Good morning. I'm the conference operator at Chorus Call. Welcome, and thanks for being with us on the Salini Impregilo call covering Full Year 2019 Financial Results. <<operator_script>> At this point, I'll hand the conference over to Mr. Pietro Salini, the Chief Executive Officer of Salini Impregilo. Sir, please go ahead.

Pietro Salini

executive
#2

Good morning, everyone, and welcome to this conference call focused on Salini Impregilo's results for the full year '19. As the group's Chief Executive, I'll share a few remarks on how we performed last year and on our future plans, before handing over to Massimo Ferrari, the group's CFO, who will walk you through the details in greater depth. For us, '19 was a busy year — it marked the beginning of our company's transformation toward growing in a more sustainable manner. We launched Progetto Italia, a plan aimed at consolidating Italy's construction sector at a moment when numerous companies have encountered tougher times. Several of these we have acquired, Cossi Costruzioni among them. Our goal is to build a group whose scale, resources and expertise allow it to do 2 things: assist in reviving infrastructure development across Italy; and compete internationally from a stronger position. One of the firms facing difficulties is Astaldi. Being Italy's second largest construction company behind Salini Impregilo, it is the one that would contribute most to our plan for a bigger group combining the finest of Italian engineering. The process of acquiring it is still underway. Even though the final creditor votes are still to be cast on the 26th of March, we are confident the acquisition will go ahead as planned.

Pietro Salini

executive
#3

This complicated deal has already gotten support from Italy's largest bank, as well as Cassa Depositi e Prestiti, the state investment fund. We carried out a EUR 600 million capital increase, brought new shareholders into our capital base, revamped our governance, altered the makeup of our Board, and picked a new name for the new group — that name will be WeBuild. None of this, obviously, kept us from the incredible work we did last year. We finished Cityringen on time. That metro line will contribute a great deal to Copenhagen's goal of becoming the first carbon-neutral capital in the world. In Australia, we secured the contract to build Snowy 2.0, the largest hydroelectric project in that country's history, as it looks to generate more renewable energy. In Texas, we're in the early phases of civil works for the first genuine high-speed railway in the United States. The train service linking Dallas and Texas will not only make travel between 2 cities easier and faster but also help cut CO2 emissions. Onto the next slide. We have close to EUR 8 billion in new orders — a record. The countries these orders came from demonstrate how our strategy of focusing on markets with low-risk profiles is paying off.

Pietro Salini

executive
#4

Australia, Europe, and the United States are among those countries. Over 80% of the value of our orders backlog now comes from them. A number of the United Nations' Sustainable Development Goals are what we are working towards. More than 85% of our revenues from contracts with customers and backlog orders now come from projects supporting these goals. While delivering our projects, we managed to cut our own CO2 emissions by an estimated 25% compared with 2018. In recognition of our commitment to sustainable development, our group rating rose from B to A- in 2019 Carbon Disclosure Project. That places us among the corporate world's leaders in the fight against climate change. On the financial side, meanwhile, revenues and margin met our expectation. Operating free cash flow improved by over EUR 300 million versus the previous year, and we brought down both our gross and net debt. Let's now turn to Slide 5 for a detailed look at our new orders. As I mentioned earlier, we booked more than EUR 8 billion in new orders. That is a genuine record. With that amount we achieved a book-to-bill of 1.66x, and over 90% of the orders relate to projects contributing to the so-called ESG goals.

Pietro Salini

executive
#5

These orders are a reflection of the strategy we have for derisking. Over EUR 6 billion, or 75% of the total value of the orders, sits in countries that carry low-risk profiles. Beyond the countries already mentioned to you, such as Australia, there are some that are new to us. Norway was entered by us for the first time when we signed a contract to build a section of the railway south of Oslo. We also came back to Canada following 3 decades of absence, winning the Hurontario Light train contract just outside of Toronto. It is the first time we have won a contract with Astaldi since Progetto Italia was announced. In the United States, our single biggest market by revenue, we signed an agreement to join the mega project to build a high-speed rail line rain in Texas, from Dallas to Houston. The total value of the project is expected to be about $20 billion, $15 billion of which for the civil works we have contract to us. Our contract include the design and construction of the viaduct, embankment sections, track system and maintenance buildings. On Slide 6, you will see how projects that support sustainable goals have come to make up a big part in the revenue from progress with customers and order backlog, more than 85%.

Pietro Salini

executive
#6

On the revenue side, the United States is still our largest single market, accounting for over 20% of the full year's total. We've also begun bringing in more revenue from Italy. Back in June, the client informed the COCIV consortium — that's the Genoa-Milano — that the project's sixth and final lot had been activated. That adds roughly EUR 528 million on top of the EUR 3.8 billion of financing activity already in progress. We can credit this to the so-called Sblocca Cantieri Decree, which the government issued to unblock projects throughout the country. As you'll see on the chart, over half of last year's revenue came from low-carbon projects — things like metro line and railway construction, which we call sustainable mobility. Examples include the M4 metro line in Milano and the high-speed rail link under construction between Naples and Bari. At the close, our construction backlog was EUR 29.5 billion, up 11%, with an increasing share of projects coming from low-risk countries, as I explained earlier. Slide 7 lays out the opportunity we've identified on every continent. While opportunities exist everywhere, the light blue columns show that we're concentrating on regions carrying comparatively less risk.

Pietro Salini

executive
#7

So that covers Australia, Europe, and North America, plus seizing the right opportunities in the Middle East. Add Canada and the Nordics, and together those regions account for over 90% of our commercial pipeline. Beginning with the chosen market for the 2020 to 2022 period, we worked out the overall worth of potential projects at roughly EUR 580 billion. We then estimate that EUR 120 billion of that figure represented our core addressable commercial activity. Potential projects in this portion of the market were pinpointed using criteria such as country, client availability, familiarity with local suppliers, partners, contractual term and so forth. As for bidding on projects, our focus is on those that align with the group strategy. We carry out a 360-degree analysis of every project, examining, for instance, the technical and economic risk before choosing which one to bid on. In the near term, we are awaiting the outcome of tenders worth over EUR 7.6 billion. Out of that total, EUR 800 million has already been awarded or selected as best offer. The rest are either still in preparation or at the prequalification stage. On Slide 8, we will give you a clear picture of the state of play in Italy.

Pietro Salini

executive
#8

The government has been giving off encouraging signals with its decision to unblock projects that had been stuck for years. I mean the Sblocca Cantieri Decree that was approved in June. The government is also moving toward investing more in infrastructure as a way to revive the economy. And the success we achieved in building the bridge in Genoa has made the government eager to apply that same so-called fast-track model to other projects. The fact that the state fund, Cassa Depositi e Prestiti, became a shareholder in our company as part of Progetto Italia demonstrates how much importance the government places on infrastructure's role in helping revive Italy's GDP. In Genoa, our workers are on site 24 hours a day, 7 days a week. It is a construction site that has never stopped, not even for weekends and holidays. A lot of activities are being carried out in parallel on the construction site so the bridge can be ready as soon as possible. We are doing all of these things in close collaboration with the Mayor of Genoa, who is also the special commissioner overseeing the project. This is a perfect example of how the client and the contractor work together to achieve the best result in the community.

Pietro Salini

executive
#9

Over in Milan, work on the M4 metro line is progressing nicely. During the past year, we came together with all parties involved to sign an agreement aimed at settling a number of unresolved matters and safeguarding the project's financial and economic stability. Fresh credit facilities totaling EUR 400 million were also established. As a result, this ranks among Europe's most significant sustainable mobility initiatives. It will connect the Linate city airport to the historic center in just 12 minutes. Service on the initial stretch, running from the airport to the Forlanini train station, is scheduled to begin next year. At this point I'll hand things over to our General Manager, Corporate and Finance, Massimo Ferrari, who will walk you through the particulars of our full year results.

Massimo Ferrari

executive
#10

Thanks, Pietro. Good morning, everyone. Before we get into the numbers, let me clarify that, as you can see on Slide 10, we have the adjusted figures that we also included in the press release yesterday, which reflect the effects from work under management — that's Lane's JVs. They're also adjusted for the impact of the Venezuela impairment, for both 2018 and 2019. Furthermore, to allow a better comparison, the 2018 results have been adjusted to IFRS 16. So the figures are homogeneous and also include the effect from the leasing accounting coming from IFRS 16. So let's now go into more detail, starting with the top line and margin performance. Revenues came in at EUR 5.3 billion, roughly in line with those of 2018. The main contribution to revenues for the period comes from some major projects, including those of the Lane Group, the works on the high-speed, high-capacity railway between Milano and Genoa, the orders active in Ethiopia, works in Saudi Arabia, such as the design and construction of the Riyadh metro line as well as the construction of Rogun dam in Tajikistan. EBITDA was about EUR 423 million, in line with those of 2018.

Massimo Ferrari

executive
#11

EBITDA for 2018 took a hit from a nonrecurring write-off — excuse me, EBITDA for 2019, the current year, was affected by a nonrecurring write-off tied to Lane's role in the I-4 Ultimate project, amounting to EUR 92 million in Florida, and I'll go into that in greater detail later on. EBIT came in at roughly EUR 184 million, before accounting for the write-off impact on I-4. EBIT also felt the effect of a write-down on certain receivables totaling some EUR 46 million owed by an Italian partner, Condotte, which as you're aware is going through a liquidation process. EBITDA and EBIT margins stood at 7.9% and 3.4%. Excluding the nonrecurring negative write-offs I just referred to, EBITDA and EBIT margins would have been 9.7% and 6%, respectively. That margin gain stems chiefly from 2 factors we talked about with many of you during the road show — the equity road show: improved operating performance driven in particular by the recovery and full consolidation of COCIV, the Milano-Genoa high-speed, high-capacity railway, through cutting to a minimum the share of the insolvent Italian partner, Condotte; and rationalization of overhead costs at both Lane and Salini Impregilo, bringing a lower revenue incidence of roughly 0.3%. Turning to Slide 11, we can see the improvements at Lane in detail.

Massimo Ferrari

executive
#12

Since the 2015 acquisition, Lane's commercial results have been robust. Backlog is up at a 17% compound annual growth rate. And as Pietro mentioned earlier, among the most significant projects awarded to Lane was the high-speed rail line planned between Houston and Dallas, in which it holds a 50% share through a JV with Salini Impregilo. Adjusted revenue at Lane rose 23%, reaching EUR 1.2 billion. In 2019, the JVs running the I-4 project, in which Lane holds a 30% stake, posted negative results. Those results stemmed from a cost increase attributable to mismanagement on the client side. The JV signed a settlement agreement with the client worth roughly $125 million, and it is preparing claims against that client. Because the settlement covers a portion of the additional costs incurred, Lane booked a loss of EUR 92 million on a conservative basis. There will be no further cash or financial impact over the coming months. Excluding that item, EBIT is close to breakeven, helped by overhead rationalization of about EUR 48 million and by a focus on projects that are more profitable. The 3% EBIT target for the midterm is confirmed, and it will probably be reached ahead of schedule.

Massimo Ferrari

executive
#13

On the strategic side, Lane has taken on a fresh business model built around 3 priorities: efficiency, effectiveness and accountability. Lane's focus is on projects carrying very large budgets — typically above $100 million. The emphasis will be on roads and railways in core markets such as California and the New York metro area. Opportunities in water and tunneling will also be examined. When it comes to projects more broadly, Lane is reviewing tenders it could handle either on its own or through a JV with peers and, naturally, with Salini Impregilo. Turning to Slide 12, you can see the group profit as well as the loss beneath the EBIT line. Financial charges come in at EUR 147 million, consistent with the 2018 figures. Those include EUR 14 million stemming from a one-off tax settlement with Ethiopian authorities. And as you're aware, repaying the 2018 bond that matured in August produced a full year saving of more than EUR 10 million, partly offset by EUR 8 million in higher banking interest cost. Exchange rates gave a positive impact of some single-digit million euro, versus EUR 13 million for the prior year. That impact is mainly tied to how the Ethiopian currency performed against the dollar and euro.

Massimo Ferrari

executive
#14

Pre-tax earnings came in at EUR 92 million, versus EUR 129 million. On income taxes, the figure mirrors extraordinary taxes stemming from the Ethiopian settlement, at EUR 19 million. Net result attributable to the parent company reached EUR 40 million, against EUR 178 million in 2018 — a year that benefited from the gain on the Plants & Paving disposal in Lane. If you strip out the Ethiopian tax settlement plus the other net effect I flagged earlier at EBIT level, net results would have come to roughly EUR 65 million, applying a figurative tax rate of 39%. Moving to Slide 13, cash flow. Here you can observe operating free cash flow before dividends and extraordinary items improving versus 2018 by EUR 311 million (sic) EUR 310 million, landing at about EUR 21 million. That improvement came courtesy of better operating results worth EUR 108 million and considerably lower cash absorption from net working capital, at EUR 248 million. During 2019, we absorbed nonrecurring cash outflows of roughly EUR 235 million, encompassing the second and final tranche of the Panama repayment at EUR 135 million, the Ethiopian tax settlement, taxes on the disposal of Plants & Paving amounting to EUR 57 million, and Progetto Italia, with a one-off cost of around EUR 10 million (sic) EUR 9 million.

Massimo Ferrari

executive
#15

During 2019, we saw a change in payments, largely tied to Italian operations, stemming from litigation plus certain high-speed train payments amounting to roughly EUR 237 million. Absent any delay, operating free cash flow prior to dividends and extraordinary items would have come in at EUR 258 million. Alongside keeping revenue growth in mind, cash generation will be our emphasis in the year ahead, and I think what we achieved in operating free cash flow represents a solid move toward that goal. Moving to Slide 14. There you can observe how gross and net debt have evolved. For comparison purposes, as I noted earlier, these figures are consistent under IFRS 16. Leaving out EUR 85 million from our subsidiary Beyond, related to interim financing for Astaldi, gross debt came to EUR 2.19 billion, an improvement of roughly EUR 235 million versus EUR 2.4 billion at the close of 2018. Net financial position stood at EUR 0.6 billion, better by approximately EUR 307 million. As the chart at the bottom of the slide shows, net financial position, once extraordinary cash-outs are excluded and the potential cash-ins that were delayed are included, would have been EUR 152 million.

Massimo Ferrari

executive
#16

Finally, turning to Slide 15, you can see the maturities for our corporate debt shown on a pro forma basis, incorporating the new bond — the bond issues completed in January 2020. The overall size of the new bond issue came to EUR 250 million, and EUR 127 million of that was exchanged against the 2021 notes. In carrying out the Progetto Italia agreement, a credit line of EUR 268 million has been extended, and we also obtained a new revolving credit facility worth EUR 200 million, bringing the total RCF line to EUR 550 million, which gives the group considerable flexibility when it comes to managing cash and the financial position. These transactions allowed us to lengthen the duration of our corporate debt and to lock in more than 70% of it at fixed rates. The pro forma average cost of debt stands at an outstanding 2.6%. I'll now hand over to Pietro for the floor and some closing remarks.

Pietro Salini

executive
#17

Thanks, Massimo. Let me walk you through the main points we'd like to leave with you today. Turning to Slide 17, Salini Impregilo booked a record level of new orders by value in 2019, and it has taken a disciplined approach to spotting business opportunity in markets that carry low-risk profiles. The risks we encountered previously — including those tied to the second Panama Canal — now sit behind us. Our financial profile has remained solid. Over the coming couple of years, opportunity will still lie in a global market this vast. In Italy, conditions are improving, since the government is putting infrastructure at the top of its agenda. Progetto Italia is expected to be a game changer. Backed by our shareholders, we will build a group with the scale, resources and expertise needed to compete more efficiently and effectively anywhere in the world. Astaldi forms a major part of this strategy, and we feel optimistic about completing our acquisition of the company successfully this year. Slide 18 sets out the main guidelines of our business plan, which will be presented during 2020. Progetto Italia will give rise to WeBuild, bringing Salini Impregilo, Astaldi and other smaller players together into one big group.

Pietro Salini

executive
#18

WeBuild is going to have scale, it'll be more efficient, it will run a portfolio that's less volatile, and it will sit in a financial position that's both more flexible and solid. The know-how and the resources this group will command are going to make it more competitive when it bids for projects anywhere around the globe. We continue to grow in markets that hold potential for the group, such as Australia, Europe, the Middle East and North America. Our attention is going to be on projects like sustainable development, hydroelectric dams, metro lines and railways, to name a few. These are complex public works, and they deliver a higher return on sales. We're also developing complementary businesses capable of stabilizing cash flows. Naturally, every contract we bid for passes through our rigorous selection process and risk management. We're pressing ahead with our efficiency push by centralizing a lot of functions, finance and procurement among them, which will make our cost structure leaner and more effective. Turning to 2020 and the same perimeter as of today, we expect to keep up our growth path in order acquisition, getting to a book-to-bill of approximately 1.1x. Revenue should grow at a high single-digit rate, and the EBITDA margin is expected to range from 7% to 7.5%.

Pietro Salini

executive
#19

We feel confident about getting to a margin nearer 7.5%. That projection is based on the group's business perimeter as it stands now. An additional update is going to be given when the business plan is presented. The forecast likewise leaves out any effect that the COVID-19 virus could have on business dynamics. The group, in compliance with government measures and providing maximum protection for the health of stakeholders and our employees, has committed to guaranteeing, where possible, operational continuity at construction sites in Italy and abroad. Thank you all for your attention. We can now take some questions and answers.

Operator

operator
#20

We'll take our first question from Emanuele Gallazzi at Equita.

Emanuele Gallazzi

analyst
#21

Yes. There are 3 questions I'd like to ask. First, regarding the EBITDA margin: for Salini Impregilo you reported a margin of 10.4%. During this call, you also referred to a favorable contribution from Condotte. Could you shed some light on that? Second, on guidance: you essentially provided guidance of high single-digit growth at the top line level. I'd just like to grasp what assumptions underlie that guidance. And finally, on Lane: EBIT remained negative in 2019. So could you share your expectation for 2020 — should we see breakeven?

Massimo Ferrari

executive
#22

Emanuele, could you say that last question again? We didn’t catch it.

Emanuele Gallazzi

analyst
#23

Right. That applies to Lane and to EBIT, which remained negative in 2019. I was wondering whether you're expecting it to at least break even in 2020.

Massimo Ferrari

executive
#24

All right. Thanks, Emanuele. Let's begin with the EBITDA margin. We cited 2 separate effects, with a positive one stemming from the COCIV consortium. To start, full operational activity restarted at the Progetto. And beyond that, we also capture the marginality percentage — the EBITDA margin — from the partner that's under a procedure, Condotte, as you're aware. That follows the law and follows the contract. They couldn't comply with the contract in '18 and '19. So we also receive the 30% stake that comes from Condotte. As a conservative measure, we've also booked a risk fund for the credit we hold toward Condotte. So the net result is a positive effect on EBITDA. Then we can skip the second question and move to the last one, Lane — we expect 2020 will land at breakeven and, we hope, in positive territory. As for the guidance, we provided only some figures, some targets, since we're preparing the business plan and are very close to disclosing it. But naturally, we must factor in the extraordinary COVID-19 situation — not just for Italy but for the world.

Massimo Ferrari

executive
#25

Right now, as Pietro said earlier, every one of our job sites is operating—chiefly the Genoa site, though the M4 and the Milan metro line are running too—but we can't exclude a few short-term effects when it comes to production slowdown.

Emanuele Gallazzi

analyst
#26

Alright, just a very quick follow-up, if I may. Regarding the net financial position, you brought up that delay in cash-in from the Italian operation for EUR 236 million. I'd just like to get a sense of when you expect those receivable claims to be cashed in.

Massimo Ferrari

executive
#27

During 2020, a portion of the cash-in has already occurred, and additional amounts are anticipated over the weeks or months ahead.

Operator

operator
#28

Our following question comes from Jamie McFarlane at Bybrook Capital.

Jamie McFarlane

analyst
#29

I have a couple of things I'd like to ask. First, what has cash flow looked like so far this year, through the start of 2019? And what cash effects do you anticipate during H1 as a result of the COVID situation?

Pietro Salini

executive
#30

Thank you for asking that. Right now, we aren't anticipating any reduction in cashing in because of the COVID situation. Naturally, it hinges on how long this lasts and which steps the government—and the various governments—will implement at the job site. That is going to have some impact. Naturally, should these circumstances persist across a number of months, some slowdown will occur. We're anticyclic, since as you probably realize, construction sites are different in that this situation doesn't affect them over the short term, unless we're forbidden from working, which is a separate matter. But that isn't the situation at present. So from that perspective, we don't foresee any specific impact. Naturally, the fact that during this period we can't be physically present at meetings, can't travel freely between one location and another, can't move about, means the supply chain will hold up for a certain number of weeks. But if every job site, or if the whole industry, runs into a problem, then it becomes a general problem, not something tied to us specifically. So I don't see anything particular occurring for us and not for the others—that's my view.

Jamie McFarlane

analyst
#31

Okay, so what's your guidance for H1 cash flow, not counting the Astaldi purchase?

Pietro Salini

executive
#32

No. Those numbers will come alongside the budget and business plan we're handing to the Board in the next few weeks.

Massimo Ferrari

executive
#33

And Jamie, as you're aware, we're looking at the creditors' vote happening at the end of March. However, the capital increase that Salini Impregilo is putting into Astaldi will take place over the summer — likely in September. So the cash-out tied to that Astaldi capital increase won't hit during the first half.

Jamie McFarlane

analyst
#34

Okay, so what is the cash sitting at the holdco in Italy? I know the accounts give consolidated cash and other financial assets, but it's usually a specific figure. What was that number as of December 31 in Italy?

Massimo Ferrari

executive
#35

As you know, once we release the full-year results, we provide the breakdown by debt and where the liquidity sits. I can confirm that over EUR 1 billion of cash we held at the close of 2019 is nicely distributed among the various countries and continents. It sits very near the operations. A lot of our cash is in the U.S., and roughly the same amount is in the Middle East and Australia. So on average we hold EUR 180 million, EUR 200 million in the main 4, 5 countries outside Italy. Our cash in Italy is a small amount, also because we run the cash pooling without using the Italian accounts.

Jamie McFarlane

analyst
#36

Okay, so considering how much of the capital increase you used up in H2 last year, and since H1 is typically a half that burns cash, it seems you likely won't be able to fund the Astaldi capital increase, or you'll need to draw down heavily on the RCF. I have to say I'm quite surprised, because the guidance you provided in June and then during the equity road show was that H2 would be a cash-generative half. Yet you've already used up half of the capital increase. So it sounds like at this point you may not even have the capital to acquire Astaldi.

Massimo Ferrari

executive
#37

No, no. The entire amount from the capital increase is still with us. Regarding our net financial position, as we said earlier, there was some shifting of payments that, naturally, weren't anticipated until year-end. The final days of December are invariably very demanding for us, since we're collecting money from clients and every receivable is large. So in certain years we manage it, and in others we see some shift. The cash from the capital increase is still coming in. We cut a great deal of short-term lines and hot money. As we said earlier, we substantially raised the long-term portion of our corporate debt, and you have to remember that this also includes leasing. So we have EUR 100 million more in debt stemming from IFRS 16. Thus, on the long-term side, we are improving our gross debt figures.

Jamie McFarlane

analyst
#38

Okay, but isn't the real issue that you still aren't collecting — you said the second half would be generative. I think the fairest comparison is one of your peers, CMC: just a year ago they said the receivables would be collected in a month's time and 2 months' time. Then within 3 months they were in concordato, and the bonds were trading at EUR 0.05. So it feels like this capital increase has already vanished. And with COVID, are you raising any additional emergency capital? Because given where the stock is and given cash flow issues, it feels like there's going to be another bankruptcy in the Italian construction space.

Pietro Salini

executive
#39

No, but I believe something is being misread here. When you look at—when you mention that there will be a shift regarding the cashing in of certain items from Italy at EUR 235 million, we are not saying that this—that the amount had vanished. What we said was that, for example, we have a judgment in place and there was a transaction that must be approved through a very lengthy procedure by the authority, the anti-corruption authority here, which has taken longer than anticipated. But this is an executive order from the judge, so we can seize the money if we do not wish to carry out the transaction for these items. And the same situation applies to the high velocity train: there is a finalization of recognition by the client of certain past items that have to be cashed. And they are moving through this procedure. We expect this amount, which had been expected before the end of the year, to be cashed in over the next coming weeks. That is the situation. So these things—the fact that you put forward that the amount has been burned, I don't think that is the right...

Jamie McFarlane

analyst
#40

My suggestion is that everyone simply examine your cash burn across the past 4 years. More than EUR 2 billion in cash has been burned. I mean, there's -- I mean, nobody can dispute that. The facts are there for you to check. And each half, you make a commitment to collect during the following half. You stated, plainly, we can return to the H1 call, but H2 would generate cash, and it did not. Half of the capital increase has already been burned. So I mean, I don't know. Like, how are you...

Pietro Salini

executive
#41

I mean, of course you've got a bias, and you've already — well, I can't change those, and you're probably not one of our investors. But to put it another way, what I'd say is that we faced quite a few issues inherited from the past and from the acquisition. As you've observed, every one of the write-offs traces back to matters that arrived with the amalgamation of Salini into Impregilo and that originated in the past. Nothing has been written off from current operations or from contracts awarded under this management over these 5 years. All of the write-offs concern the past. So what you're bringing up is the fact that if we must pay for something that occurred previously — yes, probably we have to manage that. And we did. At the same time, we did succeed in doing everything required to recover this amount — it will take time. As I mentioned, take Panama, for instance: it isn't an easy job. It's litigation that is very lengthy and complex. We had to pay EUR 600 million upfront for Panama alone. So perhaps those are the things you're referring to.

Pietro Salini

executive
#42

The fact that a few clients are pushing back payment on EUR 300 million by a couple of months — I'd say that's not the ideal situation, but it does happen. So perhaps that accounts for your perspective. I'm not sure what's...

Jamie McFarlane

analyst
#43

I mean, it's pretty rough if you're looking at EUR 300 million in delays scattered around, and you've just brought in EUR 600 million of capital on the premise that H2 will generate cash — I think you ought to provide guidance...

Pietro Salini

executive
#44

Yeah, but that's not right.

Jamie McFarlane

analyst
#45

You ought to provide guidance for H1 2020. Since you're expected to collect all this cash that got delayed, should I assume that H1 2020 will be the...

Pietro Salini

executive
#46

Each year — if you’ve ever taken a look at the paper — as we’ve just disclosed, and likely if you examine it in more detail, you’ll come away with a different view.

Jamie McFarlane

analyst
#47

Could you share your outlook for H1 2020, please?

Massimo Ferrari

executive
#48

I don't believe we ever provided guidance on cash generation over a 6-month horizon. What we've consistently stated is that this company must produce cash over a long-term period — meaning some year. That's what we communicated during the equity road show tied to the capital increase. Nobody claimed that within 3 months or 6 months we could generate cash at either equity or operational level. So we're pursuing various levers. A number of them contributed successfully to the 2019 results. Others are being worked on for 2020. Fortunately, our geographic diversification is very sound. As a result, we don't need to depend on any single project or any single country. We're able to confront this extremely challenging situation as well. Regarding COVID-19, we hold a substantial amount of cash. We still have a EUR 500 million backup line available. We have plenty of guarantees and surety support. So we can also handle this difficult period from a very strong financial position. I think we can proceed to the next question.

Operator

operator
#49

The following question comes from Alessandro Tortora at Mediobanca.

Alessandro Tortora

analyst
#50

Alright. I've got, say, 4, maybe 5 questions, but they're all really, really brief. Number one concerns the claim you brought up on the Lane side. Could you tell us, say, what the underlying issue was, okay, behind that agreement you reached on the Florida project? Was it, say, I don't know, anything -- some kind of mistake you made on, say, how the project was planned? Just so we understand the reason. My second question concerns the timeline for, say, the Astaldi deal and the -- for the amalgamation, if you're clearly taking into account the uncertain situation you stick with, say, an amalgamation around summer, before summer, just to get some idea. The third one is about Texas. So clearly, you're confident about booking, okay, the project as soon as possible. Just to get an idea, what are the next, okay, official steps needed in order to include the project in your backlog? The fourth question was about, yes, was about cash generation for 2020, in the sense that, considering the shift you mentioned during the presentation on the cash-in of some Italian projects, are you confident, say, that at least in 2020, you get debt reduction to a similar extent, thus far equal to at least EUR 200 million, so the delay in payments you saw in Italy?

Pietro Salini

executive
#51

Let's begin with Lane and the purpose behind what we did there. Now, this contract—the I-4—is one where Skanska serves as the managing company. They recorded the losses, and they determined that those losses could be offset by submitting a request to the clients. They are negotiating a transaction with the client, and they intend to sign it. Our view is that this deal is not adequate, and we are insisting that they cover the losses they have caused to the joint venture. At the same time, we have booked the same losses that we anticipate from this project. So we believe that, on one hand, we have established a provision for I-4 covering the full loss anticipated by the managing company. And on the other hand, we are pursuing litigation against the company over their conduct on this work. Beyond that, Lane in 2020 is expected to post a positive EBIT of roughly 2%. So Lane's turnaround has been accomplished. And the fact—and I'll take this opportunity to mention that Texas is now progressing even faster than anticipated. I just got a message from Texas Central saying that the process of securing the final authorization and license has been finished, and they are entirely confident that financial closure can occur in the third quarter of 2020.

Pietro Salini

executive
#52

For Lane and Salini, this creates a completely different trajectory. Lane is set to become one of the biggest construction infrastructure companies in the U.S. From this project, we'll get roughly EUR 2 billion in turnover annually over the next 7 years. And Salini — as we have, as we put it, WeBuild — will have a very large exposure to the U.S. market going forward. Turning back to Astaldi, we're quite confident that on 26 of March, the creditor will express their positive agreement to the transaction, and that the procedure in the tribunal will move as quickly as possible, of course, while respecting the laws. But everyone is aware that this amalgamation is needed for Astaldi, for the people, for the employees, for everybody, and for Italy. So I believe there's a very good atmosphere in terms of bureaucratic attitude toward the conclusion of this transaction. So the 2 put together will make a company that in 2022 will make more than EUR 11 billion of turnover, with a different financial structure and a totally renewed portfolio. I think it's very important. We'll give this list — this line in the next coming weeks as soon as is possible to make a clear view on what the effect of this pandemia will have on the market and on the future of this company, but those things remains, and the fact that the need for the infrastructure in Texas would remain, the process with Astaldi will remain.

Pietro Salini

executive
#53

Alright, so there will likely be some adjustment, but the core thrust of the business plan stays intact. Take, for example, 100 or the cluster of the business plan — it's about moving into an entirely new area, namely maintenance. As you've observed, Italy is in serious need — badly in need. Yet it isn't just Italy; this applies worldwide, where demand exists for a big operator in infrastructure maintenance, something that isn't being approached on a global scale. So in my view, there's space for a large operator. On top of that, this would simplify things for states, for concessionaires, for the network that needs maintaining, by having a big partner such as us. And it gives the ability to coordinate the smaller and smaller partners and local partners, delivering a quality product while at the same time offering a single contract to that same concessionaire. Picture, for example, what Autostrade needs, what ANAS needs across the whole maintenance network — a single operator that offers them a maintenance contract, and that this operator can then distribute to local players, to the broker community, a share of the work, while preserving quality, preserving the monitoring and all those aspects for those concessionaires, who probably require an operator of that kind.

Pietro Salini

executive
#54

Beyond that, this model is applicable in other parts of the world as well. We brought it up earlier, though we lacked the time to examine what maintenance the infrastructure in the U.S. requires, or in France, Germany, or Spain. Every one of us faces the same issue. We have reached the end of the useful life of infrastructure that was constructed in the past, and nobody has considered a comprehensive fix for the problems that come up. Because of that lack of forward thinking, we now confront the collapse of portions of this infrastructure. There is also a chance for us to get into this line of business. It will have a very large impact on stabilizing the cash flow and will provide a steady turnover derived from it, which can make our activity less volatile. So I believe this matters a great deal within the portfolio of opportunities we have.

Massimo Ferrari

executive
#55

Alessandro, the new business plan we're going to disclose involves a different business model, where obviously we still have the core business in the EPC segment. As you know — Progetto Italia included — we want those 2 separate streams: the maintenance, monitoring, and repairing stream, beginning in Italy. After that, we've just sent letters to 10 major infrastructure funds so we can build a partnership with them and bid on the enormous volume of works that involve the equity side of the investment, with a global partner working alongside us. So we're also working on stabilizing cash flow over a shorter period by using this new, different business model — and by leveraging the Progetto Italia shareholder base as well as our stronger financial position. Texas — Pietro probably has some news.

Pietro Salini

executive
#56

Regarding Texas, as I mentioned, we've just gotten word from the client that the final authorizations are in place. So this means there will be a very significant shift in Lane's activity given how important this single contract is, and it carries very good marginality. We've already handled that with our clients. They're pleased about it, and it's a major job. So I believe that this — if things go as we've anticipated, we'll be closing it during the first quarter. These contracts will even have some favorable impact on the full year 2020. But at the moment, turnover is expected to see some effect. It matters in effect for the 2021 accounts and for the business plan. So we'll talk about that later, when we present our business plan in detail.

Alessandro Tortora

analyst
#57

Alright, and Massimo, apologies — the question concerned the cash-in shift, right. If, say, at a minimum, taking the uncertainty into account, we can treat that as a reduction, right, in terms of, let's say, gross, but even net debt for 2020, in part?

Massimo Ferrari

executive
#58

Absolutely, yes.

Alessandro Tortora

analyst
#59

All right, all right. And the final question — apologies — concerned the guidance for the top line, which you place in the high single-digit area, with a focus on Italy. Given, let's say, all the effort the government is making to accelerate execution of the project, do you think Italy could beat that high single-digit top line growth this year, hopefully?

Pietro Salini

executive
#60

Yes. We’re hopeful that we can. Naturally, a substantial portion of our portfolio still comes from legacy business that is slow performing. And given those government actions, we anticipate revenue growth from that portfolio will exceed expectations. What we’re seeing now — and I just talked about this with government members — is that infrastructure has become a priority for them. They’re looking for ways to make it happen. I recently heard from the Minister of Transport that she will appoint a number of commissioners empowered to streamline all activities and cut through bureaucracy. That kind of approach will, of course, transform — it will be transformational for Italy when it comes to developing, let’s say, turnover for us in Italy, and it will have a major impact. The fact that we face no other competitors is also significant, because we are now the player for Italy on those large projects and, let’s say, I believe we must give the government a responsible response in terms of employment and in terms of development.

Pietro Salini

executive
#61

Like we're showing with the Genova bridge — regardless of all that — we're delivering, and the bridge stands there today in under 1 year. First concrete was poured by us in June of last year, and we'll close it ahead of schedule. So, in under 1 construction year, that bridge exists. I don't believe there's much to add there. These days everyone discusses the Genoa model in Italy and how to get things done. Sure, that requires very solid administration and the authority to make decisions, but also a truly strong company to carry it out. It isn't just about authority. So if you've got plenty of people who likely hold the authority to decide everything, yet no truly strong company, you can't achieve it. That's all there is to it.

Operator

operator
#62

Gentlemen, we have no further questions on the list. So I'd like to hand the conference back to Mr. Salini for any closing remarks. Mr. Salini, would you care to offer any closing comments, sir?

Massimo Ferrari

executive
#63

Is there another question?

Operator

operator
#64

No, sir. At this moment, no questions have been registered.

Pietro Salini

executive
#65

Thank you.

Massimo Ferrari

executive
#66

Alright, thanks so much. Should anything else come up, feel free to reach out to our Investor Relations team.

Pietro Salini

executive
#67

I appreciate that.

Massimo Ferrari

executive
#68

Thanks a lot.

Operator

operator
#69

Thanks, everyone, for being here. That brings the call to a close, so you can hang up your phones now.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Webuild S.p.A. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

This call discussed

For developers and AI pipelines

Programmatic access to Webuild S.p.A. earnings transcripts and 132,000+ others is available through the EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Webuild S.p.A. or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.