West Wits Mining Limited (WWI) Earnings Call Transcript & Summary

October 14, 2026

ASX AU Materials Metals and Mining shareholder_meeting 38 min

Earnings Call Speaker Segments

Jessica Fertig

executive
#1

Okay. I think we'll just get started as people come through. All right. Good morning, everyone, and thank you so much for joining us. A very warm welcome to our shareholders and also to the investors who are new to the West Wits story. I'm Jess Fertig, and I look after the Investor Relations for the company. I'm delighted to be joined by Rudi Deysel, who is the CEO and Managing Director of the company. So today's session is really about understanding how Qala Shallows ramps up. We've received a lot of very thoughtful questions recently about production. So as we know, and Rudi will chat about during this webinar that building an underground mine isn't a straight line and development comes first, followed by ounces later. So over the next sort of 25 minutes or so, Rudi will explain why the production profile looks the way that it does. So for everyone today, you can submit some questions. We do have an online chat forum. Thank you to everyone who has already submitted questions. We have actually coated those in today's discussion. Rudi welcome. Thank you so much for your time. I know that you are busy and you're in Sydney for the Gold conference this week. We have a lot about -- we've had a lot of questions about production lately. What do you most want investors to understand today?

Roelof Deysel

executive
#2

Yes. Good morning, Jess. Good morning to everybody. Nice to be here in Sydney in Australia. So thank you very much for the opportunity. Look, I think the main thing that everybody needs to understand, we are building an underground gold mine. We are building a mine that will produce at steady state 70,000 ounces per year. The buildup is not a straight line. It's mainly driven by the infrastructure that's required to get to that steady state. We are building, we are developing declines that you use to get from surface to underground workings. And you do open up levels, which will then be the vein that will actually bring out this ore from the stoping blocks that which is the main mining areas. And our focus is to get those developments in good high standard quality so that it can stand up for the life of mine of this project, which is 17 years. So we need to make sure that they are done properly and sustainable. So that's the main focus for us now.

Jessica Fertig

executive
#3

Yes, brilliant, Rudi. And it seems that investors kind of expect that output will climb steadily towards that 70,000 ounce production rate. Why doesn't it work that way?

Roelof Deysel

executive
#4

Yes. Look, once again, I've used it a few times, but mining is not a cheese factory, and it's not just pouring out tonnes. Once again, mining is hard work, and you need to set up these things. In a perfect world, you will have that straight-line buildup. But we do open up the mine as per plan. Everything is as per design as it's been in the feasibility study. And the progress is excellent. I mean we've already developed over a kilometer of tunnels underground. And that's quite a lot of development less than a year. So the project is really going excellent and following the plan that we set out in the beginning of -- when we started with this project in the definitive feasibility study.

Jessica Fertig

executive
#5

Yes, fantastic, really. Now in addition to obviously, all those infrastructure milestones that you have to build in the underground mine, there's also -- it's never just easy going, as you mentioned. And the past few months have tested the operation a little bit from safety -- a couple of safety causes to working through some challenging ground. What has the team learned in this quarter? And how has it strengthened the path forward?

Roelof Deysel

executive
#6

Yes. Look, once again, if you build a new mine, there's so many variables that's got to influence on a mine. You are going into unknown rock areas. Especially if you're close to surface, that upper levels are very oxidized and soft. So you need to put in support in there. And sometimes you get through ground that isn't as great as expected. But once again, there's engineering solutions to those. You go through put in sets, you do concrete support, which do slow down the typical advance rates in those tunnels. But once again, the team dealt with it excellently. And as you go deeper out of that oxidite areas that's close to surface, which is, by the way, also influenced by weather patterns. And we did have a lot of rain during the summer. And that was one of the aspects we had to deal with that had an influence on the unfortunate incident that we had on the mine. And that just got the team to focus much more on safety. We are a company which feels that safety is absolutely first. Our people are more important than anything else. We don't want anybody to get injured at all. So we have an absolute policy of zero harm in terms of safety. And we've got a system where we really encourage the employees to report unsafe conditions as well as do stoppages. If a place is unsafe. And I mean, it's in the law, in the Mine Health and Safety Act of South Africa as well in Section 23, which says that no employee must enter any unsafe areas. And those are, for instance, the stoppages that we encourage them to do. So you stop, you make safe and you proceed further. And that process is through, and that's what we call our leading indicators. Over the time, you would actually see that those stoppages and leading indicators reduces month by month. Which obviously accelerate the productivity in how we operate. And then obviously, your advance rates that also increases.

Jessica Fertig

executive
#7

Yes, fantastic, Rudi. And now just talking about productivity, A lot of investors are asking about ounces produced on a quarterly basis. Will they get any updates on that. But you're talking about we're not looking at ounces, what metrics can investors look at?

Roelof Deysel

executive
#8

Yes. So in a typical mining environment, you would first do the shaft and infrastructure before you actually bring up any metal at all or produce any ounces at all. The great thing about this project is that we actually do a lot of our infrastructure development on reef. So it's diluted gold that we bring out because it's development waste that comes out with the ore. Now once again, the priority and the focus is really that tunnel, that decline, that shaft. It needs to be able to bring in equipment in and out of life of mine. So once again, I don't want to say that because it's designed in the project, but that ounces that comes out is almost accidental. Until you get to that point where you actually got what we call to stop blocks, and that's where you actually produce the ore that you will actually put into the plant, and that is the high-grade material. Now currently, as our plan stands and once again, this is by design as per DFS. The first real stopes, we were able to have a few stopping panels earlier that we saw that opportunity to get quick tonnes and quick ounces out very early. But our real stoping production is planned to be to get it by February 27, which is not far from now. And that is when the first real high-grade ore will start coming out. And that's why we put it out in the public as well that our production profile is for 2027 that 10,000 to 15,000 ounces and that will build up in '28 the 42,500 ounces as per plan and then ultimately hitting that steady state in 2029 at 70,000 ounces.

Jessica Fertig

executive
#9

So, Rudi, just carrying on that, what is in place at the moment at the mine to support that step up once the stoping starts?

Roelof Deysel

executive
#10

So to get that steady state, you basically need to have 3 levels. Now we've already broken into the first level. And then the decline will develop downwards and then you open up to second level. We talk about half level. So in effect, it's 6 half levels that we need to create before we can really have that sustainable steady state production. Now that will open up over time. So once again, if you look at the buildup, it's rather than a linear line, it's almost like hockey stick. You've got very little in the beginning and then it starts accelerating an increase in that slope of that buildup. And that's why you see the profile that we actually got out there in the market. And that shows exactly how the profile is. And if you look at the production profile of the life of mine, that's exactly how it's been set up.

Jessica Fertig

executive
#11

Fantastic Rudi. Now just shifting gears a little bit. We've been getting quite a few questions coming through the chat room. And one of them is actually around the Project 200 scoping study, which we sort of semi released to the market. What they're asking is what work is still needed to meet the ASX requirements, in particular, is there any drilling or upgrades to the resource classification of when can shareholders realistically expect the scoping study announcement?

Roelof Deysel

executive
#12

Yes. So the main purpose of a scoping study. And I don't want to really go too much into the view? Or do I agree with the view once again, there's rules that we need to abide by the ASX, but the purpose of the scoping study is to give you the guidance to proceed to the next level of the study, which increases the certainty and the design of the project, which will take you then to the next phase, which is a prefeasibility study or a higher level of feasibility study depending on the type of information that you've got in the engineering that's required to get to that level before you actually start mining. Now the scoping study was completed and it came out with excellent results that we actually do have a blueprint and a pathway to get to that 200,000 ounce production. And it also increases with that increased capacity, the life of mine, which is very positive as well. So that is the only issue once again. And I don't think that's the purpose of a scoping study, but I don't want to go into that detail. Scoping study your level of classifications would normally be less. And that then actually give you the certainty that there is a business case to do more drilling, which will bring more inferred material into your reserve classifications, which is measured and indicated. Now the scoping study and the reason why we didn't bring it out is because we have to have more measured and indicated in -- especially in the initial phases of this project. So currently, there is optimized work being done because there is some work that we can do on the block model and resources itself and even on the scheduling of the project itself, we did add some prospecting rights to the project to the mining right, which actually do have some measured and indicated material. And it wasn't at the time available when we did the scoping study, which we are catching up now on, and that will optimize the schedule that will bring some more indicated measured into this study, which then will enable us because the ratio of measured and indicated has been much higher in terms of the inferred that we have, which will then enable us to actually bring it out to the market. So that's the intention now. That work is currently happening. We will bring out that results in a moment we can because, obviously, it's great news for the company as well. So we would like to bring that information out to everybody so that they can see our great investment, this project is. So this is all part of the process that you need to go through with mines and creating a new project. And it's really -- this project is really constantly showing that how good it is and how good investment it is.

Jessica Fertig

executive
#13

Fantastic Rudi. Now just on that, we have a question from Nick who is a shareholder. He's asking -- and I'm not sure if you can answer this or not Rudi. But he's asking, what is the expected cost of further work to be completed to get that -- the PFS for the Project 200 or the scoping study.

Roelof Deysel

executive
#14

Look, I think in the bigger picture, it's not a lot of money that's required. It's not a lot of cost. We are already spending a lot of money to build this mine and develop this mine. Now we do have a budget in this money that's been approved by our lenders for growth projects, which we intend to spend on exactly that to develop a pathway to grow this project even bigger. 7.24 million ounces is a huge resource, and we're going to add to that as well because there's still a lot of geological work that we can do. But that's the beauty of this project is that, while we are doing this expansion and development, and we actually got now a mine in construction that will operate and produce gold while we can spend time on developing this project further. So this is actually a great situation to be in. You don't get it with other projects. So once again, I said really think this is a much more positive view on the project than really to be worried about it.

Jessica Fertig

executive
#15

Yes, absolutely, Rudi. Just on the funding side of things. So we had another question from a shareholder sort of asking. So management is saying that Qala Shallows is fully funded to steady state, how much contingency -- the question is, is built into the current funding to cover ramp-up delays or cost overruns and what circumstances could more equity be needed before the operations cash flow positive?

Roelof Deysel

executive
#16

Yes. So look, and once again, I just want to reiterate to everybody. We do have a big brother looking over our shoulders to make sure that management actually deliver to what we should do because I mean, the banks are very strict on their money, and they want to make sure that we don't waste it, that we hit our targets and for that reason, we have this whole process of what they call cost to complete test, which includes a lot of audits. We do report monthly to that funders and then obviously, every quarterly, we plan the drawdown. And then you go through a huge process, which is a due diligence process on its own to ensure that, firstly, you hit your development targets, you are producing what is required, you are on track in terms of your employers growth in the project as it gets bigger. And so we are audited the whole time to ensure that we deliver what we said we are delivering. Now in terms of there's always a contingency on top of your funding on top of the project. In this case, we've got a total package with ABSA and Nedbank lenders which is big commercial banks in South Africa. And they also fund the big South African major companies. So the fact that they support us is a great story. Now our total package is about AUD 97 million, all right, of which AUD 76 million is the senior leaders facility. On top of that, we also have a AUD 13 million working capital facility. We're not even planning on touching that. And on top of that, there's also AUD 8 million cost overrun facility. And at this stage, once again, we're not even planning to touch that month. So there is a lot of contingency built up. So the intention is not to go into an equity raise at all. We didn't say there will never be an equity raise, but it wouldn't be to fund this project. It might be to fund any growth plans for the project itself. And again, that's a thing that will be communicated in time through the right channels to everybody so that they understand for what we are using this. But the project is on plan. We just had our second drawdown. So this is the second time that we've got that tick from the banks that they are happy with what we are doing, which should give everybody much more confidence that we are doing the right thing.

Jessica Fertig

executive
#17

Fantastic, Rudi. I've just got a couple of questions from some shareholders on early next year. So one is, will the fab stopes that get sort of mined go through the toll treating plant? And the second question they asked is, what will the expected diesel use be? And are we on main power yet?

Roelof Deysel

executive
#18

Yes. So once -- what's that first question on the stopes?

Jessica Fertig

executive
#19

Yes. So well yes, we go through toll treating, it's water.

Roelof Deysel

executive
#20

No. So we are sending as we speak, [indiscernible] is a mini plant, which is part of the Sibanye-Stillwater. So that stops will go through that plant as well. It's -- we are a major source to is mine. So it's very important for them. We are part of their life of mine or life plant plan as well. And all of that material will go through that area. And like I said, as we speak, we've got stockpiles in front of the plant. And the intention is to really increase that monthly production month by month, and that's happening currently as we speak. All right. And then the one thing about Qala shallows, if you look at the typical underground mine, the amount of diesel that they use is about 20% of their operating unit cost. In our case, we use hydropower, which optimize the type of -- for instance, we use water, and we use like a battery pack, which is normal pressure water coming in and it increases that power, and that's what we actually use to drill with and run our machinery, which is much more carbon friendly and much more cheaper in terms of power usage. So our exposure in terms of our unit cost is 8% versus the 20%, which is the normal case. Now once we actually go on to the grid, which is also planned to be completed by the first quarter of February next year, then that 8% will reduce to 3%. So our diesel exposure is very little than the typical other mines that we've got. Now, on top of that, we already have commercially agreements where we've increased our diesel storage firstly on the mine itself, so that we do not run out of diesel. As well as our agreements as such that we actually fixed our supply as well for the next 6 months. So once again, from diesel the usage, I don't think anybody needs to worry about that. the mine will proceed and operate as planned.

Jessica Fertig

executive
#21

Now really, there's a question from an investor here. And I don't think that they are familiar with the story. So apologies to shareholders who already know this answer. But Basically, what they're asking is when we expect to commission the production plant. Now as you know, we don't have a production plant. We have an agreement with Sibanye. Maybe you want to just give a bit of information on that agreement and how it all works the derisked sort of nature of this project because of that?

Roelof Deysel

executive
#22

So once again, this project was designed to lower our capital requirements and because we do have a lot of capacity in the region around us. Because this is area and especially the Central Basin area are mined out quite a lot. And we've got this virgin block of ground, which is Qala Shallows that we are mining. The opportunity to actually use the spare capacity around us is absolutely there and great for the project in terms of capital spend as well. So we've got an agreement with Sibanye Stillwater with the Ezulwini plant, which is about 40 kilometers away from us. And they've got -- so in other words, we don't need to crush our material. So we can take our run-off mine material, take it directly to Ezulwni where it's been processed, and then we pay them a cost plus for processing that material. And we get the gold as per the gold price at that stage. So that's the model that we've got currently. In the project 200, we are looking at different scenarios where -- because ultimately, we would either have our own plant or we can procure other plant or we can use toll treatment as it is depending on the commercials and the business case throughout that. So that optionality is always there still the -- and there's a lot of like plants that want our material because it is high grade or it is run off my material, which recovers very well. So we are really in a great position.

Jessica Fertig

executive
#23

Fantastic Rudi. Now I've got a really interesting question here from a shareholder. And they're asking, are the stopes going to be mined by autonomous vehicles? Or what's the outlook to integrate technology into the project? Is there any sort of...

Roelof Deysel

executive
#24

So South African ore bodies are relatively steep. We've got for instant between 30 degrees to 40 degrees in dip. And it's thin table. It's not vein mining. It's really -- it's a reef. That's why we call it the reef. And the grades are very consistent, distributed through that reef body. And which gives you much confidence in that you will actually achieve your grades much better than typical other all type of ore bodies or vein ore bodies that you get in other areas. So that's high confidence and a high conversion rate from resource through to reserves. So the consistency now orebody is outright. And that's why historically, the produced $0.22 of all gold produced ever. So that's a great thing about our ore body. The problem though is because it's a steep we really struggle to mine it autonomous or with mechanized equipment. There's a lot of work being done on that to do that. but we do still mine it conventionally. This time where we brought in the HPE equipment, which is hydropower and that's the technology that we bring in to really increase our productivity which require which means workers are exposed less time because the penetration rates are much higher in that material. And then as well as you know, energy saving type of things. We are bit on using technology in Qala Shallows. And that's why we've got this hybrid system of trackless, mechanized development, but the stoping is still conventional. And it's laid out in such a way that we actually try to make sure that the people are not exposed to that steepness of the ore bodies. And ultimately, our steep gets even more, it actually goes to the opportunity to actually utilize mechanized methodologies to mine it, which we are also looking into going into the future.

Jessica Fertig

executive
#25

Absolutely Rudi. Now there's so many thoughtful questions coming through. I'm just going to answer 2 more that are in the chat. And apologies if the shareholders did submit this question, so I'm going to ask it. Thank you so much for reminding me. So in the 7th of October announcement, so on the operations update that we put out, management referenced a target of 600 meters of underground development. per month during 2027 compared with 200 meters achieved in September 2026. They want us to clarify which month or quarter we can expect to reach that rate what the key milestones are along the way and whether achieving 600 meters per month is critical to meeting 2027 production guidance?

Roelof Deysel

executive
#26

Yes. So once again, those meters are driven by phase availability. And other with how many different tunnels do you do you have exposed at that point? You could see it almost like a tree branches, as it triggers, it branches out and you get more ends. And that increase your face availability, and that increases the possibility of your increased meters. So that's the thing. So the big thing for us is, first, you want to break into that the second level, which we call Level 4 then you get multiple ins again, which will then once again increase that. So I think by early -- I don't have the plan right front, but it should be in the first quarter of 2027 when we start opening up that second. And then obviously, the decline is advancing ahead of that to go into the third level. which will get you to that point where you can get that steady state. So that 600 meters, that's when we -- it will be early next year. But I mean there's a lot of other opportunities for us as well. The one thing that's great about this mining plan is we have multiple access to the ore boarding. So there's a lot of flexibility in the profile itself, which do give us an do derisk the production profile as well, which once again, you don't get it in other mines a lot. And because we've got that old area that we could access and which we are already accessed, while we are developing this new decline, which will develop the new brand new mine into the Virgin block, which gives us more flexibility. So our exposure to face availability is actually much bigger than what a normal line should be.

Jessica Fertig

executive
#27

Yes, absolutely. Just one more question from the shareholder. And it's an important one and something that we've actually talked a lot about internally and that you actually had a recent interview on Cracks investor, which I'm happy to share that link once again when it's ready. So the question is, what are your thoughts on the current share price and what short-term activity is to look forward to that we could can start to sort of reflect the company's true value. We've spoken a lot about this really. So we're highly undervalued as a company where we are and where we're going to go.

Roelof Deysel

executive
#28

Yes. So the one thing that we are totally undervalued. I mean our enterprise value per ounce of resource that we've got is currently around $25 per ounce, if I remember correct, which is tightly unevaluated if you compare it to other peers. The one thing that you should remember and I think I'm not sure if a lot of the investors are aware of that. There's a lot of work being done over the years, and you've got the Lone which shows this typical, what happens to a share price over the life of development of mine. And we are typically now in that construction phase where you do get more speculative type of investors that are dropping off. And that basically explains why we have this lower value at this point, but then you really get this growth. As the mine is building up to steady state and as the construction are completed. And that's why we are exactly following that theoretical curve as it is. So you get more institutional or more long-term investors. And that's the type of thing which mining requires people that be best long term because then the returns are so much higher for especially those guys that get in early enough when the share price is low. So at this stage, totally undervalued. There's a lot of things that's coming up, we do have, obviously, the scoping study. There's a lot of news that will come out on a quarterly basis as per requirements. And as what we need to report on the production and the status of the project itself. And then we've got the exploration program that we want to kick off on the Birtree Central which is also an extremely exciting project. It's also very shallow. It's outcrops on surface. We want to bring that uranium from an exploration target into resource to compliant and then there's also gold with that, which is an exciting project for us and part of our growth plan. So there's a lot of news around this its mining and it's coming out, and we do bring out a lot of news to all the investors. And I think regarding the share price, that will grow, that's reality. We, like I mentioned we just follow exactly the typical share price with how it would increase. And I do believe in that, and you could see it's classical.

Jessica Fertig

executive
#29

Yes, absolutely, Rudi. Now I'm not going to take any more questions from shareholders. Thank you so much Rudi. And I can also test the fact that you and the management team, Michael Quinert, have been traveling all over doing a lot of marketing to the Asian market, in particular, you'll be -- obviously in Siniathe Golf conference and you will be at London 1-to-1 in November as well. So really reaching out to that sort of broader network. This is a really great time to invest, as you mentioned, low share price and a lot of really, really important catalysts and milestones for the company coming up. And just to finish off Rudi, can you give us sort of 3 key things that investors can take away from today?

Roelof Deysel

executive
#30

Yes. I think the first one is, once again, the project is on track. The proof is, once again, look at what our lenders approved our project and they are audit thickness projects. So they make sure that -- and it's great that we've got that, and it's -- that should give the investors confidence. The project is fully on track. We are 61% complete on surface. We intend to have that completed by the third quarter of next year. It's not far away from now. And then the focus is really for us is to create that infrastructure, open up stopes as quick as possible. And this is the thing the guys need to understand that we are following that production profile that we set out there. And once again, the other point everything that we've promised the shareholders, we achieved it. And that's the intention. And our transparency to the market is very important, and we will stay transparent on that.

Jessica Fertig

executive
#31

Absolutely, Rudi. And just one more thing. As the company sort of advances towards that 70,000-ounce steady-state production, investors should really judge the company's progress on developing meters and milestones achieved rather than the quarter's ounces. So we're not looking at production value in terms of ounces, but more on meters achieved with that tree branch sort of analogy that you used earlier.

Roelof Deysel

executive
#32

Yes. Once again, there's 3 things that's important and the banks are also looking at. And once again, the proof is there the fact that they approved that second roll down.

Jessica Fertig

executive
#33

Absolutely, Rudi. Thank you very much. Thank you, everyone, so much for your thoughtful questions. Any other leftover questions, I will carry them forward to our quarterly webinar, which we'll have in a couple of weeks' time. Rudi, thank you so much. I know you've got to get to a conference. You're presenting later today, which I will be at. And there will, obviously, of course, be a recording of this for anyone who wants to watch back at any questions or for any investors who missed this session. Thank you, Rudi, and we'll see you later.

Roelof Deysel

executive
#34

Thanks, Jess. Speak to you later. Bye.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete West Wits Mining Limited transcript — plus 256,000+ transcripts from 12,000+ companies, speaker segments, AI summaries and full-text search — through the EarningsCalls.dev API.

Get the API View API docs →

For developers and AI pipelines

Programmatic access to West Wits Mining Limited earnings transcripts and 256,000+ others is available through the EarningsCalls.dev REST API. Plans from $24.99/month — full transcripts, speaker segments, full-text search, and the recently-added /api/v1/transcripts/recent polling endpoint for ETL pipelines.

More tools for stock research

OptionsBell: an unusual options activity scanner that tracks options flow across all US stocks and emails you when large trades appear in West Wits Mining Limited or any ticker on your watchlist.

StockMarketScan: a stock screener with alerts: 24 pre-built screens refreshed every 5 minutes, watchlists and email notifications. Both offer API and MCP access and fair monthly pricing.