Webuild S.p.A. (WBD) Earnings Call Transcript & Summary
July 26, 2024
Earnings Call Speaker Segments
Operator
operatorGood morning. I'm the conference operator for Chorus Call. Welcome, and thank you for being with us on the Webuild First Half 2024 Financial Results Conference Call. Pietro Salini, Chief Executive Officer, is hosting today's call, alongside Massimo Ferrari, General Manager, Corporate and Finance. <<operator_script>> Right now, I'd like to hand the conference over to Mr. Pietro Salini. Sir, please go ahead.
Pietro Salini
executiveGood morning, everyone, and welcome to the conference call discussing Webuild's first half 2024 results. I'm Pietro Salini, the group's Chief Executive; Massimo Ferrari, our General Manager, is here with me. Let's begin on Slide 5. Before we get into the first half results, let me pause and express my thanks to all the people who work alongside us. I've said this before, and I will continue to say it. What we accomplish comes from our team's efforts, day by day. I'm referring to 90,000 individuals working together, representing over 150 nationalities, with nearly 40% ages under 50 -- 55, sorry. I wanted to extend my thanks to all the strategic shareholders including CDP equity, Intesa Sanpaolo and Delfin, who backed us through a crucial moment in the history of the group as well as our minority stakeholders. I would also like to renew my gratitude to those who collaborate with us and believe in our values, especially the Italian international financial institutions and last but not least, our partners, clients and the nearly 20,000 companies of our supply chain. Now let's talk about our first half results. The results achieved in the first -- in this first month of 2024 speak for themselves.
Pietro Salini
executiveTwelve months ago, we set out on a course that brought the group to its present position. From Progetto Italia onward, we have made good on commitments across numerous areas — tackling risk within our operations, reducing leverage in our financial structure, and recognizing the opportunity in an expanding market, all of it made possible by our robust expertise and capabilities. We have succeeded in posting solid results, semester after semester, despite the difficulties encountered during recent years. There's no need for me to recount the global pandemic, supply chain bottlenecks, geopolitical tensions, and macroeconomic headwinds, including inflation and the corresponding monetary policies. From the start of this year, we have secured new orders valued at over EUR 7.5 billion. That converts into a fresh record backlog of EUR 65 billion. Out of that total, EUR 56 billion pertains to construction projects and completely covers our 2023-2025 revenue and EBITDA targets. The next business plan we begin with a new backlog that is more than comfortable. On the operational side, we ended the first half of the year posting double-digit growth. Revenues rose 20% to EUR 5.5 billion. That exceeds what we recorded across a full 12-month span merely 5 years ago. At the same time, EBITDA climbed 41% to EUR 407 million.
Pietro Salini
executiveNet income came in at 3x the figure posted during the first half of last year, at EUR 82 million. On the financial front, we continued reducing leverage while keeping our financial position solid. We ended with a net cash position of EUR 1.4 billion, positive for the fourth half in a row. Gross leverage sits below 3x, much better than the average across our peers. Moving to Slide 6. We have consolidated our development, becoming bigger, stronger and safer. The overall market remains strong, with infrastructure investment programs being implemented across a number of countries. The industry is evolving, and so is the customer mindset. That presents us with significant opportunities. There is a sense of urgency around developing infrastructure in response to global trends in energy and climate transitions. Infrastructure is going to be a crucial investment. When current geopolitical tensions are resolved as well as they are now to improve people's lives. We are what clients need to deal with the challenges posted by these trends. We are an undisputed global player in the construction of large complex civil infrastructure. For more than 100 years, we have been exporting engineering excellence all over the world.
Pietro Salini
executiveWe are a global leader in water infrastructure and rank among the top 10 players in sustainable mobility infrastructure. And we keep delivering on our consistent strategy, which focuses on margins and cash generation. These targets rest on three pillars: number one, focus on building highly complex and innovative infrastructure so that we remain a reference partner for our clients worldwide. Number two, consolidate our leadership positioning in core markets such as Europe and Italy, Australia, United States and Middle East. Number three, gain scale so we can invest in different strategic projects. Scale allowed us to continue investing in innovation and safety of our people. As we have previously mentioned, health and safety is a priority for the group, also included in our targets. In 2023, we successfully managed to reduce the lost time injury frequency rate to 2, and we are continuing this trajectory also in 2024. This has been possible, thanks to intensive programs, with more than 400,000 hours of training on health and safety only in the first months of 2024. There are also many other initiatives to engage both employees and subcontractors. When comparing our injury rate to those one of the -- our main European peers, it is evident that we are the best in class.
Pietro Salini
executiveBut we won't be happy until that injury ratio hits 0. As of today, we possess the platform, the proper governance, centralized processes and procedures that work, so we can capture the many opportunities in front of us. We can also move into new segments, and there is room to keep enhancing margins along with cash conversion rates. On Slide 7, we'd like to demonstrate how we deliver projects for our clients. We can say with pride that the record-breaking figures we keep posting come from a year of commitment, innovation and passion for what we do. That establishes us as a trusted global trader in this sector. Since 2012, over 270 complex infrastructure projects have been delivered by us around the world. This matters a great deal because insurance companies and other financial players back our business, since it demonstrates low operational risk. Over the last 4 years, we finished projects that make life better for present and future generations across many countries. Among them are metros, bridges, dams and hydroplant. We refer to the San Giorgio Bridge in general. It has also turned into a model of efficiency and collaboration. In Italy, we delivered the New Eni Headquarter in Milano.
Pietro Salini
executiveOverseas, we have the Cityringen Metro in Denmark, the Forrestfield Airport Link in Australia, the Al Bayt Stadium <<inaudible>> at the FIFA World Cup in Qatar, and the Long Beach International Gateway in the United States. During the opening months of this year, work keeps moving forward on the Grand Paris Express excavation, the Metro Line 16 tunnels, and handover of the initial stretch of railway linking the <<inaudible>> stations in CSC. Last week, the new earth station for Metro Line 6 in Naples was inaugurated. In December, we will hand over the full metro line in Milano. That shows how committed we are to finishing the project in line with what the client requires. And that is a major draw for clients — they see — they want infrastructure finished on time and serving people at <<inaudible>>. A few weeks back, we put forward a groundbreaking plan for restructuring Milano and Siro Stadium. Through carrying out this project, we will have built into practice the means for the two football clubs and for the city to have one of the finest areas that holds its own against international high-quality standard space. On Slide 8, you can see how our scale lets us phase advents better and successfully handle the labor shortage and supply bottlenecks.
Pietro Salini
executiveIndustrializing the whole value chain made this achievable. Alongside over 19,000 companies, we've brought in sophisticated technologies and automation to cut costs and raise the standard of what we deliver. Whenever clients arrive in the market seeking an infrastructure player, the fact that we can bring a big workforce together counts in our favor with them. We got to nearly the 90,000-people mark worldwide. And we anticipate another 36,000 hires by 2026, with, naturally, some departures from our job sites. In Italy, heavier infrastructure spending has led to a hunt for sufficient skilled labor to carry out the project. Because of that, we launched training schools as part of the Cantiere Lavoro Italia program. That program we devised for trucks and for training personnel. We anticipate bringing on 10,000 people in the country by 2026. The initiative keeps growing, particularly in the Southern region. Under Cantiere Lavoro Italia, it serves as the rapid training hub for upskilling tunnel-boring machine pilots using a TBM simulator. As you're aware, the group leads globally in tunnel links, and we're likewise among the top TBM operators. Following a circular economy approach, we established a new firm named Webuild Equipment and Machinery, which will refurbish previously used tunnel boring machines so they can be put back to work on new projects.
Pietro Salini
executiveBecause we centrally manage the supply chain, we've been very effective at tackling bottlenecks. We put money into a range of innovative solutions, such as a new robotic free cash segment plant that opened in 2024. It was the first facility of its kind in France, designed to raise productivity while keeping construction sites safe. Today, Novaga is a key strategic element for delivering big, complex infrastructure and, at the same time, safeguarding the workers. One of the innovative solutions we've rolled out is, for example, the hyperbaric escalation, a sustainable technique pioneered and brought in for the first time in Italy. It relies on compressed air for <<inaudible>> where water is present, guaranteeing the highest standard in FM safety. Moving to Slide 9, let me demonstrate how we're drawing on our competitive capacity and consistently gaining from an infrastructure market that keeps growing. I'd like to remind you that we've had a very strong order intake since 2021. We're talking about a total worth EUR 57 billion in the first half of 2024, and we're confirming this positive trend with EUR 7.5 billion of new orders already secured. That amounts to more than 65% of what's expected for the full year 2024, with over 95% of it originating in key markets that carry low-risk profiles.
Pietro Salini
executiveThe order intake contains roughly EUR 500 million in contracts where we've been named preferred repeater. The bulk of new orders originate outside Italy — for example, the Trojena projects in Saudi Arabia and the Western section of Line 15 of the Grand Paris Express in France. In addition, we've been chosen in joint venture as preferred bidder for a contract on huge rail projects in <<inaudible>>. The high backlog, which we have tidied up, fully covers the current business plan, leaving room for additional order intake selectivity. The order backlog's geographic spread strengthens our resilience against a temporary shock that might hit one region or another. Over 85% of the amount stems from low-risk markets. Italy accounts for the largest share at 44%, with Australia next at 17%. As we described on the last call, we are going through a paradigm shift into the sector. This alters the attitude toward delivering projects, derisking both our backlog and our approach. First, price is no longer the primary criterion for winning bids. Competition over technical solutions and health and safety standards is growing in Europe, including Italy and Australia. Indeed, most new orders over the last few years were won thanks to a better technical offer, which leads to better marginality at product level.
Pietro Salini
executiveSecond, the majority of the work we have on the books includes a price revision formula, which helps us offset inflation risk. In Italy, the new procurement code for <<inaudible>> Italia brought in some important items for how the sector relies on these rules. For example, there is a requirement to build in a price review process, faster payment methods, and contractual advances of up to 30%. Also, a collegial body has been created, known as the collegial <<inaudible>>, to resolve disputes promptly, since otherwise those disputes could slow down the normal execution of work on the <<inaudible>> project. Third, over the last years we have successfully put in place new contract standards, and these carry lower operational risk. For instance, progressive design and deal, used mostly in North America, is a contract foundation built on strong collaboration among the client, the contractor and the designer. Everyone is brought in early during design and planning when the project budget is being defined, which means less execution risk during the construction phases. I will now hand the floor to Massimo for the financial details.
Massimo Ferrari
executiveThanks, Pietro, and good morning, everyone. We'll begin on Slide 11. What we'd like to do here is provide an overview of the infrastructure market: the construction and engineering sector is set to stay robust for many years ahead, with that expansion powered by both public and private investment. The pace would be substantially higher than GDP growth. There's no denying that infrastructure investment serves as a catalyst for GDP growth, and so it's essential for public debt sustainability. The world is changing quickly, and governments must tackle challenges effectively. Infrastructure investment is helping address mega trends like population growth, water and resource scarcity, climate change and the energy transition. And we offer a broad range of solutions to support them, from railways and metro lines to bridges that connect people, from desalination and water treatment plants to hydro energy storage schemes. What we do enhances the lives of millions. Digitalization is an opportunity as well. We're monitoring it closely, especially with data centers expansions. Before I walk through the results, let me remind you that, as is customary, we're presenting adjusted figures to reflect the recurring performance of the business.
Massimo Ferrari
executiveThe specifics of the adjustment made for you are available in the appendix. Moving on to Slide 12, you can see just how robust our operating results were during the first half of 2024. Revenue came in at EUR 5.5 billion, which represents a 20% rise compared with the prior year. The main drivers were projects in Italy and Australia. As Pietro said earlier, these results look even more remarkable when set against where we stood 5 years ago. Over the last 6 months, both revenues and margins have come in above what we delivered across the whole of 2019. EBITDA grew 41% year over year to EUR 407 million, giving us a margin of 7.5%. The main reason is the execution of the group's high-quality order backlog along with greater absorption of corporate costs. It also reflects the renegotiation of contracts during the second half of 2023 and the rollout of efficiency initiatives. Further factors include contract management using new formulas that reduce operational risk and provide tighter coverage of inflation risk, which supported our marginality as well. EBIT climbed 63% to EUR 226 million, and results remain on track with our guidance, with sustained growth in revenues and margin.
Massimo Ferrari
executiveMoving to Slide 13, we can examine how revenue is distributed. Our business is nicely balanced, since over 90% of revenues originate in low-risk nations. Italy is our primary market, accounting for 35% of revenues. High-speed rail lines that we're constructing throughout the country are the biggest drivers of this growth. Italy has transformed considerably over recent years. A great deal of infrastructure investment has been set in motion, and clients have taken a more collaborative stance. I'd like to point out that roughly 80% of revenues stem from projects that aren't tied to Italian funds connected with next-generation EU programs. As Pietro will explain later, plenty of opportunities exist in Italy even beyond the PNRR. Yet Italy makes up just one portion of our business, which is genuinely global. We continue to bring in 65% of our revenues from outside Italy. Australia ranks as our second-largest market, with 24% of revenues originating from that continent. In North America, where we mostly operate via Lane, our subsidiary, we brought in 13% of our revenue. And across Europe, we receive 9%. Work in this region centered on France, Norway, Romania and Switzerland. The Middle East accounts for approximately 9% of the total. Turning to how revenue is distributed by activity, over 85% relates to projects that help meet sustainable development goals set out by the United Nations.
Massimo Ferrari
executiveWe've been confirmed as the global leader in the water sector, and we rank among the top 10 for construction of sustainable mobility projects. On Slide 14, you'll find the P&L below the EBIT line. We posted net income of EUR 82 million. That's more than 3x the level reached in the first half of 2023, at EUR 23 million. Net financial costs decreased by EUR 21 million. The positive effect is linked to the increase in financial income to EUR 81 million, up by about EUR 50 million, mainly thanks to bank interest on cash stock. Financial expenses are EUR 134 million, an increase of EUR 23 million versus 2023. The rise in net financing costs is mostly due to the higher cost of debt on bonds. This has been partially compensated by lower bank charges, thanks to better management of RCF lines in first half of 2024. At the bottom of the slide, you can see the reconciliation from reported net profit, which amounted to EUR 54 million, to the adjusted one. The adjustment refers to accounting nonmonetary items, such as EUR 20 million for the amortization of the positive bargain we registered in 2020 relating to install this acquisition and EUR 7 million relating to the Clough acquisition.
Massimo Ferrari
executiveTurning to the next slide, we'd like to highlight Webuild's positive credit trajectory, focusing on the key balance sheet items. As we've noted repeatedly, generating cash is a central element of our business plan. In December 2021, we achieved a historical net cash position for the first time. Since then, we've succeeded in keeping it positive. At present, we hold a strong net cash position of EUR 1.4 billion, an improvement of EUR 1 billion compared with our prior net cash balance at June 2023. Working capital management kept playing a crucial role during the opening months of 2024, acting as one of the levers behind our cash generation. That stems from our robust commercial activity, along with a number of measures we put in place to manage working capital efficiently. Those solid results are also mirrored in better credit metrics, as shown by gross leverage's steady downward trend, reaching 2.8x in June 2024. That figure is net of a temporary effect tied to the liability management we'll cover on the next slide. This outcome stems from gross debt that has stayed nearly flat in recent years, even as the group expanded exponentially. On Slide 16, we present the key figures for our corporate debt and the liquidity profile; with the new bond issued in June, we successfully refinanced the bond that matured in October '24 and partly the 2025 one.
Massimo Ferrari
executiveWhen it comes to liability management, that involved issuing a bond worth EUR 500 million along with a tender offer, and the result was EUR 71 million repurchased on the 2024 notes plus EUR 271 million on the 2025 notes. The rest of the cash generated by the new bond is going to be used to repay the receival 2024 notes when they mature. We closed June 2024 with a comfortable and exceptional liquidity position exceeding EUR 4 billion, which includes EUR 970 million of undrawn RCF lines. Nearly all of our corporate debt carries fixed rates, with an average cost of roughly 5% and a duration longer than 3 years. Over the last 2 months, both Fitch and Standard & Poor have improved our rating outlook, as Pietro mentioned earlier; if anything stands out from these rating reviews, it is that our growth and the trajectory remain positive and very visible. Both rating agencies moved our outlook to positive from stable while affirming the rating at BB, according to Standard & Poor, and the outlook revision reflects the view that it could raise the long-term operating to BB+ over the next 12 months, provided the group sustains a resilient EBITDA margin and free operating cash flow to debt.
Massimo Ferrari
executiveContinued order intake would back this up, and it would further enhance our ability to generate cash flow. Fitch likewise gave good credit to our solid business profile, describing it as consistent with an investment grade engineering and construction company. Our strong order book, along with a healthy pipeline and project opportunities, was also mentioned by Fitch. At this point I'll hand things over to Pietro, who will cover market dynamics and offer some closing remarks.
Pietro Salini
executiveThanks, Matthew. I’ll begin with a quick look at our commercial pipeline. We’re looking at a highly promising market with plenty of opportunities. On Slide 18, you can see that our commercial pipeline is still robust at over EUR 90 billion, while the global market is estimated at more than EUR 50 trillion over the next 4 years, so it appears to be a very small share of that. That gives us confidence in how sound and durable the market is for the years ahead. Because infrastructure acts as a catalyst for growth, various governments in key countries have launched multiple investment plans. Investment will be driven not only by traditional infrastructure such as rail, roads and so on, but also by energy and smart leading sectors. Thanks to our strong positioning in our key countries, our commercial momentum is running very well this year. We have already submitted EUR 18 billion of bids and are awaiting an outcome. We are focused mainly on Europe and North America, Australia and Middle East, where we are expanding our activities in segments such as hydro, sports and water treatment plants. Turning to Slide 19. Let’s have a look at how we see the Italian market.
Pietro Salini
executiveRoughly 35% of our group's revenue comes from Italy. That matches the share competitors hold in their own domestic markets. We're committed here to delivering the meaningful volume of orders we've booked over recent years, though plenty of other opportunities lie ahead. Over the next few years, additional railway projects will need completing, including the Salerno-Reggio Calabria and Adriatic Alliance. In late June, the European Parliament revised the trans-European transport network guidelines, adding numerous new rail lines, and this update will bring additional funding. We also anticipate investment in metro lines, sports, stadiums, hospitals, and a hydroelectric plant. We're committed to backing the energy transition. We recently signed an agreement with Alison to develop Pumped hydro energy storage projects across Southern Italy. We're also working to help communities cope with drought. Opportunities exist for us in the water sector. Our subsidiary Fisia recently secured the biggest water treatment project in Italy in a decade. Fisia brings long-standing expertise in this sector, with over 95 years in the business, and ranks among the most competitive global contractors in wastewater treatment and desalination, especially in the Middle East.
Pietro Salini
executiveAt the same time, steady expansion is anticipated for the data center market over the next several years. In Italy, total investment between 2024 and 2028 is projected to climb to roughly EUR 7 billion beyond 2028, with exponential growth anticipated, tied to the uptake of artificial intelligence systems. We can also draw on the expertise of our Swiss subsidiary, CFC, which has been active in the data center market since 2021 — that is, of course, the Messina bridge, which appears neither in our target nor in our folder backup. Slide 20 offers a further perspective on our second-largest market, Australia. With the integration of class, we now operate as one single company. Our backlog in that country stands at EUR 10 billion, mostly cost-plus types of countries. Among our projects are the construction of Australia's biggest renewable energy project, Snowy 2.0, and the country's largest urea plant for fertilizer production. We — just to name a few more, we are upgrading Western Australia's largest wastewater treatment plant and developing a portion of the City Metro Airport rail line. Thanks to our expertise and know-how, the group is prepared to size a market valued at nearly EUR 400 billion, including new business segments such as energy, which is delivering a major boost over the medium term.
Pietro Salini
executiveThe Powering Australia initiative from the government anticipates billions of dollars being invested in the energy transition, with the goal of positioning the country as a leader in producing clean energy. Beyond that, we're also examining fresh opportunities in hospitals, transmission lines, ports, desalination plants, and water treatment facilities. Slide 21 shows the group's two other key markets. In North America, we're developing a new hub for an integrated approach to both the American and Canadian markets, which came to nearly EUR 5 trillion in construction investment. Investment in rail, roads, and industrial and energy infrastructure will stay the main driver. We recently introduced our primary U.S. media channel, a campaign titled "webuild what American needs". Our aim is to build awareness of our global leadership in the infrastructure sector and of our long history in the country, stretching back to the 19th century. With over 1,000 kilometers of bridges and Biodex already constructed worldwide, we're prepared to apply our experience in service of U.S. authorities for rebuilding the bridge in Baltimore that collapsed. In May, alongside our U.S. subsidiary, lane, we unveiled a concept design for a safer and more innovative reach.
Pietro Salini
executiveWhat we proposed was meant to accelerate building that bridge, and that matters a lot for regional mobility. Back in 2018 we did the very same kind of thing, offering our expertise to construct a replacement for the bridge that had collapsed in <<inaudible>>. That job took us a mere 15 months to finish. Looking at the Middle East, the construction sector there should hit close to EUR 800 billion over the next few years. This comes thanks to our on-the-ground know-how and our long history in the region. We're gaining from major infrastructure spending, chiefly in Saudi Arabia. Let me make one thing clear: the reports you might have come across regarding a possible pullback on the Neom projects relate mostly to the residential portion of that work. The Saudi market is still robust. Plenty of investment is flowing into the capital, Riyadh, tied to the <<inaudible>> position and the FIFA World Cup, which will take place in 2030 and 2034 respectively. Across the Emirates, Qatar and Bahrain, big infrastructure efforts should get underway, notably metro lines in each of their capitals, along with high-speed rail links. We keep watching for chances beyond our core markets, and with our local know-how and technical skill development and projects around the globe, we can pick work that offers an excellent risk-return profile.
Pietro Salini
executiveOn Slide 22, a number of key elements are contributing to our sustainable growth. We now have a group with scale, a sizable and high-quality backdrop, sound financial discipline and risk management, and a more efficient organization. Our backdrop fully covers our current business plan, allowing us to focus on the next door. We are continuing effort on one of our strategic priorities, which is derisking. We are revising our contract department to strengthen the monitoring process to ensure the timely identification of issues that could impede the progress of the words or imply additional cost. It will allow us to act frontly and execute claim early. As I said before, try and choose our capability and experience because we excel at delivering large projects, providing efficient solution to compress challenges. Thanks to this capability, we are proud to be unmatched and unique in this regard. As we navigate through the new paradigm of client relationship, our trajectory is clear. we are set to remain a global infrastructure leader unlocking opportunities in new markets and sector. We are making progress on the cost efficiency plan. At the exact midpoint of the current business plan we have already surpassed more than half of the schedule initiatives of the EUR 180 million in cost savings targeted by 2025, we have already identified initiatives for more than EUR 110 million.
Pietro Salini
executiveWith our scale, we can boost profitability and generate more cash flow. That lets us put more money into innovation as well as health and safety, and it gives us the ability to be choosier about which clients and suppliers we work with. Scale is what lets us invest successfully in processes that optimize working capital. That's one of the levers we use for generating cash. We've launched many initiatives aimed at speeding up the compression of markets into cash. On Slide 23, we reaffirm our dedication to sustainability through the ambitious targets laid out in our ESG plan through 2025. Innovation, clean technologies, health and safety, circular economy, digitalization, and inclusivity form the necessary framework for advancing our ESG strategy and hitting the goals contained in the plan. That plan rests on the same three main pillars that have guided us successfully in recent years: green, safety, and inclusion innovation. Let's begin with Green. By 2025, we aim to cut our carbon intensity a further 10% relative to the level recorded in 2022. We can get there through investment in clean technologies like green TBMs — machines that can lower energy and water consumption while raising safety. On health and safety, as we've already covered, we are already best-in-class when compared with our main European peers.
Pietro Salini
executiveBut we won't be happy until that injury ratio hits 0. We're confident that by 2025 we can bring the ratio down another 6%, helped as well by our education and training initiatives. When it comes to gender inclusion and diversity, we've set goals for raising the number of women in leadership at the group. By 2025, our aim is for 20% of managers to be women. On innovation — apart from being a vital strategic factor for guaranteeing worker safety, it's essential for staying competitive in the market. We've committed to putting no less than EUR 430 million into clean tech projects. The principles of sustainable development are completely embedded across the group, and we firmly believe they ought to be shared throughout the whole supply chain. That's why, in July, we introduced 15 environmental rules that will apply to all our suppliers and partners. We want to build awareness and establish a shared vision on this matter. These commitments keep earning recognition from the market. In the first half of 2024, we will confirm a sustainability leader through CDP's Climate Change 2023 program with an A- rating. That's higher than the regional European average and the global construction sector.
Pietro Salini
executiveTurning now to Slide 24. Our 2024 guidance is being confirmed. Order intake got off to a strong start in 2024, helped by a significant contract in Saudi Arabia. As of today, nearly 2/3 of the new orders anticipated for this year have come in. Just to remind everyone, for 2024 we expect a book-to-bill ratio above 1, together with revenues of more than EUR 11 billion and EBITDA above EUR 900 million. For net cash position, our target is over EUR 400 million. We stay committed to our gross debt reduction goal of EUR 200 million, EUR 250 million within 2025, and to paying a stable dividend to shareholders totaling EUR 160 million, EUR 170 million for 2023, 2025. Consistency is essential for us, given the commitment we have made with all the clients to deliver very large and strategic infrastructure, and given our ability to generate cash year after year, as we have already shown. Clearly, after the first half 2024. We are very optimistic about the full year results. Thank you for your attention. We are now ready for the Q&A session. So as not to slow things down, we encourage you to focus on the group strategy and other broad initiatives that underline its current and future financial performance.
Pietro Salini
executiveIf you have any additional questions about the figures, or about other details in the table, or about some technical points that came up during the presentation, the Investor Relations team will be available after the call to answer them. Thank you, everyone.
Operator
operator<<operator_script>> Our initial question comes from Emanuele Gallazzi at Equita.
Emanuele Gallazzi
analystI'll begin with a couple of questions — the first about net working capital, the second about profitability. On net working capital, you posted a sound bid at the free cash flow level in the first one, with, let me say, a still solid contribution from net working capital. Since you confirm the guidance on the net financial position, could you help us understand what evolution you expect for net working capital in the second half? And what are the main moving parts there? The second question concerns profitability. Given — even in this case — the solid margin expansion in the first half, can you give us some color on how the Australian market and the U.S. market performed in terms of profitability during the first half? And let's say, on the U.S. market, are you still targeting reaching breakeven at the EBITDA level by year-end?
Pietro Salini
executiveYes. To return to the second question regarding market profitability, naturally we remain on schedule to reach online breakeven in the near future. The primary adverse contribution across recent years stems from certain legacy projects, which produced EUR 350 million in losses over the last 5 years. As of today, that work has been entirely finished, and collection under the contract amendment should occur by 2026. So the turnaround plan continues on track. Regarding the Australian market, we are naturally doing our utmost in assembling Class. We have brought together Klaff and Webuild, and we are now among the very large players in Australia, and I believe the conversion of most contract types that previously involved remeasurement and now operate on incentivized cost plus or other formats, as we described regarding collaborative contracts, naturally carries a significant effect on marginal value as well. On cash flow, Massimo...
Massimo Ferrari
executiveYes. Let me expand a bit on the marginality point. Australia has been a key contributor during the first half, and we anticipate it will stay so through the second half as well, though we're looking for an improved business mix on the margin side in that second half, as we kick off some very significant projects in the Middle East and carry on with the profitable activity in Italy. On working capital, we continue to anticipate some enhancement, some release of cash. We achieved what we had expected and, I believe, talked through during earlier meetings and on the conference call, concerning the balance between new advanced payments and the repayment of the advance payments we received in '23 and '22. So we keep -- we expect to hold that balance steady through the second half and to stay on the same trajectory where CapEx is concerned. So certain improvements will stem from how we manage receivables and payables as well as work in progress, the WIP, which delivered a strongly positive contribution during the first half. And that derives from the centralization we've referenced repeatedly with all of you and with the investors.
Operator
operatorOur next question comes from Matteo Bonizzoni at Kepler.
Matteo Bonizzoni
analystTo start, I have a follow-up regarding those points you were raising, Massimo, about the cash flow cycle in the back half of the year. Since, when we look at your guidance, you're steering toward broadly above EUR 500 million in net cash, and at the close of June you sit more than EUR 1 billion ahead of that. So a bit of reconciliation is needed, particularly because you mentioned during this call that regarding the delta between contract asset and contract liabilities, no deterioration is anticipated in the second half, which incidentally, in line with seasonality <<inaudible>>. Thus I simply want to square your broadly above EUR 500 million guidance with where you stand right now, at EUR 1.4 billion. Could you expand on that a little? My second question concerns gross debt. So I'd say something of which you are likely fully conscious, given this very strong set of figures and positive outlook: the sole remark, let's say, that investors have occasionally raised is gross debt. So the market observes that gross cash is climbing.
Matteo Bonizzoni
analystAt this point it's well above EUR 3 billion. You've set a goal of cutting real plan gross debt by EUR 250 million, which the market would very much welcome, I think, including when it comes to the potential rating on the shares, to see gross debt, let's say, moving steadily down toward EUR 2 billion. So my question is how much of that enormous gross cash pile do you expect to be able to deploy to pay that debt down gradually. Obviously the gross <<inaudible>> ratio lines up quite closely with plenty of other companies, 2.8%. You've noted that the rating agencies have upgraded the outlook. So no worry about debt. But just tell us, in an absolute number, where we ought to see some improvement in that very billion figure as well, on gross debt too. First question, and a quick follow-up on CapEx. I believe we don't see the cash statement in the press release, nor in the presentation, CapEx. So my thinking is that gross assets rose by EUR 300 million, sorry, between December and June, so across 6 months. So I take from that number that your CapEx in <<inaudible>> figure. So could you give us a figure?
Matteo Bonizzoni
analystAnd on top of that, I anticipate — well, what I'd anticipate for the whole year is that it lands closer on CapEx. So even with CapEx running very high relative to what we've seen historically, your cash generation is still going to be strong. Could you give us some updates on that?
Massimo Ferrari
executiveThanks, Matteo. Can you remind me what the second question was? I was concentrating on the third one. What was the second?
Matteo Bonizzoni
analystThe second item is obviously something you're fully aware of — a question involving list gross debt, no.
Massimo Ferrari
executiveUnderstood — this matters a lot, since we are holding to and preserving the goal of bringing gross debt down; something may occur in '24 and more in '25. Beyond that, though, the interest charges tied to gross debt total roughly EUR 90 million. The remainder stems from the use of the RCF line. We're working to optimize this exercise, and we achieved some improvement during the first half, with further improvement possible in the second half. Then — as you likely recall from 2023 — we had certain nonrecurrent and nonmonetary items that we aren't expecting for the second half. So we expect to hold the cost of debt line in check and considerably better than 2023. We're still at work — you didn't ask, but it's worth noting as well on the tax line — and we launched a program that will produce some effect in 2024 and another effect in 2025. We anticipate a material effect in terms of some EUR 10 million of savings. Then as for CapEx, we spent roughly EUR 360 million during the first half. We expect to spend approximately EUR 390 million, EUR 400 million in the second half.
Massimo Ferrari
executiveNaturally, we began purchasing CapEx back in 2023. As a result, we’ve managed to spread the cash outlay across three separate years: ’23, ’24, and then the most recent one, ’25. On top of that, we have all the optimization around refurbishment and so forth. As for what you’re calling some elaboration—some bridge from the net financial position of the first half to the target we’re maintaining—we’re aware that the average consensus already sits above our target. There is, naturally, some balance between a new advanced payment and the one we need to use for production, but we expect to beat the target. We still don’t know whether it will be by as large a margin as the one we achieved in the first half of 2024. I don’t know if Pietro has any further news, Pietro.
Pietro Salini
executiveThere's nothing unusual here—it's simply that, naturally, the results for the first half of 2024 are extremely substantial. So what I mean is that, even while feeling very upbeat today about delivering those results, a few days ago I was already saying how positive we felt regarding not just the semester but the full-year guidance as well. Our track record has always been to deliver and to overdeliver, and we have never overpromised on what we've done previously. So I believe holding our guidance steady has real value, because this is a plan we put together carefully for the whole budget. Given what I'd call some very, very strong results in the first half, that could also—it would also mean we might be able to be more positive on guidance at the end of the year. But I wouldn't revise the guidance on that account. Let's say, let's be out <<inaudible>>. I think this is the best thing we can do—to be serious, to stick with our plan, and to deliver.
Massimo Ferrari
executiveOn the claims side, there's no fresh material uptick. What we're seeing is purely the rise that comes with production moving forward on certain projects. I'd put it this way: for the PSN, our goal is to hit consensus and then exceed it.
Operator
operatorAlessandro Tortora from Mediobanca has the next question.
Alessandro Tortora
analystStarting with the first item, that's tied to the project we're currently executing. Could you give us a sense of whether any significant contracts this year involve you negotiating client-side modifications, or adjustments to the contract formula, similar to what you did last year? That's question one. Then the second one follows up on your net cash position. You explained before what mainly drove that, let's say, elevated cash level. What we want to grasp is whether you can tell us the primary reason behind this steady liquidity level. Is it that claim management is being handled successfully or promptly, and you're doing even better than in the past? So really, just to understand the part played, for example, by the level of claims, or stock claims, relative to the past, in this, let's say, high liquidity level. And the final question concerns the cash level, which is quite high. Is there a possibility we might see, for instance, an acceleration on the buyback side, in terms of both size and buyback program, for you?
Massimo Ferrari
executiveLet me begin with the final question. Yes, that should be feasible. On speeding up the buyback — largely because liquidity in our shares has risen considerably, since our free float stands at roughly 45%. With greater liquidity in the stock and full compliance with all the rules, we have room to do a bit more, though strictly on a tactical basis, to help the market keep liquidity in the shares at a high level. As for the substantial cash position — the bulk of it stems from successful bidding activity and our commercial operations. That's the liquidity we gained in '22 and '23, and we continue to raise more in '24 tied to new contracts. Some cash also derives from renegotiating certain large projects carried out in 2023, since the effect was spread across the years ahead. So the overall impact will be distributed and divided over various years. We aren't renegotiating any major contracts. Our relationship with the key clients is very solid, especially in Italy with RFI, aimed at holding the milestones and accelerating every project where we're encountering the usual, normal difficulties.
Alessandro Tortora
analystAlright, if I could just ask one quick follow-up about your initiative — earlier you brought up the tax rate side, so could you give us a sense of what sort of action you're putting in place? And I'd guess this is probably focused on Italy?
Massimo Ferrari
executiveYes, we kicked off a program containing five separate initiatives. I can't be — I can't provide further specifics, but some benefit will emerge from reorganizing certain activities, primarily in Italy, though not exclusively there. You need to keep in mind that we pay, naturally, a great deal of — the bulk of our taxes in Italy, and since we have numerous different companies, we can optimize from a group organization standpoint. The same applies on the international side of the business, because we have both companies and branches. And naturally, with everyone following all the rules in Italy and abroad. So we can also better manage the taxes line in terms of cash out, naturally.
Operator
operatorMoving on, our following question comes from Enrico Coco at Intermonte.
Enrico Coco
analystYes. I've got a question about Fisia — the water treatment business. Its contribution today is small, at 3% of group revenues. Could you give us some figures for this business, or the production volume or profitability you expect this year? And would you consider bringing in some investors to speed up growth in water treatment, or will you keep 100% of Fisia? That's the first question. Then, if I may, I have a question about the first-half figures. I saw that contract liabilities are up around EUR 800 million versus December, and contract — so this should be tied to advanced payments. And if I take — and this year, year-to-date orders are around EUR 7.5 billion; in the same period last year, orders were EUR 18 billion. So I'm trying to understand why you get a higher level of prepayments even though year-to-date orders are much lower than in the same period last year. Is this related to the huge prepayments in the Middle East for the NEM projects?
Pietro Salini
executiveFor me, this matters because, as we mentioned earlier, water—and water as a strategic answer to the problem, the building of water deposits—means having the chance to make water available, to treat it, and to reuse water coming from treatment. Maintaining every aqueduct and the other lines is, I believe, going to be one of the really crucial activities in the future that we can pursue with our capabilities and skills, since we are #1 worldwide in water products. So our aim is to turn this activity into that of an EPC contractor. This will be set out clearly in the new business plan: our activity moving from EPC contractor to investor and also to operator in this field. We are currently working on bringing in a strategic infrastructure fund that can work alongside us and draw on the leverage of Fisia's capable skills and experience. In my view, the water market offers strong growth potential and is estimated at roughly EUR 400 billion globally. Our subsidiary Fisia has a long history and an excellent track record in building water treatment and desalination plants around the world, and we want to take this expertise into new markets such as Italy.
Pietro Salini
executiveIn our home markets right now, desalinated water accounts for just 4% of what's consumed overall. And as you can see, water scarcity has turned into something that's weighing on the whole population. What I mean is, 5 million people are currently affected by drought. Agriculture is another area that has faced a massive challenge. So this is something we're able to focus on, and restructuring the reorganization involves not just, as I said, carrying it out, but also running operations and putting investment into that sector. Massimo, what were the other questions?
Massimo Ferrari
executiveYes. On the blend of that advance payment and the solid uplift we secured during the first half, naturally, it stems from the combination of new orders. You brought up the Middle East, and that's correct — when we landed a project worth roughly EUR 5 billion equivalent, 10% of it, which represents one payment, equals 520%. That works out to EUR 1 billion, just so you have a sense of it. So we also examine the cash profile when selecting what to bid on, the shorter list. And certain contracts and certain regions deliver a stronger contribution. As for contract assets, like I said earlier, the rise simply reflects production moving ahead on some project where we already hold certain claims that are under discussion with the client. But on the whole, we cut the stock considerably, as Pietro noted earlier, over the past 3 years by a very material amount.
Enrico Coco
analystLet me follow up on Fisia, if I could. Would you be able to give us some figures regarding the company and perhaps the valuation that you have in mind for the after?
Massimo Ferrari
executiveAt the moment, Tafisa has roughly EUR 600 million in backlog, and it will generate approximately EUR 230 million in revenues across the full year. That said, all the initiatives Pietro brought up earlier, which we kick off in September, are going to deliver a substantial lift to Fisia when it comes to marginality and growth. Naturally, we will always retain the majority stake in the company -- however, discussions are underway with several major private investors, both about joining Fisia as shareholders and about taking part as a developer in certain initiatives. This would be a subject for the next business plan, which we will draft late in 2025. And in all likelihood, we will provide some high-level guidance in the first month of 2025.
Operator
operatorOur following question comes from Giuseppe Grimaldi at BNP Paribas.
Giuseppe Grimaldi
analystI do have a single question regarding the rest of the pipeline. It moved higher, particularly in the near term versus what we observed in Q1. So 18 billion in orders are awaiting an outcome. I was wondering how confident you are going into the second half of the year about matching a similar level of order intake to what we saw in H1. And on that, could you add some color on which region basically holds the standards, and whether anyone accounts for more? Any color there would be helpful?
Pietro Salini
executiveOkay, the first thing I'd like to point out is that within this pipeline you referred to, there isn't the best in a bridge, for example. And that by itself represents EUR 6.5 billion of per quarter revenues order for Webuildiuild. So when you add that on top of the 18 points something of the pipeline, that produces a fairly substantial number of it. We expect to fully cover not only the guidance we provided in around one, but we can also be positive having a, let's say, more than on the order intake expected in the first half. So naturally, these results in the first half mean that we are more than positive on what is the remaining part of the year, because there have been some shift, some delays into the awards. The first half could have been even more positive if those delays had not occurred. So we are positive on the, let's say, order intake. I want to stress the fact that on an order intake on a portfolio of over EUR 56 billion of order that. We have already enhanced whatever it comes, do not have a significant impact in terms of turnover or revenue.
Pietro Salini
executiveI'd not focus too closely on those figures, because naturally, with such a large volume of orders already booked for execution, we take a very cautious stance on new contracts and new clients, for two important reasons. The first is that launching all of those contracts at the same time, as we're doing right now, places considerable strain on the organization. The second is that we already have plenty on our plate. So when you look at the workforce growth, we just told you that we plan to bring in 10,000 people during the year — I mean, hopefully that covers just the recruiting, not merely placing people into the organization, and recruitment itself is a substantial organizational effort. So I'd say we need to stay grounded and push fully toward those growth targets, which are very substantial. You saw, when we look at 20% of the turnover — turnover growth for the semester — and 41% growth in EBITDA, well, let's say that's a very positive statement, a very bold one. So we don't want to claim that fantastic opportunities lie ahead in the future.
Pietro Salini
executiveWe aim to stay quite cautious and keep tracking this steady stream of updates. I'm not claiming the second half is going to bring an unpleasant shock. Quite the opposite — my view is that we'll see a strongly favorable second half, and naturally we can build on where we stood at the close of the first half, yet my intention is to steer this company toward growth that lasts, even if it stays as robust as it has been before — you brought up how, over the last 5 years, we doubled, since we doubled the company's size across those 5 years, and that was no small feat. It used to be a EUR 5 billion business and this year it's running at EUR 11 billion. So what I'm saying is everyone has to recognize this represents remarkably substantial expansion for any company across 5 years' time. Doubling in size, an order of magnitude, widening the EBITDA picture — back then we were generating 1/3 of it. So the growth we've delivered up to now is really meaningful. This is a long-term undertaking and a long-term plan, and we've put in place every process that serves the future well.
Pietro Salini
executiveI have a lot of confidence that this company is capable of meaningful growth over the years ahead. If you apply 10% growth annually, that translates to closing at EUR 15 billion under the business plan. That is genuinely substantial for a company focused only on infrastructure. So within the business plan, we must — naturally, as you mentioned and as we discussed earlier — consider additional lines of business, meaning moving into sectors that currently sit outside our core, everyday activity, so to speak. That matters because growth and scale have created a meaningful shift compared with the past. So this, I believe, is the key point: scale like this transforms the outlook entirely, and the internal demand we have is able to generate value. Consider that when we refer to an EUR 11 billion company, you could be speaking of EUR 500 million in engineering services required within the company's needs each year. You are talking about EUR 600 million of special foundations as an internal need. When you look at other lines of business, you can see that each of these is a significant dimension on its own, capable of delivering added synergies and added efficiency if we handle all those needs in-house as one company or a division specialized in the products we require to execute our business plan.
Massimo Ferrari
executiveIf anyone else has a question, we have room for one final one.
Operator
operatorAnd our final question comes from Amit Deo at Deutsche Bank.
Mehmet Dere
analystI actually have four questions. First, on the contract renegotiations that brought in some inflow of EUR 223 million, do you expect anything further to come from that going forward? Then another question about the net cash position. There's obviously been a lot on this call already, but given the range is quite wide between where we are now and your target, could you give us some kind of indication whether the year-end net cash position will land closer to the current position, or closer to the EUR 400 million? That would be very helpful. And since you mentioned interest costs as well and the RCF, can you give us some specifics on the EUR 970 million RCF regarding its maturity and the interest you're paying on it? Also other fees. Then on liability management, are there still some high coupon bonds in the cap structure, and would you consider tackling some of them ahead of maturity? Obviously, the '24 maturity is coming up soon and you'll repay them from cash on the balance sheet.
Mehmet Dere
analystHowever — do you have any other plans for the remaining bonds? Then my final question concerns the credit rating: you also mentioned the positive outlook you're getting from S&P and Fitch — what internal targets do you have there? Would you — or is there an objective of reaching investment grade? And if there is one, when would that be?
Pietro Salini
executiveTo start with, thank you — and I'll do my best to address the questions that lean a bit more toward strategy. For the finer details, I'd ask that you route those to the Investor Relations team, since that makes everything smoother and gives you more depth than this call can likely offer for your models and questions. Take the rating, for example — that's a very important matter. For us, reaching investment grade or quasi investment grade has been a long-standing objective; we've been chasing it from the very start. In our view, the cost of our debt is one of the areas we need to improve on. And beyond that, having the backing of financial institutions for our growth — securing the guarantees required to do our job — gets a meaningful lift from a stronger credit rating. So we're pursuing this with real determination. We aren't diverting the cash elsewhere. We don't — we hold ourselves to very strict financial discipline, because we want to secure that rating and keep it, for exactly those reasons.
Pietro Salini
executiveOne more point I think matters, and we didn’t bring it up earlier on this call — everyone should hear it: we’re able to pull out some value while we’re already securing it from the savings across the various processes. Centralization doesn’t just give you control; it also delivers savings. On top of that, it will lift the quality of what we deliver and the margin on our results. That side mattered a great deal. Growth within the business also counts for a lot, since it naturally lowers the weight of general expenses while we keep excellence and our processes intact — and those efforts to examine retail processes and draw value out are things we’ve already completed, and we intend to keep going. So those, I’d say, are the key items: financial discipline, plus working to place and streamline every process so we capture the benefits and the cost reduction we anticipated.
Massimo Ferrari
executiveLet me just add a bit about the RCF lines — that's a rolling program involving a number of different banks. Every 2 years we renew each facility, with the varying exposure across those banks. This is a variable cost, so it runs mainly higher than the average fixed cost on the bond — we aren't renegotiating any major contracts at the moment. But as I said earlier, we're in good talks and something like a partnership with our main clients. On the bond side, we're open to any opportunity starting from September, whether with the previous bond at the top or some new bonds should interest rates come down in the near future. So thank you very much. I'll leave all the remaining answers to the investor relations team. And thank you, everybody, for joining. Thank you very much.
Operator
operatorLadies and gentlemen, we appreciate your participation. That brings the conference to a close. You're welcome to hang up your phones now. Thanks very much.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Webuild S.p.A. transcript — plus 132,000+ transcripts from 7,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.
Get the API View API docs →This call discussed
For developers and AI pipelines
Programmatic access to Webuild S.p.A. earnings transcripts and 132,000+ others is available through the
EarningsCalls.dev REST API. Plans from $39.99/month — full transcripts, speaker segments,
full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.
More tools for stock research
OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in Webuild S.p.A. or any ticker on your watchlist.
StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.