Good morning, everyone, and welcome as we walk through the complete presentation of our Q2 results along with the first half of 2024. Obviously, Monday gave you the picture — a negative quarter in Service, yet with solid headway across most other areas. I'm certain we'll dig into all of those topics in far greater detail over the next good hour. I'm equally confident that we'll examine where the full year is heading. So with that, please let me take you through the key highlights for Q2 and, to some degree, the first half. Q2 key highlights: revenue came in at EUR 3.3 billion. That marks a 4% decline versus a year earlier, hurt by Service and partly made up for by higher delivery ASP in Power Solutions. Service was hit by the plant cost adjustment, with Service EBIT at negative EUR 107 million in Q2, driven by the roughly EUR 300 million negative adjustment, which also carries no cash flow effect. Underlying earnings are moving forward as expected; the turnaround in Power Solutions remains on track and its EBIT margin has risen nearly 8 percentage points compared with Q2 2023. Order intake stood at 3.6 gigawatt.

Henrik Andersen

executive
#2

Order intake increased 54% year-on-year as a result, with onshore projects in Europe and Asia Pacific mainly fueling that. We'll cover that in more detail shortly. First-half cash flow looks robust — adjusted free cash flow of EUR 0.5 billion brings leverage down to 0.7x net interest-bearing debt to EBITDA. We then tightened the outlook: turnover is now expected to land between EUR 16.5 billion and EUR 17.5 billion, with an EBIT margin of 4% to 5% for the full year, and we'll go through the outlook in greater detail at the end. With that said, let's turn first to the business environment. The first two sections — the global environment and the market environment — I'd describe as roughly unchanged. So what we've observed is that the global environment still carries some geopolitical volatility. I'd also note that in a number of markets overall inflation is coming down, yet specific components are climbing, and wage and salary pressures remain sticky in certain local markets across Europe, the Americas and, to some extent, Australia. Turning to the market environment, grid investment is, I think, increasingly being prioritized in key markets. That is, of course, something we welcome.

Henrik Andersen

executive
#3

We can also observe that they are moving up in general, and we can go into more detail on that with examples. I think here, welcome as well to Germany and the U.K. On the whole, permitting is moving forward. With the auctions, we can see that also given the budget increase from the U.K. There are genuine political commitments here to begin turning this into concrete actions. I think for us — and both Hans and I will discuss this further at the project level — some of the supply chain normalization we have been talking about is now also affected by some of the regional disruptions. We know about the Red Sea, and I'm sure some of you will have comments or questions on that as well. But for us here, the main part is the second one, where we see that project execution is happening as we planned. And we are working patiently through the low order margins from before the first half of 2022. The really important thing here is that we can see our execution differs very little from what we planned to do, which is also one of the material contributions to the progress and the improvement in Power Solutions. But, of course, we are seeing a better ASP being executed as well.

Henrik Andersen

executive
#4

Alright, moving on to Power Solutions, where I'll walk you through the key points. Order intake was solid across all our markets. We closed at 3.6 gigawatts of orders, which is 54% higher than a year ago. That's healthy activity, led by onshore projects in Europe and Asia Pacific, plus the Nordseecluster offshore project with RWE. The biggest onshore project this quarter was the 577-megawatt Golden Plains Stage 2 wind farm in Australia — which could signal a comeback for a really important market that's currently in the middle of an auction process. I'd also point to Golden Plains 1, which came in as order intake back in '22. It illustrates the pattern that's clearly the best route to landing the next project or getting it into the order book: executing well on the first project, or on the projects you already have. And at least with this customer, TAG Energy, we're well ahead on Golden Plains 1, a project roughly 1.5 hours outside Melbourne. During the quarter, ASP rose to EUR 1.21 per megawatt in Q2. That's naturally supported by mix effects from scope, with a bigger share of EPC orders this quarter, along with continued very strong commercial discipline.

Henrik Andersen

executive
#5

Also, if you look back at their highlights and check when the first order came in at Golden Plains, you'll notice an ASP there as well. That had a meaningful effect on the quarter in '22. So on the right-hand side, you can see order intake for both onshore and offshore, and you'll spot the specific offshore order here at 660 megawatts, with the development in ASP shown below it. From there, I'll move to Service. Service continues to be a robust business area, notwithstanding the question of whether we've raised guidance following our own announcement on Monday. So looking at the highlights, the Service order backlog grew to nearly EUR 35 billion, up from EUR 32 billion a year earlier. Inflation indexation continues to be a crucial mechanism for safeguarding backlog profitability. That said, adjustments to plan costs weigh on current profitability. This revision has no material impact on the service backlog or on cash flow. There's a sharper focus on operational excellence and cost-out initiatives aimed at offsetting higher operational costs. We'll go into more detail on that. And as Q2 closed, Vestas had 151 gigawatts under active service contracts. You'll find the breakdown on the right. To repeat, the backlog stands at EUR 35 billion. And again, average contract duration comes to 11 years, across more than 80 countries, and the regional split appears below.

Henrik Andersen

executive
#6

Moving on to the development business. Once more, the Mississippi wind farm, with Amazon serving as a primary off-taker. I'll note that's one heading, but the other heading that remains within the development business is quality over quantity, since the focus right now is on bringing quality into development projects, which also explains why you're seeing a newly secured pipeline sitting at roughly zero. During Q2, Vestas' development arm commissioned Mississippi's first-ever wind project in the U.S., the 185-megawatt Delta Wind project. Amazon will buy the majority of the renewable electricity produced to Power, its nearby operations. Vestas development saw robust political backing for new renewable energy projects, yet quicker permitting and fresh grid investment are still bottlenecks. Queues persist on some grid projects in and around our key markets across the Americas and in EMEA. As of the end of Q2 2024, Vestas' development project pipeline stood at 29 gigawatts, with Australia, the U.S. and Spain ranking as the nations holding the biggest project pipeline. To the right, you'll again see the breakdown. And you'll also see the regional breakdown of the development pipeline attached to it.

Henrik Andersen

executive
#7

Moving on now to the Q2 sustainability review. Once again, during this quarter, CO2 avoided over the product's lifetime and shipped capacity rose by 11 million tonnes versus the same period last year. Emissions from our own operations fell by 7,000 tonnes year-on-year, which came from reduced fuel use as a result of lower offshore activity. This is a topic we'll begin discussing more, because as you can see, when we measure roughly 100,000 tonnes of CO2 each quarter, just 1 or 2 project activities are in reality enough to materially affect that figure. So we'll address it, and we'll also address it as we begin ramping up certain offshore construction work looking toward '25 and '26 and beyond. Recordable injuries per million working hours dropped to 2.8. We work tirelessly to enhance safety performance throughout our entire value chain. And naturally, on this measure we won't be satisfied until we are fast approaching 0. With that, I'll pass things to Hans for a walk-through of the financials.

Hans Smith

executive
#8

Thanks a lot, Henrik. Starting with the income statement, we can see revenue was up 4% year-on-year, impacted, naturally, by the adjustment to the planned costs in Service, and also by lower volumes delivered. But importantly, the higher average prices we have on turbine deliveries in Power Solutions almost fully offset that, which also indicates, as it says here on the slide, that the underlying business keeps improving in many ways. Gross profit came in at EUR 156 million, equal to a 4.7% margin, again negatively impacted by the Service adjustment. However, the underlying Power Solutions business, as I mentioned earlier, actually keeps performing better and better. We'll return to that on the next slide. EBIT margin before special items was minus 5.6%, and if you disregard the effect of the planned cost adjustments in Service, Service EBIT margin would have been positive. As I said, we are seeing profitability improve significantly in the Power Solutions segment. Revenue rose by 4% year-on-year as we are seeing that the higher pricing we have achieved on our deliveries can more than offset the declining volumes being delivered. EBIT margin before special items was sitting at around 0.7%.

Hans Smith

executive
#9

That's a big jump — nearly 8 percentage points versus a year ago. I think it's worth calling out here that this really shows profitability is getting better, that our commercial discipline is holding, and that we keep seeing this division move into stronger and stronger shape. Even so, I'd also like to flag that in this quarter as well, profitability is still being held back by the execution and completion of certain low-margin projects we took on before midyear 2022. And as we've noted previously — and I'd like to reaffirm this again — it should be largely behind us by the time we reach the end of this year. That brings us to the Service overview, and there's essentially no difference on the slide here versus the one we showed earlier in the week. And here we can see how the adjustments to planned costs affect profitability. Service posted a negative EBIT of EUR 107 million as a result, and because of — well, again, this stems from the percentage of completion method we use. And of course, that impacts EBIT in the quarter. The adjustment itself had a negative accounting impact of roughly EUR 300 million, or EUR 312 million.

Hans Smith

executive
#10

I also want to emphasize that this adjustment had no effect on cash flow during the quarter. And on that note, earnings came in pretty much flat compared with a year earlier. Service revenue fell 26%. Again, that decline is also a result of this adjustment. As a final point, I should point out that transactional sales rose somewhat in the quarter and that we faced currency headwinds of 1%. During the quarter, I'd describe our cash flow as quite strong, with operating cash flow of EUR 830 million (sic) EUR 831 million. That's what I'd call a fairly considerable improvement versus last year's EUR 783 million, so essentially moving from 0 to EUR 800 million. The drivers were a reduction in net working capital and, of course, the better underlying profitability we're seeing. Adjusted free cash flow then came in at roughly EUR 0.5 billion. That too is a significant improvement versus last year. So overall, a strong cash flow in the quarter is definitely what we saw. I touched on working capital briefly earlier. Here we can see how the composition has played out: net working capital fell in Q2 because of a decrease in contract assets, driven by customer milestones and down- and milestone payments in the Power Solutions segment, partly offset by inventories, which signal that we are preparing for our activity level over the rest of the year.

Hans Smith

executive
#11

So what I'd say is that this is a development reflecting a really busy second half of the year, yet at the same time, as we saw in the cash flow as well, I think it was well managed in a way that we can be quite pleased about. Moving on to investments. Here I'd like to point out that we are still getting ready for the production ramp-up in both Europe and the U.S. And in Europe, of course, the primary area we're investing in is the V236 offshore manufacturing platform, getting ready for the first deliveries we have next year, in 2025. But I'd also like to point out that we're investing in our onshore American footprint as well, where production is ramping up and where we expect deliveries to pick up over the coming quarters. And all in all, that brings us to an investment level of EUR 269 million, which you can see here on the slide on the right-hand side. That brings us to provisions and to the LPF overview you see here, where we can see warranty costs continuing to improve. But at the same time, we still see an LPF sitting at a level that is unsatisfactory.

Hans Smith

executive
#12

It is getting better, though, and there are focused efforts underway aimed at bringing this down. We're seeing some of those efforts bear fruit, but I'd again highlight that we remain at a level we're not pleased with when you look at the chart on the right-hand side here. Warranty cost came in at EUR 141 million for the quarter, equal to 4.3% of revenue, versus a level of roughly 5% a year ago. That brings us to the final page here in the financial section, where you can see our financial leverage is back within targets. And naturally, that reflects a mix of the profitability gains I've already mentioned plus the cash flow developments, which are also coming through quite nicely. Altogether, this leaves us with a net debt-to-EBITDA ratio of 0.7x, which I'd say compares quite favorably with the 4.5x level from a year ago. So I'd certainly say it's good to see that we're now returning to movements and levels that are, let's say, less dramatic than was the case if you go back 3, 4 quarters.

Hans Smith

executive
#13

That's a solid step forward. Last thing I'll mention is the rating Moody's gives us — Baa2, and the outlook on it is stable. With that, Henrik, I'll hand it back to you for the outlook.

Henrik Andersen

executive
#14

Thanks a lot, Hans. Now I’ll walk you through the outlook. There are definitely no changes to the slide that you saw on Monday. So revenue is EUR 16.5 billion to EUR 17.5 billion. For the group, the EBIT margin before special items is between 4% and 5%, compared with 4% to 6% previously. And the EBIT for the Service business is around EUR 500 million, taking into account the EUR 312 million adjustment in the quarter, from the previous EUR 800 million to EUR 880 million. Total investment is around EUR 1.2 billion. And all of this, of course, is based on current foreign exchange rates for the rest of the year. So with that, operator, I just want to thank everyone on the call, and also for some of the many discussions that have taken place over the last 48 hours, and I’m sure we’ll look forward to seeing many of you continue some of those over the coming days. So over to you, operator, and to Q&A.

Operator

operator
#15

<<operator_script>> Our first question is from Ajay Patel at Goldman Sachs.

Ajay Patel

analyst
#16

I've got a couple of questions, if I may. The first one concerns margin. If I look at how the business performed across the opening six months in EBIT terms along with revenue, and then compare that to the midpoint of your updated guidance, the implied margin works out at roughly 9% at the midpoint — versus your medium-term objective of 10%, and versus consensus of about 6% prior to the prerelease. So what I'm trying to get at is whether there's any one-off item sitting in that second half. Or is that 9% really a genuine 9%, obviously with greater activity, which we ought to view as a driver as we head into '25, when legacy projects will be very limited relative to this year, where we had a fair number? My second question is really just a clarification stemming from the conference call. You've now flagged this one-off cost on Service, and it stems from higher planned costs. That ought to affect the margin you'd generate on Service in the years ahead. And I believe you referenced broadly achieving the same profitability as what you saw in the last quarter.

Ajay Patel

analyst
#17

I believe across the last 6 quarters it came to 21%. Is that the correct way to frame it? And then, as a starting point, how does that carry forward into future years? Also, within your 10% margin target, was a margin assumption built in, so we can get some reference point on where we stand following this week's news flow?

Henrik Andersen

executive
#18

To begin with, Ajay, I really appreciate your questions, and I can tell that both of them are addressed and point toward the 10% EBIT target. But let me take the first thing first — you're correct regarding H2, there are no single effects on that. So it is, as we are also observing here, the ramp-up that we are doing, and it's also probably, as you can see in the numbers, when you make those comparisons even to '23 as well, we have a busy second half of the year, and we also have a second half of the year that is more back-end loaded than we have had before. And of course, that comes through with what we are seeing now on the assumptions that we are executing in an environment where we have fewer deviations, and we can see some of the ASP coming through. So in the second half of the year, we get the operational leverage with the volume we are executing on. And of course, that leaning toward normal things. But also here, and now we have had a long discussion after Q1 this year. Just be aware that, that operational leverage doesn't sit in quarters where you only have EUR 1.5 billion or EUR 2 billion.

Henrik Andersen

executive
#19

So before you kind of take your 9%, 10% and carry it forward into — this is then '25, there will be quarters in '25 as well where that operational leverage isn't there. And you'll also have the offshore ramp-up, which isn't giving us the right critical mass in '25. On Service, from that, as we said, it will perform in line with what we've seen in the recent quarters. We don't see an effect of what you're doing here hitting immediately in the coming quarters. This is a backlog review of planned costs. And therefore, it extends much longer than what you'd assume if it were just the future coming quarters as well. So for service profitability, assume what you're having in your previous quarters in the model.

Operator

operator
#20

Kristian Tornøe from SEB has the next question.

Kristian Johansen

analyst
#21

I have two questions too. The first one is about order ASP. Clearly there's a scope effect this quarter. But I also noticed your mention of good commercial discipline — actually, you described it as very good commercial discipline on the subscriber side. So does that mean there was in fact an underlying like-for-like price increase during the quarter, ASP?

Henrik Andersen

executive
#22

I realize every word here has to be chosen carefully. It's a real pleasure to observe the progress we're making. The split shown here also tells us this is happening across a broad set of countries. So the key thing for me, Kristian, is seeing that we can hold on to commercial discipline while also strengthening it. That's what I'm getting at when I say very good commercial discipline across that many. You can see as well that we've had a fairly substantial batch of unannounced orders, amounting to roughly 700 megawatts. And naturally, the bulk of that comes from our close core markets in Europe, and especially Germany too, which is, of course, another reason we welcome it. So this quarter has a very good mix. And some of you, I can see, also picked up on a line dated the 30th of June, but we've carried on with what is probably stronger momentum at the start of Q3, though it also suggests some things likely slipped from the end of Q2 into Q3, and that's what you're seeing now in the first weeks of Q3.

Henrik Andersen

executive
#23

Honestly, we're fairly happy with how things have gone commercially up to this point.

Kristian Johansen

analyst
#24

All right, that's very clear. My follow-up then concerns the business environment slide, where the supply chain dot moved from green last quarter to yellow. On Monday, we heard that inflation indexation within your Service business isn't fully offsetting the anticipated cost increases. So, thinking along similar lines for Power Solutions, given that supply chain may be somewhat tougher, should we anticipate that you can fully offset those extra costs via your deflation, contracts, pricing, and so forth?

Henrik Andersen

executive
#25

We move from a green to an amber. I think, as we also talked about earlier, the Red Sea and other factors are currently causing some discussions around time and cost. We have strong partnerships, which puts us in a good position, together with the partners, to mitigate some of these — what I call — disturbances. Over the long run, we won't be affected by that. But on the other hand, that is then also, to some extent, what will be shared with our customers. So in that sense, it's just a highlight that it seems to have gotten no better, at least, and it's starting to lead to some disruptions also in some local areas at harbors and elsewhere. But so far, not really a concern in any similar comparisons to what we have seen in previous years, Kristian.

Operator

operator
#26

Our following question is from William Mackie at Kepler Cheuvreux.

William Mackie

analyst
#27

I've got two questions. The first one is about how Power Solutions looks for the back half of the year. On volume alone, I see that your installation volumes fell 22% in Q1 and 17% in Q2. Yet the guidance for the second half suggests a meaningful revenue step-up, partly from ASP improvement. Could you give us a sense of your visibility into and confidence in that H2 installation volume step-up, and whether you see any risks emerging or opportunities to deliver on it? My second question concerns efficiency opportunities in your Service business. I see you have roughly 15,000 people in Service, but some of what they do is, so to speak, being redirected toward handling warranty issues in Power Solutions, which uses up Service employee time. So my question is: what opportunity exists to make Service more efficient as you clear your warranty backlogs, so those people have more time for Service work?

Hans Smith

executive
#28

Yes. I'll handle the first one here, Will, and then I suppose Henrik might take the next. So you're absolutely right that we expect a very busy second half of the year. And you're also right that we're seeing prices compensating for lower volumes. In some ways, that's a good thing too, right? Because then effectively, for the same amount of euros you're doing less than what you otherwise would be doing. And we have an organization that has been used to installing quite a few number of megawatts in very busy periods. But I don't think we are of admitting that it looks set to be a very busy set of quarters, Q3 and Q4. And if you look at, say, the implied Power Solutions guidance we have, you can basically go and calculate it right, you will see that it's very back-end loaded. But as we have also pointed to, we're seeing good performance there. We're seeing an organization that increasingly delivers in the right way. So that is what, when we look at it gives us the confidence, so to say that things heading in the direction that they are heading, and that's a good direction.

Hans Smith

executive
#29

So that puts them in position to put in place what we anticipate them putting in place during the back half of the year. Still, it's certainly the case that, looking at the implied guidance — whether you go midpoint against midpoint or however you happen to be framing it — the schedule is quite full, yet that's our expectation at this point.

Henrik Andersen

executive
#30

Now, regarding efficiencies and what we call inefficiencies as well. I believe you're correct in the sense that, looking back over the past couple of years, it's clear we've been investing heavily alongside the 15,000-plus employees throughout the Service business, and certain areas are hit harder by this than others. That's what drives some of those comparisons, and we're carrying that out not just country by country but also cluster by cluster. Within that, there are things we also label as inefficiencies. We track that in a number of ways. Naturally, we track it as progress on warranty, which feeds into repair and upgrade, as we're also noting here. But it likewise feeds into the parallel consideration of what backlog of tasks we carry for the normal business. And naturally, that's a comparison we're working on. And naturally, that task backlog ought to trend toward 0 within the scope and size of our business — across the task backlog, it will never be 0. So from our perspective, we can see that task backlog has been higher, it's trending downward, and that's positive for us too, since it signals that we're recovering efficiencies in parts of the Service business, though there are also parts of the Service business where we still have it outstanding.

Henrik Andersen

executive
#31

That much I can promise you, and we're on it — from both a cluster and a country angle. That's why we're tackling it and telling you it's in the Americas, and at present it's in the main part of Europe.

Operator

operator
#32

The next question is from Daniel Haugland at ABG.

Daniel Vårdal Haugland

analyst
#33

I've got a couple of questions. First one: versus the Q1 guidance you provided, the implied guidance for Power Solutions is significantly higher. Looking at implied full-year EBIT for that segment, I believe it's up over 60%. So what changed between Q1 and now to drive that raise? Because my assumption is you already knew at the Q1 presentation which projects would be delivered in the second half. That's question one. Question two: you mentioned briefly that in small revenue quarters, you'll also see a margin below the 10% target in 2025, and from an operational leverage standpoint that clearly makes sense. But if we focus more on underlying profitability when trying to estimate gross margin, excluding warranty costs — once we reach a higher level in the second half of this year, should we assume it roughly holds at that level, or how should we think about it?

Hans Smith

executive
#34

Yes. Let me begin there. It's certainly true that Power Solutions is doing better, as you say. I touched on this a little in response to Will's question too. What we can say, I suppose, is that execution is coming in stronger than we had anticipated. Fewer risks are materializing, as well. Worth remembering that we've been through a pretty rough stretch, where predicting precisely how things would unfold with supply chain logistics at the sites, transport, and plenty of other factors was really hard. And while the environment there looks more uncertain, as Henrik noted, my general take — which I've said before as well — is that the execution machine, so to speak, is shifting into a higher gear. Naturally, it also has to be in a high gear given what it must deliver later in the year. Still, relatively speaking, I'd say execution is better and risks are not materializing, to a degree that lets us form the view we have about the second part of the year. In some ways, of course, you could argue this is the trajectory we want to be on — but I think it's also encouraging to see it in the first half of the year.

Hans Smith

executive
#35

And going off what we know at this point, since it's also been confirmed that this is the path it's headed down. Yes. Then regarding your second question, let me just check whether I can recall that one precisely. I suppose you mean the underlying profitability of what's happening there. As I mentioned, we're still carrying out projects this year that stem from the old backlog, and broadly we're seeing continued improvement in our business. So looking beneath the surface, we also anticipate that the underlying profitability journey will carry on into 2025. But naturally, various effects come into play here. There's leverage. And even in the numbers we report, there's leverage in the gross profit as well, for instance. But with everything else held equal, our hope would definitely be that this underlying improvement in the profitability journey we're on can keep going.

Daniel Vårdal Haugland

analyst
#36

Yes. And just so we’re 100% clear on that point, should we be expecting some quarters in 2025 to include low-margin projects as well? Or, since you’ll be wrapping up those low-margin projects this year—2025—will the quarter-to-quarter margin differences be driven more by operational leverage?

Hans Smith

executive
#37

That comes back around. I think — I mean, we've pretty much forgotten it at this point, but there was a time when you didn't have all this turmoil either. But we've also been through the past, and we've had good quarters and bad quarters, good quarters with good projects, bad projects. That's always going to be the nature of what we're dealing with. So those fluctuations are going to happen. So I think we're seeing — we're getting back to that kind of situation, but that doesn't mean you can't get hit in a small quarter if you have a small — or a bad project in that quarter still, that might impact the numbers. But overall, we're certainly seeing that profitability should keep coming up.

Henrik Andersen

executive
#38

What I believe Hans meant is that a shift in gross margin is visible, and that is the key point. And we're pleased with that, so there will always be fluctuations around that elevated level.

Operator

operator
#39

Casper Blom from Danske Bank has the next question.

Casper Blom

analyst
#40

I've got a couple of questions too. First, I was hoping you could speak a bit about the offshore ramp-up you're undertaking. You've said, of course, that you expect to have 0 production of the 236 in 2025, but should we view this as something that simply begins on 1st of January and then continues across the year? That's the first part of that question. The other is that previously, at one point, you had a target of EUR 3 billion of offshore sales next year. I think perhaps today we're expecting closer to EUR 2 billion or so. Could you address where that will take the offshore business in terms of profitability? Will it show up in group profitability next year? And also, what is the kind of hurdle rate in terms of activity for the offshore business to hopefully contribute to a group margin of these around 10%? That's the first question, please.

Henrik Andersen

executive
#41

Thanks, Casper — quite a bit there. As a Dane who's been driving around, I'm fairly sure you'll have noticed a lot of activity in and around both <<inaudible>>, where the main ramp-up is taking place. So the ramp-up is underway right now as we speak — it isn't waiting for 1st of January, since if that were the case I'm fairly certain we'd be far too late on some of the deliveries. You've also seen that we placed prototype #2 on the Danish West Coast. So that's what we're doing. And that means considerable ramp-up is happening, not just in cereal manufacturing but also in training and in really getting service technicians accustomed to working in that offshore turbine. So how do you change things? That is going on as we speak. And of course, you could say that given we're in a year when we're absorbing those ramp-up costs, and we're also absorbing those fixed capacity costs as we discussed — that isn't — that's also going to weigh on 2024 in that sense. As we look toward 2025, I think — over the last quarters we have pushed strongly toward the EUR 3 billion.

Henrik Andersen

executive
#42

We don't have to chase that EUR 3 billion, since with the two projects currently in our pipeline we'll likely land at roughly EUR 2 billion. That's quite clear given <<inaudible>> and the Baltics respectively, in Germany and Poland. And it isn't at scale yet, because so much is happening as you ramp up both on the tooling side and with service technicians and construction teams. So that initial EUR 2 billion carries all the incremental investment of setting things up for the first time. Once we begin building past EUR 2 billion, that's when meaningful margin accretion will start to come through — but certainly not in '25.

Casper Blom

analyst
#43

Alright, thank you, Henrik — that's really helpful. Now, for my second question, I'd like to turn to your warranty provisions. As you noted, they came in at 4.3% of revenue for the quarter. I suppose someone could be cheeky and strip out the EUR 312 million, which brings you down to 3.9. Would you call that a turning point? And are you still — how should I put it — optimistic about getting to the 3% level next year?

Hans Smith

executive
#44

To start with, when you have a quarter like this—roughly EUR 3-point-something billion in revenue—the figures you're referring to are quite small, like 4.3 versus an implied 3.9, that sort of thing. Let me be clear: this really isn't necessarily all that meaningful. What matters, I think—and I understand where you're coming from—is this: yes, I'd say it's encouraging to see it declining, relatively speaking, compared with where we stood previously. So we remain optimistic. I suppose the takeaway is that we can keep bringing it down. And as we've also emphasized, the goal is to reach roughly 3%. That's still what we're focused on. In that respect, this quarter is a solid data point showing that things are moving strongly in the right direction. So yes.

Operator

operator
#45

Our following question is from Akash Gupta at JPMorgan.

Akash Gupta

analyst
#46

I also have two questions. My first one concerns the balance sheet. Looking at the solvency ratio, it dropped to a record low of 12.4%. And compared with your competitors, your figure sits well under your peers as well as below the target you historically set. There's a substantial offshore ramp coming our way, and the industry will also expand beyond where it stands today. So my question is how you view your balance sheet in terms of participating in that industry growth and successfully delivering on the offshore ramp, or anything else you'd like to point out. My second question is about the development unit. My earlier understanding was that you handle early stage development and don't build projects on your own balance sheet within that unit. But today I see you mentioned commissioning the Delta wind project. So perhaps you could clarify whether this sits on your balance sheet, or whether it's a project already sold to customers and you were simply bringing it up because it came out of the development unit?

Henrik Andersen

executive
#47

Let me start with the final point, which was announced quite clearly and quite a while back in the U.S. So that’s done for the benefit of customers. So I suppose there’s nothing to worry about there. That means we aren’t putting unnecessary capital onto our balance sheet for these items. On solvency — I think that’s what you’re raising here, and you’re also asking, as a result, whether any changes to the capital structure are warranted, and the plain, brief response is no. It isn’t a problem. We also spoke with some of you 4 quarters ago, when our leverage KPI was, naturally, considerably higher. And you’ll also note that after 2 quarters this year, you don’t have a higher net profit. But if you were then to map out a trajectory over the quarters ahead, with earnings improving, that is in fact the best route to a recurring and positive contribution to your solvency ratio. So the solvency ratio isn’t at the current level. Any concern, and retained earnings will, of course, assist in that respect on solvency too.

Operator

operator
#48

Our following question is from Deepa Venkateswaran at Bernstein.

Deepa Venkateswaran

analyst
#49

Alright, I’ve got a couple of questions, and they both relate to the service business. First, I’d like to talk about the growth outlook. Obviously, there’s a contract asset buildup that ought to level off and then begin to decline. So could you speak to what you expect near term for top line growth in that business? My second question concerns margin. Can you confirm whether the backlog service margin sits around that 20%, 21% level, or whether it’s a different figure? And then, Henrik, on Monday you said 25% remains a target. Could you say more about the time frame? Is it 2030, 2028? Anything at all? And what kinds of actions would be required to move from this 21% to 25%? So yes, I think those are my two questions.

Hans Smith

executive
#50

Now, regarding the growth trajectory, naturally, there's a connection to the service assets sitting on the balance sheet. But broadly speaking, we do anticipate the Service business continuing to expand overall. That much is clear. And I should note that numerous factors feed into, let's say, what the growth trajectory for the Service business looks like. It also depends, for example, on how many turbines get installed, the volume of transactional sales, and plenty of other considerations. We'll circle back, naturally, to what that implies for next year once we get closer to it. But once again, that's the expectation. Your second question then concerned the backlog margin.

Deepa Venkateswaran

analyst
#51

Can you narrow that down a little—perhaps under 5%? I mean, roughly speaking, over the next 2 to 3 years, not only for '25—more because I believe consensus sits at 8% growth, at least before the earnings. So I was just wondering, maybe in relation to that.

Hans Smith

executive
#52

So over the long term, we've said we want to grow at, say, market growth plus, and that points to a level of 8% to 10%. That's what we've stated, and that's what we're focused on when it comes to growth. I hope that gives you, say, some degree of indication there. Then, on the second question about backlog margin, I should note that we aren't disclosing the margin in the backlog. But as we've also indicated, of course, right now, looking at where we stand, we're also saying that for the Service business we expect it to deliver, over the short term, margin levels on par with the margin levels we've carried in past and prior quarters. And of course, that gives you a kind of indication of where we are. You also rightly point to the fact that we have a 25% ambition level. And of course, that's what we're targeting over the long term, and there are various initiatives, say, that are put in place and that we're working on to get us to that level. And speaking to the growth part of it as well, of course, this is an EBIT margin target.

Hans Smith

executive
#53

And because the business keeps expanding, that also gives us a certain amount of operational leverage within the business itself. That, too, helps us move toward that ambition.

Operator

operator
#54

Our following question is from Colin Moody at RBC Capital Markets.

Colin Moody

analyst
#55

I just wanted to ask about how your customers view their willingness to invest, maybe split out by region — the U.S. versus Europe versus APAC? Then, as a follow-up, could you give us a bit more specificity on the sort of time frame for when U.S. orders should begin picking up again? Is it more like H2 this year, or more like 2025? And then maybe just a quick follow-up to that U.S. market question — specifically the IRA and the 45 tax credit, as more of a longer-term question. Do you get to keep much of those benefits? Or is the market situation such that you have to share views of customers?

Henrik Andersen

executive
#56

Let me start with the final point, since the U.S. market is tight. I'd say there aren't many players over there — essentially just a handful of us supplying. So it really becomes a case-by-case matter between us and each customer. Broadly speaking, I'd say it's a market that's functioning well. And at the moment it's also a ramp market, where to some degree there are capacity discussions happening with customers. So I think we're sharing information and, from a commercial standpoint, we're taking the orders in the U.S. that we're happy with, and I'm sure everyone else is doing the same and prioritizing likewise. On the customer conversations in the U.S., you've seen a number of U.S. orders actually come through now in Q3. A few of those may have been slated for Q2. So I'd say the U.S. market is still moving forward. We don't — I don't — we don't generally see a halt; in fact, it's the opposite. So people are eager to move their projects ahead. But naturally, they're only eager to move projects ahead once they have all full permitting as well as the grid access sorted.

Henrik Andersen

executive
#57

So those, I think, are a few of the bottlenecks at the moment. And with 5th of November approaching, I don't see the IRA speeding up or slowing down. But as I mentioned, I'll be spending a substantial amount of time in the U.S. over the next 2 weeks as well. So I'm fairly confident there'll be an update on that. That said, on the whole, our commercial team in the U.S. remains very busy with planning.

Colin Moody

analyst
#58

That's quite clear. On that note, do you have any comments regarding investment sentiment in the other regions, APAC and EMEA?

Henrik Andersen

executive
#59

When it comes to EMEA, I'd say it has a language all its own. It's progressing, and it also fits inside EU 2026. The range is wide. In some nations, activity is minimal. Others are coming back as countries, and you can spot certain orders landing specifically in some of those countries where the result looks somewhat positive. They've now restarted. And I believe you mentioned a spot in the U.K. — what has been announced and carried out, probably over the last couple of months or the first 1.5 months under a new government, appears to open an onshore market fully. And potentially, we'll learn a little more once we see the CFD outcome around 6 on the offshore side too. But that gives a good signal of the direction we're heading. And then, of course, in Asia Pacific, we've had various developments come through — fairly reasonable on both New Zealand and Australia. And Australia is working its way through a new policy and a new auction regime, which — yes, I was in Australia in June. So it's imminent in the discussion in and around how that gets organized, and the government in Australia is very much steering toward a new program that spans 5, 10 years, aiming at absolutely accelerating renewables.

Henrik Andersen

executive
#60

So that's a positive there. We have an excellent team in place. And as you can see as well, we also have a track record of delivering on our projects effectively in Australia.

Operator

operator
#61

Sebastian Growe from BNP Paribas has the next question.

Sebastian Growe

analyst
#62

I have a couple of questions as well. First, on Germany: installations appear to be up roughly 20% year-to-date. Given your historical share of the market at around 35%, plus the meaningful acceleration in allocated option volumes that we've observed over time, can you tell us how you expect volumes to develop for you going forward? And could that eventually become a 3 gigawatt delivery market for you — if you could lay out your thinking on that? Then I have a quick follow-up about offshore. You characterized this wage inflation as a quarter 2 adjustment in the Service business; I'd be interested to know whether we previously indicated that you'd expect the Power Solutions business in '25 to have further expanded, as has been said. And perhaps you can also give a quick update on how the over-hiring activity is progressing, particularly in Poland?

Henrik Andersen

executive
#63

Regarding that second question, I'll return to it — I'm not certain I caught the whole thing, but I'll do my best to answer, or just correct me, Sebastian. On the German markets, I'd say things are developing nicely. We started from a very low point 3 years ago. Since then, we've witnessed an acceleration. And maybe you shouldn't ask me about market size, auctions, and permitting, but broadly we can observe that auctions are happening. Permitting is coming through as well, and the German government has collaborated with the Department of Energy, working out planning modes of renders that succeed with a high number of projects getting approved and moving ahead. I think it matters that many European countries actually adopt that approach, since it does contribute to volume. Could it turn into a 3 or 4 gigawatt market? I believe the market will. As for Vestas' market share, we have a solid market, we've been present there with a long history and a long tradition of handling the projects and also taking good care of customers on maintenance and service afterward.

Henrik Andersen

executive
#64

We're not taking our foot off the gas there.

Sebastian Growe

analyst
#65

Mind if I jump in quickly? What I was getting at was specifically your delivery volume, which could be heading toward 3 gigawatts. So apparently the market is moving in the direction of 6 to 8 gigs, probably in the not-too-distant future. I was curious whether you could give a bit more color on your order intake, the pipeline, and so on?

Henrik Andersen

executive
#66

Yes. Sebastian, you know me well enough by now. I'm not about to give out your splits in a market where there are potentially 2.5 people looking at it right now. So -- so I think we would much rather talk about individual markets, and that is something we are in the middle of. We are positive there. And I won't give you a split of what we expect, because that is flagging to any competitor sitting on the same call as we are now. So that one is your guess, but you can see we have our historical market shares, and we are working towards that, because the quality of our turbines and solutions is there.

Sebastian Growe

analyst
#67

All right, and what about the offshore portion?

Henrik Andersen

executive
#68

As for the offshore side, I think it's about getting the Service organization, the technicians, and the factories ramped up. That's something we're actively working on at the moment. Offshore isn't new to us in this region, but the turbine and the solution we're installing are, of course, new. So because of that, a lot of the Service side and the Service technicians are being onboarded, including in some of our existing parts, and they'll then be trained and will work on that, and then be passed on as well once we have the construction completed during '25 for the 2 projects there. So the really important thing here is to be slightly ahead on onboarding and slightly ahead on training, because that's the whole aspect of the scale and the ramp-up of offshore. And that is going to have a dilutive effect for '25.

Sebastian Growe

analyst
#69

Sorry for asking for specifics on this point, but considering what actually occurred in the Service business, has that further weakened the overall outlook for the offshore business as part of our solutions, given the wage inflation on these?

Henrik Andersen

executive
#70

No. You're conflating two different areas here. When it comes to service business at a site — this particular one — we're looking into it, and this one gets priced both from a solution standpoint and other things. So that's not — what we're doing there is trying to pull together areas that shouldn't be pulled together.

Operator

operator
#71

Our following question is from Vlad Sergievskii, who is with Barclays.

Vladimir Sergievskii

analyst
#72

Just two brief housekeeping questions, if I may. First, could you walk us through what drove the underlying rise in unbilled revenue during the second quarter? The service reset cut contract assets by roughly EUR 300 million, yet the actual decrease came to about EUR 140 million — so absent that reset, you're still booking more revenue than you bill customers. Could you give us a rough timeline for when invoicing would begin to catch up with revenue recognition? That's the first one. And then quickly, the second: your developing projects in progress assets hit around EUR 1 billion this quarter, roughly 3x what it has historically been. Can you give us a sense of whether some offshore ramp-up costs have been capitalized into that asset? When do you plan to begin amortizing this EUR 1 billion? And what kind of yearly increase in amortization might that bring?

Hans Smith

executive
#73

Yes. So let me take a shot at that. On the first question, regarding contract assets, you're completely right — of course, what we're trying to do is assess what sort of development we should anticipate there. And naturally, as time goes on, we'd expect that to, let's say, level off and decline. That's the expectation we have. And of course, we also see now, thanks to, say, the adjustment we've made here, that this has had an impact on that asset. But as I said, there is — I mean, there's an expectation that this will level off. And then in time, it will also come down. But many reasons exist for why this can happen. So of course, the influence on how that develops. On the development project offshore and its capitalization, I would expect that we begin to, how should I put it, depreciate that fairly soon once we start the installations. I don't believe we've made specific, say, disclosures about what that level would be. But of course, given how large the project is, it's a quite significant amount that we'll need to depreciate as a result of that.

Hans Smith

executive
#74

At the same time, naturally, we do anticipate the offshore operation reaching a meaningful size. Yet to return to the point Henrik raised before regarding how large the business is—take 2025, for example—of course, that situation doesn't automatically play to our advantage when the scale of the business is suboptimal, again in terms of just how large it stands in a year like that, when you bring in, let's say, more than EUR 2 billion of revenue.

Operator

operator
#75

Our next question is from Claus Almer at Nordea.

Claus Almer

analyst
#76

I have a few questions of my own as well. First, regarding the pipeline being turned into firm orders: Henrik, you said certain projects had been pushed or deferred from Q2 into Q3. Is there a shared cause behind that, or is it simply the usual quarter-to-quarter fluctuation? That's my first one.

Henrik Andersen

executive
#77

When you mentioned a year and include last year too, Claus, you also observed that we finished at plus 18 gigawatts — there are always going to be deviations. And naturally, when you see things coming through during the first couple of weeks of July, a portion of those simply crossed the line on the same 30th of June. So there's no other reason; generally we'd prefer to have it in the quarter if that's possible, because that also provides much more security and clarity on execution going forward. On the other hand, getting it in matters more, whether that happens in Q2 or Q3. So I think the fact that those which picked up — it appears July and the first couple of weeks here in August have actually contributed more than you'd typically see — is a good indication that sometimes there is simply spillover between quarters. I won't call it a sort of, how we, we generally, I'd say, I'm still more focused on what the overall gigawatts is on the 31st of December, because that, I think, is an important number.

Henrik Andersen

executive
#78

And you can see that number moving in our favor, with our backlog having risen from roughly EUR 20 billion to EUR 28 billion now in Power solution. And for us, that's really the key thing to watch at this point, along with the backlog that's better priced.

Claus Almer

analyst
#79

That makes sense. So if we focus a bit more on the U.S. market here. You've made a few remarks about this really important market. Are there any differences in your conversations with, say, smaller versus larger developers, utilities and so on and so forth, that we ought to know about? Particularly regarding the U.S. addition, obviously.

Henrik Andersen

executive
#80

Yes. No, I think you could kind of put it this way: you probably saw as well today that Bill Fehrman had to step off our Board once more. He's joining a player in the U.S. market too. And naturally, if he must exit an investor Board, that also signals there's a commercial conversation underway involving both regulated utilities and infrastructure, and typically developers. In the U.S., I'd say it's still the same. I think we all recognize an election is approaching, and we all recognize the uncertainty surrounding it. But I'd add here that the priority given to critical infrastructure in the U.S. is also stated fairly plainly, though perhaps candidates phrase it differently. Still, I think both parties acknowledge that the underlying drive is the same. There will be plenty of uncertainty on the 5th of -- up to the 5th of November, but generally we don't see customers decelerating or speeding up their projects because of the upcoming state election, since the legislation is solidly in place, at least regarding the onshore.

Claus Almer

analyst
#81

All right. Let's just suppose Trump becomes President — do you think some developers would attempt to lock in firm orders ahead of a potential change to the IRA or the PTC scheme? Or is it the way I and others see it, that this has no effect on the onshore target?

Henrik Andersen

executive
#82

Claus, I’m not going to add anything to that speculation. I just don’t know. And like I said here, I’ll be seeing customers over the next 10 days, many of them in the U.S., and I’m sure in a couple of weeks’ time I’ll have a better answer. But broadly, there is a real focus on the commercial development of projects, and if your assumption is right, we will also see that early development of projects will be slowing down. That’s not the case either. So I don’t think—I think everyone in all the states is preparing for more projects, more energy to be generated. And don’t forget, there’s still the offtake, there’s still the offtake from the data centers, the AI, all of that. And don’t forget the green hydrogen, the ammonia and other parts are out there in the States. So we are going to see—and some of that is, of course, coming from major infrastructure build-outs in the U.S. So I can’t say much else, Claus, right now. And it is lumpy when you have sizes of projects of that nature.

Claus Almer

analyst
#83

That's reasonable. So we'll put you on the spot about Australia. You've been out there before and gave some estimates on when orders would arrive. And you've just come back from Australia. Should we expect some of those bigger orders you've mentioned before to show up this year?

Henrik Andersen

executive
#84

I believe we just had one, which is likely why I brought it up. No, I think Australia here has been a start-and-stop situation. That wasn't the intention, and the government didn't plan for it to be start-and-stop either. But when you ask Mr. Market to set the electricity price as both a floor and a ceiling in an auction, it simply takes more time. Still, if you consider the turnover or the volume of projects that entered the first auction, they're in an incredibly fortunate position, because that auction drew tremendous attention with volume. So if that volume—a double-digit gigawatt figure that came into the first auction—doesn't materialize as expected, then the auction will be held again, but that also signals Australia is ramping up. If you visit Amor, the grid company with the CEO, he'll tell you the same: he's preparing for a grid company in Australia that is far more receptive and ready to handle that volume. So, having learned from the beating you gave me last year over my poor timing predictions, I'll hold off on making any.

Henrik Andersen

executive
#85

Still, I'd say the momentum we're seeing from 577 on Golden Plains likely works to my advantage in the second quarter, wouldn't you agree?

Operator

operator
#86

Ben Heelan from Bank of America has the next question.

Ben Heelan

analyst
#87

Yeah, the main thing I wanted to ask about was the cash generation you've seen in Services over the last couple of years? And any general expectations for this year? Yeah, that's basically it.

Hans Smith

executive
#88

Yes. So in general, we tend to view our Service business as a solid cash-generating business as well, even though we haven't disclosed particular numbers on the cash flow in that business — that's how we would think about it. So I don't know how much more specific I can be there given that this is not something that we are outright in informing about. But it's — that's kind of the logic we're having. And of course, with the kind of profitability we are looking at, referring back to what we discussed earlier on, that also gives an indication of what it is that we're expecting from the business. It's a good solid business. And as I pointed to earlier on also, the effect from the adjustment we're doing is, for instance, non-cash. So I mean, that's out as much as I think we can talk about it here.

Ben Heelan

analyst
#89

Right, that's very clear. And a quick follow-up, I think, in response to one of the earlier questions. You said there were none of these, in quotes, sort of bad projects or underperforming projects in 2025. And when we think about it, it should really just come down to operating leverage in the given quarters. So is it true that none of these sorts of badly performing contracts exist in 2025? Or is it a very low number?

Hans Smith

executive
#90

The way to think about it is this: as I mentioned earlier, in a business like ours there will always be, say, a mix of different kinds of projects—a few are good, a few are bad. But at this point we've come down to, say, a more normalized profile than what has been the case in recent years. So that's the way to think about it. That doesn't mean that once in a while you won't run into a door of a project—that might happen—but it's a normalized thing compared to where we have been in recent years.

Operator

operator
#91

Sean McLoughlin from HSBC has the next question.

Sean McLoughlin

analyst
#92

Turning to offshore, we're now seeing Q2 Power Solutions revenues. The share from offshore is the largest we've witnessed in quite a while — many quarters, in fact. So my question is, what role did offshore play in delivering that positive margin for Power Solutions in Q2? And how significant is it to the 9% margin assumption for the second half? Should we view it as happening despite offshore wind, or because of offshore wind? Then the second part: you also referred to a bigger drag in 2025 coming from offshore. How should we frame the profitability bridge from where offshore stands today to the EUR 2 billion top line guide for '25?

Henrik Andersen

executive
#93

Sean. On your first question, it is despite, because when we examine it, what we're presenting now, we have a handful of projects sitting with us tied to a turbine type that is essentially phasing out. That's the V174. So that's why it's despite, and naturally, it's execution. And you'd also recognize that in certain of those quarters, things get lumpy, particularly when you draw the comparison. Yet you'll likewise notice, comparing, say, on the sustainability side, that we can actually observe a reduced CO2 footprint, since we're using fewer of those vessels. But it is, as you mention, a smaller share, and you should not anticipate any of that uptick in the second half of the year arriving favorably from the remaining portion of the -- of those projects. Then regarding '25 -- as I stated, I will still attempt to hold back from being more specific on '25 beyond the fact that there is no positive margin-accretive impact from the roughly EUR 2 billion. That simply cannot happen in a year when you're ramping up for two projects, because, returning to Vlad's point as well, depreciations will hit a business unit that has only approximately EUR 2 billion in turnover.

Henrik Andersen

executive
#94

So because of that, when you run the EBIT calculation, it’ll be dilutive to your target for ’25. And because of that, I haven’t set any target for ’25, but it will be diluted to the target regardless—diluted to the target.

Operator

operator
#95

Our next question is from Henry Tarr at Berenberg.

Henry Tarr

analyst
#96

Two fast questions. First, do you perceive any conflict right now, I suppose, between ASPs and market share? And I guess, is this still a market where competition is really intense? If you could also say whether you see your rivals behaving rationally and so on, that would help. Then my second one is about the Service provision. I know you have discussed it at length. As far as monitoring it going forward—the overall soundness of the costs and similar items—should warranty provision plus LPF plus cash conversion be the measure we use to judge whether costs here are staying on pace with your estimate?

Henrik Andersen

executive
#97

Thanks, Henry. On the first question about market share versus ASP: for a very, very long time, and quarter after quarter as well, I've said that quality and value over volume is absolutely the priority. So that's what we'll focus on. Yes, we do look at our market share as a reflection and an outcome of that, but it isn't the driver. The driver is the health of the backlog, and we can see the rest of the industry, for obvious reasons, has had to do exactly the same. So with that, we continue on the path we're on. We're very pleased with it. And for the first time, I think, on a quarter-on-quarter basis for this period on the Power Solutions side, you can see the effect of it, and it's actually paying off.

Hans Smith

executive
#98

Yes. And then regarding tracking — let's say, regarding how the Service business is developing — I think the best way to look at that would be to see what margin we're delivering quarter-on-quarter. That, I guess, is the best indicator that things are, say, heading in the right direction and on track. Of course, we can think about all kinds of things. But at the end of the day, it comes down to a margin. And so from our perspective, the best way to think about this is the Service margin that you're looking at. And then yes, of course, it also helps if you see that the LPF comes down — let's say, the warranty provisions come down — although the provisions are a function of work that needs to go on later, right? So the provisions actually indicate work that needs to happen out there. So there's a delay factor in that. And then just let me point to the last point on that. It's not a provision we're making. It's a cost update. We are making just a small technical point.

Henrik Andersen

executive
#99

And with that, operator, could we have the final questions for this conference call?

Operator

operator
#100

Could we have the next question, please?

Henrik Andersen

executive
#101

Sure — please let that be the final question for this conference call. So operator, kindly move on to the next question.

Operator

operator
#102

Our next question comes from Lucas Ferhani at Jefferies.

Lucas Ferhani

analyst
#103

I had just one question on Service, and it's more tied to offshore. The contract length is a bit shorter, and in the offshore fuel orders you've got, it looks more like a warranty plus what you'd call long-term support. So would Service in offshore lean more toward a spare parts agreement, rather than the kind of full coverage you're able to offer onshore? And then, as we saw and knew earlier, there are a lot of assumptions baked into the accounting on the Service side. How do you view that in offshore, where there are even moving parts when it comes to serving — Service in offshore wind turbines?

Henrik Andersen

executive
#104

Thanks, Lucas, for that question. And really, at this point, I think we're—as a sector, and not only from Vestas's perspective—we're building up in an industry and a business area that's still in its early stages. If you'd asked someone 3 or 5 years ago, I think there was a clear view that the Service setup in offshore would look different, that it would be much shorter, because there would be a push from especially customers and others to eventually take over the self provision of Services in offshore. I think over the last couple of years that has raised more of a question too—is that really the right structure, because if you end up as a partner there with limited megawatt or gigawatt or potentially only one project, then the turbine provider and the partner in that position will be much better off, because, of course, we'll have several projects coming out of the same harbor. So I don't think necessarily the sort of the estimations of ramp and scale and maturity gives us a clear answer yet on how that will be. We can see it. Certain customers will like to go for a longer in offshore.

Henrik Andersen

executive
#105

That contract could look different depending on whether the break falls at 15 or 20 years. That said, someone else might say they'll commit for 5 years, and after that the later years could lean far more toward components assistance technology. So several pieces of the Service differ, likely from the onshore setup. Still, I'd add that certain elements in the offshore side show how the market is evolving — that it increasingly resembles the onshore model when we look 5 or 10 years out at the customer structure. Okay. So with that, many thanks to all of you. I know we've handed you — and we're certainly handing ourselves — a week different from what we probably anticipated. Hopefully we'll be seeing plenty of you in the days ahead, and then we can hold far more discussions directly in person. With that, I'd simply like to thank you for joining this conference call and wish you a good day from here.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Vestas Wind Systems A/S transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Vestas Wind Systems A/S earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Vestas Wind Systems A/S or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.