. And therefore, we work diligently with all customers to get that plan. And that is, in more or less all of the cases, a very close partnership with the customer both in terms of managing the construction on site and also be ready on site and getting commissioned at time.

Supriya Subramanian

analyst
#55

Alright, a quick follow-up here. Regarding those projects — perhaps outside the U.S. — in other regions where some delays have occurred, based on your early conversations with customers at least, how well do you think it could potentially work — being able, perhaps, to invoke — or maybe not invoke — the force majeure clauses in the contract, so that you aren't liable for any damages?

Henrik Andersen

executive
#56

No, I believe that's accurate. I'd say essentially the entire globe is in a sort of force majeure situation at the moment. So I think we can't get around the fact that force majeure is a legal framework, but naturally, it's also a force majeure that in practice prompts the 2 parties to get on the phone and begin discussing how we're mitigating these matters. But if you look at certain countries worldwide where you must place, say, some of our specialists, foreign specialists, into quarantine, where they're put into 2 weeks or perhaps even longer quarantine, then you'll need to have some of those replacements arranged and so on, and that, naturally, will push some of these weeks. And I think there's a broadly shared understanding that this isn't solely a Vestas issue. It's a global issue rather than a Vestas issue. So I think, on the whole, our customers at the other end want insight, they want the in-depth discussions about the details, which is entirely understandable. But I don't think anybody has called me yet and said Vestas is to blame for it. That's certain.

Operator

operator
#57

And our next question comes from Casper Blom at ABG.

Casper Blom

analyst
#58

I have two questions as well. By the end of 2019, somewhat unexpectedly, we saw the production tax credit extended in the U.S., and even at 60%. Are you already seeing interest from customers to sign up for that, perhaps to make up for the PTC contracts that weren't signed yesterday — or sorry, last year? And do you have any indications regarding the levels of that? That's my first question. Second, given that you've had some delays and so forth year-to-date from COVID-19 and factories being shut down, are you already sort of making up for that lost time, given that you sort of say that reaching the original guidance is still possible?

Marika Fredriksson

executive
#59

Yes. So starting with the 60% PTC, Casper, I believe it's too early to observe what comes of that. And my sense is that it will track the usual pattern. So a signature of it will show up at the end of this year, rather than early. That isn't what we expect, given how busy everyone is — not just us, but customers too, in meeting the obligations we have this year. Then on the factory side, I'd say we've done very well. We face challenges around the world, or globally, in our industrial platform, but we've been good at maintaining the activity level while also securing and protecting our people from COVID-19 — just to be clear on that. The places where we have the most challenges right now are Brazil and India. Other than that, we're pretty much up and running, as you heard Henrik say earlier. And here in Denmark, I think people have been pretty fantastic about going to work, and we've done — our primary focus really is protecting the people, and that has worked fine. And then from a revenue perspective, I'd say that compared with last year, Q1 is good, but we also expected that to be the sort of slowest activity level of this year.

Marika Fredriksson

executive
#60

So it's tracking the usual pattern we see at the start of a year. And of course, "usual" is tough to pin down given these conditions. But from what we can observe, activity levels are rising. That said, we clearly require access to sites to ensure we can carry out the projects.

Casper Blom

analyst
#61

But just so we're very clear on this, that, let's say, average of 1 or 2 weeks that you've lost in various parts of the world — is it possible to make that up?

Henrik Andersen

executive
#62

We attempt to move production between our plants to keep things in balance. And I think, by and large, only a handful of our factories are dedicated to a single step that the entire value chain relies on. So because of that, we can offset this to a significant degree. We're also aware that certain components are currently either in short supply or something like that. And there, naturally, we collaborate tightly with suppliers to figure out how to make up that gap, whether by adding extra shifts or similar measures. But that's -- up to now, it's been working. Still, as Marika was kind enough to mention a moment ago, in Brazil and India there is some stop and go resulting from shifts in local guidance, so to speak, coming from the country on a day-to-day basis.

Operator

operator
#63

Dan Togo from Carnegie has the next question.

Dan Togo Jensen

analyst
#64

Yes. The first question concerns Power and EBIT, where we're trying to bridge the delta, so to speak, from last year's figure—a little more than EUR 100 million at the EBIT level. And Marika, you began by pointing to both currency and warranties having an impact here. What remains is some EUR 60 million to EUR 70 million in this bridge. A low-margin order is affecting things here as well, and there are logistical challenges and bottlenecks. Could you elaborate a bit on the remaining part? Just so we can get a grip on what exactly is caused by these bottlenecks and logistical challenges. And could we basically assume that these additional costs will escalate in coming quarters as you start, sort of say, to actually deliver more? Should we think that these costs will not actually be less as you push through more in coming quarters? That's the first question.

Marika Fredriksson

executive
#65

Yes. Dan, that's quite a lengthy question. Yes. So when you examine EBIT, I believe my earlier point was that there's a purely COVID-19-related isolation effect, excluding currency, which I haven't discussed. However, COVID-19 alone in the quarter amounts to EUR 10 million. Then there's the warranty increase, which is EUR 34 million versus a year ago. And the Service portion is also smaller because volume is greater, or revenue is greater, in this quarter. Those 3 together form a major component. And then, as I mentioned — or as you were noting — there are the logistical challenges, supply chain challenges and delayed projects. And to be very clear, when I refer to delayed projects or low-margin projects, the main issue there is primarily a cost factor. It isn't that these projects are low-priced. It's a cost factor, since the delays and shifts in our planning initially cost us more on these projects. And then everything has simply been amplified by corona regarding challenges on the logistical side. We haven't been explicit about the impact from logistics or transportation relative to the project, but they matter equally in this quarter when it comes to negative impact.

Marika Fredriksson

executive
#66

Looking ahead, sure — what we’re constantly trying to do is manage the total cost, and to carry out — as we’re doing at this moment, carrying out volume — it appears more expensive. Whether and when that will go away across that year, we aren’t certain. Still, as we’ve said, we continue to aim for what we stated at the start of the year. And one key element in maintaining those commitments to the market is clearly our ability to deliver on the revenue and the projects.

Dan Togo Jensen

analyst
#67

Right. That was going to be my follow-up anyway: what exactly has to be executed from Q2 onward for the guidance you're pointing to to remain achievable? What does the execution actually demand here? Does it have to be flawless? Or can it accommodate — so to speak — these logistics challenges and so on, and the bottlenecks, continuing, because it's a bit hard to square those remarks with flawless execution, if that's what's needed?

Henrik Andersen

executive
#68

That's likely the reason we continue to say a possibility exists, yet we lack the visibility to state it and take that position. I believe you're right that this is now part of an ongoing discussion in countries across the board about reopening societies within probably the next 4 to 8 weeks. And of course, that will also make it simpler for us to prevent any delays or anyone further in quarantine from moving across borders. And as I said, just a natural simple thing like getting somebody back and across countries on a plane is still causing most of us a super big issue.

Dan Togo Jensen

analyst
#69

Alright, and maybe just a follow-up on that point. From a geographic perspective, where would you say you're seeing the biggest risk at the moment? China has reopened, and Europe and the U.S. are also beginning to open up slowly now. Would you say the U.S. really remains the key to hitting guidance going forward?

Henrik Andersen

executive
#70

Sure. That said, the biggest delivery volumes are clearly Europe and the Americas — especially the U.S. — so those regions will obviously carry the greatest risk for us. Still, as I mentioned, our U.S. plants have actually remained fully open the whole time, with strong backing from customers and other stakeholders alike. So I'd say we're feeling positive, given that commitment from everyone involved. But like I said, some of this we just have to take week by week.

Operator

operator
#71

Martin Wilkie with Citi has the next question.

Martin Wilkie

analyst
#72

Martin here, from Citi. My first question concerns the electricity market as a whole. One thing we've witnessed through the crisis is, clearly, that demand has dropped, and as a result wind and renewables now account for a record share of electricity supply. Perhaps this is really a question for your customers, but has anything reached you about whether people worry that the system is unstable, or about any indication for the future regarding whether this is demonstrating that wind can in fact represent a far bigger percentage of power going forward? I'm just curious whether you've heard anything on that.

Henrik Andersen

executive
#73

I’m not going to take the credit away from you there, Martin — that’s certain. I’ll most likely simply build on what you said. What we are observing at this moment, naturally, includes some near-term and extremely sharp swings in energy prices. If you were in this seat at this moment and trying to look at a PPA covering a set period, that can be hard to pull off. But as we are also now moving into — we came out of a pandemic, it’s an economic recession. And then possibly we also need to begin coping with what arrives as part of the recovery. Then naturally, we will handle our share, to pursue renewable and the green energy agenda. And that is plainly fashionable now. It is fashionable with every party we speak with from a public governmental standpoint. We have not encountered a nation where it isn’t on the agenda for discussion. And also, quite literally, just to talk with us about how it is we can contribute and what it is we needed to do. And that, I think, has likely given something to everybody — that there is something you can do that favors both the energy supply and also the climate over the longer run.

Martin Wilkie

analyst
#74

Let me ask something unrelated and go back to inventory. Obviously, you've accumulated some stock for the second half. But just so I understand: do you believe there's now a structural requirement for more inventory, given the possibility of bottlenecks, meaning you'd want a cushion of components or materials? Or, if goods spend more time in transit, should we anticipate that inventory will simply run higher as a percentage of sales going forward? Or is your view that this effect completely reverses during 2020?

Marika Fredriksson

executive
#75

Right. And clearly, what we've now built up matches our expectations for activity level. That said, I think it's certainly something we'll use to ensure we're able to meet the commitments we have. Still, up to this point, it lines up with what's in front of us. So we haven't pulled that lever yet, Martin, but it's definitely one we could use if needed.

Operator

operator
#76

Our following question comes from Frans Hoyer at Handelsbanken.

Frans Hoyer

analyst
#77

I've got a question about this change, or the write-down, in the first quarter. Does this shift in the EnVentus strategy affect the minimum 10% EBIT margin target we're aiming for in due course at all?

Henrik Andersen

executive
#78

Yeah — the direct response there is no. What we're saying internally, in fact, is that we're speeding up other areas of modularization tied to EnVentus. So that's the straightforward reply on that. And that remains a really significant supporting piece as well for reaching 10% EBIT.

Frans Hoyer

analyst
#79

Alright. The next question has to do with the low oil price. I also noticed the EIA was discussing how low oil prices could affect renewable energy in general over time. What are your views on that?

Henrik Andersen

executive
#80

As I mentioned to Martin a moment ago, I believe that over the near term we'll see more volatility, since it hinges on the timing of reopenings in particular regions and sectors. That said, I think the past couple of months have also taught us some lessons about climate. So my sense is that interest remains broadly present underneath, and as I've already shared with everyone here, there could be a trend toward stronger backing for renewables as part of that. And naturally, we will definitely put both our time and our effort into speeding that up further.

Operator

operator
#81

Sean McLoughlin of HSBC has the next question.

Sean McLoughlin

analyst
#82

I've got two questions. First, regarding CapEx, how far under EUR 700 million could you go without compromising new product development?

Marika Fredriksson

executive
#83

And Sean, let me be very clear on that point: we will not compromise. That isn't the reason we've halted the order write-down of the platform we were just discussing. We haven't provided an exact number, but it's clear we're coming in lower on the CapEx side because of the platform and the activities tied to it from a CapEx standpoint. And I think, given these circumstances, it's also wise to keep a close eye on CapEx and cash, as we always do. But once again, that focus is simply further amplified by the situation we're facing globally.

Sean McLoughlin

analyst
#84

Then second, returning to the supply chain constraints — how soon in Q2 do you anticipate relief? Or will those persist throughout 2020? This is a major delivery year for the industry. We're aware that production — not only yours, but supply chain output — has taken a hit from COVID-19. And how important is that when it comes to whether you can potentially hit the original guidance?

Marika Fredriksson

executive
#85

No. But I think, when it comes to how fast the supply chain recovers or how quickly we get back, it's hard to say. Q2 is still ahead of us. And obviously, we have visibility into that. And we also have a certain amount of visibility simply because our order backlog is full and obviously there's a lot to exercise this year. And we're in continuous discussions. The good thing is that we're a reliable customer and a reliable partner. And that obviously puts us in a good position with the supply chain. The main — the big challenge is really transportation if we have to change and we have to change quickly. But it's also, I would say, something we've been pretty accustomed to during last year. We did a lot of changes because of headwinds, but it's obviously a matter of the cost that we have to bear for that as well. But we have certain visibility over the full year. We don't have the crystal ball, though, and that is missing. And that's also why we are not prepared to get back to a full guidance of this year, but we have definitely visibility because of the strong order backlog.

Operator

operator
#86

Our following question comes from Claus Almer at Nordea.

Claus Almer

analyst
#87

And I have a couple of questions too. My first one concerns the order pipeline, perhaps the nearer-term part of it. Henrik, you said earlier during this call that certain auctions had been pushed back, perhaps by a few months or so. But what about project financing? What feedback are you getting from clients, yes, when they discuss obtaining financing? That is my first question.

Henrik Andersen

executive
#88

Yeah. And here, I think it's probably somewhat similar to what Marika brought up regarding the facility we secured. When you come in early, financing would typically be flowing. What I'd say is that at present, smaller developers in particular may face tighter — or looser — conditions when it comes to closing financing. Or others might run into difficulties, since the PPA, or the PPA market, may not deliver what you're obligated to perform. So in certain of those cases, it likely works — whether I'd call it in favor or disfavor, I'm not sure — but at minimum, those who are highly liquid, those with enough capital, and, you know, at least many of our customers globally, the utilities, the big developers, and the infrastructure funds as well, they have the capital regardless, Claus. So for them, it won't pose a problem. At least, right now it isn't a problem whatsoever.

Claus Almer

analyst
#89

All right, that sounds good. My next question concerns the production execution problems that you have also brought up for a few quarters now. When do you expect all of that to be behind you, and when will efficiency at your factories be up where it should be?

Henrik Andersen

executive
#90

If you had posed that question to me on May 5th, given what we were handling here, we're now in the process of reopening and starting up factories as we go, Claus. I would hold off on providing you with a specific date and quarter. We're scaling up at full speed while simultaneously encountering situations where certain countries suddenly tell us we're not permitted. But let me offer a few examples. We were among the earliest to be granted permission for full operations in China, thanks to rigorous protocols. We had a roster of our employees. Everything was handled with discipline. And we're doing the same in India and elsewhere. So we're among the first that have been permitted to reopen. That demonstrates that with 30 cases of COVID-19 out of 25,500, we've asked some individuals to remain at home for health reasons. We've asked many people to safeguard one another, to act with complete discipline. And out of those 30, 20 have already recovered.

Henrik Andersen

executive
#91

And when we look at it that way, in that quarter, please don't ask me to say when we'll be done putting the efficiencies in place, because that wouldn't really be fair. Still, we feel comfortable that if we can run it at this level of efficiency amid these challenges, there is something for us to achieve afterward.

Claus Almer

analyst
#92

My apologies. I wasn't doubting your capacity to take in COVID-19. I'm quite confident you're handling everything properly. My point was more about the situation when a factory is operating, as it was in Q4, where your peak count — perhaps the improved count — might not hit that same level. So it's really about that aspect when new turbines are being brought in.

Henrik Andersen

executive
#93

Yes. From a manufacturing standpoint, we know we launch things in Q4. And once 2 quarters have passed, the learning curve will typically begin to work in our favor regarding TAC time and all the rest in the factories. But there, of course, as I mentioned here — and that's the reason I answered the way I did — because when you're suddenly in the middle of improving TAC time, and there's a stop and a go, with people away from the factories for a couple of weeks, then it becomes hard to see. So I believe we're working diligently through this year. And I'll say, yes, let's take it quarter-by-quarter. We have in fact improved. I mean, if you asked one of the factory managers in part of Denmark, he'd actually say he's been the most efficient he's ever been this past quarter, because everyone probably helped one another very well in the factory. So I'm just saying here, let's return to that when we have a bit more visibility into how the factories are working. But generally, a couple of quarters after we've opened, we are back.

Operator

operator
#94

Mark Freshney with Crédit Suisse has our next question.

Mark Freshney

analyst
#95

I have a question, if I may. First, regarding input costs — that is, your supply chain — are you noticing suppliers attempting to pass along increased costs because of any difficulties they may be encountering? And second, this is more of a thematic one, but we've had Brexit planning — it wasn't major for you, but we've had it. We've had tariff mitigations. Now we've got COVID. Do you think, broadly, that you'll be pursuing these, that you'll end up with a supply chain that is less globalized — meaning considerably more local content instead of shipping equipment across borders?

Henrik Andersen

executive
#96

Taking the last one first, I'll hand supply chain over to Marika. But on this point, it seems clear that right now countries are making national decisions, and probably to a smaller degree there's a global decision being made across them. On the other hand, we're dealing with that. I also think many of our manufacturing localization efforts are in fact set up to handle some of these challenges. So I think we've built a supply chain that functions and in fact performed well here. But of course, I don't think we should allow ourselves to be swayed if a country shuts its border transport for a period of time, because I think we'll also learn from that once we come out of this crisis. So we believe there's still ample room for a global supply chain and also for global companies such as ours. As for the cost to us, Marika, I'll leave that to you.

Marika Fredriksson

executive
#97

Yeah. So clearly, I think in relation to what Henrik mentioned too, I think our supply chain is very solid and loyal. And we haven’t observed them unfairly adding an extra cost to us so they can make more money. I think all of us have a great deal of respect for getting things to work as well as possible. But obviously, as I said, because of delays and the constraints in supply on their side, there could be extra cost for us in total. And that is something we have seen here in the quarter, and we will most likely see that going forward as well. Then the order of magnitude is very difficult to define over the longer term.

Henrik Andersen

executive
#98

Thank you. And perhaps we could take the last question from — let's see — the final one.

Operator

operator
#99

And our final question comes from Rajesh Singla at Societe Generale.

Rajesh Singla

analyst
#100

Since project scope varies quite a bit between regions, could you give us some insight into your project margins in Asia Pacific compared with the Americas or Europe? Are they comparable, or are they better? And my second question is about the supply chain. In the current market environment, do you see the offshore supply chain as somewhat better positioned than the onshore supply chain?

Marika Fredriksson

executive
#101

Alright, starting with the first question about margins by region: the same thresholds must be met before we accept a firm order intake. The current situation has not altered that. So scope may vary country by country. But regarding how much we earn per project in margin terms, there is no difference. The thresholds are identical. Then, on the supply chain question—whether offshore has a more solid chain than onshore—I would say that, considering onshore volume and our onshore experience, we have a good supply chain today. And clearly, all of us are striving to honor the commitments we have toward our customers and our supply chain. We are their customers. Everyone, obviously, is making a major effort to honor their commitments. That is what is ongoing, and that is also why we can actually present the revenue increase we have here in the quarter.

Rajesh Singla

analyst
#102

Alright, a follow-up from me would focus on Vestas, where the order backlog has looked pretty robust. Still, how much of that surprise cost inflation — whether in logistics or other areas — do you expect in the near term? After all, it could take a few months for the supply chain to return to where it was before COVID, or perhaps a few quarters before logistics gets back to that pre-COVID level. So is it possible to pass this higher cost along to the customer? Do any clauses exist that address that?

Marika Fredriksson

executive
#103

As I believe you grasp just as well as I do — I mean, the two of us are talking it through at this very moment. What we're doing is meeting our obligations at the most favorable cost we can achieve. And then, clearly, we're in conversation with customers when that's needed, just as we would be with suppliers. But that, obviously, is fairly confidential, and it isn't something we intend to disclose.

Henrik Andersen

executive
#104

I appreciate that. Thanks for the questions and for your interest. We’re looking forward to speaking with many of you over the next few days. And thanks from all of us here.

Marika Fredriksson

executive
#105

Thanks.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Vestas Wind Systems A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Vestas Wind Systems A/S earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Vestas Wind Systems A/S or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.